Drawing

View the file

Other files

File Type Posted
Amendment_03.pdf PDF
Monday Crk Ford Paddle Creek Replacement.docx DOCX document
Attachment 10001.pdf PDF
Schedule of Items__updated 4-16-10.xlsx XLSX spreadsheet
Solicitation_02.pdf PDF
Specification Paddle Creek_updated.pdf PDF
Paddel Creek Drawings_updated 4-16-2010.pdf PDF
SF 1442 Cont_0411.pdf PDF
Paddle_Creek_BOX_CULVERT_DETAILS_3of3.pdf PDF
SF 1442.pdf PDF
COVER SHEET.pdf PDF
CIM-0914-18EW-230-0914-04_Specs Paddle Crk.pdf PDF
Paddle_Creek_PROFILE_VIEW_2of3.pdf PDF
DBA_WD.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXISTING 4 FT. PE CULVERT

TO BE REPLACED BY 14' (W) X 6' (H) X 28' (L)

CONCRETE BOX CULVERT

0 71

0 72 0 73

TWP.RD. 245

FOREST ROAD 73

PADDLE CREEK

TRAILHEAD

EXISTING

PLUNGE

POOL

BANK CUT AREA

NOTE:

BANK CUT AREA EXTENDS THE COMPLETE

ARCH FROM POINT #1 TO POINT #2. FILL

THESE AREA & PLUG AREA. GRADE AND SEED

& MULCH THE OTHER AREA.

EXISTING CHANNEL

OLD CHANNEL BED (THIS CHANNEL

BED TO BE REESTABLISHED, APPROX.

215 FEET) FROM POINT #1 TO POINT #2

POINT #1

POINT #2

BORROW

AREA FOR

PLUNGE POOL

FILL AND

DOWNSTREAM

FILL

0+00

1+50 1+00

3+00

2+00

1+50

C OF REESTABLISHED STREAM CHANNELL

SEDIMENT CONTROL

DIKE

DOWNSTREAM

STEPS

DOWNSTREAM

STEPS

DOWNSTREAM

STEPS

FO

RE

ST

R

O

AD

FOREST ROAD 613

DOWNSTREAM

STEPS

PLUG FILL THESE

CHANNEL AREA

ROOT WAD

BARB

ROOT WAD

BARB

ROOT WAD

BARB REINFORCE

ROOT WAD

BARB

REINFORCE

ROOT WAD

BARB

SITE PLAN

North

( IN FEET )

GRAPHIC SCALE

030 30 60 12015 Paddle_Creek_plan.dwg

1"=30'

Drawing Title

Scale

Date

CAD File No.

Checked

Drawn

Drawing No.

Project

Date

Project Name

No.

Revision/Issue

Sheet of

DWS

TCW

(1) MOBILIZATION

(2) SEDIMENT CONTROL DIKE

(3) REMOVAL OF EXISTING CULVERT

(4) CONCRETE BOX CULVERT.

(5) "C" & "D" ROCK FOR PLUNGE POOL &

DOWNSTREAM STEPS .

(6) EXCAVATION & FILL WITH NATIVE CHANNEL

BED MATERIALS.

(7) REESTABLISH CHANNEL & FILL BANK CUT

AREA.

(8) PAVEMENT.

(9) SEEDING & MULCHING.

(10) ROOT WAD BARB.

(11) REINFORCEMENT ROOT WAD BARB.

1 3

CHANNEL BED

30Á FLOW

PLAN VIEW ROOT WAD BARB

FLOW

SECTION 1 - 1

STREAM BED

RATIO EMD/EXPOSED = 3

EXPOSED END

EMBEDMENT (EMD)

ROOT WAD BARB

NOTE:

USE ONSITE LOG/ROOT MASS DEBRIS OR CLEARING

TREES LOG/ROOT MASS AS DIRECTED BY COR. MINIMUM

DIAMETER OF TREE 10 INCH.

NOT TO SCALE

CHANNEL BED FLOW

"B" ROCK

PLAN VIEW REINFORCED ROOT WAD BARB

FLOW

SECTION 2 - 2

STREAM BED

EXPOSED END

EMBEDMENT (EMD)

4'

"B" ROCK

REINFORCED ROOT WAD BARB

NOT TO SCALE

NOTE:

USE ONSITE LOG/ROOT MASS DEBRIS OR CLEARING

TREES LOG/ROOT MASS AS DIRECTED BY COR. MINIMUM

DIAMETER OF TREE 10 INCH.

2' MIN.