Amendment No. 1 - OPENING EXTENDED TO 07/20/2009
Text of this file
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGE(S)
1 | 2
2. AMENDMENT NO.
One (1)
3. EFFECTIVE DATE
07/06/2009
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)
6. ISSUED BY:
USDA, Forest Service, Regions 8 and 9 Western Operations Center, Acquisition Management 401 Fairgrounds Road Rolla, MO 65401
7. ADMINISTERED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
X
9A. AMENDMENT OF SOLICITATION NO.
AG-447U-S-09-0041AY
9B. DATED (SEE ITEM 11): 06/26/2009
10A. MODIFICATION OF CONTRACT/ORDER
FACILITY CODE:
10B. DATED (SEE ITEM 13):
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[ XX ] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [XX] is extended, [ ] is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning ONE (1) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) E. IMPORTANT: Contractor [ ] is not, [ XX ] is required to sign this document and return _1_ copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Answers to questions asked at the pre-proposal meeting are attached.
THE DATE FOR RECEIPT OF PROPOSALS HAS BEEN EXTENDED TO 07/20/2009, CLOSE OF
BUSINESS LOCAL TIME AT PLACE OF OPENING.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA
BY
( Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 STANDARD FORM 30 (REV. 10-83)
AMENDMENT NO. 1
SOLICITATION NO. AG-447U-S-09-0041AY
| 1. | What type of shingles? |
| 3-tab, 25-year as specified in the solicitation. | |
| 2. | What tpe of felt? |
| 30-lb. as specified in the solicitation. | |
| 3. | Is soffit to be installed? |
| No, only fascia as specified in the solicitation. | |
| 4. | Have the buildings been tested for lead paint? |
| Yes. Results and specifications are attached as a separate document to this amendment. | |
| 5. | Do we paint only the fascia that’s being replaced or all exposed? |
All exposed fascia and roof decking/soffit will be painted in accordance with the requirements shown in the attached results of lead testing for these buildings.
| 6. | Are ridge vents to be installed? |
| Install Tamco Cool Ridge on all three roofs according to manufacturer’s written directions. | |
| 7. | Does the chimney on Garage No. 1 stay? |
| Yes. | |
| 8. | Do the vents on Garage No. 2 get replaced? |
| Yes, remove and install with Tamco Cool Ridge vent. | |
| 9. | Is the flashing to be surface mounted or cut in? |
| Surface mount flashing for chimney. | |
| 10. | Where is the closest dump site? |
Possible dump sites are Hartville, Lebanon, West Plains, Cuba and St. Robert. It will be the contractor’s responsibility to verify dump site and to obtain any permits necessary for dumping.
Other files
| File | Type | Posted |
|---|---|---|
| Roby Tower Lead Report.pdf | ||
| 09.0041.Roby.Roofing.Offerors.Copy.doc | DOC document | |
| 09.0041.Roby.Roofing.Proposal.Copy.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .