SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Description: The renovation of the Office building to address both an interior and and exterior issues. These include but not limited to asbestos containing materials, accessibility issues, and snow hazard.
1.2 LOCATION
A. This project is located at the Fraser Experimental Forest Headquarters that is located at ****.
1.3 GENERAL SITE CONDITIONS AND WEATHER
A. The elevation of the site is approximately **** feet above mean sea level. The construction site is accessible year round but from November through May it is **** .
B. In-depth soil surveys have not been performed; however, rocks at the ground surface are evident throughout the area. The Contractor should expect to encounter such rock during excavation and grubbing operations. Blasting of rocks will not be permitted without special permission.
1.4 USE OF PREMISES
A. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees.
C. Confine storage of materials to areas as approved by the CO.
D. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
E. Preservation of Natural Features: Confines all operations to work limits of the project.
Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with CO and remove agreed-on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Existing Utilities: The electrical was provided by a generator but the service has been abandoned. This contract includes the removal of all abandoned electrical service line.
There are existing water lines, but services are not on for the facilities.
1. Contractor shall be responsible for locating and preventing damage to known utilities.
If damage occurs, repair utility at no additional expense to the Government.
2. Interruption of Existing Utility Service: Notify CO, 48 hours in advance of any interruption of existing utilities.
1.5 MEALS AND LODGING
A. Meals and lodging are commercially available in the City of Fraser, Colorado within 10 miles of the construction site. Meals or lodging will not be available at Forest Service facilities.
1.7 CONSTRUCTION SEQUENCE
A. There is no specified construction sequence or season for this project however it is recommended that exterior work be performed first..
B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.
1.8 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
1.9 PERMITS
A. Any permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 01100
SECTION 01020
MEASUREMENT AND PAYMENT
PART 1 - PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general; and method of measurements and basis of payment for work items listed in the Schedule of Items.
B. Work:
1. Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the Contractor.
C. Payment:
1. For each individual item listed in the Schedule of Items for each Task Order, payment shall be full compensation for all work related to the particular item in accordance with these specifications, as shown on the drawings, and as staked in the field.
2. Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.
1.2 DETERMINATION OF QUANTITIES
A. The contractor shall perform, or cause to be performed, all measurement of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.
B. Quantity Measurements:
1. The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Designed Quantity (DQ) or Lump Sum Quantity (LSQ).
2. The contractor shall compute the quantities for periodic progress payments; the Contracting Officer shall compute the quantities for the final payment based on measurements taken by the Contractor.
3. All Contractor measurements are subject to verification.
4. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities.
5. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.
C. The following measurements and calculations are used to determine contract quantities.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting, and erosion control blankets shall be along slope lines.
2. The average end area method shall be used to compute volumes of excavation or embankment. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three dimensional methods.
3. Structures shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, and underdrains; measurements shall be made parallel to the base or foundation upon which the structures are placed. Pipes shall be measured along center of invert.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items--such as fence, wire, plates, rolled shapes, pipe conduits--identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
B. Cubic Yard: A measurement computed by one of the following methods:
1. Excavation, Embankment, or Borrow: The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
2. Material in Place or Stockpile: The measurement computed using the dimensions of the in-place material.
3. Material in the Delivery Vehicle: The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
C. Each: One complete unit, which may consist of one or more parts.
D. Linear Foot: Linear feet measured horizontally.
1.4 METHOD OF MEASUREMENT
A. GENERAL
1. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
B. DESIGNED QUANTITIES (DQ)
1. These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
C. ACTUAL QUANTITIES (AQ)
1. These estimated quantities which are determined from actual measurements of completed work.
D. LUMP SUM QUANTITIES (LSQ)
1. These quantities denote one complete unit of work as required by or described in the contract including necessary materials, equipment, and labor to complete the job. They shall not be measured.
