SF 1442 Continuation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Monday Crk Ford Paddle Creek Replacement.docx | DOCX document | |
| Amend_01.pdf | ||
| Attachment 10001.pdf | ||
| DBA_WD.pdf | ||
| Drawings_2-17-2010.pdf | ||
| Monday Creek Specs_03_30_2010.PDF | ||
| SF 1442.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOL NO: AG-4419-S-10-0441
Unit: 0914
PROJ NAME: Monday Creek Ford Replacement
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
U.S.F.S. WAYNE NATIONAL FOREST
JOBS TO IMPROVE OHIO FISH PASSAGE - TIER 2 MONDAY CREEK FORD REPLACEMENT
WARD TOWNSHIP, HOCKING COUNTY, OHIO - CIM-0914-18EW-230-0914-05
SCHEDULE OF ITEMS
Method of
Item Description Measurement Unit Price Quantity Unit Items Total
1 Mobilization LSQ 1 Each
2 Demolition LSQ 1 Each
3 Reinforced Concrete Abutments CQ 56 Cu. Yd.
4 Pre-Fab Steel Bridge with 2x4 Vet. Plank Floor LSQ 1 Each
5 Fill for Approaches CQ 712 Cu. Yd.
6 "B" Rock Riprap AQ 326 Tons
7 Guardrail - Approaches to Bridge CQ 180 LF
8 Guradrail - Bridge CQ 100 LF
9 Type A Guardrail Assembly AQ 4 EA
10 ODOT 304 Limestone Road Surface AQ 42 Tons
11 Seeding and Mulching AQ 2 Acres
OPTIONAL ITEM 1 Temporary Bridge/Trail LSQ 1 Each
TOTAL FOR PROJECT
SUB-TOTAL ITEMS 1 THRU 12
SUB-TOTAL OPTIONAL ITEM 1
109.01 Me thods of Me asureme nt
One of the following methods of measurement for determining final payment is DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM:
a.) Contract Quantitie s (CQ). These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:
d.) Ve hicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.
e.) Lump Sum Quantitie s (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the unit of work.
(1) Changes in the work authorized by the CO.
(2) A determination by the CO that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.
(3) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.
b.) Stake d Quantities (SQ). These quantities are determined from staked measurements prior to construction.
c.) Actual Quantitie s (AQ). These quantities are determined from measurements of completed work.
PROJ NAME: Monday Creek Ford Replacement
"NOTE: Please be sure to certify in ORCA for the NAICS specified on the contract form or elsewhere in this solicitation."
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Contract :
Work will consist of the following items: Demolition of reinforced concrete and CMP located within Monday Creek streambed, and disposal of items; construction of Reinforced Concrete Abutment; supply of prefabricated Steel Bridge; excavation and placement of Fill Material; Guardrail construction; Rock Riprap installation; Limestone Road Surface and Seeding and Mulching. Movement and placement of temporary bridge and construction of temporary ATV trail. Reinforced Concrete Abutment; supply of prefabricated Steel Bridge; excavation and placement of Fill Material; Guardrail construction; Rock Riprap installation; Limestone Road Surface and Seeding and Mulching.
Project Location:
Hocking County, Ohio, Ward Township access off of SR78 and Twp. Rd. 279. Site location maps are shown on Title page of project drawings.
Price Range
The Government's estimate is:
between $100,000 and $250,000.
AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION D--PACKAGING AND MARKING
{For this Solicitation, there are NO clauses in this Section}
SECTION E--INSPECTION AND ACCEPTANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
52.242-14 Suspension of Work (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within _10_ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than _90 calendar days after receipt of Notice To
Proceed. The time stated for completion shall include final cleanup of the premises.
SECTION G--CONTRACT ADMINISTRATION DATA
PROJ NAME: Monday Creek Ford Replacement
SECTION H--SPECIAL CONTRACT REQUIREMENTS
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
52.203-15 Whistleblower Protections Under the American Recovery and Reinvestment Act of 52.204-11 American Recovery and Reinvestment Act-reporting Requirements (Mar 2009) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (MAY 2008)
(Applicable if contract exceeds $30,000) 52.215-2 Audit and Records-Negotiation w/Alt I (Mar 2009) 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (JULY
2005).
