Amend_1.pdf
PDF 377 KB Posted
- Attached to
- BA-27c Barataria Landbridge CU#7 and #8
- Solicitation number
- AG-7217-S-15-0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| Amend_3_-_Final.pdf | ||
| Amend_2.pdf | ||
| LA2.txt | TXT text file | |
| SF1442_Solicitation_Package.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
AG-7217-S-15-0001
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
NRCS-LA-127217
ALEXANDRIA LA 71302
3737 GOVERNMENT ST.
USDA-NRCS-LOUISIANA STATE OFFICE
02/13/2015000001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/27/2015
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
CWPPRA - BA27c Barataria Basin Landbridge Project CU #7 and 8, MIPR W42HEM11119946 and
W42HEM11119947, located in Lafourche Parish, Louisiana.
The purpose of this amendment is to provide the Questions & Answers (Q&A's) and Sign In
Sheet from the site showing.
Q1. The riprap material has to be brought in by barge? It can't be by dump trucks and dump trailers?
A1. The NRCS does not dictate the contractor's means and methods to perform the work or how material is to be brought to the site; however, the only access to the job site is by water/marine access.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
DENISE A. BURRUSS
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
AG-7217-S-15-0001/000001
Q2. Will the rock be accepted in segments?
A2. No, the rock will not be accepted until all of the rock has been placed for the entire length of the job and upon verification it is to the lines and grades established in the construction specifications and drawings.
Q3. If a major hurricane occurs and fills in the access channel will the contractor be reimbursed for having to re-excavate the area?
A3. No, the contractor is responsible for the job site until final acceptance has been made.
Q4. Under the rockfill specification it states
"orange peal or clamshell buckets shall not be used to place rock riprap" Will the NRCS consider the use of this equipment to place the rock?
A4. No, the specification will not be changed and the contractor will need to bid the project as per the specification.
Q5. Temporary signs - Due to the soils in this area, it is unknown where the soil will spread during spoil placement as part of the excavation operations. How is the contractor to ensure the signs are installed before the hazard is present as is required in the specification?
A5. Adjustments may need to be made in the field due to this occurrence; therefore, final temporary sign placement will be made based on these conditions; however, the contractor needs to be ready to set these signs as they are performing the construction that creates these hazards.
Q6. Will spoil be allowed to be placed on top of the Chevron pipeline depicted on Sheet 10?
A6. No, it will be placed away from the pipeline or in another location in or near the vicinity of the pipelines; however, it is not anticipated that there will be a large amount of material in this area.
Q7. The MH and ML water elevations do not appear to be shown, will these be provided?
A7. The MH and ML water elevations are shown on
Sheet 23.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
AG-7217-S-15-0001/000001
Q8. Will the contractor be allowed to spoil on both sides of the perpendicular access channel on
Sheet 5?
A8. No, the spoil will be placed on the west side of the perpendicular access channel as shown until we reach the transition and then the contractor will be allowed to place material on both sides.
Q9. What does the gap on Sheet 8 represent?
Does the pipeline run through the access channel and will they be able to place spoil on top of line?
A9. No they will not be allowed to place spoil on top of line. Field adjustments may need to be made for spoil placement in other areas depending on the amount of material.
Q10. Will the land based construction require geotextile placement prior to placement of rock riprap?
A10. Yes, the land based construction will require geotextile to be placed prior to placement of rock riprap. The typical section shown on the plans will be revised and issued in a subsequent amendment.
Q11. Will the contractors be able to utilize the
Clovelly Boat Launch?
A11. Contractors wishing to utilize the Clovelly
Boat Launch must contact Randy Moertle at (985)
856-3630 (cell) or (985) 532-6388 (work) to discuss these arrangements.
Q12. When is the cutoff date for questions?
A12. February 12, 2015 at 4:00 p.m.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .