DollyCopp_FS_SupplementalSpecificationsandSoilBoringData.pdf

PDF 2 MB Posted

Attached to
Dolly Copp Campground Renovation Federal contract opportunity
Solicitation number
AG-1484-S-16-0002
Issued by
Department of Agriculture Forest Service R9-Eastern Region

About this file

Dolly Copp_FS_SupplementalSpecificationsandSoilBoringData

View the file

Other files for this federal contract opportunity

Other files attached to Dolly Copp Campground Renovation, newest first.
File Type Posted
Dolly_Copp_Scope_of_Work_(3).docx DOCX document
DollyCopp_100RevisedConstructionSpecifications_20150507.pdf PDF
DollyCopp_100RevisedConstructionPlans_20150507.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Supplemental Standard Specifications for Construction of Roads and Bridges on Federal

Highway Projects (FP-03) And

Soil Boring Data

FP03 SUPPLEMENTAL SPECIFICATIONS

- Preface

101 - Terms, Format, and Definitions

102 - Bid, Award, and Execution of Contract

103 - Scope of Work

104 - Control of Work

105 - Control of Material

106 - Acceptance of Work

107 - Legal Relations and Responsibility to the Public

108 - Prosecution and Progress

109 - Measurement and Payment

155 - Schedules for Construction Contracts

201 - Clearing and Grubbing

204 - Excavation and Embankment

251 – Riprap

552 - Structural Concrete

625 - Turf Establishment

626 – Plants, Trees, Shrubs, Vines, and Groundcovers

635 - Temporary Traffic Control

704 – Soil

705 – Rock

714 - Geotextile and Geocomposite Drain Material

Preface

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

101 - Terms, Format, and Definitions

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp Milepost ppm Part Per Million

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

101-1 http://www.nist.gov/

Contracting Officer’s Representative (COR)-- Authorized representative of the contracting officer acting within the limits of authority as delegated by the contracting officer.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

101-2

Figure 101-1—Illustration of road structure terms.

101-3

102 - Bid, Award, and Execution of Contract

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

102-1

103 - Scope of Work

Deletions

Delete all but subsection 103.01 Intent of Contract.

103-1

104 - Control of Work

Deletions

Delete Sections 104.01, 104.02, and 104.04.

104.03 Specifications and Drawings.

Add the following:

(c) As-Built-Plans. Furnish one set of as built plans. The Government will provide one set of contract plans to be used exclusively for recording the as-built details of the project. Clearly mark changes, deletions, and addition’s using USDA Forest Service drafting standards to show actual construction conditions. Show additions in red, deletions in green, and special instruction in blue.

Note all additions or revisions to the location, character, and dimensions of the prescribed work shown on the contract plans. Line out all details shown that are not applicable to the completed work. Check off details shown that were incorporated into the completed work without change.

Retain the plans at the project site and, as work progresses, continually update them to reflect the as-built details. Upon request, make the plans available to the CO to review for compliance with these specifications.

Show the following types of changes on the as-built plans:

(1) Typical section(s)

• Revisions in dimensions

• (b) Revisions in materials

(2) Plan and profile

• Revisions to the alignment

• Changes in the construction limits

• Revisions in location, type, and grade of road approaches

• Location and type of utilities

• Location, size, and type of underdrains

• Skew of culverts

• Channel changes

• Location of monuments and permanent references

• Elevations for all aerial and underground crossings of utilities

• Location, length, and type of fencing

• Revisions to grades, elevations, and stationing of intersection PIs

• Equations

• Culvert diameter, length, type, and stationing. On culvert extensions, indicate the length of the existing pipe and the length of the extension.

• Location, length, stationing, and type of retaining walls

• Location, length, stationing, and end treatment of guardrail

104-1

(3) Bridge

Stationing of bridge ends

• Revisions to footing and seal elevations

• Pile length, size, type, and tip elevation

• Any changes in plan or dimensions including any major changes in reinforcing

(4) Miscellaneous

• Revisions to parking areas or turnouts

• (b) Final location, type and length of curbs, sidewalks, etc.

Furnish the as-built working plans to the CO before the final inspection. Correct all details found during the final inspection that are not shown on the as-built plans and return to the CO within 5 days.

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

104-2

105 - Control of Material

105.02 Material Sources.

105.02(a) Government-provided sources.

