SOL NO: AG-3604-S-14-0005

Construction UNIT: NRS - St. Paul, MN PROJ NAME: Chiller Replacement

Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SECTION C - DESCRIPTION/SPECIFICATION/WORK STATEMENT

SECTION D--PACKAGING AND MARKING

SECTION E--INSPECTION AND ACCEPTANCE

SECTION F--DELIVERIES OR PERFORMANCE

SECTION G--CONTRACT ADMINISTRATION DATA

SECTION H--SPECIAL CONTRACT REQUIREMENTS

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

Attachment A, Davis Bacon WD No. MN140040

Attachment B, SAM & Banking Information

Attachment C, Experience Questionnaire

Attachment D, Chilled Water Piping Layout

Attachment E, Chilled Water Piping Schematic

Attachment F, Electric Riser Schematic

Attachment G, Architectural Drawing Sheet 3-6

Attachment H, Structural Drawing Sheet 7-3

Attachment I, Structural Drawing Sheet 7-4

Attachment J, Structural Drawing Sheet 7-8

Attachment K, Structural Drawing sheet 7-9

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF

OFFERORS OR RESPONDENTS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

SECTION M--EVALUATION FACTORS FOR AWARD

ATTACHMENT A – SCA Wage Determination

ATTACHMENT B – SAM & Banking Information

ATTACHMENT C - EXPERIENCE QUESTIONNAIRE

ATTACHMENT D - CHILLED WATER PIPING LAYOUT

PROJ NAME: Chiller Replacement

ATTACHMENT E - CHILLED WATER PIPING SCHEMATIC

ATTACHMENT F - ELECTRIC RISER SCHEMATIC

ATTACHMENT G - ARCHITECTURAL DRAWING SHEET 3-6

ATTACHMENT H - STRUCTURAL DRAWING SHEET 7-3

ATTACHMENT I - STRUCTURAL DRAWING SHEET 7-4

ATTACHMENT J - STRUCTURAL DRAWING SHEET 7-8

ATTACHMENT K - STRUCTURAL DRAWING SHEET 7-9

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

B.1 Description of Requirement

Location: USDA Forest Service, Northern Research Station, 1992 Folwell Avenue, St. Paul, MN 55108

A. The contractor shall provide all labor and equipment necessary to do the following: determine air conditioning cooling load for sizing cooling equipment; selective demolition of existing chillers and associated equipment; review of allowable roof loading and provision of necessary structural modifications; provide and install new chiller(s); modification and repair of roofing system to accommodate chiller replacement; network integration into the building control system.

B. Period of Performance: Anticipated Award Date is on or about July 18, 2014; Demolition Start Date is September 8, 2014.

C. One contract will be awarded as a Best Value Tradeoff to the offeror whose technical and cost proposal is the most advantageous to the Government. Award may not necessarily be made to the offeror submitting the lowest price, or to the offeror with the highest technical score. The critical factor in making any cost/technical tradeoffs is not the technical spread, but rather what is the significance of that difference. See Section M for additional details.

D. Bonding requirements: 20% bid bond with offer; 100% performance & payment bonds upon contract award.

E. All prospective offerors are encouraged to inspect the site prior to submitting an offer to assess the condition of the site and the scope of work proposed. Failure to do so does not relieve the offeror from accurately determining the scope of work required. A Pre-Proposal Conference is scheduled for Friday, June 13, 2014 at 1:00 PM Central Time (2:00 PM Eastern Time) at the USDA Forest Service, Northern Research Station, 1992 Folwell Avenue, St. Paul, MN 55108. You must confirm your attendance by contacting Rick Sindt at 651-649-5120 or rsindt@fs.fed.us

F. A post award pre-work meeting will be scheduled with the successful offeror/contractor. This meeting must take place within ten days of contract award.

G. This requirement is a total small business set aside. The NAICS Code for this acquisition is 238220, with a small business size standard of $14.0 Million.

H. Contractors are required to be registered in the System for Award Management (SAM) per FAR 52.204-7, System for Award Management – See Attachment C. Registration in this website is

FREE.

mailto:rsindt@fs.fed.us

B.2 QUOTED PRICE – SCHEDULE OF ITEMS

Please fill out this Schedule and return it as part of your proposal package. You must submit pricing for all items, including any option items to be considered.

