Construction and Materials Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract of Offers.pdf | ||
| Amendment 1.pdf | ||
| Site Showing Notes.pdf | ||
| Wage Rates - Erie County.pdf | ||
| Colonial Drive_Approved Drawings.pdf | ||
| SF1442.pdf | ||
| Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NY-COLONIAL DRIVE NRCS-NEH-20 4-1
Construction Specification 4—Channel Clearing and Shaping
1. Scope The work consists of clearing designated areas by the removal and disposal of trees, logs, stumps, shrubs, brush, and rubbish, and the shaping of the channel.
2. Protection of existing vegetation Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the duration of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.
Earthfill, stockpiling of materials, vehicle or equipment parking, and excessive foot or vehicle traffic shall not be allowed within the drip line of vegetation designated to remain in place.
Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.
Any cuts, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.
Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk.
All roots 1 inch or larger in diameter that are cut, broken, or otherwise severed during channel shaping shall have the end smoothly cut perpendicular to the root. Roots exposed during channel shaping operations shall be covered with moist soil as soon as possible to prevent roots from drying out.
3. Marking The limits of the area(s) to be cleared and shaped are marked by stakes, flags, paint, tree markings, or other suitable methods or as specified in section 8 of this specification, or they will be shown on the drawings. Trees to remain standing, undisturbed, and uninjured are designated by special markings.
4. Clearing Trees and other vegetation marked for clearing shall be cut off as near the ground surface as conventional tools and equipment normally permit. All trees not marked for preservation and all snags, logs, brush, shrubs, stumps, and rubbish shall be cleared from within the area limits identified.
5. Disposal All woody material, vegetation, and rubbish resulting from clearing from designated areas shall be disposed of at the locations and in a manner shown on the drawings, or as specified in section 8 of this specification.
NY-COLONIAL DRIVE NRCS-NEH-20 4-2
6. Shaping The channel bottom and side slopes shall be shaped as shown on the drawings. The resulting shaped channel surface shall be reasonably smooth. Material excavated during the channel shaping operation shall be removed from the channel and disposed of as specified in section 8 of this specification.
7. Measurement and payment Method 1—For items of work for which specific unit prices are established by the contract, the designated cleared and shaped area is measured and the area determined to the nearest 0.1 acre.
Payment for clearing and shaping is made at the contract unit price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.
Method 2—For items of work for which specific unit prices are established by the contract, the length of the cleared and shaped channel designated is measured to the nearest 100 feet. Payment for clearing and shaping is made at the contract unit price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory performance of the work.
Method 3—For items of work for which specific unit prices are established by the contract, the cleared and shaped area(s) is measured and the area determined to the nearest 0.1 acre. The designated cleared and shaped area(s) is determined from the measured width at representative sections and the distance between the sections. Payment for clearing and shaping is made at the contract unit price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.
Method 4—For items of work for which specific lump sum prices are established by the contract, the extent of clearing and shaping is not measured or determined for payment. Payment for clearing and shaping is made at the contract lump sum price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and items to which they have been made subsidiary are identified in section 8 of this specification.
NY-COLONIAL DRIVE NRCS-NEH-20 4-3
8. ITEMS OF WORK AND CONSTRUCTION DETAILS
The items of work to be performed in conformance with this specification and the construction details are:
A. Bid Item 2, Channel Clearing
1. This item shall consist of clearing within the construction limits as designated by the drawings and NRCS representative. Work generally involves clearing brush and trees.
2. In Section 5, Disposal, all materials shall be disposed of at a pre-approved off-site location. Disposal site shall be approved NRCS prior to disposal.
3. In Section 7, Measurement and Payment, Payment will be by Method 4.
NY-COLONIAL DRIVE NRCS-NEH-20 5-1
Construction Specification 5—Pollution Control
The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.
2. Material All material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.
3. Erosion and sediment control measures and works The measures and works shall include, but are not limited to, the following:
Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.
Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.
Mulching—Mulching to provide temporary protection of the soil surface from erosion.
Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.
Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.
Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Sediment filters—Straw bale filters or geotextile sediment fences trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under or around them. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Other—Additional protection measures as specified in section 8 of this specification or required
NY-COLONIAL DRIVE NRCS-NEH-20 5-2
by Federal, State, or local government.
4. Chemical pollution The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to dispose of chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer washwater, or asphalt, produced as a by-product of the construction activities. At the completion of the construction work, sumps shall be removed and the area restored to its original condition as specified in section 8 of this specification. Sump removal shall be conducted without causing pollution.
Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.
5. Air pollution The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.
Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.
All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.
6. Maintenance, removal, and restoration All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.
7. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.
Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment.
Payment of the lump sum contract price will constitute full compensation for completion of the work.
NY-COLONIAL DRIVE NRCS-NEH-20 5-3
Method 3—For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.
NY-COLONIAL DRIVE NRCS-NEH-20 5-4
8.
ITEMS OF WORK AND CONSTRUCTION DETAILS
Items or work to be performed in conformance with this specification and the construction details therefore are:
A.
Subsidiary Item, Pollution Control
1. This item shall consist of applying and performing all construction activities in a manner that will minimize water pollution, air pollution, and soil erosion. It shall include maintenance and installation of the following:
a. Temporary stream crossings.
b. Sediment basins to receive outflows from pumps used to remove water.
c. Diversions and/or coffer dams.
2. Special precautions shall be taken in the scheduling and use of construction equipment to minimize erosion. The crossing of live streams by fording will not permitted. Temporary stream crossing such as culverts or bridges shall be installed and maintained as necessary, to allow equipment to cross without entering the stream.
3. Stabilized construction entrances shall be maintained in a condition that will prevent tracking or flowing of sediment onto public right-of-ways, including cleanout and paving with additional stone as conditions demand. All sediment spilled, dropped, washed or tracked onto public right-of-ways shall be removed immediately.
4. Excavation and Clearing operations shall not be started until pollution control measures are in place to control runoff and the sediment from respective work area.
5. In Section 2, MATERIALS
a. Stone pavement for stabilized construction entrance shall be Type 2 or Type 4 as specified in NYS DOT Specification Section 304 and shall be crushed.
, the following material specifications shall be followed:
b. Culverts used for temporary stream crossing shall be of sufficient strength and durability to withstand the loadings of the equipment that will be crossing. Damaged culverts shall be replaced immediately.
6. In Section 5, AIR POLLUTION
, firebreaks or guards shall not be required.
Burning of any material shall not be permitted.
7. In Section 7, MEASUREMENT AND PAYMENT, no separate payment shall be made for pollution control. Compensation for Pollution Control shall be included in the payment of Bid Item 3, Removal of Water.
NY-COLONIAL DRIVE NRCS-NEH-20 8-1
Construction Specification 8—Mobilization and Demobilization
The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.
2. Equipment and material Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.
Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.
This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.
3. Payment Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.
Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.
NY-COLONIAL DRIVE NRCS-NEH-20 8-2
4. ITEMS OF WORK AND CONSTRUCTION DETAILS
A. Bid Item 1, Mobilization and Demobilization
1. This item shall consist of mobilization and demobilization of forces and equipment under this contract. Access to the project will be at the Kenyon Residence, 6564 Colonial Drive, Boston, New York.
2. Payment will be made after restoration of private property to a before project condition and to the satisfaction of NRCS. All costs associated with property restoration shall be included in this item.
NY-COLONIAL DRIVE NRCS-NEH-20 11-1
Construction Specification 11—Removal of Water
1. Scope The work consists of the removal of surface water and ground water as necessary to perform the construction required by the contract in accordance with the specifications. It shall include: (1) constructing, installing, building, and maintaining all necessary temporary water containment facilities, channels, and diversions; (2) furnishing, installing, and operating all necessary pumps, piping, and other facilities and equipment; and (3) removing all such temporary works and equipment after their intended function is no longer required.
