Attachment 2 - 5711 PASP Requirements.doc

DOC document 25 KB Posted

Attached to
RECOVERY* Mine Closure-Upper Peninsula-Michigan Federal contract opportunity
Solicitation number
AG-4419-S-10-0022
Issued by
Department of Agriculture Forest Service Washington Office Economic Recovery Operations Center East

About this file

Attachment 2 - 5711 PASP Requirements

View the file

Other files for this federal contract opportunity

Other files attached to RECOVERY* Mine Closure-Upper Peninsula-Michigan, newest first.
File Type Posted
Amendment 2 - SF30.pdf PDF
Attachment 3 - pre-bid_mtg_attendee_list.doc DOC document
Attachment 1 - pre-bid_mtg_notes.doc DOC document
Amendment 1 - SF30 .pdf PDF
C - SECTION J_attach_and_exhibits.docx DOCX document
C - NEPA_Map1_Norwich_dm.pdf PDF
C - SECTION H_special_requirements.doc DOC document
C - Schedule_of_items.xls XLS spreadsheet
C - SECTION J_attach_and_exhibits.docx DOCX document
C - SECTION F_deliveries_performance.doc DOC document
C- SECTION C _SOW_SPECS.doc DOC document
SF1442.pdf PDF
C - SECTION E_inspection_acceptance.docx DOCX document
C - Wage Determination.doc DOC document
C - Construction ARRA Clauses.doc DOC document
C - SECTION G_contract_admin.docx DOCX document
C - Evaluation Criteria.doc DOC document
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5711.1 - Project Aviation Safety Plan

Elements of a Project Aviation Safety Plan are:

1. Supervision. Identify the qualified Project Aviation Manager.

2. Project Name and Objectives. Provide a brief description of the project and its objectives.

3. Justification. Indicate why the project will require the use of aircraft in special-use flight conditions/environments and list the most practical alternatives for completion of the project.

4. Project Date(s). State the date(s) the project will begin and end. These may be approximate, since exact dates of flight may not be known at the beginning of the year.

5. Location. Enter the descriptive location and indicate a map clearly showing the area where flight(s) will be made; aerial hazards must be clearly indicated.

6. Projected Cost of Aviation Resources. Enter cost coding, projected flight hours and cost, projected miscellaneous expenses (such as overnight charges or service truck mileage) and total cost of the project.

7. Aircraft. If known, identify vendor(s) that own aircraft to be used, registration number, aircraft type, aircraft data card expiration date and missions for which the aircraft is approved.

8. Pilot(s). If known, identify pilot(s), type of aircraft qualified in, type of missions qualified for and pilot card expiration date.

9. Participants. List individuals involved in flight(s), their qualifications (such as Helicopter Manager, Passenger(s), Helibase Manager, or Fixed-Wing Flight Manager), dates of their last aviation training and their project responsibilities.

10. Flight Following and Emergency Search-and-Rescue. Identify the procedures to be used.

11. Aerial Hazard Analysis. Provide an aerial hazard analysis for each flight with an attached map.

a. Require a prior ground and/or aerial hazards survey for flights made in confined areas (such as deep, narrow canyons).

b. Provide a copy of the hazard map to the pilot prior to any project flights.

c. Accomplish necessary planning concerning temporary flight restrictions (TFRs) and coordination with the Federal Aviation Administration and military authorities (if appropriate) prior to project flights.

12. Protective Clothing/Equipment. Identify the protective equipment and clothing necessary for the particular operation and any survival equipment (such as extra water, flotation devices, or sleeping bags) beyond the normal Personal Protective Equipment (PPE) complement that may be required.

13. Load Calculations and Weight-and-Balance.

a. Include the Load Calculations provided by the pilot, who is responsible for the accurate completion of load calculations.

b. Ensure that trained aviation personnel have determined that the scheduled aircraft are capable of performing the mission(s) safely and within the capabilities of the type of aircraft needed.

c. Ensure that manifests and load calculations/weight-and-balance calculations are completed and noted properly by the Helicopter Manager if the project requires the use of a helicopter.

14. Risk/Hazard Assessment. Complete a Risk/Hazard Assessment that identifies hazards associated with the operation and the mitigations and controls put in place to reduce or eliminate them. The process for completing this assessment is found in the Interagency Helicopter Operations Guide (IHOG) and in Chapter 17 of Interagency Standards for Fire and Aviation Operations.