Line Item

Description Unit QTY Amount

001 Cooling load determination LS 1

002 Selective demolition LS 1

003 Structural Analysis LS 1

004 Replacement chillers and appurtenances LS 1

005 Roof repair LS 1

006 Building control system integration LS 1

007 Option #1/Add-Alt 1 Replace primary chilled water pump

LS 1

008 Option #2/Add-Alt 2 Replace secondary chilled water pumps

009 Option #/Add-Alt 3 Replace chilled water pump motor starters

010 Option #4/Add-Alt 4 Extended warranty

TOTAL

Contractor: _____________________________________

Signature: ______________________________________

Date: _______________________

SECTION C - DESCRIPTION/SPECIFICATION/WORK STATEMENT

PERFORMANCE WORK STATEMENT

ST PAUL CHILLER REPLACEMENT

SECTION 01100 SUMMARY

PART 1 GENERAL

1.1 Contract Description

A. Determine air conditioning cooling load for sizing cooling equipment.

B. Selective demolition of existing chillers and associated equipment.

C. Review of allowable roof loading and provision of necessary structural modifications.

D. Provide and install new chiller(s).

E. Modification and repair of roofing system to accommodate chiller replacement.

F. Network integration into the building control system.

1.2 The number of Packaged Water Chillers units required to meet the cooling demand is left to the Contractor’s discretion. Contractor shall include this information as part of their proposal.

1.3 Additive-Alternatives

Add-Alt 1: Replace primary chilled water pump.

Add-Alt 2: Replace secondary chilled water pumps.

Add-Alt 3: Replace chilled water pump motor starters.

Add-Alt 4: Provide the manufacturer’s Whole Unit Parts Warranty.

1.4 Location:

1992 Folwell Ave.

St Paul, MN 55108

1.5 Work Sequence

A. Prior to commencement of demolition and construction, provide cooling load report for Government review.

B. Prior to commencement of demolition and construction, provide structural report, stamped by a professional engineer, of proposed chiller mounting method for Government review.

PROJ NAME: Chiller Replacement

C. Prior to commencement of work, Contractor shall submit a construction schedule for approval by the Government.

1.6 Contractor’s Use of Site and Premises

A. Limit use of site and premises to allow:

1. Owner occupancy.

2. Access to employee contract parking.

B. Access to Site: Visitor parking will be discontinued throughout the duration of the Work.

C. Construction Operations: Owner’s premises are surrounded by property owned and controlled by the University of Minnesota. Including employee contract parking areas, Contractor shall not limit access to University property without prior approval of the Owner and University, and for limited duration only.

D. The use of premises controlled by the Owner shall be available for construction operations, including visitor parking areas. Contractor shall protect, to the extent possible, surrounding site features including but not limited to: pavement and landscaping.

E. Contractor shall follow University guidelines for protecting pavement and landscaping from damage caused by vehicles and equipment. Protection measures include but are not limited to: use of wood panels and wood mulch to minimize compactions of soils, trimming or moving tree branches out of the way, etc. Coordinate work with the Owner and the University.

F. Time Restrictions for Performing Work: Building hours of operation is Monday-Friday, 08:00 to 16:30. Coordinate with Owner work outside these hours.

G. Safety, Health, & Security Plan: Prior to commencement of Work, Contractor shall submit for Owner approval, a plan to facilitate the work in a safe and secure manner, protecting Owner and Contractor employees from construction operations and the security of the building and its occupants.

1.7 Government Furnished Information

A. Attached Documents:

1. Chilled Water Piping Layout

2. Chilled Water Piping Schematic

3. Electric Riser Schematic

4. Architectural Drawing Sheet 3-6

5. Structural Drawing Sheet 7-3

6. Structural Drawing Sheet 7-4

7. Structural Drawing Sheet 7-8

8. Structural Drawing sheet 7-9

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

PROJ NAME: Chiller Replacement

Not used

SECTION 01300 ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 Cooling Load Study

A. Utilize commercial, off the shelf, computer program.

B. Conduct on-site review of existing conditions. Utilize Government provided documents to review materials and equipment.

C. Provide a detailed report showing the results of the study.

1.2 Structure Report

A. Utilize Government furnished documents to review allowable roof loads.

B. Based upon the systems, equipment and mounting methods provided in the Contractor’s offer provide a structural report demonstrating that the proposed mounting methods will not exceed allowable roof loads.

C. Provide Professional Structural Engineers stamp on the report.

1.3 Preconstruction Meeting

A. Government will schedule meeting at project site after Notice of Award.

B. Attendance Required: Government, Contractor, and major Subcontractors.

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

3.1 Cutting and Patching

A. Employ skilled and experienced installer to perform cutting and patching.

B. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit.

C. Utilize a Firestone-licensed applicator to perform all roofing modifications and repairs.

Applicator shall have minimum five years’ experience working with Firestone TPO membrane roofing systems.

SECTION 01330 SUBMITTAL PROCEDURES

1.1 Submittal Procedures

A. Provide four copies of the required documents; all will be reviewed, signed, and two will be returned, either approved or rejected.

B. Documents may instead be provided in Adobe Acrobat .pdf format.

1.2 Progress Schedules

A. Submit initial schedule within 15 days after date established in Notice to Proceed.

B. Submit revised Progress Schedule with each Application for Payment.

1.3 Product Data

A. Product Data: Submit to Government for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents.

B. Provide copies and distribute in accordance with Submittal Procedures article and for record documents purposes described in Section 01700.