2. Diverting surface water The contractor shall install, maintain, and operate all cofferdams, channels, flumes, sumps, and all other temporary diversion and protective works needed to divert streamflow and other surface water through or around the construction site. Control of surface water shall be continuous during the period that damage to construction work could occur. Unless otherwise specified and/or approved, the diversion outlet shall be into the same drainageway that the water would have reached before being diverted.
The contractor shall furnish the contracting officer, in writing, a proposed plan for diverting surface water before beginning any construction activities for which a diversion is required, unless waived in section 8 of this specification. Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities related to this activity during the process of completing the work as specified.
3. Dewatering the construction site Foundations, cutoff trenches, and all other parts of the construction site shall be dewatered and kept free of standing water and muddy conditions as necessary for the proper execution of the work. The contractor shall furnish, install, operate, and maintain all drains, sumps, pumps, casings, well points, and all other equipment required to properly dewater the site as specified.
Dewatering systems that cause a loss of soil fines from the foundation areas will not be permitted.
The contractor shall furnish the contracting officer, in writing, a proposed plan for dewatering before commencing with any construction activity for which dewatering may be required, unless waived in section 8 of this specification. Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities for completing the specified work.
4. Dewatering borrow areas The contractor shall maintain all borrow areas free of surface water or otherwise provide for timely and effective removal of surface and subsurface water that accumulates within the borrow area, unless waived in section 8 of this specification. Borrow material shall be processed as necessary to achieve proper and uniform moisture content at the time of placement.
If pumping to dewater borrow areas is included as a bid item of work in the bid schedule, each pump discharge pipe shall be equipped with a water meter. The meter shall be such that the measured quantity of water is accurate within 3 percent of the true quantity. The contractor shall provide necessary support to perform accuracy tests of the water meter when requested by the contracting officer.
NY-COLONIAL DRIVE NRCS-NEH-20 11-2
5. Erosion and pollution control Removal of water from the construction site, including the borrow areas, shall be accomplished so that erosion and the transporting of sediment and other pollutants are minimized. Dewatering activities shall be accomplished in a manner that the water table water quality is not altered.
Pollution control activities shall not conflict with the requirements of Construction Specification 5, Pollution Control, if it is a part of this contract.
6. Removal of temporary works When temporary works are no longer needed, the contractor shall remove and return the area to a condition similar to that which existed before construction. Areas where temporary works were located shall be graded for sightly appearance with no obstruction to natural surface waterflows or the proper functioning and access to the works of improvement installed. The contractor shall exercise extreme care during the removal stages to minimize the loss of soil sediment and debris that was trapped during construction.
Pipes, casings, and any other material used to dewater the site shall be removed from temporary wells. The wells shall be filled to ground level with clean gravel or other suitable material approved by the contracting officer. The contractor shall exercise extreme care to prevent pollution of the ground water by these actions.
7. Measurement and payment Method 1—Items of work listed in the bid schedule for removal of water, diverting surface water, and dewatering construction sites and borrow areas are paid for at the contract lump sum prices. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 2—Items of work listed in the bid schedule for removal of water, diverting surface water, dewatering construction sites, and dewatering borrow areas are paid for at the contract lump sum prices. Such payment will constitute full compensation for furnishing, installing, operating, and maintaining the necessary trenches, drains, sumps, pumps, and piping and for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work. The exception is that additional payment for pumping to dewater borrow areas and the removal of water will be made as described in the following paragraph.
If pumping to dewater borrow areas is a contract bid item, payment is made at the contract unit price, which shall be the price per 1,000 gallons shown in the bid schedule. Such payment will constitute full compensation for pumping only. Compensation for equipment and preparation and for other costs associated with pumping is included in the lump sum payment for removal of water or the lump sum payment for dewatering the borrow areas. Payment is made only for pumping that is necessary to dewater borrow areas that cannot be effectively drained by gravity or that must have the water table lowered to be usable as a suitable borrow source. Pumping for other purposes will not be included for payment under this item.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the contract line item to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 8 of this specification.