PART 2 - PART 2 – Product (not Used)
PART 3 - PART 3 – Execution (Not Used)
END OF SECTION 01020
SECTION 01170
ACCIDENT PREVENTION
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1.2 SUBMITTALS
A. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer (CO) will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be processed until the program is approved. The program shall include:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
5. Training, both initial and continuing.
6. Planning for possible emergency situations such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
B. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
C. Submit a brief report of safety meetings and of inspections.
D. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
1.3 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting
OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
2. To as great an extent as possible, do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within seven (7) days of a reportable accident, fill out and forward to the CO a DI-134 form, which may be obtained from CO.
B. All Other Accidents: The Contractor shall report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.
PART 2 - PRODUCTS
2.1 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site.
2.2 PERSONNEL PROTECTIVE EQUIPMENT: Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
2.3 BARRIERS: See Division 1, Section “Temporary Facilities and Controls” for Barriers.
PART 3 - PART 3 – EXECUTION
3.1 EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.2 ESCAPE ROUTES: Provide and maintain adequate escape routes at all times in accordance with the Life Safety Code (NFPA 101-91). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with escape routes.
3.3 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.4 SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
B. Conduct monthly safety meetings for all levels of supervision. Notify the CO and Contracting Officer Representative (COR) so that he/she may attend. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program. The CO/COR will enter the results of the meetings into Governments daily log.
3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat area will be designated by the contractor and approved by the CO. The hard hat area shall be posted by the Contractor in a manner satisfactory to the CO.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide six hard hats for use by visitors. Change liners before reissuing hats.
3.6 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF SECTION 01170
SECTION 01330
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.
B. See Division 1 Section "Quality Requirements" for submitting test and inspection reports and Delegated-Design Submittals.
C. See Division 1 Section "Closeout Procedures" for submitting warranties Project Record Documents, operation and maintenance manuals, and “As Built” Drawings.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Contracting Officer’s (CO's) responsive action.
B. Informational Submittals: Written information that does not require CO's approval.
Submittals may be rejected for not complying with requirements.
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. CO reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow ten (10) days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 10 days for processing each resubmittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately four (4) by five (5) inches on label or beside title block to record Contractor's review and approval markings and action taken by
CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. Other necessary identification.
D. Deviations: Encircle or otherwise identify deviations from the Contract Documents on submittals. Do not use a highlighter for marking products as it may fade or disappear if photocopied.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
PART 2 - part 2 – PRODUCTS
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
C. Shop Drawings: Prepare Project-specific information drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Division 1 Section "Quality Requirements."
B. Contractor's Construction Schedule: Prepare a schedule showing the projected timeline for completing the work for each Task Order within ten (10) days of award.
C. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
D. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location for compliance with requirements.
E. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements in Division 1 Section "Closeout Procedures."
F. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
3.2 SUBMITTAL LOG
A. Refer to specification sections for each item for details on requirements for submittals.
The submittals include, but are not limited to:
o Health and Safety Plan
Accident Prevention Plan Lead based paint management plan Asbestos containing materials management plan Hazardous waste management plan Rodents/Infestations management plan o Hazardous Waste Manifest o Construction Schedule o Quality Control Plan o Paint
Interior Exterior Metal Handrail o Roofing o Vinyl Lattice and Attachment System o Composite Decking and Handrail o Tankless Hot Water System o Poly-grid for ADA ramps o 3- pipe Metal Handrail o House 2 Bathroom Layout o Shower (House 3 & 4) o Toilets (Office, House 2, 3, & 4) o Bathroom Faucet (Office, House 2, 3, & 4) o Kitchen faucet (House 2, 3, & 4) o Kitchen Countertop (House 2, 3, 4) o FRP (porch on House 2) o Screen Doors (as needed) o Exterior Doors (as needed) o Lever Hardware o Windows (as needed) o VCT Flooring o Concrete Sealant o LED Light Fixtures o Solar PV
Panels Mounting System (Pole and Roof Mount) Battery System Inverter Battery storage system for House 2, 4 and Office o Smoke Detectors (10 yr)
END OF SECTION 01330
SECTION 01400
QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for Quality Assurance and Quality Control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specified tests, inspections, and related actions do not limit Contractor's quality-control procedures that facilitate compliance with the Contract Document requirements.