Add the following:

Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

105-1

106 - Acceptance of Work

106.07 Delete

Delete subsection 106.07.

106-1

107 - Legal Relations and Responsibility to the Public

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

• Exact time and location of spill including a description of the area involved.

• Containment procedures.

• Summary of any communications the Contractor had with news media, Federal, State and local regulatory agencies and officials, or Forest Service officials.

• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

• When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

• The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, State, and local laws and regulations.

107-1

108 - Prosecution and Progress

108 Delete.

Delete Section 108 in its entirety.

108-1

109 - Measurement and Payment

109 Deletions

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of ±15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

109-1

155 - Schedules for Construction Contracts

155 Delete.

Delete Section 155 in its entirety.

155-1

201 - Clearing and Grubbing

201.02 Material:

Delete Tree wound dressing material reference.

201.03 General.

Delete the last sentence.

201.04 Clearing.

Delete the last sentence of (d).

201.01 Description

Replace with the following

This work consists of clearing and grubbing within clearing limits and other designated areas.

201.04 Clearing.

Add the following:

When marked in advance, remove dead trees over 6 inches in diameter measured at 12 inches above the ground that lean toward the road and are tall enough to reach the roadbed.

201.04 Clearing. (c)

Delete paragraph (c) and replace with the following:

(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground.

201.04 Clearing.

Delete subsection (d) and replace with the following:

(d) Do not cut vegetation less than 3 feet tall and less than 3 inches in diameter, that is within the clearing limits but beyond the roadway and not in a decking area, and that does not interfere with sight distance along the road.

Add the following:

(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.

(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.

201-1

204 - Excavation and Embankment

Replace Section 204 in its entirety with the following:

Description

204.01 This work consists of the following:

(a) Trench excavation material and labor.

(b) Temporary shoring.

(c) Protection of adjacent work.

(d) Backfilling with native or imported materials.

(e) Barricades and protection devices.

(f) Compaction.

(g) Disposal of unused materials.

(h) Excavation Dewatering.

(i) Rock excavation.

(j) Fine grading

204.02 Definitions.

(a) Excavation consists of removal of material encountered to subgrade elevations indicated and subsequent disposal of materials removed.

(b) Unauthorized excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without specific direction of the Owner’s Designated Representative. Unauthorized excavation, as well as remedial work directed by the Owner’s Designated Representative, shall be at Contractor's expense.

(c) Backfill and compact unauthorized excavations as specified for authorized excavations of same classification, unless otherwise directed by the Owner’s Designated Representative.

(d) Additional Excavation: When excavation has reached required subgrade elevations, notify the Owner’s Designated Representative, who will make inspection of conditions.

If Owner’s Designated Representative determines that bearing materials at required subgrade elevations are unsuitable, continue excavation until suitable bearing materials are encountered and replace excavated material as directed by Owner’s Designated Representative.

204-1

Subgrade: Undisturbed/unexcavated earth or compacted soil layer immediately below subbase, drainage fill, or topsoil materials.

(e) Structure: Buildings, foundations, slabs, tanks, curbs or other manmade stationary features occurring above or below ground surface.

(f) Subbase: Compacted material of required type and thickness as detailed specifically for this project and located immediately above subgrade in roadways, sidewalks, etc.

(g) Rock: Material in beds, ledges, unstratified masses, conglomerate deposits, and boulders of rock material 3/4 cu. yd. or more in volume that exceeds a standard penetration resistance of 100 blows/2 inches when tested by an independent geotechnical testing agency, according to ASTM D 1586.

204.03 Quality Assurance.

(a) Codes and Standards: Perform excavation work in compliance with applicable requirements of authorities having jurisdiction.

(b) Contractor must follow excavation safety practices as mandated by 29 CFR Part 1926

(OSHA).

(c) Special Inspections: The Contractor shall retain the services of a qualified Special Inspector for this project. The Special Inspector will provide and/or coordinate inspection and testing requirements in accordance with the provisions of Chapter 17 of the International Building Code and the Statement of Special Inspections. The Contractor shall provide access as required for the special inspections to take place. The Contractor shall notify the Special Inspector of the construction schedule so that the inspections are completed in a timely manner. The Special Inspector or Contractor will retain an independent geotechnical testing agency to perform soil and material testing and inspection services during the earthwork operations. It shall be the Contractor’s responsibility to notify the testing agency when the work will be ready for testing. A minimum of 48 hours notice will be required.