NY-COLONIAL DRIVE NRCS-NEH-20 11-3
Items of work to be performed in conformance with this specification and the
A. Bid Item 3, Removal of Water
1. This item shall consist of the removal of all surface and subsurface water necessary to perform the required excavations, as well as earthfill and rock placement.
2. Any stream flow shall be diverted and the ground water level drawn down and maintained so that earthfill, bedding, and riprap are not placed in flowing or standing water.
3. The NRCS recommendation for dewatering at the site is to install a temporary instream diversion dam (using concrete block, sandbags, and plastic sheeting) just upstream of STA 5+60 across the low flow channel, and route flow into a temporarily constructed diversion ditch across the north side of the gravel bars.
4. The contractor must submit a Dewatering/Erosion and Sediment Control
Plan to NRCS for acceptance prior to commencing any work on the site.
Such plan must indicate the method to be used for diverting surface water from the work area and include the method for removing water from the toe trench excavation.
5. In Section 7, MEASUREMENT AND PAYMENT, payment for this item shall be by Method 1, contract lump sum price. Such payment shall constitute full compensation for all labor, equipment, tools and all other items necessary and incidental to the completion of the work.
6. Items of work subsidiary to this Bid Item are:
a. Pollution Control – Construction Specification 5
NY-COLONIAL DRIVE NRCS-NEH-20 21-1
Construction Specification 21—Excavation
The work shall consist of the excavation required by the drawings and specifications and disposal of the excavated materials.
2. Classification Excavation is classified as common excavation, rock excavation, or unclassified excavation in accordance with the following definitions.
Common excavation is defined as the excavation of all materials that can be excavated, transported, and unloaded using heavy ripping equipment and wheel tractor-scrapers with pusher tractors or that can be excavated and dumped into place or loaded onto hauling equipment by excavators having a rated capacity of one cubic yard or larger and equipped with attachments (shovel, bucket, backhoe, dragline, or clam shell) appropriate to the material type, character, and nature of the materials.
Rock excavation is defined as the excavation of all hard, compacted, or cemented materials that require blasting or the use of ripping and excavating equipment larger than defined for common excavation. The excavation and removal of isolated boulders or rock fragments larger than 1 cubic yard encountered in materials otherwise conforming to the definition of common excavation shall be classified as rock excavation. The presence of isolated boulders or rock fragments larger than 1 cubic yard is not in itself sufficient cause to change the classification of the surrounding material.
For the purpose of these classifications, the following definitions shall apply:
Heavy ripping equipment is a rear-mounted, heavy duty, single-tooth, ripping attachment mounted on a track type tractor having a power rating of at least 250 flywheel horsepower unless otherwise specified in section 10.
Wheel tractor-scraper is a self-loading (not elevating) and unloading scraper having a struck bowl capacity of at least 12 cubic yards.
Pusher tractor is a track type tractor having a power rating of at least 250 flywheel horsepower equipped with appropriate attachments.
Unclassified excavation is defined as the excavation of all materials encountered, including rock materials, regardless of their nature or the manner in which they are removed.
3. Blasting The transportation, handling, storage, and use of dynamite and other explosives shall be directed and supervised by a person(s) of proven experience and ability who is authorized and qualified to conduct blasting operations.
Blasting shall be done in a manner as to prevent damage to the work or unnecessary fracturing of the underlying rock materials and shall conform to any special requirements in section 10 of this specification. When specified in section 10, the contractor shall furnish the engineer, in writing, NY-COLONIAL DRIVE NRCS-NEH-20 21-2 a blasting plan before blasting operations begin.
4. Use of excavated material Method 1—To the extent they are needed, all suitable material from the specified excavations shall be used in the construction of required permanent earthfill or rockfill. The suitability of material for specific purposes is determined by the engineer. The contractor shall not waste or otherwise dispose of suitable excavated material.
Method 2—Suitable material from the specified excavations may be used in the construction of required earthfill or rockfill. The suitability of material for specific purposes is determined by the engineer.
