Attachment 2 - 5711 PASP Requirements.doc
DOC document 25 KB Posted
- Attached to
- RECOVERY* Mine Closure-Upper Peninsula-Michigan Federal contract opportunity
- Solicitation number
- AG-4419-S-10-0022
About this file
Attachment 2 - 5711 PASP Requirements
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 2 - SF30.pdf | ||
| Attachment 3 - pre-bid_mtg_attendee_list.doc | DOC document | |
| Attachment 1 - pre-bid_mtg_notes.doc | DOC document | |
| Amendment 1 - SF30 .pdf | ||
| C - SECTION J_attach_and_exhibits.docx | DOCX document | |
| C - NEPA_Map1_Norwich_dm.pdf | ||
| C - SECTION H_special_requirements.doc | DOC document | |
| C - Schedule_of_items.xls | XLS spreadsheet | |
| C - SECTION J_attach_and_exhibits.docx | DOCX document | |
| C - SECTION F_deliveries_performance.doc | DOC document | |
| C- SECTION C _SOW_SPECS.doc | DOC document | |
| SF1442.pdf | ||
| C - SECTION E_inspection_acceptance.docx | DOCX document | |
| C - Wage Determination.doc | DOC document | |
| C - Construction ARRA Clauses.doc | DOC document | |
| C - SECTION G_contract_admin.docx | DOCX document | |
| C - Evaluation Criteria.doc | DOC document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5711.1 - Project Aviation Safety Plan
Elements of a Project Aviation Safety Plan are:
1. Supervision. Identify the qualified Project Aviation Manager.
2. Project Name and Objectives. Provide a brief description of the project and its objectives.
3. Justification. Indicate why the project will require the use of aircraft in special-use flight conditions/environments and list the most practical alternatives for completion of the project.
4. Project Date(s). State the date(s) the project will begin and end. These may be approximate, since exact dates of flight may not be known at the beginning of the year.
5. Location. Enter the descriptive location and indicate a map clearly showing the area where flight(s) will be made; aerial hazards must be clearly indicated.
6. Projected Cost of Aviation Resources. Enter cost coding, projected flight hours and cost, projected miscellaneous expenses (such as overnight charges or service truck mileage) and total cost of the project.
7. Aircraft. If known, identify vendor(s) that own aircraft to be used, registration number, aircraft type, aircraft data card expiration date and missions for which the aircraft is approved.
8. Pilot(s). If known, identify pilot(s), type of aircraft qualified in, type of missions qualified for and pilot card expiration date.
9. Participants. List individuals involved in flight(s), their qualifications (such as Helicopter Manager, Passenger(s), Helibase Manager, or Fixed-Wing Flight Manager), dates of their last aviation training and their project responsibilities.
10. Flight Following and Emergency Search-and-Rescue. Identify the procedures to be used.
11. Aerial Hazard Analysis. Provide an aerial hazard analysis for each flight with an attached map.
a. Require a prior ground and/or aerial hazards survey for flights made in confined areas (such as deep, narrow canyons).
b. Provide a copy of the hazard map to the pilot prior to any project flights.
c. Accomplish necessary planning concerning temporary flight restrictions (TFRs) and coordination with the Federal Aviation Administration and military authorities (if appropriate) prior to project flights.
12. Protective Clothing/Equipment. Identify the protective equipment and clothing necessary for the particular operation and any survival equipment (such as extra water, flotation devices, or sleeping bags) beyond the normal Personal Protective Equipment (PPE) complement that may be required.
13. Load Calculations and Weight-and-Balance.
a. Include the Load Calculations provided by the pilot, who is responsible for the accurate completion of load calculations.
b. Ensure that trained aviation personnel have determined that the scheduled aircraft are capable of performing the mission(s) safely and within the capabilities of the type of aircraft needed.
c. Ensure that manifests and load calculations/weight-and-balance calculations are completed and noted properly by the Helicopter Manager if the project requires the use of a helicopter.
14. Risk/Hazard Assessment. Complete a Risk/Hazard Assessment that identifies hazards associated with the operation and the mitigations and controls put in place to reduce or eliminate them. The process for completing this assessment is found in the Interagency Helicopter Operations Guide (IHOG) and in Chapter 17 of Interagency Standards for Fire and Aviation Operations.