Ground Source Heat Pump AG.docx

DOCX document 11 KB Posted

Attached to
RECOVERY Ground Source Heat Pump Powel Ranger District Office
Solicitation number
AG-82B1-S-10-0397
Issued by

About this file

Answer to Questions

View the file

Other files

File Type Posted
Amendment 2.pdf PDF
Pre-BidGround Source Heat Pump.docx DOCX document
01.pdf PDF
F-Title1.pdf PDF
F-Powell-site_plan2.pdf PDF
F-Powell_mechplans4.pdf PDF
F-Powell_mechplans3.pdf PDF
Solicitation.doc DOC document
f-OKLA university-Standards2009s.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ground Source Heat Pump AG-82B1-S-10-0397

Your only allowing about 5 weeks to complete the project. Is there any chance of extensions? What if the weather closed in? The equipment for this job could take up to 1 ½ weeks to receive and could also cut into install time.

The time can be extended as the contract is being solicited later in the year than we anticipated. However, since this is a working building utility interruptions should be kept to a minimum during the cold time of year.

Did you want to replace the 5 electric furnaces with 5 GSHP’s? Just attached to existing ductwork.

They are to propose the new system utilizing GSHP technology. However, we recognize that for winter heating auxiliary heat will likely be needed due to harsh climate. I think, we thought they would use the existing ductwork with minimal changes as necessary to connect to other ducts if need be.

And finally. Is there a person to contact at Powell for a walk through? Doug Hunt or Susan Graves can be contacted for a walk through. I guess we could have a prebid meeting on the 8th at 1030. It seems like we have been having trouble with the individual walk throughs.