2. Requirements for Contractor to provide Quality-Control Services required by Contracting Officer (CO) or authorities having jurisdiction, are not limited by provisions of this Section.
C. See Divisions 2 through 16 Sections for specific test and inspection requirements.
1.2 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and ensure that proposed construction complies with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that completed construction complies with requirements. Services do not include contract enforcement activities performed by
CO.
C. Testing Agency: An entity engaged to perform specific tests, inspections, or both.
Testing laboratory shall mean the same as testing agency.
1.3 SUBMITTALS
A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
B. Reports: Prepare and submit certified written reports that include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
9. Test and inspection results and an interpretation of test results.
10. Ambient conditions at time of sample taking and testing and inspecting.
11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on retesting and reinspecting.
C. Permits, Licenses, and Certificates: For CO’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.
1.4 QUALITY ASSURANCE
A. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
B. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
C. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
D. Professional Engineer Qualifications: A Professional Engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this Project in material, design, and extent.
E. Testing Agency Qualifications: An agency with the experience and capability to conduct testing and inspecting indicated, as documented by ASTM E 548, and that specializes in types of tests and inspections to be performed.
1.5 QUALITY CONTROL
A. Contractor Responsibilities: Unless otherwise indicated, provide Quality-Control Services specified and required by authorities having jurisdiction.
1. Where Services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these Quality-Control Services.
a. Contractor shall not employ the same entity engaged by the Government, unless agreed to in writing by CO.
2. Notify testing agencies at least 48 hours in advance of time when Work that requires testing or inspecting will be performed.
3. Where Quality-Control Services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each Quality-Control Service.
4. Testing and inspecting requested by Contractor and not required by the Contract
Documents are Contractor's responsibility.
5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct special tests and inspections required by authorities having jurisdiction as the responsibility of Contractor.
1. Testing agency will notify CO and Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services.
2. Testing agency will submit a certified written report of each test, inspection, and similar Quality-Control Service to CO with copy to Contractor and to authorities having jurisdiction.
3. Testing agency will submit a final report of special tests and inspections at Substantial Completion, which includes a list of unresolved deficiencies.
4. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
5. Testing agency will retest and reinspect corrected work.
C. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing.
D. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide Quality-Control Services including retesting and reinspecting for construction that revised or replaced Work that failed to comply with requirements established by the Contract Documents.
E. Testing Agency Responsibilities: Cooperate with CO and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.
1. Notify CO and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.
2. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.
3. Submit a certified written report, in duplicate, of each test, inspection, and similar Quality-Control Service through Contractor.
4. Do not release, revoke, alter, or increase requirements of the Contract Documents or approve or accept any portion of the Work.
5. Do not perform any duties of Contractor.
F. Associated Services: Cooperate with agencies performing required tests, inspections, and similar Quality-Control Services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:
1. Access to the Work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.
4. Facilities for storage and field-curing of test samples.
5. Preliminary design mix proposed for use for material mixes that require control by testing agency.
6. Security and protection for samples and for testing and inspecting equipment at
Project site.
G. Coordination: Coordinate sequence of activities to accommodate required Quality- Assurance and Quality-Control Services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.
1. Schedule times for tests, inspections, obtaining samples, and similar activities.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.
1. Provide materials and comply with installation requirements specified in other
Sections of these Specifications. Restore patched areas and extend restoration into adjoining areas in a manner that eliminates evidence of patching.
2. Comply with the Contract Document requirements for Division 1 Section "Cutting and Patching."
B. Protect construction exposed by or for Quality-Control Service activities.
C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for Quality-Control Services.
END OF SECTION 01400
SECTION 01430
CONTRACTOR QUALITY CONTROL
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work of this section consists of preparing and executing a Quality Control Program.
1.2 SUBMITTALS
A. As specified in Division 1 Section “Submittal Procedure”.
B. Quality Control Plan:
1. At the time of the preconstruction conference, submit for approval a written
Contractor Quality Control (CQC) Plan.
2. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 (ten) days.
3. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified.
4. No change in the approved plan may be made without written concurrence by the Contracting Officer.
5. The plan shall include:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing Quality Control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
C. Contractor's Quality Control Daily Reports: Submit showing all inspections and tests on the first workday following the date covered by the report.
D. Test Reports:
1. Submit Daily Test Information Sheets with Quality Control Daily Reports.
2. Submit failing test results and proposed remedial actions within four (4) hours of noted deficiency.
3. Submit three copies of complete test results not later than three (3) calendar days after the test was performed.
E. Off-Site Inspection Reports: Submit prior to shipment.
F. If the CQC plan and Quality Control Daily Reports are not submitted as specified, the Contracting Officer may retain all payments until such time a plan is approved and implemented.
1.3 QUALITY ASSURANCE
A. General:
1. The quality of all work shall be the responsibility of the Contractor. Testing shall be the responsibility of an independent testing laboratory.
2. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
3. Quality Control Daily Reports shall be completed by the Quality Control Supervisor.
4. Test reports shall be completed by person performing the test.
5. The Contracting Officer may designate locations of tests.
1) Design and complexity of the project.
2) Location of the project.
3) Characteristics of area construction labor market.
4) Duration of project.
5) Cost and type of contract.
6) Amount and type of off-site fabrication.
B. Quality Control Staff:
1. The Contractor’s Quality Control Supervisor may also perform the duties of
Project Superintendent.
2. The Contractor’s Quality Control Supervisor shall be assigned no other duties.
3. The Contractor’s designated Quality Control Supervisor shall be on the project site whenever contract work is in progress.
4. The Contractor’s job supervisory staff may be used to assist the Quality Control
Supervisor, supplemented as necessary by additional certified testing technicians.
C. Testing Laboratory and Equipment:
1. Employ certified independent laboratories to perform sampling and testing. The testing laboratory organization shall be certified for the type of testing work to be done.
2. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards in accordance with
NBS requirements. Upon request, measuring and testing devices shall be made available for use by the Government for verification tests.
PART 2 - PART 2 - PRODUCTS (Not used).
PART 3 - PART 3 - EXECUTION
2.1 OFF-SITE CONTROL
A. Items that are fabricated or assembled off-site shall be inspected for Quality Control at the place of fabrication.
2.2 ON-SITE CONTROL
A. Notification:
1. Notify the Contracting Officer at least 48 hours in advance of the preparatory phase meeting.
2. Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.
B. Preparatory Phase: Perform before beginning each feature of work.
1. Review control submittal requirements with personnel directly responsible for the quality control work. As a minimum, the Contractor's Quality Control Supervisor and the foreman responsible for the feature of work shall be in attendance.
2. Review all applicable specifications sections and drawings related to the feature of work.
3. Ensure that copies of all referenced standards related to sampling, testing, and execution for the feature of work are available on site.
4. Ensure that provisions have been made for field control testing.
5. Examine the work area to ensure that all preliminary work has been completed.
6. Verify all field dimensions and advise the Contracting Officer of discrepancies with contract documents.
7. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.
8. Prepare a report on all preparatory phase activities and discussions. Attach report to Contractor's Quality Control Daily Report.
C. Initial Phase:
1. As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship.
2. Review control-testing procedures to ensure compliance with contract requirements.
3. Prepare a report on all initial phase activities and discussions. Attach report to Contractor's Quality Control Daily Report. Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.
D. Follow-Up Phase: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
E. Additional Preparatory and Initial Phases: Additional preparatory and initial phases may be required on the same feature of work for the following reasons:
1. Quality of on-going work is unacceptable.
2. Changes occur in the applicable quality control staff, on-site production supervision, or work crew.
3. Work on a particular feature of work is resumed after a substantial period of inactivity.
2.3 DOCUMENTATION
A. Maintain Quality Control Daily Reports and Daily Test Report Information Sheets (samples attached) of Quality Control activities and tests.