1.4 Shop Drawings

A. Shop drawings means drawings, submitted to the Government by the Contractor, subcontractor, or any lower tier subcontractor showing in detail, the proposed fabrication and assembly of components, equipment and materials.

B. It includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the contractor to explain in detail specific portions of the work required by the contract. The Government may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract.

C. The Contractor shall coordinate all such drawings, and review them for accuracy, completeness, and compliance with contract requirements and shall indicate its approval thereon as evidence of such coordination and review. Shop drawings submitted to the Government without evidence of the Contractor’s approval may be returned for resubmission. The Government will indicate a review of the shop drawings. Any work done before such review shall be at the Contractor’s risk. Review by the Government shall not relieve the Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with the requirements of this contract.

1.5 Manufacturer’s Instructions

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Government in quantities specified for Product Data.

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

Not used

SECTION 01400 QUALITY REQUIREMENTS

PART 1 GENERAL

1.1 Quality Control and Control of Installation

A. See individual Sections.

B. Comply with manufacturer’s instructions.

C. Perform work by persons qualified to produce required and specified quality.

D. Verify field measurements are as indicated on Shop Drawings or as instructed by manufacturer.

1.2 References

A. When reference standards conflict, comply with the requirements of the more stringent standard.

B. When specified reference standards conflict with Contract Documents, request clarification from the Government.

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

Not used

SECTION 01500 TEMPORARY FACILITIES AND CONTROLS

PART 1 GENERAL

1.1 Utilities

A. Contractor may use the facility electrical power. Exercise measures to conserve energy.

B. Contractor may use facility water. Exercise measures to conserve water.

C. Contractor may not use facility: telephone, computer, fax machine, or copy machines.

D. Contractor may not use facility sanitary. Provide and maintain required facilities and enclosures.

PROJ NAME: Chiller Replacement

1.2 Progress Cleaning and Waste Removal

A. Maintain areas free of waste materials, debris and rubbish. Maintain site in clean and orderly condition.

B. Collect and remove waste materials, debris and rubbish from site weekly and dispose of off-site.

SECTION 01600 PRODUCT REQUIREMENTS

PART 1 GENERAL

1.1 Products

A. Furnish products of qualified manufacturers suitable for intended use. Furnish products of each type by single manufacturer unless specified otherwise.

B. Furnish interchangeable components from same manufacturer for components being replaced.

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

Not used

SECTION 01700 EXECUTION REQUIREMENTS

PART 1 GENERAL

1.1 Closeout Procedures

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Government review.

B. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.

1.2 Final Cleaning

A. Clean debris from roofs, gutters, downspouts, and drainage systems.

B. Clean site; sweep paved areas, rake clean landscaped surfaces.

C. Remove waste and surplus materials, rubbish, and construction facilities from site.

1.3 Protecting Installed Construction

PROJ NAME: Chiller Replacement

A. Protect installed Work and provide special protection where specified in individual specifications sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Protect finished floors, stairs, and other surfaces from traffic, dirt wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

1.4 Project Record Documents

A. Maintain on site one set of the following record documents; record actual revisions to the Work:

1. Performance Work Statement.

2. Specifications.

3. Drawings.

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, Product Data, and Samples.

B. Ensure entries are complete and accurate, enabling future reference by Government.

C. Record information concurrent with construction progress, not less that weekly.

1.5 Product Warranties and Product Bonds

A. Execute and assemble transferable warranty documents and bonds from subcontractors, suppliers, and manufacturers.

B. Provide manufacturer standard warranties for all products unless noted otherwise.

C. Submit prior to final Application for Payment.

D. Provide manufacturer’s standard warranty.

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

Not used

DIVISION 15 MECHANICAL

SECTION 15000 SUPPLEMENTAL MECHANICAL GENERAL REQUIREMENTS

1.1 MATERIALS AND LABOR

A. Furnish materials and labor necessary to deliver to the Government a complete and operable system installed in accordance with the contract documents.

B. Materials shall be of the best quality. Workmanship shall be of highest grade and construction shall be done according to best practices of the trade.

1.2 PROTECTION OF WORK AND MATERIALS

A. Protect and care for materials delivered and work performed until the completion of the work.

Defective equipment or equipment damaged in the course of storage, installation or test shall be replaced or repaired to the satisfaction of the Government at no additional cost.