52.222-3 Convict Labor (JUN 2003) 52.222-6 Davis-Bacon Act (JUL 2005) 52.222-7 Withholding of Funds (FEB 1988) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (FEB 1988) 52.222-20 Walsh-Healy Public Contracts Act (DEC 1996) (Applicable if contract exceeds $10,000) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) (Applicable if contract exceeds $10,000) 52.222-26 Equal Opportunity (MAR 2007) (Applicable if contract exceeds $10,000) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) (Applicable if contract exceeds $10,000) 52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998) (Applicable if contract exceeds $10,000) 52.222-50 Combating Trafficking in Persons (SEP 2007) 52.222-54 Employment Eligibility Verification (Jan 2009) 52.223-6 Drug-Free Workplace (MAY 2001) (Applicable if contract is awarded to an individual)
PROJ NAME: Monday Creek Ford Replacement
52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.224-1 Privacy Act Notification (APR 1984) 52.224-2 Privacy Act (APR 1984) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) (Applicable if contract exceeds $30,000) 52.228-11 Pledges of Assets (FEB 1992) (Applicable if contract exceeds $30,000) 52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) (Applicable if contract exceeds $30,000) 52.228-14 Irrevocable Letter of Credit (DEC 1999) (Applicable if contract exceeds $30,000) 52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002) 52.232-23 Assignment of Claims (JAN 1986) 52.232-27 Prompt Payment for Construction Contracts (OCT 2008) 52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003) 52.233-1 Disputes (JUL 2002) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-17 Layout of Work (APR 1984) 52.243-5 Changes and Changed Conditions (APR 1984) 52.244-6 Subcontracts for Commercial Items (MAR 2009) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short From) (APR 1984) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)
(Applicable if contract is over $30,000) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
52.204-7 Central Contractor Registration (APR 2008)
(a) Definitions. As used in this clause—
“Central Contractor Registration (CCR) database” means the primary Government repository for Contractor information required for the conduct of business with the Government.
“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.
“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.
“Registered in the CCR database” means that—
(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and
(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record “Active”. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.
(b)
(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number—
(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or
PROJ NAME: Monday Creek Ford Replacement
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business name.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(iii) Company physical street address, city, state and Zip Code.
(iv) Company mailing address, city, state and Zip Code (if separate from physical).
(v) Company telephone number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering.
Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(g)
(1)
(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements
PROJ NAME: Monday Creek Ford Replacement regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to:
(A) Change the name in the CCR database;
(B) Comply with the requirements of Subpart 42.12 of the FAR;
(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.
(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the Internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961-5757.
52.228-1 Bid Guarantee. (Sept 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be __20__ percent of the bid price.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
PROJ NAME: Monday Creek Ford Replacement
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.228-15 Performance and Payment Bonds—Construction (Nov 2006)
(a) Definitions. As used in this clause—
“Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is $100,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection.
(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid
Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of the Treasury
Financial Management Service
Surety Bond Branch
3700 East West Highway, Room 6F01
Hyattsville, MD 20782.
Or via the internet at http://www.fms.treas.gov/c570/.
PROJ NAME: Monday Creek Ford Replacement
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
(End of clause)
AGAR 452.228-70 Alternative Forms of Security (NOV 1996)
If furnished as security, money orders, drafts, cashier's checks, or certified checks shall be drawn payable to: USDA Forest Service.
Order of Precedence--Construction
Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The Schedule (excluding the specifications)
(2) Representations and Other Instructions
(3) Contract Clauses
(4) Other Documents, Exhibits, and Attachments
(5) The Specifications
(6) Drawings
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
ATTACHMENT 1: SPECIFICATIONS
ATTACHMENT 2: DRAWINGS
ATTACHMENT 3: EXPERIENCE/CAPABILITY STATEMENT
ATTACHMENT 4: DAVIS-BACON WAGE DETERMINATION
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND
OTHER STATEMENTS OF OFFERORS OR RESPONDENTS
NOTE: Offerors should address questions concerning VETS-100 reporting and reporting requirements to the Office of Veterans Employment and Training Services offices at the following address:
U. S. Department of Labor VETS-100 Reporting 4200 Forbes Blvd., Suite 202 Lanham, MD 20703 Telephone: (301) 306-6752
Website: www.vets100.cudenver.edu Reporting Questions: HelpDesk@vets100.com
Reporting Verification: Verify@vets100.com
AGAR 452.219-70 SIZE STANDARD AND NAICS CODE INFORMATION (JANUARY 2005)
The North American Industrial classification System Code(s) and business size standard(s) describing the products and/or services to be acquired under this solicitation are listed below:
Contract line item(s): _____All items --NAICS Code 237310 _____ --Size Standard 33.5
The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (FEB 2009)
(a)
(1) The North American Industry classification System (NAICS) code for this acquisition is ____237310_____.