5. Disposal of waste materials Method 1—All surplus or unsuitable excavated materials are designated as waste and shall be disposed of at the locations shown on the drawings.
Method 2—All surplus or unsuitable excavated materials are designated as waste and shall be disposed of by the contractor at sites of his own choosing away from the site of the work. The disposal shall be in an environmentally acceptable manner that does not violate local rules and regulations.
6. Excavation limits Excavations shall comply with OSHA Construction Industry Standards (29CFR Part 1926) Subpart P, Excavations, Trenching, and Shoring. All excavations shall be completed and maintained in a safe and stable condition throughout the total construction phase. Structure and trench excavations shall be completed to the specified elevations and to the length and width required to safely install, adjust, and remove any forms, bracing, or supports necessary for the installation of the work. Excavations outside the lines and limits shown on the drawings or specified herein required too meet safety requirements shall be the responsibility of the contractor in constructing and maintaining a safe and stable excavation.
7. Borrow excavation When the quantities of suitable material obtained from specified excavations are insufficient to construct the specified earthfills and earth backfills, additional material shall be obtained from the designated borrow areas. The extent and depth of borrow pits within the limits of the designated borrow areas shall be as specified in section 10 or as approved by the engineer.
Borrow pits shall be excavated and finally dressed to blend with the existing topography and sloped to prevent ponding and to provide drainage.
8. Overexcavation Excavation in rock beyond the specified lines and grades shall be corrected by filling the resulting voids with portland cement concrete made of materials and mix proportions approved by the engineer. Concrete that will be exposed to the atmosphere when construction is completed shall meet the requirements of concrete selected for use under Construction Specification 31, Concrete for Major Structures, or 32, Structure Concrete, as appropriate.
Concrete that will be permanently covered shall contain not less than five bags of cement per cubic yard. The concrete shall be placed and cured as specified by the engineer.
NY-COLONIAL DRIVE NRCS-NEH-20 21-3
Excavation in earth beyond the specified lines and grades shall be corrected by filling the resulting voids with approved, compacted earthfill. The exception to this is that if the earth is to become the subgrade for riprap, rockfill, sand or gravel bedding, or drainfill, the voids may be filled with material conforming to the specifications for the riprap, rockfill, bedding, or drainfill.
Before correcting an overexcavation condition, the contractor shall review the planned corrective action with the engineer and obtain approval of the corrective measures.
9. Measurement and payment For items of work for which specific unit prices are established in the contract, the volume of each type and class of excavation within the specified pay limits is measured and computed to the nearest cubic yard by the method of average cross-sectional end areas or by methods outlined in section 10 of this specification. Regardless of quantities excavated, the measurement for payment is made to the specified pay limits except that excavation outside the specified lines and grades directed by the engineer to remove unsuitable material is included. Excavation required because unsuitable conditions result from the contractor's improper construction operations, as determined by the engineer, is not included for measurement and payment.
Method 1—The pay limits shall be as designated on the drawings.
Method 2—The pay limits shall be defined as follows:
a. The upper limit shall be the original ground surface as it existed before the start of construction operations except that where excavation is performed within areas designated for previous excavation or earthfill, the upper limit shall be the modified ground surface resulting from the specified previous excavation or earthfill.
b. The lower and lateral limits shall be the neat lines and grades shown on the drawings.
Method 3—The pay limits shall be defined as follows:
a. The upper limit shall be the original ground surface as it existed before the start of construction operations except that where excavation is performed within areas designated for previous excavation or earthfill, the upper limit shall be the modified ground surface resulting from the specified previous excavation or earthfill.
b. The lower and lateral limits shall be the true surface of the completed excavation as directed by the engineer.
