SolicitationSol10-0012BakerCampground.pdf

PDF 604 KB Posted

Attached to
Baker Lake Campground Renovation Federal contract opportunity
Solicitation number
AG-05M6-S-10-0012
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Baker Lake Campground Renovation, newest first.
File Type Posted
AMENDMENT-2.pdf PDF
AmendmentNo1ReplacementSheet27.pdf PDF
AmendmentNo1ReplacementSheet19.pdf PDF
AmendmentNo1ReplacementSheet22.pdf PDF
AMENDMENT 1.pdf PDF
AmendmentNo1ReplacementSheet28.pdf PDF
AmendmentNo1ReplacementSheet25.pdf PDF
AmendmentNo1ReplacementSheet26.pdf PDF
AmendmentNo1ReplacementSheet20.pdf PDF
AmendmentNo1ReplacementSheet21.pdf PDF
AmendmentNo1Electrical4Pages.pdf PDF
Attachment01Sheets01to03.pdf PDF
Attachment07Sheets15to18.pdf PDF
Attachment04Sheet12RdClosureGate.pdf PDF
Attachment10PagesEleectrical23pgs.pdf PDF
Attachment08Sheets19to23.pdf PDF
CopyToSubmitSol 10-0012 Baker Campground.pdf PDF
Attachment09Sheets24to28.pdf PDF
Attachment06Sheet14Kiosk.pdf PDF
Attachment05Sheet13EntranceSign.pdf PDF
Attachment02Sheets04to06.pdf PDF
Attachment03Sheets07to11.pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-05M6-S-10-0012

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

04/21/10

PAGE OF PAGES

1 of

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

6. PROJECT NO.

7. ISSUED BY CODE 8. ADDRESS OFFER TO

Mt Baker-Snoqualmie National Forest 2930 Wetmore Avenue Suite 3A Everett, WA 98201

Contracting Officer Mt Baker-Snoqualmie National Forest 2930 Wetmore Avenue Suite 3A Everett, WA 98201

9. FOR INFORMATION

CALL:

A. NAME

Bonnie Childs B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

425-446-2743

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

BAKER LAKE CAMPGROUND RENOVATION

Mt Baker-Snoqualmie National Forest

Mt Baker Ranger District Whatcom County, Washington

Price Range: The Government's estimate is between $500,000 and $1,000,000.

Technical Contact: Thomas Warter Office: (425) 783-6082 Cell: (425) 210-5751

This solicitation is 100 percent set-aside for certified HubZone businesses

11. The Contractor shall begin performance within 10 calendar days and complete it within 300 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See Section F.)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 4:00 pm (local time 5/20/10 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required. (20%)

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract.

The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

BAKER LAKE CAMPGROUND RENOVATION

MT. BAKER RANGER DISTRICT

WHATCOM COUNTY, WASHINGTON

BASE ITEM

ITEM

NO.

DESCRIPTION

PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

01200

Mobilization

Lump Sum

02100

Construction Staking (Recreation Facilities)

02102

Clearing and Grubbing

02111

Removal of Structures and Obstructions: Concrete Septic Tank and Concrete Pad

Each

02205

Barrier Rock

02213(A)

Trails: Construction of 3’ wide, 5/8” minus Aggregate, Compaction B

Linear Feet

02213(B) Trails: Construction of 5’ wide, Limestone surfacing for Outdoor Recreational Access Trail (ORAT)

Linear Feet 3800 $___________ $___________

02214 ORAR Crossings: 4”x6” Treated Timber

Edging including 2” of 1 ¼” minus or Limestone

Each 13 $___________ $____________

02217

Tent Pads: 14’x 14’

02218

Signle/Double Campground Unit 5/8” minus, Compaction B

Ton

02232 Roadway Aggregate Surfacing, 1 ¼” minus, Compaction B Ton 2180 $___________ $___________

02510(A) 1” I.D. pipe includes trenching, backfill, bedding, and valves Linear Feet 1000 $___________ $___________

02510(B) 2” I.D. pipe includes trenching, backfill, bedding, and valves Linear Feet 3310

02510(C) Filling, Testing, Flushing Lump Sum 1 $___________ $___________

02510(D) Composite Utility Markers Each 10 $___________ $___________

02512(A) Post Water Hydrants with Sump-including valve

Each 17 $___________ $___________

02512(B) Self-Closing Shower Hydrant: (height

6’6” from ground on 6”x6” treated post, 5’x5’ Concrete Pad)

