Solicitation AG-84N8-S-16-0121

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-84N8-S-16-0121 Page 1 of 51

REGION 4 UTAH AQUISTION SUPPORT CENTER INSTRUCTIONAL COVER SHEET

ISSUING OFFICE: USDA-FOREST SERVICE

UTAH ACQUISITION SUPPORT CENTER

2222 WEST 2300 SOUTH

SALT LAKE CITY, UT 84119-2020

FAX 801-975-3483

SOLICITATION NO. AG-84N8-S-16-0121

PROPOSALS ARE SOLICITED FOR: RED CANYON AND DUTCH JOHN ROOF REPLACEMENT PROJECT – ASHLEY

NATIONAL FOREST

SET-ASIDE: SMALL BUSINESS

IMPORTANT –OFFEROR SHALL SUBMIT THE FOLLOWING DOCUMENTS WITH THEIR RESPONSE TO THIS

SOLICITATION:

1. SF 1442 (Complete, date, and sign Pages 2 & 3)

2. Section B - Schedule of Items (Page 4-5)

3. Experience Questionnaire (Exhibit 1, Pages 33-35)

4. Section K - Representations and Certifications (Pages 41-44) – (Complete the Representations and Certifications electronically via the System for Award Management (SAM) website at www.sam.gov).

5. Section M – Technical Proposal (Pages 50-51)

IT IS REQUIRED THAT YOU WRITE THE SOLICITATION NUMBER ON THE OUTSIDE OF YOUR ENVELOPE.

FAXED QUOTES WILL BE ACCEPTABLE: FAX 801-975-3483, Attn: Christine Howick

Return to: Utah Acquisition Support Center

2222 West 2300 South

Salt Lake City, UT 84119-2020

Solicitation No. AG-84N8-S-16-0121, Attn: Christine Howick

AN AWARD WILL BE MADE FROM THIS SOLICITATION WHEN THE EVALUATION OF OFFERS HAS BEEN COMPLETED WHICH IS ANTICIPATED

TO OCCUR SHORTLY AFTER THE CLOSING DATE OF THE SOLICITATION. IN ORDER TO BE CONSIDERED FOR ANY AWARD, IT IS

REQUIRED THAT CONTRACTORS BE REGISTERED, ACTIVE AND VALID IN THE SYSTEM FOR AWARD MANAGEMENT (SAM)

DATABASE AT THE TIME THAT AWARD WILL BE MADE. REFERENCE FAR 52.204-7 SYSTEM FOR AWARD MANAGEMENT. IT IS

RECOMMENDED THAT IF YOU ARE A CONTRACTOR THAT WILL BE RESPONDING TO THIS SOLICITATION AND NOT CURRENTLY

REGISTERED, ACTIVE AND VALID IN THE SAM DATABASE, THAT YOU IMMEDIATELY BEGIN THE PROCESS. CONTRACTORS MUST ALSO

MEET THE SMALL BUSINESS SIZE STANDARD OF THE NAICS CODE THAT THIS SOLICITATION IS ISSUED UNDER

OMB APPROVAL NO. 2700-0042

http://www.sam.gov/

AG-84N8-S-16-0121 Page 2 of 51

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-84N8-S-16-0121

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

807809

6. PROJECT NO.

7. ISSUED BY CODE 84N8 8. ADDRESS OFFER TO

Utah Acquisition Support Center

2222 West 2300 South

Salt Lake City, UT 84119-2020

Utah Acquisition Support Center

ATTN: Christine Howick

2222 West 2300 South

Salt Lake City, UT 84119-2020

9. FOR INFORMATION

CALL:

A. NAME

Christine Howick (Contracting)

Scott Bingham (Technical)

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

801-975-3725

435-781-5107

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

A site visit has been scheduled for Friday, 7/29/2016 @ 11:00 a.m. MDT. Meet @ Red Canyon turnoff – Hwy 44 intersection of Forest Road 095. For more information, please contact Scott Bingham @ 435.781.5107.