1.3 APPLICABLE CODES

A. Work and materials shall conform to the latest rules and regulations listed below and these rules and regulations hereby are made part of this specification. They include, but are not necessarily limited to the following:

American Society for Testing and Materials (ASTM) Underwriters' Laboratories, Inc. (UL) Air Moving and Conditioning Assoc. (AMCA) American Society of Heating, Refrigerating, and Air Conditioning Engineers (ASHRAE) American Society of Mechanical Engineers (ASME) National Electrical Manufacturers Association (NEMA) Institute of Electrical and Electronics Engineers (IEEE) American National Standards Institute (ANSI) National Fire Protection Association (NFPA) American Water Works Association (AWWA) Local Fire Code Local Plumbing Codes American Welding Society International Building Code (IBC) International Existing Building Code (IEBC) International Mechanical Code (IMC) International Plumbing Code (IPC) National Electrical Code National Fire Protection Association (NFPA) 70-2005 Life Safety Code (NEC) International Energy Conservation Code (IECC) International Fire Code (IFC)

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

3.1 EQUIPMENT SUPPORTS

A. Furnish and install equipment supports for mechanical equipment as required.

3.2 CONNECTION TO EQUIPMENT

A. Provide piping connections, supports, brackets, compensators or flexible connections to prevent application of excessive stresses to equipment.

B. Equipment shall be installed with flanges or unions in such a manner as to permit disconnecting for removal of tubes, coils, elements and other equipment for inspection, service and repairs.

3.3 ACCESS TO EQUIPMENT

A. The installation of work performed shall provide reasonable accessibility for operation, inspection, and maintenance of equipment and accessories. The Government shall determine the adequacy of such accessibility.

3.4 ELECTRIC MOTORS AND MOTOR CONTROLS

A. Motors shall be built in accordance with the latest applicable NEMA, IEEE and ANSI Standards.

Motor efficiencies shall be premium high efficiency type per the Consortium for Energy Efficiency Standard and/or be “Energy Star” compliant.

B. Magnetic motor starters for mechanical items of equipment shall be furnished under Division 16 unless the starter is an integral part of a factory packaged item of equipment. Each starter furnished as an integral item of equipment shall be provided with overload heater elements. Starters shall have phase loss protection or shall have relays installed to provide this feature. Starters shall be equipped with suitable step-down transformers to provide required control voltage.

3.5 CLEANING OF SYSTEMS

A. Piping systems shall be thoroughly cleaned and flushed prior to initial operation.

B. Thoroughly clean exposed portions of the mechanical installation, removing labels and foreign substance.

3.6 OPERATIONAL TESTING

A. Operate systems until successful operation is demonstrated to the Government. This initial operation shall be in addition to the testing of the system and shall be done after the system is cleaned and finished.

3.7 EXISTING UTILITIES AND EQUIPMENT

A. Field verify and coordinate with existing utilities and equipment.

SECTION 15082 PIPING INSULATION

1.1 SECTION INCLUDES

A. Piping insulation.

B. Jackets and accessories.

1.2 REFERENCES

A. ASTM B 209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate;

2000.

B. ASTM B 209M - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate (Metric); 2000.

C. ASTM C 177 - Standard Test Method for Steady-State Heat Flux Measurements and Thermal Transmission Properties by Means of the Guarded Hot Plate Apparatus; 1997.

D. ASTM C 547 - Standard Specification for Mineral Fiber Pipe Insulation; 2000.

E. ASTM E 84 - Standard Test Method for Surface Burning Characteristics of Building Materials;

2000a.

F. ASTM E 96 - Standard Test Methods for Water Vapor Transmission of Materials; 2000.

G. NFPA 255 - Standard Method of Test of Surface Burning Characteristics of Building Materials;

National Fire Protection Association; 2000.

H. UL 723 - Standard for Test for Surface Burning Characteristics of Building Materials;

Underwriters Laboratories Inc.; 1996.

1.3 SUBMITTALS

A. See 01330 – Submittal Procedures, for submittal procedures.

B. Product Data: Provide product description, thermal characteristics, list of materials and thickness for each service, and locations.

1.4 QUALITY ASSURANCE

A. Manufacturer Qualifications: Company specializing in manufacturing the Products specified in this section with not less than ten years of documented experience.

1.5 DELIVERY, STORAGE, AND PROTECTION

A. Accept materials on site, labeled with manufacturer's identification, product density, and thickness.

PROJ NAME: Chiller Replacement

PART 2 PRODUCTS

2.1 REQUIREMENTS FOR ALL PRODUCTS OF THIS SECTION

A. Surface Burning Characteristics: Flame spread/Smoke developed index of 25/50, maximum, when tested in accordance with ASTM E 84, NFPA 255, or UL 723.

2.2 GLASS FIBER

A. Owens Corning Fiberglas SSL II: www.owenscorning.com.

B. Approved equal.

C. Insulation: ASTM C 547; rigid molded, noncombustible.

1. 'K' value: ASTM C 177, 0.24 at 75 degrees F.

2. Maximum service temperature: 850 degrees F.

3. Maximum moisture absorption: 0.2 percent by volume.

D. Vapor Barrier Jacket: White kraft paper with glass fiber yarn, bonded to aluminized film;

moisture vapor transmission when tested in accordance with ASTM E 96 of 0.02 perm-inches.