Method 4—The pay limits shall be defined as follows:
a. The upper limit shall be the original ground surface as it existed before the start of construction operations except that where excavation is performed within areas designated for previous excavation or earthfill, the upper limit shall be the modified ground surface resulting from the specified previous excavation or earthfill.
b. The lower limit shall be at the bottom surface of the proposed structure.
c. The lateral limits shall be 18 inches outside of the outside surface of the proposed structure or shall be vertical planes 18 inches outside of and parallel to the footings, whichever gives the larger pay quantity, except as provided in d below.
d. For trapezoidal channel linings or similar structures that are to be supported upon the sides of the excavation without intervening forms, the lateral limits shall be at the underside of the proposed lining or structure.
NY-COLONIAL DRIVE NRCS-NEH-20 21-4
e. For the purposes of the definitions in b, c, and d, above, any specified bedding or drainfill directly beneath or beside the structure will be considered to be a part of the structure.
All methods—The following provisions apply to all methods of measurement and payment.
Payment for each type and class of excavation is made at the contract unit price for that type and class of excavation. Such payment will constitute full compensation for all labor, materials, equipment, and all other items necessary and incidental to the performance of the work except that extra payment for backfilling overexcavation will be made in accordance with the following provisions.
Payment for backfilling overexcavation, as specified in section 8 of this specification, is made only if the excavation outside specified lines and grades is directed by the engineer to remove unsuitable material and if the unsuitable condition is not a result of the contractor's improper construction operations as determined by the engineer.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 10 of this specification.
NY-COLONIAL DRIVE NRCS-NEH-20 21-5
10.
ITEMS OF WORK AND CONSTRUCTION DETAILS
Items or work to be performed in conformance with this specification and the
Bid Item 4, Excavation, Common
1. This item shall consist of the following:
a. Excavation required to place the toe rock, slope rock (including the upstream key), and bedding along the planned alignment.
b. Excavation required to place rock and bedding for the stream barbs.
c. Excavation required to shape the in-channel gravel bars as shown on the plans.
2. In Section 4, Use of excavated material
, Method 1 shall apply.
3. In Section 5, Disposal of waste materials
, Method 2 shall apply.
4. In Section 9, Measurement and payment
, payment will not be by any of the indicated methods. Payment will be by lump sum for all excavation required to complete the work.
NY- COLONIAL DRIVE NRCS-NEH-20 23-1
Construction Specification 23—Earthfill
The work consists of the construction of earth embankments, other earthfills, and earth backfills required by the drawings and specifications.
Earthfill is composed of natural earth materials that can be placed and compacted by construction equipment operated in a conventional manner.
Earth backfill is composed of natural earth material placed and compacted in confined spaces or adjacent to structures (including pipes) by hand tamping, manually directed power tampers or vibrating plates, or their equivalent.
2. Material All fill material shall be obtained from required excavations and designated borrow areas. The selection, blending, routing, and disposition of material in the various fills shall be subject to approval by the engineer.
Fill materials shall contain no frozen soil, sod, brush, roots, or other perishable material. Rock particles larger than the maximum size specified for each type of fill shall be removed prior to compaction of the fill.
The types of material used in the various fills shall be as listed and described in the specifications and drawings.
3. Foundation preparation Foundations for earthfill shall be stripped to remove vegetation and other unsuitable material or shall be excavated as specified.
Except as otherwise specified, earth foundation surfaces shall be graded to remove surface irregularities and shall be scarified parallel to the axis of the fill or otherwise acceptably scored and loosened to a minimum depth of 2 inches. The moisture content of the loosened material shall be controlled as specified for the earthfill, and the surface material of the foundation shall be compacted and bonded with the first layer of earthfill as specified for subsequent layers of earthfill.
Earth abutment surfaces shall be free of loose, uncompacted earth in excess of 2 inches in depth normal to the slope and shall be at such a moisture content that the earthfill can be compacted against them to produce a good bond between the fill and the abutments.
Rock foundation and abutment surfaces shall be cleared of all loose material by hand or other effective means and shall be free of standing water when fill is placed upon them. Occasional rock outcrops in earth foundations for earthfill, except in dams and other structures designed to restrain the movement of water, shall not require special treatment if they do not interfere with compaction of the foundation and initial layers of the fill or the bond between the foundation and the fill.