Red Canyon and Dutch John Roof Replacement Project on the Vernal Ranger District, Uintah County, Ashley National

Forest

The magnitude estimated price range is: $25,000 - $100,000.

This requirement is being procured as a fixed price Simplified Acquisition.

NAICS Code: 238160 Size Standard: $15.0

11. The Contractor shall begin performance within 10 calendar days and complete it within 85 calendar days after receiving

Award, Notice to Proceed. This performance period is mandatory, negotiable. (See .)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If “YES,” indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Quotes/Offers to perform the work required are due at the place specified in Item 8 by 1:00 p.m. MDT Local time 8/16/2016 Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required, unless offer exceeds $150,000.00.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

AG-84N8-S-16-0121 Page 3 of 51

Computer Generated STANDARD FORM 1442 BACK

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

PLEASE PROVIDE DUNS NUMBER: __________________________

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D.

Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO

SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

AG-84N8-S-16-0121 Page 4 of 51

SECTION B

Supplies or Services and Prices/Costs Schedule of Items

SCHEDULE OF ITEMS

Red Canyon and Dutch John Roof Replacement Project

Ashley National Forest

Base Bid: Red Canyon Roof

NUMBER

DESCRIPTION

METHOD

OF MEAS

UNI

T

QTY

PRICE

SUB TOTAL

011900-1 Mobilization LSQ EA

000050-1

Remove Existing Wood Shingle Roof and Install New Metal Roof

(Government furnished metal panels, drip edge and ridge cap).

LSQ EA 1 $

Total Base Bid $

Option #1: Dutch John Roof #3022

011900-2 Mobilization LSQ EA

000050-2 Remove Existing Asphalt Shingle

Roof and Install New Metal Roof

LSQ EA 1 $

Total Option #1 $

Option #2: Dutch John Roof #3023

000050-3 Remove Existing Asphalt Shingle

Roof and Install New Metal Roof

LSQ EA

Total Option #2 $

TOTAL of Base plus Option 1 & Option 2 $____________________

AG-84N8-S-16-0121 Page 5 of 51

Name of Company: _____________________________________ Date: __________________

(Please print)

Signature of Company Agent: _____________________________DUNS # ________________

Email Address: ________________________________________ Phone # ________________

This solicitation and any resulting contract is a firm-fixed price type of contract, which under the definition in FAR 16.202-1, “this type of contract provides for a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract. This contract type places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss.”

Quoters shall submit a quote for Base Bid, Option #1and Option #2 in the Schedule of Items.

Failure to comply with the instructions may render your quote nonresponsive and ineligible for contract award.

Government reserves the right to exercise Options within 30 days from award.

Prices on the Schedule shall reflect Contractor’s full cost for materials, labor, supervision, overhead costs, and incidental items.

Quote on all items. Only quotes to the nearest cent will be accepted.

The Government shall issue a contract to the Contractor who offers the best value to the Government.

Best Value will be based on the evaluation factors listed in Section M.

Point of Contacts: Scott Bingham, Technical, 435-781.5107, srbingham@fs.fed.us

Christine Howick, CO, 801-975-3725, chowick@fs.fed.us mailto:srbingham@fs.fed.us mailto:chowick@fs.fed.us

AG-84N8-S-16-0121 Page 6 of 51

Section C - Description/Specifications/Statement of Work

1.1 SCOPE OF CONTRACT

A. This project includes all requirements and necessary construction to replace a failing roof system on the Red Canyon duplex and two roofs on the Dutch John trailers on the Ashley

National Forest. Construction work includes the following:

1. Remove and dispose of existing roof materials according to drawings and specifications.

2. Install new plywood roof sheathing (Red Canyon only), peel and stick membrane at the roof perimeter and #30 roofing felt over entire roofs.

3. Install metal roof panels’ w/slip sheet and trim according to drawings and specifications.

Provide and install incidental roof trim and gutters to provide a complete roof assembly.