E. Vapor Barrier Lap Adhesive:

1. Factory applied double pressure sensitive adhesive along longitudinal joint. Joints at insulation sections sealed with butt strips with adhesive factory applied.

2.3 JACKETS

A. PVC Plastic.

1. Manufacturers:

a. Johns Manville International, Inc: www.johnsmanville.com.

b. Approved equal.

2. Jacket: One piece molded type fitting covers and sheet material, off-white color.

a. Minimum Service Temperature: 0 degrees F.

b. Maximum Service Temperature: 150 degrees F.

c. Moisture Vapor Permeability: 0.002 perm inch, maximum, when tested in accordance with

ASTM E 96.

d. Thickness: 10 mil.

e. Connections: Brush on welding adhesive.

3. Covering Adhesive Mastic:

a. Manufacturers:

1) Chicago Mastic

2) Approved equal.

b. Compatible with insulation.

B. Aluminum Jacket: ASTM B 209 (ASTM B 209M) formed aluminum sheet.

1. Thickness: 0.016 inch sheet.

2. Finish: Smooth.

3. Joining: Longitudinal slip joints and 2 inch laps.

PROJ NAME: Chiller Replacement

4. Fittings: 0.016 inch thick die shaped fitting covers with factory attached protective liner.

5. Metal Jacket Bands: 3/8 inch wide; 0.015 inch thick aluminum.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify that piping has been tested before applying insulation materials.

B. Verify that surfaces are clean and dry, with foreign material removed.

3.2 INSTALLATION

A. Install in accordance with manufacturer's instructions.

B. Install in accordance with NAIMA National Insulation Standards.

C. Exposed Piping: Locate insulation and cover seams in least visible locations.

D. Insulated pipes conveying fluids below ambient temperature: Insulate entire system including fittings, valves, unions, flanges, strainers, flexible connections, pump bodies, and expansion joints.

E. Glass fiber insulated pipes:

1. Provide vapor barrier jackets, factory-applied or field-applied. Secure with self-sealing longitudinal laps and butt strips with pressure sensitive adhesive. Secure with outward clinch expanding staples and vapor barrier mastic.

2. Insulate fittings, joints, and valves with molded insulation of like material and thickness as adjacent pipe. Finish with glass cloth and vapor barrier adhesive or PVC fitting covers.

I. Inserts and Shields:

1. Application: Piping 1-1/2 inches diameter or larger.

2. Shields: Galvanized steel between pipe hangers or pipe hanger rolls and inserts.

3. Insert location: Between support shield and piping and under the finish jacket.

4. Insert configuration: Minimum 6 inches long, of same thickness and contour as adjoining insulation; may be factory fabricated.

5. Insert material: Hydrous calcium silicate insulation or other heavy density insulating material suitable for the planned temperature range.

J. Continue insulation through walls, sleeves, pipe hangers, and other pipe penetrations. Finish at supports, protrusions, and interruptions.

K. Exterior Applications: Provide vapor barrier jacket. Insulate fittings, joints, and valves with insulation of like material and thickness as adjoining pipe, and finish with glass mesh reinforced vapor barrier cement. Cover with aluminum jacket with seams located on bottom side of horizontal piping.

3.3 SCHEDULES

A. Chilled Water:

PROJ NAME: Chiller Replacement

1. Glass Fiber Insulation:

a. Pipe Size Range: 2 inch.

1) Thickness: 1 1/2 inch.

b. Pipe Size Range: 2 to 4 inch.

1) Thickness: 2 inch.

c. Pipe Size Range: over 4 inch.

1) Thickness: 2.5 inch.

SECTION 15621 PACKAGE WATER CHILLERS

PART 1 GENERAL

1.1 SUMMARY

A. Section includes chiller package, charge of refrigerant and oil, controls and control connections, chilled water connections, condenser water connections, refrigerant connections, auxiliary water connections, starters.

1.2 REFERENCES

A. ASHRAE 15 (American Society of Heating, Refrigerating and Air-Conditioning Engineers) - Safety Code for Mechanical Refrigeration.

B. ASHRAE 90.1 (American Society of Heating, Refrigerating and Air-Conditioning Engineers) - Energy Standard for Buildings Except Low-Rise Residential Buildings.

C. ANSI/NFPA 70 (ANSI/National Fire Protection Association) – National Electrical Code.

D. ASME SEC VIII (American Society of Mechanical Engineers) - Boiler and Pressure Vessel Code.

E. NEMA 250 (National Electrical Manufacturers Association) - Enclosures for Electrical Equipment (1000 Volts Maximum).

F. NEMA MG1 (National Electrical Manufacturers Association) - Motors and Generators.

G. UL 207 (Underwriters Laboratories, Inc.) - Refrigerant-Containing Components and Accessories, Non-Electrical.

H. UL 303 (Underwriters Laboratories, Inc.) - Refrigeration and Air Conditioning Condensing, and Air-Source Heat Pump Equipment.