B. Quality Control Daily Reports may not be substituted for other written reports required under clauses of the contract such as Disputes, Differing Site Conditions, or Changes.
2.4 ENFORCEMENT
A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer.
END OF SECTION 01430
CONTRACTOR’S QUALITY CONTROL DAILY REPORT
REPORT NO.
SHEET 1 OF
PROJECT
CONTRACT NO.
DATE
FOREST
CONTRACTOR'S REPRESENTATIVE ON THE JOB
WEATHER (Rain, Snow, Cloudy, Windy, etc.)
RAINFALL
Inches
TEMPERATURE GROUND CONDITIONS (Dry, Damp, Wet, Frozen, etc.)
MAX.
MIN.
1. PRIME CONTRACTOR
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON JOB NO. UNITS HRS. WORKING
YES NO Comments
WORK PERFORMED BY PRIME CONTRACTOR:
MATERIALS DELIVERED OFFICIAL VISITORS TO SITE
2A. SUBCONTRACTOR, _____________________________________________: (If more than one subcontractor use copies of following page.)
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON JOB NO. UNITS HRS. WORKING
WORK PERFORMED BY SUBCONTRACTOR:
3. SPECIFIC INSPECTIONS: (Inspections performed, results, and corrective actions)
4. TESTING: 1 Check if any testing was performed today. (Complete and attach Test Report Information Sheets.)
Type and Location of Testing: ____________________________________________________________________________________
5. VERBAL INSTRUCTION RECEIVED FROM GOVERNMENT ON CONSTRUCTION DEFICIENCIES OR RE-TESTING REQUIRED:
6. REMARKS:
7. CERTIFICATION:
I certify that the above report is complete and correct and that I, or my authorized representative, have inspected all work performed this day by the prime contractor and each subcontractor and determined that all materials, equipment, and workmanship are in strict compliance with the plans and specifications except as may be noted above.
Contractor's Quality Control Representative
SUBCONTRACTOR WORK CONTINUED:
CONTRACT NO. REPORT NO. _______
SHEET ____ OF ____
2 SUBCONTRACTOR,
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON JOB NO.
UNITS
HRS. WORKING
2 SUBCONTRACTOR,
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON JOB NO.
UNITS
UNITS
UNITS
YES NO COMMENTS
DAILY TEST REPORT INFORMATION SHEET
CONTRACT NO. REPORT NO. _____________
SHEET _____ OF _________
1. Individual Making Inspection or Test:
2. Testing Laboratory; Name: Phone #:
Address:
3. Description of Work and Test Method:
4. Location of Samples and Tests or Inspections:
5. Specification Section:
6. Inspection or Test Data:
7. Test Results and Interpretations of Test Results:
8. Comments or Professional Opinion About Compliance of Inspected Work or Tested Work with contract Document Requirements:
9. Recommendations:
10. Corrective Actions Taken:
CERTIFICATION:
I certify that the above testing report is complete and correct and that all testing performed this day for this contract is in strict compliance with the plans and specifications except as noted above.
Signature of Inspector
SECTION 01500
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes requirements for temporary facilities and controls including temporary utilities, support facilities, and security and protection facilities.
B. See Division 1 Section "Execution Requirements" for progress cleaning requirements.
1.2 DEFINITIONS
A. Permanent Enclosure: As determined by Contracting Officer (CO), permanent or temporary roofing is complete, insulated, and weather tight; exterior walls are insulated and weather tight; and all openings are closed with permanent construction or substantial temporary closures.
1.3 USE CHARGES
A. General: Cost or use charges for temporary facilities are not chargeable to Government
B. Water Service: Use water from Government’s existing water system without metering and without payment of use charges.
1.4 QUALITY ASSURANCE
A. Standards: Comply with ANSI A10.6, NECA's "Temporary Electrical Facilities," and
NFPA 241.
1. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with
NFPA 70.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.