Foundation and abutment surfaces shall be no steeper than one horizontal to one vertical unless
NY- COLONIAL DRIVE NRCS-NEH-20 23-2
otherwise specified. Test pits or other cavities shall be filled with compacted earthfill conforming to the specifications for the earthfill to be placed upon the foundation.
4. Placement Earthfill shall not be placed until the required excavation and foundation preparation have been completed and the foundation has been inspected and approved by the engineer. Earthfill shall not be placed upon a frozen surface nor shall snow, ice, or frozen material be incorporated in the earthfill matrix.
Earthfill shall be placed in approximately horizontal layers. The thickness of each layer before compaction shall not exceed the maximum thickness specified in section 10 or shown on the drawings. Materials placed by dumping in piles or windrows shall be spread uniformly to not more than the specified thickness before being compacted.
Hand compacted earth backfill shall be placed in layers whose thickness before compaction does not exceed the maximum thickness specified for layers of earth backfill compacted by manually directed power tampers.
Earth backfill shall be placed in a manner that prevents damage to the structures and allows the structures to assume the loads from the earth backfill gradually and uniformly. The height of the earth backfill adjacent to a structure shall be increased at approximately the same rate on all sides of the structure.
Earthfill and earth backfill in dams, levees, and other structures designed to restrain the movement of water shall be placed to meet the following additional requirements:
(a) The distribution of materials throughout each zone shall be essentially uniform, and the earthfill shall be free from lenses, pockets, streaks, or layers of material differing substantially in texture, moisture content, or gradation from the surrounding material.
Zone earthfills shall be constructed concurrently unless otherwise specified.
(b) If the surface of any layer becomes too hard and smooth for proper bond with the succeeding layer, it shall be scarified parallel to the axis of the fill to a depth of not less than 2 inches before the next layer is placed.
(c) The top surface of embankments shall be maintained approximately level during construction with two exceptions: A crown or cross-slope of about 2 percent shall be maintained to ensure effective drainage, or as otherwise specified for drainfill or sectional zones.
(d) Dam embankments shall be constructed in continuous layers from abutment to abutment except where openings to facilitate construction or to allow the passage of streamflow during construction are specifically authorized in the contract.
(e) Embankments built at different levels as described under (c) or (d) above shall be constructed so that the slope of the bonding surfaces between embankment in place and embankment to be placed is not steeper than 3 feet horizontal to 1 foot vertical. The bonding surface of the embankment in place shall be stripped of all material not meeting the requirements of this specification and shall be scarified, moistened, and recompacted when the new earthfill is placed against it. This ensures a good bond with the new earthfill and obtains the specified moisture content and density at the contact of the inplace and new earthfills.
NY- COLONIAL DRIVE NRCS-NEH-20 23-3
5. Control of moisture content During placement and compaction of earthfill and earth backfill, the moisture content of the material being placed shall be maintained within the specified range.
The application of water to the earthfill material shall be accomplished at the borrow areas insofar as practicable. Water may be applied by sprinkling the material after placement on the earthfill, if necessary. Uniform moisture distribution shall be obtained by disking.
Material that is too wet when deposited on the earthfill shall either be removed or be dried to the specified moisture content prior to compaction.
If the top surface of the preceding layer of compacted earthfill or a foundation or abutment surface in the zone of contact with the earthfill becomes too dry to permit suitable bond, it shall either be removed or scarified and moistened by sprinkling to an acceptable moisture content before placement of the next layer of earthfill.
6. Compaction Earthfill—Earthfill shall be compacted according to the following requirements for the class of compaction specified:
Class A compaction—Each layer of earthfill shall be compacted as necessary to provide the density of the earthfill matrix not less than the minimum density specified in Section 10 or identified on the drawings. The earthfill matrix is defined as the portion of the earthfill material finer than the maximum particle size used in the compaction test method specified.
