02111_SEPTICTANKCLOSURE.doc

DOC document 29 KB Posted

Attached to
Mingus Work Center and Fire Center Rappel Tower demolition
Solicitation number
AG-8191-S-16-0005
Issued by

View the file

Other files

File Type Posted
Pre-bid_Sign-in_Sheet.pdf PDF
Mingus_Roofing_Asbestos_Removal_2005_1117_Final_Report.pdf PDF
Amendment_0001.pdf PDF
02221_BUILDINGDEMOLITION.doc DOC document
01010_SUMMARYOFWORK.doc DOC document
02230_SITECLEARING.doc DOC document
Amended_AG-8191-S-16-0005.docx DOCX document
FCRappelTowerPlans.pdf PDF
02221_BUILDINGDEMOLITION.doc DOC document
WD_96-0223.docx DOCX document
AG-8191-S-16-0005.pdf PDF
Photos.pdf PDF
01010_SUMMARYOFWORK.doc DOC document
028200_ASBESTOSREMEDIATION.doc DOC document
MingusWC_CrewQtrs_1993asbestosreport.pdf PDF
02230_SITECLEARING.doc DOC document
Prescott_Fire_Plan.doc DOC document
Past_Performance_Questionnaire.docx DOCX document
01500_CONST_FACILITIES_TEMP_CONTROLS.doc DOC document
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Forest Service Prescott National Forest Project Specifications Mingus Work Center and Fire Center Rappel Tower Demolition

SECTION 02111

SEPTIC TANK CLOSURE

PART 1 – GENERAL

1.1 sUMMARY

A. Includes removal, disposal, and backfilling of existing or abandoned septic tank, and utilities to the extent shown on the drawings. Refer to ADEQ A.R.S. R18-9-A309(D) for closure requirements. The internet link to the regulations is referenced in the STATEMENT OF WORK.

PART 2 – PRODUCTS

NOT APPLICABLE

PART 3 – EXECUTION

1.2 GENERAL

A. Topsoil stripping and storage, if required, shall comply with the applicable specification.

B. The abandoned septic tank shall be pumped prior to closure. Pumped liquid waste and septic tanks, or parts of them, shall be disposed of the same day as pumped or removed in accordance with location health requirements.

C. Backfill for removed items may be excess material from other excavation or borrow from an approved source.

1. Backfill shall be brought up in 12-inch compacted layers.

2. Compaction shall be by mechanical tampers, with at least three passes over the entire surface.

3. Maximum size of rock in backfill shall be 8 inches.

4. Backfill shall be compacted and rounded 6 inches above the natural ground.

D. When topsoil replacement is required, backfill and compaction shall comply with SECTION 02300, except the backfill shall terminate 6 inches below the natural ground. Placement of topsoil, when required, shall comply with the applicable specifications.

E. Excessive settlement or other evidence of improper backfill shall be corrected by reopening the excavation to the depth required for proper refilling and compaction.

END OF SECTION 02111