I. UL 1995 (Underwriters Laboratories, Inc.) – Heating and Cooling Equipment.

1.3 SUBMITTALS

A. Section 01330 - Submittal Procedures: Submittal procedures.

PROJ NAME: Chiller Replacement

B. Shop Drawings: Indicate components, assembly, dimensions, weights and loads, required clearances, and location and size of field connections. Indicate valves, strainers, thermometers, flow switches, pressure gauges and thermostatic valves required for complete system.

C. Product Data: Submit rated capacities, weights, specialties and accessories, electrical requirements and wiring diagrams.

D. Manufacturer's Installation Instructions: Submit assembly, support details, connection requirements, and include startup instructions.

E. Manufacturer's Certificate: Certify products meet or exceed specified requirements including those furnished but not produced by manufacturer.

1.4 CLOSEOUT SUBMITTALS

A. Section 01700 - Execution Requirements: Closeout procedures.

B. Operation and Maintenance Data: Submit start-up instructions, maintenance data, parts lists, controls, and accessories. Include trouble-shooting guide.

1.5 QUALIFICATIONS

A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum ten years’ experience.

B. Installer: Company specializing in performing Work of this section with minimum five years’ experience.

1.6 FIELD MEASUREMENTS

A. Verify field measurements prior to fabrication.

1.7 WARRANTY

A. Furnish manufacturer’s standard warranty.

B. Extended Warranty: Provide as an add-alt, additional cost for the manufacturer’s Whole Unit Parts Extended Warranty.

PART 2 PRODUCTS

2.1 AIR-COOLED SCROLL CHILLER

A. Manufacturer:

1. TRANE Model CGAM Air Cooled Scroll Chiller

2. Approved equal.

2.2 Electrical Characteristics and Components

A. Service equipment and voltages for the facility are shown on the attached electric riser diagram.

B. Contractor shall make best use of existing infrastructure unless directed otherwise.

PART 3 EXECUTION

3.1 INSTALLATION

A. Align chiller(s) on approved roof mount.

B. Arrange piping for easy dismantling to permit tube cleaning.

3.2 FIELD QUALITY CONTROL

A. Furnish cooling season start-up, winter season shutdown service, for first year of operation.

When initial start-up and testing takes place in winter and machines are to remain inoperative. Repeat start-up and testing operation at beginning of first cooling season.

3.3 MANUFACTURER’S FIELD SERVICES

A. Furnish services of factory trained representative as required to comply with manufacturer’s warranty requirements and to instruct Government on operation and maintenance.

B. Furnish initial charge of refrigerant and oil.

3.4 ADJUSTING

A. Furnish cooling season start-up, winter season shutdown service, for first year of operation.

3.5 DEMONSTRATION AND TRAINING

A. Demonstrate system operations and verify specified performance Demonstrate low ambient operation during winter testing for air-cooled condensers.

DIVISION 16 ELECTRICAL

SECTION 16000 ELECTRICAL

PART 1 GENERAL

1.1 SCOPE

A. The work covered by this section includes the furnishing of labor and materials, equipment, and incidentals and the performing of operations in connection with "electrical work" as indicated on the drawings and/or specified herein and including incidental items to affect a finished, complete and operable system as indicated. The electrical work shall include but not be limited to:

PROJ NAME: Chiller Replacement

1. Perform all electrical work in accordance with requirements of 2011 NEC, NFPA 72 and NFPA 101.

2. Provide new wiring and disconnects for HVAC equipment and controls as required.

B. Work shall be subject to the conditions of the contract and shall be in strict accordance with these plans and specifications.

1.2 CODES AND STANDARDS

A. Where referred to, published standard specifications of technical societies, trade associations and governmental agencies codes and regulations of Underwriters and protective organizations, Federal, State and Municipal regulations and codes and publications of a similar nature shall be the edition current as of the date of this Specification.

B. The applicable requirements of the latest publications of the following organizations shall apply to the work under this section as if fully written herein:

1. American National Standards Institute, Inc. (ANSI)

2. National Electrical Manufacturers Associations (NEMA)

3. National Fire Codes (NFPA)

4. Underwriters Laboratories, Inc. (UL)

5. Federal, State and Municipal Building Codes.

6. National Electrical Code (NEC)

7. Americans with Disabilities Act (ADA)

8. Occupational Safety and Health Administration (OSHA)

1.3 MATERIALS AND EQUIPMENT

A. Materials shall be of the best quality. Workmanship shall be of highest grade and construction shall be done according to best practices of the trade.

B. Provide, when required, labeled samples of material or equipment specified herein or proposed to be used in this work.