(2) The small business size standard is ____33.5___.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)
PROJ NAME: Monday Creek Ford Replacement
(1) If the clause at 52.204-7, Central Contractor Registration, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the clause at 52.204-7 is not included in this solicitation, and the offeror is currently registered in CCR, and has completed the ORCA electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certification in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)
(1) The following representations or certifications in ORCA are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $100,000.
(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the clause at 52.204-7, Central Contractor Registration.
(iv) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(v) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(vi) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(vii) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
PROJ NAME: Monday Creek Ford Replacement
(viii) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(ix) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(x) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xi) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xii) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xiii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xiv) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA- designated items.
(xv) 52.225-2, Buy American Act Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xvi) 52.225-4, Buy American Act--Free Trade Agreements--Israeli Trade Act Certificate. (Basic, Alternate I, and Alternate II) This provision applies to solicitations containing the clause at 52.225- 3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $67,826, the provision with its Alternate II applies.
(xvii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xviii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification.
(xix) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to—
PROJ NAME: Monday Creek Ford Replacement
(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and
(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.
(2) The following certifications are applicable as indicated by the Contracting Officer:
[Contracting Officer check as appropriate.]
----(i) 52.219-19, Small Business Concern Representation for the Small Business Competitiveness Demonstration Program.
------(ii) 52.219-21, Small Business Size Representation for Targeted Industry Categories Under the Small Business Competitiveness Demonstration Program.
------(iii) 52.219-22, Small Disadvantaged Business Status.
------(A) Basic.
------(B) Alternate I.
------(iv) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
------(v) 52.222-48, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment Certification.
------(vi) 52.222-52 Exemption from Application of the Service Contract Act to Contracts for Certain Services--Certification.
------(vii) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA- Designated Products (Alternate I only).
------(viii) 52.223-13, Certification of Toxic Chemical Release Reporting.
------(ix) 52.227-6, Royalty Information.
------ (A) Basic.
------ (B) Alternate I.
------(x) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The offeror has completed the annual representations and certifications electronically via the Online Representations and Certifications Application (ORCA) website at http://orca.bpn.gov . After reviewing the ORCA database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference
PROJ NAME: Monday Creek Ford Replacement
(see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR Clause Title Date Change
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on ORCA.
FAR 52.219-28 Post-Award Small Business Program Rerepresentation. (APR 2008)
(a) Definitions. As used in this clause--
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall re-represent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts—
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
PROJ NAME: Monday Creek Ford Replacement
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/services/contractingopportunities/sizestandardstopics/ .
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure they reflect the Contractor’s current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it [ ] is, [ ] is not a small business concern under NAICS Code ______________ assigned to contract number ______________.[Contractor to sign and date and insert authorized signer's name and title].
52.225-21 Required Use of American Iron, Steel, and Other Manufactured Goods—Buy American
Act—Construction Materials.
REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED GOODS-BUY AMERICAN ACT-
CONSTRUCTION MATERIALS (MAR 2009)
(a) Definitions. As used in this clause—
“Construction material” means an article, material, or supply brought to the construction site by the
Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of
PROJ NAME: Monday Creek Ford Replacement those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States; or
(2) A construction material manufactured in the United States.
“Foreign construction material” means a construction material other than a domestic construction material.
“Manufactured construction material” means any construction material that is not unmanufactured construction material.
“Steel” means an alloy that includes at least 50 percent iron, between .02 and 2 percent carbon, and may include other elements.
“United States” means the 50 States, the District of Columbia, and outlying areas.
“Unmanufactured construction material” means raw material brought to the construction site for incorporation into the building or work that has not been—
(1) Processed into a specific form and shape; or
(2) Combined with other raw material to create a material that has different properties than the properties of the individual raw materials.
(b) Domestic preference.
(1) This clause implements—
(i) Section 1605 of the American Recovery and Reinvestment Act of 2009 (Recovery Act) (Pub. L.
111-5), by requiring, unless an exception applies, that all iron, steel, and other manufactured goods used as construction material in the project are produced in the United States; and
(ii) The Buy American Act (41 U.S.C. 10a - 10d) by providing a preference for unmanufactured domestic construction material.
(2) The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraph (b)(3) and (b)(4) of this clause.