4. Provide and install new roof vents and stain existing wood fascia (Red Canyon only).

B. Option Bid Items

1. Option #1: Dutch John Roof #3022

2. Option #2: Dutch John Roof #3023

C. Government Furnished Materials

1. Seventy-eight 36” wide by 17’1/2” long metal roof panels (for Red Canyon only).

2. Six 10’6” long pieces of ridge cap (for Red Canyon only).

3. Twenty-two 10’6” long pieces of drip edge (for Red Canyon only).

4. Ten 10’6” long pieces of hip cap (for Red Canyon only).

1.2 PROJECT LOCATION

A. The work will be conducted at an existing duplex on the Red Canyon site near Flaming Gorge and two existing trailer homes in Dutch John. The Red Canyon site is 15 miles southwest of the town Dutch John. This site may be accessed from State Highway 44 and Forest Road 095. The

Dutch John trailers are located near the airport in Dutch John. This site may be accessed from

Airport Road just south of Dutch John, Utah. Government furnished materials are located at the

Forest Service Warehouse yard on South Blvd., Dutch John, Utah.

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the Contractor will not be paid directly for any of the following items:

1. The construction site will remain open and used by the residents during construction.

The Contractor will be responsible for signing and limiting access to materials and construction areas for those in the residence.

AG-84N8-S-16-0121 Page 7 of 51

2. Use of site – Verify locations for materials storage and construction with COR. Do not disturb portions of site beyond areas in which the COR specifies. Relocate the warehoused roof materials to the site from Dutch John, approximately 15 miles away.

3. There is existing electrical service for both sites. Contractor shall have permission to use existing electrical services during construction. Contractor shall be aware of the use of electrical services, and shall limit the use of electrical services to the construction alone.

Contractor shall provide connections and extensions of services as required for construction operations.

4. The residence will be occupied during the construction. The contractor shall take necessary precautions to keep the facility weather tight and to avoid damage to the interior of the facility.

5. Water is available at the site for construction purposes.

6. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.

7. Construction hours – Hours of operation for the construction, demolition, excavation and subsequent cleanup shall be only between the hours of 7:00 a.m. and 7:00 p.m., Monday through Saturday.

1.4 TEMPORARY ACCESS

A. Parking: Use designated areas for construction personnel or as approved by the Contracting

Officer. All other parking is prohibited.

1.5 WASTE MANAGEMENT AND DISPOSAL

A. Waste Management Plan: Submit 2 copies of plan within 14 days of date established for the

Notice to Proceed.

B. The Contractor shall provide and maintain appropriate waste disposal containers or bins at the project site for the duration of the project construction. Verify with the Contracting Officer

Representative (COR) for placement of disposal containers and bins on the project site.

C. Waste material and debris shall be picked up and deposited in the waste disposal bins on a daily basis. Containers must be emptied on a weekly basis unless more frequent emptying is needed.

Construction materials and debris shall not be allowed to become airborne or migrate into adjacent properties.

D. Burning or burying of construction waste material on site will not be permitted. Material shall be disposed of in accordance with the Waste Material Disposal specification.

1.6 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the

Contractor and approved by the COR and Utah Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices

(MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

AG-84N8-S-16-0121 Page 8 of 51

1.7 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the Contracting

Officer (CO). The Contractor must request in writing for approval from the CO to stage trailers

(work) on site.

1.8 INSPECTION OF WORKSITE

A. The Contractor shall acknowledge they have taken the necessary steps to determine the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.9 START DATE

A. Aug, 2016

1.10 CONTRACT TIME

A. Base Bid: 45 Calendar Days from Notice to Proceed

B. Option #1: 20 Calendar Days

C. Option #2: 20 Calendar Days

1.11 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made

Section 000050 – Project Description

Section 011700 – Accident Prevention

Section 013300 – Submittal Procedures

Section 014100 – Quality Control

Section 017320 – Selective Demolition

Section 024100 – Waste Material Disposal

Section 061600 – Sheathing

Section 074113 – Metal Roof Panels

Section 076200 – Sheet Metal Flashing and Trim

AG-84N8-S-16-0121 Page 9 of 51

1.12 BIOBASED PRODUCT UTILIZATION

The Contractor must comply with the Agricultural Act of 2014; the Food, Conservation and Energy Act of

2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C.