204.04 Project Conditions.

(a) Existing Utilities. Locate existing underground utilities in areas of excavation work. If utilities are indicated to remain in place, provide adequate means of support and protection during earthwork operations.

a. Should uncharted, or incorrectly charted, piping or other utilities be encountered during excavation, consult Owner’s Designated Representative immediately for directions. Cooperate with Owner’s Designated Representative and utility

204-2 companies in keeping respective services and facilities in operation. Repair damaged utilities to satisfaction of Owner’s Designated Representative.

Contractor will be responsible for repair costs caused by construction activities.

b. Do not interrupt existing utilities serving facilities occupied by the Owner or others, during occupied hours, except when permitted in writing by Owner’s Designated Representative and then only after acceptable temporary utility services have been provided.

c. Provide minimum of 72-hour notice to the Owner’s Designated Representative and receive written notice to proceed before interrupting any utility.

(b) Use of Explosives. Use of explosives is NOT permitted.

(c) Protection of Persons and Property. Barricade open excavations occurring as part of this work and post with warning lights.

a. Operate warning lights as recommended by authorities having jurisdiction.

b. Protect structures, utilities, sidewalks, pavements and other facilities from damage caused by settlement, lateral movement, undermining, washout and other hazards created by earthwork operations.

c. Perform excavation by hand within drip-line of large trees to remain. Protect root systems from damage or dry-out to greatest extent possible. Maintain moist condition for root system and wrap exposed roots with microrhizae fabric and cover with soil compost as soon as possible.

(d) Dewatering. Where water is encountered in excavations, notify the Owner’s Designated Representative and submit method for temporary water diversion. Remove water during installation operations and maintain excavation area water-free until installation operations are complete. If installing pipe, do not allow water or deleterious material to enter pipe at any time.

(e) Rock Excavation. Excavate to subgrade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include rock, soil materials, and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for rock excavation or removal of obstructions.

a. If excavated materials intended for fill and backfill include unsatisfactory soil materials and rock, replace with satisfactory fill materials.

Material

204-3

204.05 Conform to the following Subsections:

Backfill material 704.03 Select borrow 704.07 Select topping 704.08 Topping 704.05 Unclassified borrow 704.06 Water 725.01

Construction Requirements

204.06 Preparation:

A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations.

B. Protect subgrades and foundation soils against freezing temperatures or frost.

Provide protective insulating materials as necessary.

C. Provide erosion control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways. All existing storm structures in the vicinity of the work are to receive inlet sediment protection until the ground surface is stabilized.

204.07 Stability of Excavations:

A. General: Comply with local codes, ordinances and requirements of agencies having jurisdiction.

B. Slope sides of excavations to comply with local codes, ordinances and requirements of agencies having jurisdiction. Shore and brace where sloping is not possible because of space restrictions or stability of material excavated.

Maintain sides and slopes of excavations in safe condition until completion of backfilling.

C. Shoring and Bracing: Provide materials for shoring and bracing, such as sheet piling, uprights, stringers and cross braces, in good serviceable condition.

Provide and install as required to insure safety of persons and property and in compliance with all local, State and Federal regulations.

D. Trenches may be widened to provide stable slopes in lieu of sheeting; however, this will not change specified pay limits. Remove sheeting as backfill progresses when safe from collapse.

204.08 Storage of Excavated Materials:

204-4

A. Stockpile excavated materials acceptable for backfill and fill adjacent to excavations or as directed. Place, grade and shape stockpiles for proper drainage.

1. Locate and retain soil materials away from edge of excavations. Do not store within drip line of trees indicated to remain.

2. Install silt fence protection on down slope side of stockpile.

3. Dispose of excess excavated soil material and materials in a legal manner when determined by Owner’s Designated Representative not acceptable for use as backfill or fill.

204.09 Excavation for Site Work:

A. Excavate trenches or areas to uniform width down to virgin soil, sufficiently wide to provide ample working room. Remove all existing material and debris.

Prepare the subgrade by the following method:

1. Proof compact the subgrade, in the presence of the Owner’s Designated Representative, with a smooth steel drum non-vibratory compactor with a static weight of at least five (5) tons. Perform proof compaction operations by completing at least six (6)-overlapping passes of the compactor operating in the non-vibratory mode. Excavate all areas, which fail to stabilize, or become unstable after proof rolling, backfill with structural fill material and conduct proof compaction operations as described above.