Class B compaction—Each layer of earthfill shall be compacted to a mass density not less than the minimum density specified.
Class C compaction—Each layer of earthfill shall be compacted by the specified number of passes of the type and weight of roller or other equipment specified or by an approved equivalent method. Each pass shall consist of at least one passage of the roller wheel or drum over the entire surface of the layer.
Earth backfill—Earth backfill adjacent to structures shall be compacted to a density equivalent to that of the surrounding inplace earth material or adjacent required earthfill or earth backfill.
Compaction shall be accomplished by hand tamping or manually directed power tampers, plate vibrators, walk-behind, miniature, or self-propelled rollers. Unless otherwise specified heavy equipment including backhoe mounted power tampers or vibrating compactors and manually directed vibrating rollers shall not be operated within 2 feet of any structure. Towed or self-propelled vibrating rollers shall not be operated within 5 feet of any structure. Compaction by means of drop weights operating from a crane or hoist is not permitted.
The passage of heavy equipment will not be allowed:
• Over cast-in-place conduits within 14-days after placement of the concrete
• Over cradled or bedded precast conduits within 7 days after placement of the concrete cradle or bedding
• Over any type of conduit until the backfill has been placed above the top surface of the structure to a height equal to one-half the clear span width of the structure or pipe or 2 feet, whichever is greater, except as may be specified in section 10.
Compacting of earth backfill adjacent to structures shall not be started until the concrete has
NY- COLONIAL DRIVE NRCS-NEH-20 23-4
attained the strength specified in section 10 for this purpose. The strength is determined by compression testing of test cylinders cast by the contractor's quality control personnel for this purpose and cured at the work site in the manner specified in ASTM C 31 for determining when a structure may be put into service.
When the required strength of the concrete is not specified as described above, compaction of earth backfill adjacent to structures shall not be started until the following time intervals have elapsed after placement of the concrete.
Structure Time interval (days)
Vertical or near-vertical walls with earth loading on one side only 14
Walls backfilled on both sides simultaneously 7
Conduits and spillway risers, cast-in-place (with inside forms in place) 7
Conduits and spillway risers, cast-in-place (inside forms removed) 14
Conduits, pre-cast, cradled 2
Conduits, pre-cast, bedded 1
Cantilever outlet bents (backfilled both sides simultaneously) 3
7. Reworking or removal and replacement of defective earthfill Earthfill placed at densities lower than the specified minimum density or at moisture contents outside the specified acceptable range of moisture content or otherwise not conforming to the requirements of the specifications shall be reworked to meet the requirements or removed and replaced by acceptable earthfill. The replacement earthfill and the foundation, abutment, and earthfill surfaces upon which it is placed shall conform to all requirements of this specification for foundation preparation, approval, placement, moisture control, and compaction.
8. Testing During the course of the work, the engineer will perform quality assurance tests required to identify material; determine compaction characteristics; determine moisture content; and determine density of earthfill in place. Tests performed by the engineer will be used to verify that the earthfills conform to contract requirements of the specifications and not as a replacement for the contractor's quality control program.
Densities of earthfill requiring Class A compaction will be determined in accordance with ASTM D 1556, D 2167, D 2922, or D 2937 except that the volume and moist weight of included rock particles larger than those used in the compaction test method specified for the type of fill will be determined and deducted from the volume and moist weight of the total sample before computation of density or, if using the nuclear gauge, added to the specified density to bring it to the measure of equivalent composition for comparison (See ASTM D 4718). The density so computed is used to determine the percent compaction of the earthfill matrix. Unless otherwise specified, moisture content is determined by one of the following methods: ASTM D 2216, D 3017, D 4643, D 4944, or D 4959.
9. Measurement and payment
NY- COLONIAL DRIVE NRCS-NEH-20 23-5
For items of work for which specific unit prices are established in the contract, the volume of each type and compaction class of earthfill and earth backfill within the specified zone boundaries and pay limits is measured and computed to the nearest cubic yard by the method of average cross-sectional end areas.