Each 1 $___________ $___________

02512(C) Campground Host Water Hook-up (height

4’6” from ground on 6”x6” treated post) Each 3 $___________ $___________

02512(D) Recreational Vehicle Fill Hydrant (height

8’ from ground on 6”x6” treated post) Each 1 $___________ $___________

02614 Repairing and Reconditioning of Existing

Roadways Mile 1.4 $___________ $___________

02621

Concrete Curb Construction

Linear Feet

02636

24” Diameter Dry Well

02710

Wooden Fence, post and rails, height 8’

02712(A)

Wood Post/Bollards 8” diameter, height 4’

02712(B)

Retractable Wood Post/Bollards 8” diameter, height 4’ (Buried Metal casing surrounding Bollard and connected with a removable bolt/pin)

02715

Campground Closure Devices (Gates), type weathering steel (coreten) I-beam, size single gate

02722

Traffic Control Signs

02726

Bulletin Boards Panel Sign Base (Government Furnished Material-GFM)

02731

Septic Tank, Concrete w/ abs liner, 1,000 gallon, concrete floor w/ vault and cleanout lid

02821

Chain Link Fence (with brown slotting)

02922(A)

Wheel Stops, Rubber 6’, parking lot

02922(B)

Wheel Stops, Rubber 8’, parking spurs

10416

Entrance Sign and Base (GFM)

Lump Sum

10417

Three Panel Kiosk

10418(A)

Pedestal Cooking Grill for Group Sites (Q24B2)

Total Price - Base Item = $______________

TOTAL PRICE: BASE PLUS OPTION ITEMS = $_______________

10418(B)

Pedestal Cooking Grill for Individual Sites

(A20SB2)

16910

Construction of Water System within Pump House Building (Well pump and wire, Distribution System, connections from within building)

Lump

16920 Construction of Electrical System within

Pump House Building (Controls, Panels, store building and Recreation Vehicle connections)

Lump

1 $___________ $___________

16930 Generator (including installation) Each 2 $___________ $___________

16800

OPTION ITEM A

Photovoltaic system (Solar Light and Posts)

02875

OPTION ITEM B

Picnic Shelter Construction and Installation (20’ x 30’)

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 DESCRIPTION OF WORK:

This project consists of renovation of an existing resort area to a new campground on the Baker Lake near the town of Concrete, Washington. Work includes but is not limited to: construction staking, clearing & grubbing, removal and disposal of waste, excavation, embankment, crushed aggregate, road recondition, concrete curbs, campground trail, spur camp, tent pads, barrier rocks, barrier posts, picnic shelters, fence, information kiosks, entrance sign base, regulatory signs, fence, gate, solar lights, building structures, water system, septic holding vault, generators, mobilization and miscellaneous site work.

C.2 PROJECT LOCATION:

This project is located at The Baker Laker Resort on the Mt. Baker Ranger District of the Mt.

Baker- Snoqualmie National Forest, Section 8, Township 37 North, Range 09 East, Whatcom County, Washington. Project may be reached from Sedro-Woolley, Washington by traveling east on Highway 20 follow the road for 15 miles then turn left onto County road #68 by following County road approximately 20 miles Baker Laker Resort in the right..

C.3 CONTRACT TIME:

Contract time is 300 calendar days with an estimated start work of June 1, 2010.

C.4 SPECIFICATIONS

Specifications from the Construction Specification Institute

C.5 MATERIAL CERTIFICATIONS, INVOICES, SUBMITTALS AND TESTING REPORTS

Materials associated with the following Pay Items will require certifications and/or testing reports submitted to the Contracting Officer Representative.

Item 02205 Barrier Rock Item 02616 Roadway Aggregate Surfacing (1 ¼” -minus State DOT) Item 02601 Aggregate Base or Surface Course (5/8”- minus State DOT) Item 02213 Aggregate surfacing (Limestone) Item 02922 Wheel stops

Refer to the Standard Specifications and Supplemental Specifications for required certification and reports for Items mentioned above.

C.6 MATERIAL SOURCES

The Government will provide the following item(s) of material sources to the Contractor for use in the performance of his contract.

Item No. Description Quantity Source Location None

C.7 CONSTRUCTION WORK DAYS

Work is allowed 7 days a week.

C.8 WILDLIFE RESTRICTIONS (INCLUDING FISHERIES):

Contractor shall not start daily work until two hours after sunrise and stop work two hours before sunset from April 1 thru September 15.

C.9 AGAR 452.211-73 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS

(FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

I.1 2.246-12 INSPECTION OF CONSTRUCTION (Aug 1996)

(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not—

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary.

The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may—

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction.

However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

SECTION F--DELIVERIES OR PERFORMANCE

F.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984)

F.2 CONTRACT TIME:

Contract time is 300 calendar days with an estimated start work of June 1, 2010.