8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in

Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening

Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and

Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February 2012, to provide biobased products.

The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s

Representative (COR).

The following is an example list of products that may be used in this contract for which biobased products are available. The list is not all inclusive. It is desirable that Contractors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

(*Sample of biobased products for construction projects)

Grease Removers Insulating Foam Concrete and Asphalt Release

Fluids

Fluid-filled Transformers Wood and Concrete Sealers Composite Panels

Adhesive and Mastic Removers Carpets Roof Coatings

Hydraulic Fluid Water Tank Coatings

(*Sample of biobased products for building mtce – light construction projects (Operations and Maintenance)

Hydraulic Fluids Penetrating Lubricants Concrete and Asphalt Release

Fluids

Absorbents Diesel Fuel Additives Greases

Dust Suppressants 2-Cycle Engine Oil Wood and Concrete Sealers

Fertilizers Roof Coatings Water Tank Coatings

Adhesive and Mastic Removers Cleaners Sorbents

Floor Finish Floor Stripper Composite Panels

Insulating Foam Sealers Carpet

Metalworking Fluids Graffiti and Grease Removers Stain Removers

Degreasers De-icers

Biobased products that are designated for preferred procurement under USDA’s Biopreferred Program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material.

In addition to the biobased products designated by the U.S. Department of Agriculture in the Biopreferred

Program, the Contractor is encouraged to use other commercially available biobased products.

http://www.biopreferred.gov/

AG-84N8-S-16-0121 Page 10 of 51

The Contractor shall submit with the initial proposal a complete list of biobased products, indicating the name of the manufacturer, cost of each material, and the intended use of each of the materials that are to be used in carrying out the requirements of this contract (see Experience Questionnaire, pages **).

Additionally, the winning Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes (see Section I, FAR Clause 52.223-2).

Within thirty (30) days of contract award, the Contractor shall submit an Operation Plan. This submittal will be approved by the COR in writing. The Contractor shall not commence work until this submittal is approved by the COR in writing. The Plan must be reviewed and updated annually, and as required by the COR. The Plan must contain and define the following elements:

The Contractor’s written policy stating its commitment to the use of biobased products, employee health and safety, and sound environmental management practices.

Detail on how the Contractor intends to keep abreast of the development and increasing availability of designated and non-designated biobased products and how any new or improved products will be incorporated on an ongoing basis into contract performance.

Proposed biobased construction products which must be selected in accordance with the criteria included above. At a minimum, the Plan must identify products by brand name for each of the product types.

NOTE: A Contractor may propose more than one product within a product category and/or propose a product or products addressing more than one product category.

The product guides which define standard operating procedures for instructing staff in the proper use, storage, and disposal of biobased products; proper maintenance of equipment; and other procedures/instructions to accomplish work under this contract.

The Contractor shall provide data on the quantity and dollar values of biobased products used in this contract. The data shall be submitted to the COR quarterly.

A demonstration of proper use, an effective training program, and technical assistance are essential to the success of the purchase and use of some biobased products that may function differently than a conventional product.

AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section C and

Section J.

AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

AG-84N8-S-16-0121 Page 11 of 51

FAR 52.223-1 Biobased Product Certification (MAY 2012)

As required by the Farm Security and Rural Investment Act of 2002 and the Energy Policy Act of 2005 (7

U.S.C. 8102(c)(3)), the offeror certifies, by signing this offer, that biobased products (within categories of products listed by the United States Department of Agriculture in 7 CFR part 3201, subpart B) to be used or delivered in the performance of the contract, other than biobased products that are not purchased by the offeror as a direct result of this contract, will comply with the applicable specifications or other contractual requirements.

NOTE: Offeror’s are cautioned to carefully review these Project Specifications prior to submission of offers. All specifications contained in Section J are binding on the parties signing the contract.