B. Excavate trenches or areas to depth indicated or required to establish indicated foundation elevations and to support foundations on undisturbed soil. Fill depressions with tamped subbase fill.

204.10 Trench Excavation for Pipes and Conduits:

A. Excavate trenches to uniform width, sufficiently wide to provide ample working room. Minimum width to be pipe and conduit diameter plus one foot, or as directed to provide suitable working room. Maximum width at top of pipe and conduit to be pipe and conduit diameter plus two feet.

B. Excavate trenches to depth required to establish indicated slope and invert elevations and to support bottom of pipe and conduit on undisturbed soil.

Excavate trenches to allow installation of top of pipe and conduit below frost line.

204-5

1. For pipe and conduits less than six inches (6") in nominal size, do not excavate beyond indicated depths. Hand-excavate bottom cut to accurate elevations and support pipe or conduit on undisturbed soil.

2. For pipes and equipment six inches (6") or larger in nominal size, shape bottom of trench to fit bottom of pipe for ninety degrees, i.e., bottom 1/4 of pipe circumference. Fill depressions with tamped sand backfill. At each pipe joint, dig bell holes to relieve pipe bell of loads to ensure continuous bearing of pipe barrel on bearing surface.

204.11 Cold Weather Protection:

A. Protect excavation bottoms and sides against freezing when atmospheric temperature is less than thirty-five degrees (35o) Fahrenheit.

204.12 Backfill and Fill:

A. Pipe bedding shall be minimum of six inches (6") in thickness and shall be compacted to minimum 95 percent of Modified Proctor Density (ASTM D1557) using minimum of six passes of mechanical tamper.

B. Trench Backfill: In all pipe trenches suitable selected material shall be filled in around pipe and to height of not less than one (1) foot and to greater height if so directed, over top of pipe. This fill shall be brought up evenly on both sides of pipe in layers of thickness as directed by Owner’s Designed Representative. Each layer shall be tamped and thoroughly consolidated to provide proper support and bearing for pipe and so as not to disturb line and grade of pipe.

C. Backfill excavations as promptly as work permits, but not until completion of the following:

1. Acceptance of construction below finish grade.

2. Removal of concrete formwork.

3. Removal of shoring/bracing and backfilling of voids with satisfactory materials. Cut off temporary sheet piling driven below bottom of structures. Remove in manner to prevent settlement of structure or utilities, or leave in place if required.

1. Removal of trash and debris from excavation.

204-6

D. Use structural fill to increase grades within building areas, as interior backfill against foundations and in trenches, as exterior backfill against walls with footing drains, and as exterior backfill where pavement or walkways abut the building.

204.13 Placement and Compaction:

A. General: In gravel pavement and under structures and slabs, each lift (8-inch maximum thickness) of existing subgrade and backfill material shall be thoroughly compacted with minimum of six (6) passes of approved mechanical rolling, or tamping equipment to a minimum of 95 percent of its maximum Modified Proctor Density (ASTM D-1557).

B. In lawn areas and other areas not covered above, each lift of backfill material shall be thoroughly compacted with minimum of six (6) passes of approved mechanical rolling, tamping or vibratory equipment to a range of 85 to 90 percent of its maximum Modified Proctor Density (ASTM D-1557).

C. Aggregate and Crushed Stone: Compact with approved mechanical rolling, tamping or vibratory equipment to consolidate the material to a density acceptable to the Owner’s Designated Representative.

204.14 Field Quality Control:

A. Contractor shall engage a qualified independent geotechnical engineering and testing agency to perform field quality control testing.

B. Quality Control Testing During Construction: Allow testing service to inspect and approve each subgrade and fill layer before further backfill or construction work is performed.

C. Testing agency will test compaction of subgrade and soils in place according to ASTM D 1556, ASTM D 2167, ASTM D 2922, and ASTM D 2937, as applicable. Tests will be performed at the Gatehouse and Bathhouse slab areas at subgrade and at each compacted fill and backfill layer, at least one test for every 200 sq. ft., but in no case fewer than two tests.

D. Testing agency will test compaction of aggregate subbase and crushed stone trail material to 95% of the maximum density as established through the modified proctor compaction test per ASTM D-1557. Tests will be performed at the following locations and frequencies

1. Roadway: At aggregate subbase courses with at least one test for every 250 linear feet of road but in no case fewer than two tests.

2. Gatehouse and Bathhouse Slab Areas: At aggregate subbase course and at least one test for every 200 sq. ft., but in no case fewer than two tests.

204-7

E. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required; recompact and retest until specified compaction is obtained.

F. If, in opinion of the Owner’s Designated Representative, based on testing service reports and inspection, subgrade or fills that have been placed are below specified density, perform additional compaction and testing until specified density is obtained, at no additional costs to Owner.

204.15 Grading:

A. General: Uniformly grade areas within limits of grading under this section including adjacent transition areas. Smooth finish surface within specified tolerances, compact with uniform levels or slopes between such points and existing grades or points where elevations are indicated.

B. Grading Outside Building Lines: Grade areas adjacent to building lines to drain away from structures and to prevent ponding. Finish surfaces free from irregular surface changes and as follows:

1. Lawn or Unpaved Areas: Finish areas to receive 4 inches minimum topsoil to within not more than 0.10 foot above or below required subgrade elevations.

2. Pavements: Shape surface of areas under pavement to line, grade, and cross-section, with finish surface not more than ½ inch above or below required subgrade elevation.

C. Compaction: After grading, compact subgrade surfaces to the depth and indicated percentage of maximum or relative density for each area classification.

204.16 Aggregate Course Placement:

A. General: aggregate course consists of placing material in layers of specified thickness, over proof-rolled subgrade surface.

B. Grade Control: During construction, maintain lines and grades including crown and cross-slope of pavement wearing course.

C. Placing: Place aggregate pavement course material on prepared subgrade.

Maintain optimum moisture content for compacting subbase material during placement operations.

204-8

204.17 Surface Restoration:

A. Where details of surface restoration for lawns, pavement, etc., are not shown on plans or specified elsewhere, all surfaces shall be restored to original condition.

204.18 Erosion Control:

A. Provide erosion control methods in accordance with/as shown on plans and specifications to prevent erosion and sedimentation during earthwork operations.

204.19 Maintenance:

A. Protect newly graded areas from traffic and erosion. Keep free of trash and debris.

B. Repair and re-establish grades in settled, eroded and rutted areas to specified tolerances.

C. Where completed compacted areas are disturbed by subsequent construction operations or adverse weather, scarify surface, reshape and compact to required density prior to further construction.

D. Settling: Where settling is measurable or observable at excavated areas during general project warranty period, remove surface (pavement, lawn or other finish), add backfill material, compact and replace surface treatment. Restore appearance, quality and condition of surface or finish to match adjacent work and eliminate evidence of restoration to greatest extent possible.

Payment

204.20 Payment for lump sum items will be prorated based on percentage of work completed.

Work shall include all material, labor, and appurtenances necessary for the completion of earthwork operations including, but not limited to the following: excavation and embankment, embankment and backfill compaction, backfilling with native or imported materials, rock excavation, trench excavation material and labor, excavation for all buildings, temporary shoring, protection of adjacent work, barricades and protection devices, and disposal of unused materials.

204-9

251 - Riprap

251.08 Measurement.

Add the following:

Payment for excavation and embankment required for placement of riprap is indirectly included in the pay item for riprap.

251-1

552 - Structural Concrete

Material

552.02 Add the following:

Anchor bolts 717.01 Dowels 717.17 Epoxy resin adhesives 725.21 High strength non-shrink grout 701.02 Mortar 701.02 Portland cement 701.01 Sealants, fillers, seal, and sleeves 712.01

552.03 Composition (Concrete Mix Design).

Delete Tables 552-1, 2, and 3 and replace with the following:

Table 552-1 Composition of Concrete

Class of Concrete

Minimum Cement Content

(pound per cubic yard)

Maximum W/C Ratio

Slump (1) (inches)

Maximum Nominal Coarse

Aggregate Size (5)

(inches) A 611 0.49 2 to 4 1½

A(AE) 611 0.44 1 to 4 1½ B 517 0.58 2 to 4 2½

B(AE) 517 0.58 2 to 4 2½ C 658 0.49 2 to 4 ¾

C(AE) 658 0.44 1 to 3 ¾ D(AE)(2) 611 0.40 1 to 3 1½ E(AE)(3) 611 0.40 4 to 6 (4) ¾

P (Prestressed) 658 0.44 0 to 4 1

P(AE) 658 0.44 0 to 4 1 Seal 658 0.54 4 to 8 1½

(1) Maximum slump is 8 inches if approved mix design includes a high-range water reducer.