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 GOVERNMENT-FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.

Property to be Furnished Delivery Point Time of Delivery

Entrance Sign, 2 each Komo Kulshan Compound During construction

Bulletin Boards Panel Sign Komo Kulshan Compound During construction

L-Shape Grill On site

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 POST AWARD CONFERENCE (AGAR 452.215-73) (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 14 days after the date of contract award. The conference will be held at: (To be determined after award)

H.2 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS ( FAR 52.236-9) (APR 1984)

(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.

(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made know to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

H.3 USE OF PREMISES

(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for the Contractor.

(b) Unless provided otherwise, the Contractor shall: (i) provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State, and local regulations.

H.4 ARCHAEOLOGICAL OR HISTORIC SITES (USDA 452.236-73) (FEB 1988)

If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.

H.5 CONTROL OF EROSION, SEDIMENTATION AND POLLUTION (USDA 452.236-74)

(FEB 1988)

(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

(b) Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged on the ground; into or near rivers, streams, and impoundments; or into natural or manmade channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(c) Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H.6 RIGHTS IN AND USE OF MATERIALS

(a) The Contractors, with the written approval of the Contracting Officer, may use on the project suitable stone, gravel, and sand or other material found in the excavation. Payment will be made both for the excavation of such materials at the corresponding contract unit price and for the pay items for which the excavated material is used. The Contractor shall replace without additional compensation sufficient suitable materials to complete the portion of work which was originally contemplated to be constructed with such material.

(b) Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to reimburse the Contractor for the cost of their production.

H.7 STORAGE AND STOCKPILING OF MATERIALS

Material shall be stored to assure the preservation of quantity and fitness for the work. Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by Forest Service, may be used for storage purposes and for the placing of Contractor's plant equipment. All storage sites provided by Forest Service shall be restored at Contractor's expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered land.

H.8 EMERGENCY RESPONSE (USDA 452.236-77) (NOV 1996)

(a) Contractor's Responsibility for Fighting Fire. (1) The Contractor, under the provision of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish, all fires on the work site other than those fires in use as a part of the work. (2) The contractor may be held liable for all damages and for all costs incurred by the Government for labor subsistence, equipment, supplies, and transportation deemed necessary to suppress a fire set or caused by the Contractor or the Contractor's agent or employees.

(b) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor's Responsibility for Responding to Emergency. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to restricted to fire fighting).

An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.

H.9 LANDSCAPE PRESERVATION

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products onsite, appropriate preventive measures shall be taken to ensure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states.

Servicing of all equipment shall be done only in the area approved by the Contracting Officer.

If the total oil or oil products storage exceeds 6,000 litters or if any single container exceeds a capacity of shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

The Contractor will be required to make reasonable attempts to preserve the scenic and natural environment along this construction project.

(c) Trash and Refuse - Contractor shall remove all of his own trash and refuse from the contract area. Material to be removed includes, but is not limited to; used engine oil, oil filters, oil cans, grease cartridges, camp refuse such as tin cans, paper, garbage, etc. This material must be removed to a State, County, or Municipality-designated solid waste disposal area.

H.10 CONTROL OF NOXIOUS WEEDS--CLEANING OF EQUIPMENT (March 2004)

To prevent the introduction and control the spread of seeds of noxious weeds onto and around National Forest land, the Contractor shall ensure all equipment moved onto National Forest land is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. When the Contractor is working in an area that has been identified as a noxious weed infestation area, the Contractor shall ensure equipment is cleaned of weed seeds prior to moving to another work area on the Forest. The Contractor shall employ whatever cleaning methods necessary to ensure compliance with the terms of this provision, and shall notify the Forest Service prior to moving each piece of equipment onto National Forestland, unless otherwise agreed in writing.

Notification will include identifying the location of the equipment's most recent operations.

The Contractor shall certify, in writing, compliance with the terms of this clause prior to each start-up of operations. For the purposes of this clause, "equipment" includes all motorized equipment operated off system roads, transport vehicles, and all motorized equipment used in road maintenance. Not included are log trucks, chip vans, pickup trucks, cars, or other vehicles used to daily transport personnel.

H.11 PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Forest Personnel.

Weather Conditions: Normal.

Elevation of this project averages 800’.