AG-84N8-S-16-0121 Page 12 of 51

SECTION D - Packaging and Marking

{For this Solicitation, there are NO clauses in this Section}

AG-84N8-S-16-0121 Page 13 of 51

SECTION E - Inspection and Acceptance

52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es): www.acquisition.gov www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

52.246-13 Inspection–Dismantling, Demolition or Removal of Improvements

(AUG 1996)

INSPECTION AND ACCEPTANCE: Periodic filed inspections will be made by the Contracting

Officer’s Representative (COR). Work not completed to contract standards shall be rejected and reworked without additional compensation to the Contractor.

http://www.acquisition.gov/ http://www.usda.gov/procurement/policy/agar.html

AG-84N8-S-16-0121 Page 14 of 51

SECTION F - Deliveries or Performance

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es): www.acquisition.gov

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use 85 calendar days after the date the contractor receives the notice to proceed.

The time stated for completion shall include final cleanup of the premises.

52.242-14 Suspension of Work (APR 1984)

AGAR 452.236-75 Maximum Workweek – Construction Schedule (NOV 1996) Within 2 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

The maximum workweek that will be approved is to be negotiated if needed.

AG-84N8-S-16-0121 Page 15 of 51

SECTION G - Contract Administration Data

G-1 MEASUREMENT OF PAYMENT: Units of measurement shall be as indicated in the

Schedule of Items. Designated Method of Measurement:

DQ - Designed Quantities, AQ - Actual Quantities, LSQ - Lump Sum Quantities, SQ - Staked Quantities, CQ - Contract Quantities

G-2. CONTRACTING OFFICE

The Utah Acquisition Support Center of the United States Forest Service, Department of

Agriculture is responsible for this solicitation, award and administration of the contract. All written correspondence shall reference the contract number and/or solicitation number.

Communications shall be directed to:

Contracting Officer

USDA-FS, Utah Acquisition Support Center

2222 West 2300 South, 2nd Floor

Salt Lake City, UT 84119-2020

G-3. CONTRACTING OFFICER’S REPRESENTATIVE

An awarded contract will have a Contracting Officer’s Representative (COR). Such designations will made by appointment letter.

G-4. SUBCONTRACTS

Before entering into a subcontract covering any part of the work called for, the Contractor shall inform the Contracting Officer and submit information required by the Contracting Officer.

G-5. INVOICES

An invoice shall be submitted after each transaction stating their total dollar value, supported by receipt copies. The information will be the responsibility of the contractor. Failure to provide this information will result in delayed payment.

All invoices will be processed using the Department of Treasury’s Invoice Processing Platform

(IPP), visit http://www.ipp.gov to learn more. Contractors must follow the instructions on how to register and submit invoices via IPP.

http://www.ipp.gov/

AG-84N8-S-16-0121 Page 16 of 51

SECTION H - Special Contract Requirements

H-1 FIRE PRECAUTIONS

This plan outlines the channels of responsibility for fire prevention and suppression activities and sets up an attack procedure in the event of fire within the Project Area. The Project Area is defined as that area which is in and adjacent to the project rights-of-way and work areas and all roads used in connection with the work.

I. RESPONSIBILITIES

A. Contractor

Fire Suppression

1. It is understood and agreed that the Contractor will do all in his power to prevent and suppress fires on or adjacent to the Project Area, as stipulated in the contract.

2. Is responsible for and will direct all fires activities on the project until relieved by a Forest

Officer and will insure that prevention and suppression action are in accordance with contract requirements, including this fire plan. He will delegate the next higher in authority on the job to be responsible for the above activities when he is not on the project.

3. In line with this agreement, men will be supplied from the Contractor's crew to fight fires on the project area up to the total number of men employed by the Contractor as they are needed by the Fire

Boss. The Forest Service will make every effort to avoid calling on the Contractor for action on fires outside the Contract project area except in emergencies and will call out all needed available help to control fires in the general area.

4. The Contractor issures that this Fire Plan will be complied with by him and his employees for the duration of the contract.

B. Forest Service District Ranger

1. Is responsible for all fire activities on the Ranger District on which the contract project is located. He or his representative will discuss the fire plan with the Contractor and will discuss with him the equipment and manpower action to be taken when a fire occurs. He will notify the Contractor through the Contracting Officer's Representative (COR) to take correction measures when fire requirements are not complied with.