(2) Concrete with a water reducing and retarding admixture conforming to AASHTO M 194, type D.

(3) A latex modified concrete with 0.037 gallons of modifier per pound of cement.

552-1

(4) Measure the slump 4 to 5 minutes after the concrete is discharged from the mixer.

(5) Meeting the processing requirements of AASHTO M43, Table 1 – Standard Sizes of Processed Aggregate.

(6) Use Class P (AE) concrete in the entire depth of the top flange of all multi-beam bridge girders. In lieu of this, Class P (AE) concrete may be used for fabrication of the entire girder, and throughout the entire depth of prestressed slabs. In all cases, furnish concrete meeting the 28 day specified minimum concrete strength requirements for the prestressed members as shown on the plans, unless otherwise specified.

Table 552-2

Minimum Air Content for Air Entrained Concrete

Nominal Maximum Aggregate Size (1)

As Delivered Minimum Air

Content (2) (3) (%) 2½ inch 3.5 2 inch 3.5

1½ inch 4.0 1 inch 4.5 ¾ inch 4.5 ½ inch 5.5

(1) Meeting the processing requirements of AASHTO M 43, Table 1 – Standard Sizes of Processed Aggregate.

(2) These air contents apply to the total mix. When testing these concretes, aggregates larger than 1½ inches are removed by handpicking or sieving, and air content is determined on the minus 1½-inch fraction of the mix. Air content of the total mix is computed from the value determined on the minus 1½-inch fraction.

(3) For P(AE) concrete, the as delivered minimum air contents may be reduced 1.0 % and the maximum air content is 6.0 %

552-2

Table 552-3 Required Average Compressive Strength (1)

Specified Compressive Strength (f’c)

(psi)

Required Average Compressive Strength

(f’cr) (psi)

Less than 3000 f’c + 1000 3000 to 5000 f’c + 1200

Over 5000 1.10f’c + 700

(1) Use this table when there is not enough data available to establish a standard deviation

Delete the first paragraph after Table 552-2 and replace with the following:

Submit written concrete mix designs for approval at least 30 calendar days before production.

Add the following under the list of items to be included in the mix design submittal:

(y) Evaluation of potential aggregate reactivity

552.08 Delivery.

(a) Truck mixer/agitator.

Add the following:

Do not exceed 130 total revolutions at mixing speed, including both initial mixing and remixing. Do not exceed 300 total revolutions, including both mixing and agitating speed.

552.09 Quality Control of Mix.

Add the following after the first paragraph:

At least 2 weeks prior to the start of concrete placement operations, arrange a pre-concrete placement conference. Coordinate attendance with the CO and any applicable subcontractors.

Be prepared to discuss and/or submit the following:

(1) Proposed concrete placement schedule.

(2) Review approved concrete mix design and determination of batch weights.

(3) Discuss Section 153, Contractor Quality Control, minimum frequency schedule for process control sampling and testing (to be performed by the Contractor).

(4) Discuss batching, mixing, placing, and curing requirements.

(5) Discuss Subsections 106.03, Certification, and 106.05, Statistical Evaluation of Material for Acceptance.

552-3

552.11 Handling and Placing Concrete.

Add the following after the forth paragraph:

Use an approved form release agent to produce a minimum of staining, air holes, and hydration discoloration.

552.12 Construction Joints.

Add the following at the end of the first paragraph:

Provide form cleanout ports at construction joints.

552.16 Finishing Plastic Concrete.

(c) Texturing.

(4) Exposed aggregate finish

Add the following at the end of the first paragraph:

Construct a 5.0 ft x 5.0 ft (minimum) job site sample at a location approved by the Engineer using the same concrete that will be used for the permanent work. Construct a maximum of three samples to demonstrate the proposed process and final texture to the satisfaction of the Engineer.

Power wash the exposed aggregate surface 2 weeks (minimum) after curing to remove curing compounds, laitance, oil, dirt or other foreign particles. Allow the concrete to dry a minimum of 24 hours prior to applying a penetrating type protective sealer in accordance with the manufacturer’s instructions. Provide those instructions to the Engineer before pressure washing.