Transportation facilities: General Road Level 3 access Other Physical Data: None

H.12 FIRE PROTECTION REQUIREMENTS

The following fire requirements are attached in Section J and are applicable:

Fire Protection and Suppression, R6-FS-6300-52 (5/97)

Additional Fire Precautionary Measures - Tank Truck, R6-FS-6300-53 (5/89)

Additional Fire Precautionary Measures - Communications, R6-FS-6300-54 (5/89)

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.202-1 Definitions (JUL 2004) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (APR 1984) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (JUL 1995) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

(JAN 1997)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEP 2007) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (MAY 2008) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (JUN 1999) 52.219-8 Utilization of Small Business Concerns (MAY 2004) 52.219-14 Limitations on Subcontracting (DEC 1996) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (JUL

2005) 52.222-6 Davis-Bacon Act (JUL 2005) 52.222-7 Withholding of Funds (FEB 1988) 52.222-8 Payrolls and Basic Records (FEB 1988) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (FEB 1988) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) 52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and other Eligible Veterans (SEP 2006) 52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998)

52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and other Eligible Veterans (SEP 2006)

52.222-50 Combating Trafficking in Persons (SEP 2007) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-14 Toxic Chemical Release Reporting (AUG 2003) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (FEB 1992) 52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) 52.228-14 Irrevocable Letter of Credit (DEC 1999) 52.228-15 Performance and Payment Bonds – Construction (NOV 2006) 52.229-3 Federal, State, and Local Taxes (APR 2003) 52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002) 52.232-17 Interest (OCT 2008) 52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims (JAN 1986) 52.232-27 Prompt Payment for Construction Contracts (OCT 2008) 52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT

2003) 52.233-1 Disputes (JULY 2002) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by The Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (AUG 1987) 52.244-6 Subcontracts for Commercial Items (MAR 2009) 52.245-1 Property Records (JUN 2007) 52.245-2 Government Property (Fixed-Price Contracts) (JUN 2007) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (SEP 2006) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004)--

Alternate I (SEP 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV

1996) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988)

I.2 52.204-7 CENTRAL CONTRACTOR REGISTRATION (APR 2008)

(a) Definitions. As used in this clause—

“Central Contractor Registration (CCR) database” means the primary Government repository for Contractor information required for the conduct of business with the Government.

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.

“Registered in the CCR database” means that—

(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and

(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record “Active”. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.

(b)

(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.

(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number—

(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S.

Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business name.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company physical street address, city, state and Zip Code.

(iv) Company mailing address, city, state and Zip Code (if separate from physical).

(v) Company telephone number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(g)

(1)

(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to:

(A) Change the name in the CCR database;

(B) Comply with the requirements of Subpart 42.12 of the FAR;

(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.

(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.

(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the Internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961- 5757.

I.3 FAR 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $1,000,000 whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.4 52.228-15 PERFORMANCE AND PAYMENT BONDS—CONSTRUCTION (NOV 2006)

(a) Definitions. As used in this clause—

“Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) Amount of required bonds. Unless the resulting contract price is $100,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:

(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds (Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(3) Additional bond protection.

(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.

(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.

(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.

(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:

U.S. Department of the Treasury Financial Management Service Surety Bond Branch 3700 East West Highway, Room 6F01 Hyattsville, MD 20782.

Or via the internet at http://www.fms.treas.gov/c570/.

(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.

I.5 52.219-3 NOTICE OF TOTAL HUBZONE SET-ASIDE (Jan 1999)

(a) Definition. “HUBZone small business concern,” as used in this clause, means a small business concern that appears on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration.

(b) General.

(1) Offers are solicited only from HUBZone small business concerns. Offers received from concerns that are not HUBZone small business concerns shall not be considered.

(2) Any award resulting from this solicitation will be made to a HUBZone small business concern.

(c) Agreement. A HUBZone small business concern agrees that in the performance of the contract, in the case of a contract for—

(1) Services (except construction), at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other HUBZone small business concerns;

(2) Supplies (other than acquisition from a nonmanufacturer of the supplies), at least 50 percent of the cost of manufacturing, excluding the cost of materials, will be performed by the concern or other HUBZone small business concerns;

(3) General construction, at least 15 percent of the cost of the contract performance incurred for personnel will be spent on the concern’s employees or the employees of other HUBZone small business concerns; or

(4) Construction by special trade contractors, at least 25 percent of the cost of the contract performance incurred for personnel will be spent on the concern’s employees or the employees of other HUBZone small business concerns.

(d) A HUBZone joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (c) of this clause will be performed by the HUBZone small business participant or participants.

(e) A HUBZone small business concern nonmanufacturer agrees to furnish in performing this contract only end items manufactured or produced by HUBZone small business manufacturer concerns. This paragraph does not apply in connection with construction or service contracts.

I.6 FAR 52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (FEB 2009)

(a) Definitions. As used in this clause--

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C.

App. 1702), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means--

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to the construction material or components listed by the Government as follows: NONE.

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American Act.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration,…