863_drawings.pdf
PDF 3 MB Posted
- Attached to
- Sand Creek Surfacing Rock Replacement
- Solicitation number
- AG-67T0-S-15-0044
About this file
Drawings
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_1.doc | DOC document | |
| Amend._1_Note_replacement.pdf | ||
| SOL.docx | DOCX document | |
| Instruction_Sheet.doc | DOC document | |
| SF-1442.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MP/Station Units
TONS
Grading Spec.
Feature Lengt h in Feet
DESCRIPTION OF WORK 863.1
FDR 863
79+20 B.O.P. Sta 79+20
BEGIN RECONDITIONING - SPEC. 303(01) TO E.O.P.
Rebuild Ditches and Clean All Culverts and cattleguards as needed Begin clearing both sides of road to 205+00 Clearing shall remove all small trees and brush up to 6 inches in diameter. Larger remaining trees will have all overhanging branches trimmed flush to a height of 15 feet above finished road bed elevation.
Maximun stump height for larger trees shall be 8 inches and small trees and brush 2 inches.However, remove stumps of any tree cleared if the is within the road travelway,shoulder, turnouts.curve widening, ditch slope, or is in a location where a vehicle tire could impact the stump.
Clearing shall be a minimun of 6 feet from each shoulder or top of cut slope or toe of fill whichever is the further distance.All costs for this work are included in item 303(18)
4,200 J BEGIN AGGR Grading J 4" COMPACTED DEPTH TO EOP
124+80 CMP Install 18"x36 ft culvert
130+00 680 pit run Begin pit run taper to 20 " @ sta 131+50
131+50 Begin 20" depth pit run
132+50 CMP Install 24"x38ft Culvert
133+00 Begin pit run taper down to sta 134+50
205+00 End of Project
OPTIONAL BID ITEM
RECONDITIONING- SPEC 303(01) 0 to 2.5 Mi as awarded
Begin clearing clearing both sides of road to be marked by Engineer Clearing shall remove all small trees and brush up to 6 inches in diameter. Larger remaining trees will have all overhanging branches trimmed flush to a height of 15 feet above finished road bed elevation.
Maximun stump height for larger trees shall be 8 inches and small trees and brush 2 inches.However, remove stumps of any tree cleared if the is within the road travelway,shoulder, turnouts.curve widening, ditch slope, or is in a location where a vehicle tire could impact the stump.
Clearing shall be a minimun of 6 feet from each shoulder or top of cut slope or toe of fill whichever is the further distance.All costs for this work are included in item 303(18) (Note - optional work will be awarded before base contract is complete.)
0 to 4550 J Aggr Grading J 4" compacted depth stations to be marked by Engineer
DESCRIPTION OF WORK Sand creek surfacing rock replacment Page 11 of 11
MP/Station Units
TONS
Grading Spec.
Feature Lengt h in Feet
DESCRIPTION OF WORK 863.1
DESCRIPTION OF WORK Sand creek surfacing rock replacment Page 11 of 11
| title sheet |
| Index to pages (2) |
| Forest location map (3) |
| FDR 863 Surfacing Layout (4) |
| Project Notes (5).1pdf |
| Pay item notes (6) |
| 156-01_const_signs Model (7) |
| Temporary traffic control typical (8) |
| Culvert bedding details typical (9) |
| Typical surfacing sections (10) |
| desc_of_work.pdf (11) |