II. CONTRACTOR'S RESPONSIBILITY WHEN A FIRE OCCURS WITHIN THE CONTRACT

PROJECT AREA

A. He will immediately send the entire contract crew with tools and equipment t o the fire and take initial-attack suppression action.

AG-84N8-S-16-0121 Page 17 of 51

B. Immediately notify the nearest Forest Service Fire Control Officer or other Forest Service employee of fire location and action taken

C. Designate a man to act as dispatcher who will handle messages and initiate action upon request until relieved.

III. CONTRACTOR FURNISHED MANPOWER, TOOLS, AND EQUIPMENT REQUIRED ON ALL

CONTRACTS (PROJECTS) DURING FIRE SEASON

A. The Contractor shall furnish to the COR a list of manpower and equipment used on the contract on forms furnished by the Forest Service. Changes in Contractor's personnel shall be reflected in amendment to the list.

Fire Prevention

Smoking. Will be prohibited in the woods during the fire season, May 10 through October 20, except in areas agreed upon by the Contractor and Contracting Officer's Representative. No smoking is permitted while walking or working in the woods.

Refueling Chainsaw/Soil Auger. Refueling will be confined to a six-foot diameter cleared to mineral earth. Chainsaws/soil auger sparks arrester shall be U.S. Forest Service approved, and will be cleaned daily. A size "0" or larger round-pointed shovel with a minimum of a 38-1/2" handle and a fire extinguisher shall be within 10 feet of actual point of chainsaw/soil auger operation.

Burning, Blasting, or Welding. Permit will be required and will contain special stipulations pertinent to the particular job.

Spark Arresters. All internal combustion power equipment used by the Contractor on the project shall be equipped with an approved spark arrester as set forth in the publication of the USDA Forest Service, entitled "Standard 5100-1a for Spark Arresters for Internal Combustion Engines" as amended under date of July 1970, and be listed in the most recent "Spark Arrester Guide" as having been approved as meeting above standard. They shall be cleaned regularly and maintained in satisfactory working condition. The following are exempt from the requirements of the rule:

(a) Turbo-charged internal combustion engines in which 100 percent of the exhaust gasses pass through a turbo-charged;

(b) Engines of passenger carrying vehicles and light trucks equipped with a muffler with baffles that are kept in good repair (glass packs are not an approved muffler for wildland work);

(c) Water pumping equipment used in firefighting.

Spark arresters must comply with all State and Federal fire requirements.

Lunch and Warming Fires. Cooking and warming fires will not normally be permitted and then only by written permit by the COR which contain stipulations regulating use of such fires.

Hand Tools. The Contractor shall furnish one size "0" shovel (38-1/2" handle minimum) or larger, one axe, or pulaski with 26" handle or larger, and one 5 BC or larger rated pressurized fire extinguisher for

AG-84N8-S-16-0121 Page 18 of 51 each truck, each personal vehicle, each tractor, and each grader. For each welder he shall furnish one size

"0" shovel and one backpump pump. For each gasoline power tools (power saw, soil auger, etc.), one shovel (38-1/2" handle minimum) and one 8-ounce or larger BC rated chemical-pressurized fire extinguisher.

Contractor shall also furnish any other equipment called for elsewhere in the contract. The shovel and fire extinguisher will be located within 10 feet of the operating chainsaw/power auger.

Storage and Parking Areas. Equipment service area, parking area, and gas and oil drum storage areas will be cleared of all flammable material for a radius of at least fifty feet. These areas must be approved in writing by the Contracting Officer's Representative in advance of use. Small stationary engine sites shall be cleared of flammable material for a radius of at least fifteen feet from such engine.

Fire Tool Box. A red fire tool box will be required to be on each work site while work is being performed. This fire tool box will contain sufficient tools to equip all persons engaged in Contractor's operation. Fire tools shall be used only for suppressing wildfires. Tools shall be stored in fireboxes provided by the Contractor and readily available to employees. Each tool box shall be marked, "Tools for

Fire Only." The COR will inspect the fire tool box and then seal the box.

