Amendment_03_-_Attachment_01_-_Bid_Item_1_-_SOI.pdf

PDF 57 KB Posted

Attached to
Road Reconstruction - Eleven Point Ranger District - Mark Twain
Solicitation number
AG-64R4-S-16-0025-BR
Issued by

About this file

Attachment 01 - Bid Item 1 - SOI

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE OF ITEMS

Guardian– Bid Item 1, Line Item 1

FR 3261 – Little Pike Creek – Roadway Reconditioning/Reconstruction

Eleven Point District

Mark Twain National Forest Shannon County, Misssouri

ITEM PAY EST. UNIT TOTAL

NO. DESCRIPTION UNIT QTY. PRICE PRICE_

20101 Clearing and Grubbing Acre 0.59 ________ ________

20402 Roadway Excavation, Compaction Method (a), Finishing Method (a) Mile 0.76 ________ ________

20420 Drainage Excavation, Type A-A Outlet Ditch Each 11 ________ ________

20420 Drainage Excavation, Type B-B Outlet Ditch Each 15 ________ ________

20420 Drainage Excavation, Type A Dip Each 1 ________ ________

20420 Drainage Excavation, Type B Dip Each 1 ________ ________

30321 Roadway Reconditioning, Compaction Method A Mile 2.77 ________ ________

30802 Crushed aggregate grading: 1” Clean, Compaction Method 1 Ton 1522 ________ ________

30802 Crushed aggregate grading: 4”- 6” Clean, Compaction Method 1 Ton 20 ________ ________

TOTAL ________

Guardian– Bid Item 1, Line Item 1

FR 3261 – Little Pike Creek – Roadway Reconditioning/Reconstruction

B-2 Note: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Mobilization costs are INCIDENTAL to all roads – no extra payments shall be made fo bond premiums.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

Mowing and Limbing as well as Seeding shall be considered incidental to pay item 20101, Clearing and Grubbing and/or pay item 30321, Roadway Reconditioning.

Compaction Method 1 shall be for aggregate placement compaction according to FS Supplemental Specification 308.05(a).

Surface course blading may be required to mix subgrade and /or smooth surface course. Surface blading will be considered incidental to pay item 30321, Roadway reconditioning.

All items are design quantities: no payment will be made for variations within +/-15% of the design quantity, without a CO approved modification.

Guardian – Bid Item 1, Line Item 1

FR 3261 C – Windes Creek – Roadway Reconditioning

NO. DESCRIPTION UNIT QTY. PRICE PRICE

30321 Roadway Reconditioning, Compaction Method A Mile 1.28 ________ ________

30802 Crushed aggregate grading: 1” Clean, Compaction Method 1 Ton 532 ________ ________

B-2 Note: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Mobilization costs are INCIDENTAL to all roads – no extra payments shall be made fo bond premiums.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

Mowing and Limbing as well as Seeding shall be considered incidental to pay item 20101, Clearing and Grubbing and/or pay item 30321, Roadway Reconditioning.

Compaction Method 1 shall be for aggregate placement compaction according to FS Supplemental Specification 308.05(a).

Surface course blading may be required to mix subgrade and /or smooth surface course. Surface blading will be considered incidental to pay item 30321, Roadway reconditioning.

All items are design quantities: no payment will be made for variations within +/-15% of the design quantity, without a

FR 3261 F – Spur F – Roadway Reconditioning

Carter and Shannon Counties, Misssouri

Compaction Method A Mile 1.06 _______ ________

Compaction Method 1 Ton 450 ________ ________

B-2 Note: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Mobilization costs are INCIDENTAL to all roads – no extra payments shall be made fo bond premiums.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

Mowing and Limbing as well as Seeding shall be considered incidental to pay item 20101, Clearing and Grubbing and/or pay item 30321, Roadway Reconditioning.

Compaction Method 1 shall be for aggregate placement compaction according to FS Supplemental Specification 308.05(a).

Surface course blading may be required to mix subgrade and /or smooth surface course. Surface blading will be considered incidental to pay item 30321, Roadway reconditioning.

All items are design quantities: no payment will be made for variations within +/-15% of the design quantity, without a

FR 4097 – Patty Hollow– Roadway Reconditioning

Compaction Method A Mile 2.63 ________ ________

Compaction Method 1 Ton 532 ________ ________

B-2 Note: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Mobilization costs are INCIDENTAL to all roads – no extra payments shall be made fo bond premiums.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

Mowing and Limbing as well as Seeding shall be considered incidental to pay item 20101, Clearing and Grubbing and/or pay item 30321, Roadway Reconditioning.

Compaction Method 1 shall be for aggregate placement compaction according to FS Supplemental Specification 308.05(a).

Surface course blading may be required to mix subgrade and /or smooth surface course. Surface blading will be considered incidental to pay item 30321, Roadway reconditioning.

All items are design quantities: no payment will be made for variations within +/-15% of the design quantity, without a

FR 4097 A – Patty Hollow Spur – Roadway Reconstruction

20101 Clearing and Grubbing Acre 0.20 ________ ________

20402 Roadway Excavation, Compaction Method (a), Finishing Method (a) Mile 0.30 ________ ________

20420 Drainage Excavation, Type A-A Outlet Ditch Each 4 ________ ________

20420 Drainage Excavation, Type B-B Outlet Ditch Each 5 ________ ________

20420 Drainage Excavation, Type B Dip Each 1 ________ ________

30802 Crushed aggregate grading: 1” Clean, Compaction Method 1 Ton 128 ________ ________

30802 Crushed aggregate grading: 4”- 6” Clean, Compaction Method 1 Ton 10 ________ ________

B-2 Note: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Mobilization costs are INCIDENTAL to all roads – no extra payments shall be made fo bond premiums.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

Mowing and Limbing as well as Seeding shall be considered incidental to pay item 20101, Clearing and Grubbing and/or pay item 30321, Roadway Reconditioning.

Compaction Method 1 shall be for aggregate placement compaction according to FS Supplemental Specification 308.05(a).

Surface course blading may be required to mix subgrade and /or smooth surface course. Surface blading will be considered incidental to pay item 30321, Roadway reconditioning.

All items are design quantities: no payment will be made for variations within +/-15% of the design quantity, without a CO approved modification.

FR 4261 – Grassy Pond – Roadway Reconditioning

30321 Roadway Reconditioning, Compaction Method A Mile 0.70 _________ ________

Compaction Method 1 Ton 294 ________ ________

B-2 Note: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Mobilization costs are INCIDENTAL to all roads – no extra payments shall be made fo bond premiums.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

Mowing and Limbing as well as Seeding shall be considered incidental to pay item 20101, Clearing and Grubbing and/or pay item 30321, Roadway Reconditioning.

Compaction Method 1 shall be for aggregate placement compaction according to FS Supplemental Specification 308.05(a).

Surface course blading may be required to mix subgrade and /or smooth surface course. Surface blading will be considered incidental to pay item 30321, Roadway reconditioning.

All items are design quantities: no payment will be made for variations within +/-15% of the design quantity, without a

Tram – Bid Item 1, Line Item 2

FR 4248 – Bull Camp Hollow – Reconstruction

Oregon County, Misssouri

20101 Clearing and Grubbing Acre 0.55 _________ ___________

20402 Roadway Excavation, Compaction Method (a), Finishing Method (a) Mile 0.90 __________ ___________

20420 Drainage Excavation, Type A-A Outlet Ditches Each 20 __________ ___________

20420 Drainage Excavation, Type B-B Outlet Ditches Each 9 __________ ___________

30802 Crushed aggregate grading: 1” Clean, Compaction Method 1 Ton 480 __________ ___________

30802 Crushed aggregate grading: 4”- 6” Clean, Compaction Method 1 Ton 54 __________ __________

TOTAL ____________

B-2 Note: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Mobilization costs are INCIDENTAL to all roads – no extra payments shall be made fo bond premiums.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

Seeding shall be considered incidental to pay item 30321, Roadway reconditioning.

Mowing and Limbing as well as Seeding shall be considered incidental to pay item 20101, Clearing and Grubbing and/or pay item 30321, Roadway Reconditioning, Compaction Method 1 shall be for aggregate placement compaction according to FS Supplemental Specification 308.05(a).

Surface course blading may be required to mix subgrade and /or smooth surface course. Surface blading will be considered incidental to pay item 30321, Roadway reconditioning.

All items are design quantities: no payment will be made for variations within +/-15% of the design quantity, without a

Tram – Bid Item 1, Line Item 2

FR 4249 – Edmundson Pond – Roadway Reconditioning

Shannon, Misssouri

30321 Roadway Reconditioning, Compaction Method A Mile 1.39 ________ _________

30802 Crushed Aggregate Grading: 1” Clean, Compaction Method 1 Ton 800 ________ _________

TOTAL _________

B-2 Note: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Mobilization costs are INCIDENTAL to all roads – no extra payments shall be made fo bond premiums.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

Seeding shall be considered incidental to pay item 30321, Roadway reconditioning.

Mowing and Limbing as well as Seeding shall be considered incidental to pay item 20101, Clearing and Grubbing and/or pay item 30321, Roadway Reconditioning, Compaction Method 1 shall be for aggregate placement compaction according to FS Supplemental Specification 308.05(a).

Surface course blading may be required to mix subgrade and /or smooth surface course. Surface blading will be considered incidental to pay item 30321, Roadway reconditioning.

All items are design quantities: no payment will be made for variations within +/-15% of the design quantity, without a

***Note: Bid Item 1, Line Item 2 Tram will only be funded if the Government has funds available after funding all other line/bid items.

Bid Item 1, Line Item 1 Guardian - SOI
Bid Item 1, Line Item 2 Optional - Tram - SOI
SCHEDULE OF ITEMS
***Note: Bid Item 1, Line Item 2 Tram will only be funded if the Government has funds available after funding all other line/bid items.

File details come from the government source that posted it. Updated .