C. Where words "furnish", "provide", or "install" are mentioned, either singly or in combination, these words are hereby interpreted to mean "furnish and install" or "provide and install", including materials complete with connections, supplemental devices, accessories and appurtenances, unless specifically noted otherwise. These words are likewise hereby interpreted as being prefixed to materials, equipment, and apparatus hereinafter mentioned, either in abbreviated or scheduled information or in the technical sections of the specifications.

1.4 PROTECTION OF EQUIPMENT AND MATERIALS

A. Protect equipment and material for the electrical work after delivery, before and after installation. This protection must be extended against pilferage, dampness and damages from all causes until the work is accepted by the owner.

1.5 MATERIALS AND INSTALLATION

PROJ NAME: Chiller Replacement

A. Only the best materials of each class specified shall be used and the installation shall be made in a neat and workmanlike manner, complete in every detail, ready for immediate satisfactory operation by the Government.

PART 2 PRODUCTS

2.1 MATERIALS GENERAL

A. Unless otherwise indicated, the materials to be furnished under this specification shall be the standard products of manufacturers regularly engaged in the production of such equipment and shall be the manufacturer's latest standard design that complies with the specification requirements.

B. Materials shall be delivered to the site in the original sealed containers of packages bearing the manufacturer's name and brand designated. Materials shall be stored in a clean, well-ventilated, warm area. Care shall be exercised in handling materials during delivery, storage and installation. Materials damaged, in the opinion of the Architect, shall be replaced at no additional cost to the Government.

2.2 EQUIPMENT MOUNTING AND SUPPORTS

A. Provide supports including supplementary steel, channels, rods and guys required for the proper installation, mounting and support of equipment.

B. Except as otherwise required by the Contract Documents the type and size of supports shall be as determined by the Contractor and shall be of sufficient strength and size to allow only a minimum deflection as required by codes or standards and the support manufacturer's requirements for loading.

C. Supports shall be installed in a neat and workmanlike manner, perpendicular or parallel to walls, floor, columns, beams or ceilings.

2.3 GROUNDING

A. Furnish and install grounding system as required by codes or standards.

B. Flexible metal conduit and electric metallic tubing feeder raceways shall include grounding conductor.

C. Grounding conductors shall be stranded copper wire with green color insulation. Grounding conductors shall be run with all circuits, feeders, etc. Raceways alone will not be considered as a grounding means.

D. Grounding bushings shall be provided for raceways where required.

E. Provide exterior inter-system ground in accordance with NFPA 70, 250.94.

2.4 RACEWAYS

A. Install wiring in electric metallic tubing (EMT), and or schedule 40 PVC. Schedule 40 PVC may be used outside only, raceways within the building shall be metal.

2.5 CONDUCTORS - WIRE AND CABLE

A. Joints and splices shall be made in a manner equivalent electrically and mechanically to the conductor itself.

B. Conductors shall be color coded - Phase A: black, Phase B: red, Neutral: white, Ground: green.

C. Colors, except colors for conductors No. 4 and larger, shall be factory applied the entire length of the conductors by solid color compound, solid color coating or colored striping or bands, 2 sets 180 degree apart. On-site coloring shall not be done, except color coding by means of paint or tapes is acceptable only for conductors No. 4 and larger.

D. Voltage rating, manufacturers, type and conductor, AWG size indication shall be continuous, factory applied the entire length for each conductor.

E. Wire No. 8 AWG and larger shall be stranded. Wires smaller than No. 8 AWG shall be solid.

F. Minimum wire size is #12 AWG.

2.6 PULL BOXES AND JUNCTION BOXES

A. Pull boxes of code gauge galvanized steel with screw covers to match, shall be as required.

2.7 NAMEPLATES

A. Provide nameplates for motor disconnect switches, and motor starters designating equipment controlled and function.

B. Nameplates shall be laminated plastic with engraved white letters. Letters shall be 1/4 inches high. Nameplates shall have identifying color background for each system.

2.8 MECHANICAL SYSTEM CONNECTIONS

A. Connect mechanical equipment as shown on the drawings. Control wiring shall be furnished and installed by the Mechanical Contractor.

2.9 ENCLOSED DISCONNECTS

A. Disconnect Switches:

1. Acceptable Manufacturers

a. Square D

b. Westinghouse

c. Eaton (CH)

d. General Electric

2. Fusible Switch Assemblies: NEMA KS 1; Type HD; quick-make, quick-break, load interrupter enclosed knife switch with externally operable handle interlocked to prevent opening front cover with

PROJ NAME: Chiller Replacement switch in ON position. Handle lockable in OFF position. Fuse Clips: Designed to accommodate Class R or J fuses as applicable.

3. Non-Fusible Switch Assemblies: NEMA KS 1; Type HD; quick-make, quick-break, load interrupter enclosed knife switch with externally operable handle interlocked to prevent opening front cover with switch in ON position. Handle lockable in OFF position.