H-2 SITE SUPERINTENDENT

It shall be the responsibility of the Contractor to provide a responsible site superintendent to represent the

Contractor in the field in all matters under this contract including, but not limited to construction, day-to-day coordination of activities, control over employees and subcontractors, and coordination with local

Government personnel. The site superintendent shall be designated in writing. They shall be available on site in person to respond to any and all problems during normal working hours. The site superintendent shall be responsible for on-site Quality Control.

Site superintendent shall maintain on site a file containing the following project documents.

Executed Copy of the Contract

Contract Drawings

Contract Specifications

Quality Control Plan – (up to date)

As-Built Drawing – (up to date) if required

Work Orders

Modifications

This file shall be maintained and available to the Contracting Officer upon request. If the Site

Superintendent is replaced, the existing Superintendent shall review all documents and ongoing issues with the new Superintendent.

H-3 - Designation of Contracting Officer Representative

Prior to the commencement of work, the COR will be designated. The COR is responsible for administering the performance of the work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by the Contracting Officer prior to the completion of this contract.

AG-84N8-S-16-0121 Page 19 of 51

SECTION I - Contract Clauses

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es): www.acquisition.gov

52.202-1 Definitions (NOV 2013)

52.203-03 Gratuities (APR 1984)

52.203-5 Covenant against Contingent Fees (MAY 2014)

52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006)

52.203-7 Anti-Kickback Procedures (MAY 2014)

52.204-9 Personal Identity Verification of Contractor Personnel (JAN 2011)

52.204-13 System for Award Management (JUL 2013)

52.204-18 Commercial and Government Entity Code Maintenance (JUL 2015)

52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)

52.211-18 Variation in Estimated Quantity (APR 1984)

52.219-6 Notice of Total Small business Set-Aside (NOV 2011)

52.219-8 Utilization of Small Business Concerns (OCT 2014)

52.219-14 Limitations on Subcontracting (NOV 2011)

52.222-3 Convict Labor (JUN 2003)

52.222-6 Construction Wage Rage Requirements (MAY 2014)

52.222-7 Withholding of Funds (MAY 2014)

52.222-8 Payrolls and Basic Records (MAY 2014)

52.222-9 Apprentices and Trainees (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (MAY 2014)

52.222-12 Contract Termination - Debarment (MAY 2014)

52.222-13 Compliance with Davis-Bacon and Related Act Regulations (MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (MAY 2014)

52.222-21 Prohibition of Segregated Facilities (APR 2015)

52.222-26 Equal Opportunity (MAR 2007)

52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015)

52.222-35 Equal Opportunity for Veterans (OCT 2015)

52.222-36 Affirmative Action for Workers with Disabilities (JUL 2014)

52.222-40 Notification of Employee Rights Under the National Labor Relation Act (DEC 2010)

52.222-50 Combating Trafficking in Persons (MAY 2015)

52.222-55 Minimum Wages under Executive Order 13658 (DEC 2015)

52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

(SEP 2013)

52.223-3 Hazardous Material Identification and Material Safety Data (JAN 1997) Alternate I

(JUL 1995)

52.223-5 Pollution Prevention and Right-to-Know Information (May 2011)

52.223-6 Drug-Free Workplace (MAY 2001)

AG-84N8-S-16-0121 Page 20 of 51

52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts

(MAY 2008)

52.223-18 Contractor Policy to Ban Text Messaging While Driving (AUG 2011)

52.224-1 Privacy Act Notification (APR 1984)

52.224-2 Privacy Act (APR 1984)

52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)

52.225-25 Prohibition on Engaging in Sanctioned Activities Relating to Iran-Certification (OCT

2015)

52.228-15 Performance and Payment Bonds – Construction (OCT 2010)

52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014)

52.232-23 Assignment of Claims (MAY 2014)

52.232-27 Prompt Payment for Construction Contract (MAY 2014)

52.232-33 Payment by Electronic Funds Transfer – System for Award Management (JUL 2013)

52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)

52.233-1 Disputes. (MAY 2014)

52.233-3 Protest after Award (AUG 1996)

52.233-4 Applicable law for Breach of Contract Claim (OCT 2004)

52.236-2 Differing Site Conditions (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)

52.236-5 Material and Workmanship (APR 1984)

52.236-6 Superintendence by the Contractor (APR 1984)

52.236-7 Permits and Responsibilities. (NOV 1991)

52.236-8 Other Contracts. (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.