1.5 PROJECT CONDITIONS
A. Temporary Utilities: At earliest feasible time, when acceptable to Government, change over from use of temporary service to use of permanent service.
1. Temporary Use of Permanent Facilities: Installer of each permanent service shall assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Government acceptance, regardless of previously assigned responsibilities.
B. Conditions of Use: The following conditions apply to use of temporary services and facilities by all parties engaged in the Work:
1. Keep temporary services and facilities clean and neat.
2. Relocate temporary services and facilities as required by progress of the Work.
PART 2 - part 2 – PRODUCTS
2.1 MATERIALS
A. General: Provide new materials. Undamaged, previously used materials in serviceable condition may be used if approved by CO. Provide materials suitable for use intended.
B. Portable Chain-Link Fencing: Minimum 2-inch (50-mm) 9-gage, galvanized steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts, with 1-5/8-inch- (42-mm-) OD top and bottom rails. Provide galvanized steel bases for supporting posts.
C. Wood Enclosure Fence: Plywood, 6 feet high, framed with four 2-by-4-inch (50-by- 100-mm) rails, with preservative-treated wood posts spaced not more than 8 feet (2.4
m) apart.
D. Lumber and Plywood: Comply with requirements in Division 6 Section "Rough Carpentry."
E. Gypsum Board: ASTM C 36, minimum 1/2 inch (12.7 mm) thick by 48 inches (1219
mm) wide by maximum available lengths, regular-type panels with tapered edges.
F. Insulation: Unfaced mineral-fiber blanket, manufactured from glass, slag wool, or rock wool; with maximum flame-spread and smoke-developed indices of 25 and 50, respectively.
G. Water: Potable.
2.2 EQUIPMENT
A. Field Offices: Prefabricated, mobile units, or job-built construction with lockable entrances, operable windows, and serviceable finishes; heated and air conditioned; on foundations adequate for normal loading.
B. Fire Extinguishers: Hand carried, portable, UL rated. Provide class and extinguishing agent as indicated or a combination of extinguishers of NFPA-recommended classes for exposures.
1. Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and size required by location and class of fire exposure.
C. Self-Contained Toilet Units: Single-occupant units of chemical, aerated recirculation, or combustion type; vented; fully enclosed with a glass-fiber-reinforced polyester shell or similar nonabsorbent material.
D. Drinking-Water Fixtures: Containerized, tap-dispenser, bottled-water, drinking-water units, including paper cup supply.
E. Heating Equipment: Unless CO authorizes use of permanent heating system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control.
1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.
2. Heating Units: Listed and labeled, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use for type of fuel being consumed.
F. Electrical Outlets: Properly configured, NEMA-polarized outlets to prevent insertion of 110- to 120-V plugs into higher-voltage outlets; equipped with ground-fault circuit interrupters, reset button, and pilot light.
G. Power Distribution System Circuits: Where permitted and overhead and exposed for surveillance, wiring circuits not exceeding 125-V ac, 20-A rating, and lighting circuits may be nonmetallic sheathed cable.
PART 3 - PART 3 – EXECUTION
3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required.
B. Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.
C. Provide field offices, storage trailers, and other support facilities as necessary for the Work.
D. Collect waste daily and, when containers are full, legally dispose of waste off-site.
1. Handle hazardous, dangerous, or unsanitary waste materials in separate closed waste containers. Dispose of material according to applicable laws and regulations.
2. Recycling of materials is encouraged, but not required.
E. Provide temporary enclosures for protection of construction and workers from inclement weather and for containment of heat.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Engage appropriate local utility company to install temporary service or connect to existing service. Where utility company provides only part of the service, provide the remainder with matching, compatible materials and equipment. Comply with utility company recommendations.
1. Arrange with utility company, CO, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.
2. Provide adequate capacity at each stage of construction. Before temporary utility is available, provide trucked-in services.
3. Obtain easements to bring temporary utilities to Project site where Government easements cannot be used for that purpose.
B. Water Service: Install water service and distribution piping…