(3) This requirement does not apply to the construction material or components listed by the
Government as follows:
____________NONE______________________________
(4) The Contracting Officer may add other foreign construction material to the list in paragraph
(b)(3) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable.
(A) The cost of domestic iron, steel, or other manufactured goods used as construction material is unreasonable when the cumulative cost of such material will increase the cost of the contract by more than 25 percent;
(B) The cost of unmanufactured construction material is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available quantities and of a satisfactory quality; or
(iii) The application of the restriction of section 1605 of the Recovery Act or the Buy American
Act to a particular construction material would be inconsistent with the public interest.
PROJ NAME: Monday Creek Ford Replacement
(c) Request for determination of inapplicability of Section 1605 of the Recovery Act or the Buy
American Act
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph
(b)(4) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Cost;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(4) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed cost comparison table in the format in paragraph (d) of this clause.
(iii) The cost of construction material shall include all delivery costs to the construction site and any applicable duty.
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the
Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to section 1605 of the
Recovery Act or the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable cost of a domestic construction material, adequate consideration is not less than the differential established in paragraph
(b)(4)(i) of this clause.
(3) Unless the Government determines that an exception to section 1605 of the Recovery Act or the
Buy American Act applies, use of foreign construction material is noncompliant with section 1605 of the
American Recovery and Reinvestment Act or the Buy American Act.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Construction Material Description Unit of Measure Quantity Cost (Dollars)*
Item 1:
Foreign construction material
Domestic construction material
PROJ NAME: Monday Creek Ford Replacement
Item 2:
Foreign construction material
Domestic construction material
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
[* Include all delivery costs to the construction site.]
Foreign and Domestic Construction Materials Cost Comparison
(End Clause)
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1)
52.215-1 Instructions to Offerors--Competitive Acquisition (JAN 2004)
AGRICULTURE ACQUISITION REGULATIONS (48 CFR CHAPTER 4) CLAUSES
452.204-70 Inquiries (FEB 1988)
52.219-19 Small Business Concern Representation for the Small Business Competitiveness
Demonstration Program. (Oct 2000)
(a) Definition. “Emerging small business” as used in this solicitation, means a small business concern whose size is no greater than 50 percent of the numerical size standard applicable to the North American Industry Classification System (NAICS) code assigned to a contracting opportunity.
PROJ NAME: Monday Creek Ford Replacement
(b) [Complete only if the Offeror has represented itself under the provision at 52.219-1 as a small business concern under the size standards of this solicitation.] The Offeror o is, o is not an emerging small business.
(c) [Complete only if the Offeror is a small business or an emerging small business, indicating its size range.] Offeror’s number of employees for the past 12 months [check this column if size standard stated in solicitation is expressed in terms of number of employees] or Offeror’s average annual gross revenue for the last 3 fiscal years [check this column if size standard stated in solicitation is expressed in terms of annual receipts]. [Check one of the following.]
No. of Employees Avg. Annual Gross Revenues
____ 50 or fewer ____ $1 million or less
____ 51–100 ____ $1,000,001–$2 million
____ 101–250 ____ $2,000,001–$3.5 million
____ 251–500 ____ $3,500,001–$5 million
____ 501–750 ____ $5,000,001–$10 million
____ 751–1,000 ____ $10,000,001–$17 million
____ Over 1,000 ____ Over $17 million
FAR 52.222-5 Davis-Bacon Act—Secondary Site of the Work (JUL 2005)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Davis-Bacon Act, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment
Opportunity for Construction (FEB 1999) (Applicable if contract exceeds $10,000)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered are, are as follows:
Goals for minority participation for each trade: _7.3%____ Goals for female participation for each trade: __6.9%____
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative actions obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects.
The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U. S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is _Hocking, County.
52.225-22 Notice of Required Use of American Iron, Steel, and Other Manufactured Goods—Buy
American Act—Construction Materials.
NOTICE OF REQUIRED USE OF AMERICAN IRON, STEEL, AND OTHER MANUFACTURED GOODS—BUY
AMERICAN ACT—CONSTRUCTION MATERIALS (MAR 2009)
(a) Definitions. “Construction material,” “domestic construction material,” “foreign construction material,” “manufactured construction material,” “steel,” and “unmanufactured construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Required Use of Iron, Steel, PROJ NAME: Monday Creek Ford Replacement and Other Manufactured Goods—Buy American Act—Construction Materials” (Federal Acquisition
Regulation (FAR) clause 52.225-21).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of section 1605 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5)
(Recovery Act) or the Buy American Act should submit the request to the…