(APR 1984)

52.236-10 Operations and Storage Areas. (APR 1984)

52.236-11 Use and Possession Prior to Completion. (APR 1984)

52.236-12 Cleaning Up. (APR 1984)

52.236-13 Accident Prevention. (NOV 1991)

52.236-14 Availability and Use of Utility Services. (APR 1984)

52.236-15 Schedules for Construction Contracts. (APR 1984)

52.236-17 Layout of Work. (Apr 1984)

52.236-21 Specifications and Drawings for Construction. (FEB 1997)

52.236-26 Preconstruction Conference (FEB 1995)

52.236-28 Preparation of Proposals -- Construction (Oct 1997)

52.243-4 Changes. (JUN 2007)

52.246-12 Inspection of Construction (AUG 1996)

52.246-21 Warranty of Construction. (MAR 1994)

52.249-1 Termination for Convenience of the Government (Fixed-Price)(Short Form) (APR 1984)

52.249-10 Default (Fixed-Price Construction). (APR 1984)

52.251-1 Government Supply Sources (APR 2012)

52.253-1 Computer Generated Forms (JAN 1999)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.224-70 Confidentiality of Information (FEB 1988)

452.236-71 Prohibition against the Use of Lead-Based Paint. (NOV 1996)

452.236-73 Archaeological or Historic Sites. (FEB 1988)

AG-84N8-S-16-0121 Page 21 of 51

452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)

452.236-76 Samples and Certificates (FEB 1988)

52.204-12 Data Universal Numbering System Number Maintenance (DEC 2012)

(a) Definition. “Data Universal Numbering System (DUNS) number,” as used in this clause, means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities, which is used as the identification number for Federal contractors.

(b) The Contractor shall ensure that the DUNS number is maintained with Dun & Bradstreet throughout the life of the contract. The Contractor shall communicate any change to the DUNS number to the

Contracting Officer within 30 days after the change, so an appropriate modification can be issued to update the data on the contract. A change in the DUNS number does not necessarily require a novation be accomplished. Dun & Bradstreet may be contacted—

(1) Via the internet at http://fedgov.dnb.com/webform or if the Contractor does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(2) If located outside the United States, by contacting the local Dun and Bradstreet office.

52.204-21 Basic Safeguarding of Covered Contractor Information Systems (JUN 2016)

(a) Definitions. As used in this clause–

“Covered contractor information system” means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

“Federal contract information” means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the

Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.

“Information” means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual

(Committee on National Security Systems Instruction (CNSSI) 4009).

“Information system” means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

“Safeguarding” means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of http://fedgov.dnb.com/webform http://uscode.house.gov/

AG-84N8-S-16-0121 Page 22 of 51 authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract

Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access;

and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract

AG-84N8-S-16-0121 Page 23 of 51 information residing in or transiting through its information system.

52.209-11 – Representation by Corporations Regarding Delinquent Tax Liability or a Felony

Conviction under any Federal Law.

Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any

Federal Law (Feb 2016)

(a) As required by sections 744 and 745 of Division E of the Consolidated and Further Continuing

Appropriations Act, 2015 (Pub. L 113-235), and similar provisions, if contained in subsequent appropriations acts, the Government will not enter into a contract with any corporation that--

(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless an agency has considered suspension or debarment of the corporation and made a determination that suspension or debarment is not necessary to protect the interests of the Government; or

(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless an agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.

(b) The Offeror represents that—

(1) It is [ ] is not [ ] a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability; and

(2) It is [ ] is not [ ] a corporation that was convicted of a felony criminal violation under a

Federal law within the preceding 24 months.

52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013)

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to

Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall

AG-84N8-S-16-0121 Page 24 of 51 be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the

Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—