4. Enclosures: NEMA KS 1; Provide labels for all disconnects describing loads served. Provide Arc Flash labels in accordance with NFPA 70, Article 110.

B. Fuses:

1. Manufacturers:

a. Buss

b. Chase Shawmut

c. Cooper

2. Fuses 600 Amperes and Less: ANSI/UL 198C, Class J; ANSI/UL 198E, Class RK1; RK5; dual element, current limiting, time delay, one-time fuse, 250 or 600 volt as indicated or required.

3. Interrupting Rating: 200,000 rms amperes.

2.10 MOTOR STARTERS

A. Combination-Starter, Factory-assembled combination of contactor, solid state overloads, OCPD (MCP), and disconnecting means.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Eaton Electrical Inc.; Cutler-Hammer Business Unit.

b. General Electric Company; GE Consumer & Industrial - Electrical Distribution.

c. Rockwell Automation, Inc.; Allen-Bradley brand.

d. Siemens Energy & Automation, Inc.

e. Square D; a brand of Schneider Electric.

B. Enclosures:

1. Enclosed Controllers: NEMA-ICS-6, to comply with environmental conditions at installed location.

a. Dry and Clean Indoor Locations: Type 1.

b. Outdoor Locations: Type 3R.

d. Other Wet or Damp Indoor Locations: Type 4.

C. Accessories:

1. Cover gaskets for Type 1 enclosures.

PART 3 EXECUTION

3.1 COORDINATION

A. It shall be the responsibility of this contractor to coordinate his work with other trades to insure that his work is terminated is a satisfactory manner.

3.2 WORKMANSHIP AND PREPARATION

PROJ NAME: Chiller Replacement

A. Work shall be executed in a workmanlike manner by experienced electricians in accordance with the most modern engineering practice and shall present a neat appearance when completed. The work shall be carefully laid out in advance and where cutting, channeling, chasing, or drilling of floors, walls, partitions, and ceiling or other surfaces is necessary for the proper installation, support or anchorage of the conduit, raceways or other electrical work, this work shall be carefully done and any damage to the building, piping or equipment shall be repaired by skilled mechanics of the trades involved and at no additional cost to the Government.

B. After installation, electrical equipment shall be protected to prevent damage during the construction period. Openings in conduits and boxes shall be closed to prevent entrance of foreign materials. The interior of boxes and cabinets shall be left clean, exposed surfaces shall be cleaned and plated surfaces polished.

3.3 OBTAINING INFORMATION

A. Obtain information from the manufacturers of the apparatus which is to be provided for the proper methods of installation. Also obtain information from the General Contractor and other Sub- Contractor which may be necessary to facilitate work and the completion of the whole project.

3.4 RACEWAYS

A. Raceways, where applicable, shall be supported and secured at intervals of not more than 10 ft.

with minimum of two supports shall be provided if required. Tie wire or perforated metal straps shall not be used to support or secure raceways or other equipment. Electric metallic tubing shall be supported within 18: of each coupling or connector. In finished areas, furnish and install escutcheons for exposed conduit passing through or entering finished floors or walls.

B. Expansion coupling shall be provided in each raceway crossing building expansion joint and when length of raceway requires expansion coupling, expansion coupling shall have a total minimum expansion of 4" and shall have a flexible bonding conductor. Setting of expansion coupling shall be a function of the temperature at the time of installation. Flexible couplings shall be provided where required.

3.5 INTENT OF DRAWINGS

A. It is not intended that the drawings show in detail every conduit, junction box, etc., but material necessary to complete the electrical system in accordance with the best practices of the trade and to the complete satisfaction of the Government, shall be furnished without additional recompense under this section of the specifications.

AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

PROJ NAME: Chiller Replacement

AGAR 452.211-73 Attachments To Statement Of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

E.1 FAR 52.246-12 Inspection of Construction (Aug 1996)

The Contractor is responsible for performing or having performed all inspections and tests necessary to substantiate that the supplies or services furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers' parts. This clause takes precedence over any Government inspection and testing required in the contract's specifications, except for specialized inspections or tests specified to be performed solely by the Government.

(End of clause)

SECTION F--DELIVERIES OR PERFORMANCE

FAR 52.211-10 -- Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to

(a) commence work under this contract within 14 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than December 31, 2014. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

Alternate I (Apr 1984). If the completion date is expressed as a specific calendar date, computed on the basis of the contractor receiving the notice to proceed by a certain day, add the following paragraph to the basic clause:

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by July 18, 2014. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

FAR 52.225-9 -- Buy American Act–Construction Materials (Sep 2010)

(a) Definitions. As used in this clause--

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C.

App. 1702), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

PROJ NAME: Chiller Replacement

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means--

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: ______ [Contracting Officer to list applicable excepted materials or indicate “none”]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American Act.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material.

However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the…