Table 301-1: Add the following:
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Subbase & Base Courses L, M, N, O, P, Q, R |
| Measured and tested conformance (Subsection 106.04) |
| Plastic Limit |
| - |
| AASHTO T 90 |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| Yes |
| 4 Hours |
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Aggregate Width |
| Measured and tested conformance (Subsection 106.04) |
| Width |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Aggregate Thickness |
| Measured and tested conformance (Subsection 106.04) |
| Thickness |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Additive |
| Measured and tested conformance (Subsection 106.04) |
| Amount of Additive |
| - |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| No |
| 4 Hours |
301.08_nat_us_02_07_2007
Table 301-1 Field Density Requirements.
Table 301-1: Delete laboratory and field density requirements for base, subbase, and surfacing and replace with the following:
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Base and Subbase |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| --- |
| Method C |
| --- |
| AASHTO T 99 |
| 1 per type and source of material |
| Source of material |
| Yes |
| Before using in work |
| Method C-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| “ |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| Method D-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| “ |
| Method C, C-1, D, D-1 |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |
| Surfacing |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| Method C-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| Before using in work |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| Method D-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| “ |
Compaction
| Method C, C-1, D, D-1 |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |