Sheet1

8-June-2016
Solicitation #AG-569R-S-16-0025
FR 311 Culvert Replacement -
UNC Brunet River
Chequamegon-Nicolet National Forest
Section B - Supplies or Services and Price/Cost
Schedule of Items
FR 311, UNT Brunet
Great Divie Ranger District-Sawyer County
Item / DescriptionQuantityUnitUnit PriceTotal Cost
151011.00LS
Mobilization$0.00
157131.00LS
Soil Erosion and Pollution Control$0.00
$0.00
203041.00LS
Removal Existing Culverts$0.00
Disposal Method 'E'
2041130.00CY
Embankment Construction, Compaction
Method 'B', Finishing Method 'A'
20415400.00CY
Unsuitable Excavation
20801370.00CY
Structure Excavation$0.00
$0.00
208051.00L.S.
Coffer Dams
2510140.00CY
Placed RipRap, Class 4$0.00
30111300.00CY
Aggregate Surface Course, Grade G or$0.00
equivalent, Compaction method B$0.00
303291.00L.S.
Road Reconditioning
6020280.00LF
21x15 Galvanized Arch Pipe
$0.00
6020548.00LF
10'x4' Concrete Box Culvert
w/ 2:1 partial end bevel
(Includes Crane to Set Sections)
60513
Geogrid Material, TriAx TX14070.00SY
Or Equivalent
625031.00LS
Seeding (Mulching and Fertilization)
Dry Method
6290140.00SY
Erosion Control Mat
Type 'ENS2' or Equivalent
635011.00LS
Temporary Traffic Control
OPTIONAL BID ITEMS
6020280.00LF
21x15 Galvanized Arch Pipe
PROJECT TOTAL

Sheet2

15101 1.00 L.S. 8,000.00 8,000.00
Mobilization
15102 1.00 L.S. 1,000.00 1,000.00
Bond Premium
20304 1.00 L.S. 7,000.00 7,000.00
Removal of Existing Structures
(asphalt and culverts)
20801 1.00 L.S. 15,000.00 15,000.00
Structure Excavation
40101 80.00 TON 100.00 8,000.00
Superpave Hot Asphalt concrete
pavement
Type:E1
41501 1.00 L.S. 2,000.00 2,000.00
Paving Geotextile
55101 400.00 L.F. 18.00 7,200.00
Treated Timber Piles,
CCA Preservative,
Driven
55109 630.00 L.F. 13.00 8,190.00
Treated Timber Piles,
CCA Preservative,
Furnished
57101 1.00 L.S. 70,000.00 70,000.00
Prefabricated bridge superstructure-
Design, fabricate, deliver, and install
57106 1.00 L.S. 20,000.00 20,000.00
Bridge Substructure,
(Bridge Abutments System)
(Excluding Pilings)
Wed. March 31, 2004
Road Estimate And Payments System
*** R E A P S *** Chequamegon-Nicolet NF
PW ENGINEERING PROJECT ESTIMATE
Elvoy Creek/FR 2193 Bridge
ROAD NUMBER – 2193 Sub Unit – Eagle River/Florence
County - Forest
Terrain - Flat
Item / Description Quantity Unit UNIT PRICE TOTAL COST
================== ======== ==== ========== ============
62501 1.00 L.S. 500.00 500.00
Seeding (Mulching and Fertilization)
Dry Method
63501 1.00 L.S. 2,000.00 2,000.00
Temporary Traffic Control

Sheet3

Contractor’s _______________________________

Name & Address: _______________________________

Phone Number: _______________________________

DUNS # _______________________________

e-mail Address: _______________________________

Please complete and submit SF-1442 Form, Section B & K and the experience questionnaire to the address in block 8 of the SF 1442 form by 1:00 PM EST on June 17, 2016. Documents may be e-mailed to acaliguri@fs.fed.us or mailed to:

USDA Forest Service

LSAT Contracting, Solicitation #AG-569R-S-16-0024

Attn: Annette

820 Rains Drive

Gladstone, MI 49837

File details come from the government source that posted it. Updated .