552.16 Finishing Plastic Concrete.

Add the following after (4):

(c) Texturing.

(5) Stamp and color finish

A. Colored & Imprinted Concrete: Integral concrete color, imprint tools and patterns, release agent, and curing and sealing agent shall be manufactured by L.M. Scofield Company, 4155 Scofield Road, Douglasville, Georgia, 30134, (770) 920-6000, or approved equal. Areas designated for colored and imprinted concrete shall consist of the following:

1. Colored & Imprinted Concrete Pavement:

a. Color: ‘CHROMIX Admixtures for Color-Conditioned Concrete’, Color shall be ‘Shadow Gray’; Submit 2” x 2” concrete color square samples for approval;

b. Pattern: Imprint pattern shall be ‘Fractured Earth’Random Interlocking Pattern;

saw cut control joints.

B. Release Agent: Release agent shall be ‘Lithochrome Antiquing Release’, or approved equal;

552-4

C. Curing & Sealing: Curing and sealing agent shall be ‘Scofield Cureseal-W’, or approved equal;

D. Joint Sealant: Joint sealant coloring to match colored concrete. Submit color samples for approval. Comply with joint sealer manufacturers' printed installation instructions.

1. Use masking tape where required to prevent contact of sealant with adjoining surfaces which otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.

2. Clean off excess sealants or sealant smears adjacent to joints as work progresses by methods and with cleaning materials approved by manufacturers of joint sealers and of products in which joints occur.

3. Protect joint sealers during and after curing period from contact with contaminating substances or from damage resulting from construction operations or other causes so that they are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint sealers immediately and reseal joints with new materials to produce joint sealer installations with repaired areas indistinguishable from original work.

E. Non-Slip Additive: For all imprinted concrete surfaces, Contractor shall apply a non-slip anti-slip powder per manufacturer’s recommendations. Non-slip additive shall be applied integral to the curing and sealing application.

552.18 Loads on New Concrete Structures.

Add the following paragraph:

Do not allow public traffic on the bridge until approaches, curbs, and bridge rail are completed and in-place. Erect barricades at each end of bridge spans when road approaches allow vehicles to drive directly onto the structure.

Delete Table 552-3 and substitute the following:

Table 552-3 Required Average Compressive Strength

552-5

Table 552-3

Required Average Compressive Strength When Data

Are Not Available to Establish a Standard Deviation

Specified Compressive

Strength (f’c)

(pounds per square inch)

Required Average Compressive Strength (f’cr)

(pounds per square inch)

Less than 3000 f’c + 1000

3000 to 5000 f’c + 1200

Over 5000 1.10f’c + 700

552.21 Payment

Delete section and substitute the following:

Payment for structural concrete shall be subsidiary to the item requiring it.

552-6

625 - Turf Establishment

625 Delete.

Delete Section 625 in its entirety.

625-1

626 – Plants, Trees, Shrubs, Vines, and Groundcovers

626 Delete.

Delete Section 626 in its entirety.

633-1

633-2

635 - Temporary Traffic Control

635.03 General.

Add the following:

Install temporary traffic control signs to temporary posts or approved temporary sign mounts.

635-1

704 - Soil

704.02 Bedding Material.

Delete Subsection 704.02 and substitute the following:

Furnish a well graded, free draining material free of excess moisture, muck, frozen lumps, roots, sod, or other deleterious material conforming to the following:

(a) Maximum particle size 3 inch or half the corrugation depth, whichever is smaller

(b) Material passing No. 200 sieve, 10% max.

AASHTO T 27 and T 11

704-1

705 - Rock

705.02 Riprap Rock.

Delete Table 705-1 and replace it with the following:

Gradation Requirements for Riprap Class Percent of

Rock by Mass Mass

(pounds) Approximate Cubic

Dimension b,c (inches)

20 22 to 33 6 to 8 30 11 to 22 5 to 6 40 1 to 11 2 to 5 10a 0 to 1 0 to 2

20 55 to 110 8 to 10 30 22 to 55 6 to 8 40 2 to 22 3 to 6 10a 0 to 2 0 to 3

20 220 to 330 14 to 16 30 110 to 220 10 to 14 40 11 to 110 5 to10 10a 0 to 11 0 to 5

20 550 to 770 18 to 20 30 220 to 570 14 to 18 40 22 to 220 6 to 14 10a 0 to 22 0 to 6

4a

20 770 to1353 20 to 24 30 330 to 770 16 to 20 40 33 to 330 7 to16 10a 0 to 33 0 to 7

20 1540 to 2200 26 to 28 30 1100 to 1540 20 to 26 40 55 to 1100 8 to 20 10a 0 to 55 0 to 8

20 1870 to 3520 28 to 34 30 1100 to 1870 22 to 28 40 110 to 1100 10 to 22 10a 0 to 110 0 to 10

20 4400 to 5940 35 to 39 30 2200 to 4400 28 to 35 40 220 to 2200 14 to 28 10a 0 to 220 0 to 14

705-1

Class Percent of Rock by Mass

Mass (pounds)

Approximate Cubic Dimension b,c (inches)

20 7000 to 10000 42 to 47 30 4000 to 7000 35 to 42 40 400 to 4000 16 to 35 10a 0 to 400 0 to 16

(a) Furnish spall and rock fragments graded to provide a stable dense mass.

(b) The volume of a rock with these cubic dimensions has a mass approximately equal to the specified rock mass.

(c) Furnish rock with breadth and thickness at least one-third its length.

705-2

714 - Geotextile and Geocomposite Drain Material

Tables 714-1 and 714-4.

Add the following note to both tables:

(4) Woven slit film will not be allowed.

Add the following:

714.03 Geogrids.

Furnish geogrids consisting of polymeric materials such as polypropylene, polyethylene, or polyester formed into a stable network of bars or straps fixed at their junctions such that the bars retain their relative position to each other.

Elevate and protect rolls with a waterproof cover if stored outdoors.

(a) Physical requirements. Furnish geogrid treated to resist ultraviolet degradation, and conforming to the physical strength requirements shown in table 714-7 according to ASTM D 4595 for the specified geogrid category. Strength values shown in table 714-7 represent minimum average roll values and are for the direction of primary reinforcement. Ensure that the aperture size for all geogrids is between ¾ to 3 inches.

(b) Evaluation procedures. Geogrids will be evaluated under Subsection 106.03. Furnish a certification and a sample of the geogrid.

Table 714-7—Physical strength requirements for geogrids.

Category Minimum Ultimate Strength at Breakage (lbs/ft)

1 890

2 1985

3 2875

4 4110

5 5475

6 8215

714-1

718-1

DollyCopp_Supplemental FP03 Specs
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations.
101.04 Definitions.
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.03 Specifications and Drawings.
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
105.05 Use of Material Found in the Work.
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims.
107.06 Contractor’s Responsibility for Work.
107.10 Environmental Protection.
108 - Prosecution and Progress
108 Delete.
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions.
155 - Schedules for Construction Contracts
155 Delete.
201 - Clearing and Grubbing
201.02 Material:
201.01 Description
201.04 Clearing.
201.04 Clearing. (c)
204 - Excavation and Embankment
C. Testing agency will test compaction of subgrade and soils in place according to ASTM D 1556, ASTM D 2167, ASTM D 2922, and ASTM D 2937, as applicable. Tests will be performed at the Gatehouse and Bathhouse slab areas at subgrade and at each compac...
D. Testing agency will test compaction of aggregate subbase and crushed stone trail material to 95% of the maximum density as established through the modified proctor compaction test per ASTM D-1557. Tests will be performed at the following location...
1. Roadway: At aggregate subbase courses with at least one test for every 250 linear feet of road but in no case fewer than two tests.
2. Gatehouse and Bathhouse Slab Areas: At aggregate subbase course and at least one test for every 200 sq. ft., but in no case fewer than two tests.
E. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required; recompact and retest until specified compaction...
251 - Riprap
552 - Structural Concrete
Table 552-3 Required Average Compressive Strength
625 - Turf Establishment
625 Delete.
626 – Plants, Trees, Shrubs, Vines, and Groundcovers
626 Delete.
635 - Temporary Traffic Control
635.03 General.
704 - Soil
704.02 Bedding Material.
705 - Rock
705.02 Riprap Rock.
714 - Geotextile and Geocomposite Drain Material
Tables 714-1 and 714-4.
714.03 Geogrids.
Table 714-7—Physical strength requirements for geogrids.