REQUEST FOR QUOTATION PAGE OF PAGES
(THIS IS NOT AN ORDER) THIS RFQ IS IS NOT A SMALL BUSINESS SET- ASIDE 1 54
1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT.DEF. RATING
AG-05GG-S-16-0022 7/29/2016 812558
UNDER BDSA REG. 2
AND/OR DMS REG. 1
5a. ISSUED BY 6. DELIVER BY (Date)
USDA Forest Service
Okanogan-Wenatchee National Forest
215 Melody Lane
Wenatchee, WA 98801-8122
See Section F
5b. FOR INFORMATION CALL (NO COLLECT CALLS) 7. DELIVERY FOB DESTINATION
NAME TELEPHONE NUMBER OTHER (See Schedule)
Mariah Morris, CO
Lori McAllister, COR
AREA CODE
NUMBER
664-9317
664-9263
9. DESTINATION
a. NAME OF CONSIGNEE
8. TO:
a. NAME b. COMPANY b. STREET ADDRESS
c. STREET ADDRESS c. CITY
d. CITY e. STATE f. ZIP CODE d. STATE e. ZIP CODE
10. PLEASE FURNISH QUOTATIONS TO THE
ISSUING OFFICE IN BLOCK 5A ON OR
BEFORE CLOSE OF BUSINESS
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5A.
This request does not commit the Government to pay any costs incurred in the preparation of the
August 24, 2016
4:30 PM (Pacific Time) submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT
PRICE
AMOUNT
(a) (b) (c) (d) (e) (f)
Lake Chelan Erosion Control
Phase 7
Okanogan-Wenatchee National Forest
Chelan Ranger District
Chelan County
TIN #: ________________________
DUNS #: _______________________
E-MAIL: ______________________
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS
12. DISCOUNT FOR PROMPT PAYMENT NUMBER PERCENTAGE
NOTE: Additional provisions and representations are are not attached.
13. NAME AND ADDRESS OF QUOTER 14. SIGNATURE OF PERSON AUTHORIZED TO 15. DATE OF
a. NAME OF QUOTER SIGN QUOTATION QUOTATION
b. STREET ADDRESS 16. SIGNER
a. NAME (Type or print) b. TELEPHONE
c. COUNTY AREA CODE
d. CITY e. STATE f. ZIP CODE c. TITLE (Type or Print) NUMBER
NSN 7540-01-152-8084
Previous edition not usable
18-121 STANDARD FORM 18 (Rev. 6-95) Prescribed by GSA-FAR (48 CFR) 53.215-1(a)
Construction RFQ Lake Chelan Erosion Control Phase 7
AG-05GG-S-16-0022
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
Lake Chelan Erosion Control – Phase 7, Sites 14, 15, 16 & 17
Chelan Ranger District
Okanogan Wenatchee National Forest
Chelan County
B- 1 - SCHEDULE OF ITEMS
ITEM
NO.
DESCRIPTION
PAY
UNIT
EST.
QTY.
PRICE
TOTAL
SITE 14 (T.30 N. R.19E, Sec 20)
25202(b.1) Special Rock Embankment, Erosion Control Treatment T3 Modified, Zones A and B.
Ton
Site 14
Site 15 (T.30 N. R.19E, Sec 20)
15756(b) Erosion Control, Permanent Excelsior Fiber Wattles Zones A, B & C.
Foot
15756(d) Erosion Control, Log (Horizontal Large Woody Debris). Five (5) pieces in Zone A. Thirteen (13) pieces in Zone B. Seven (7) pieces in Zone C. Wood is Government Furnished at Prince Creek, Contractor haul.
Each
Erosion Control Treatment T3, Treatment Zone A, B, C and D.
Site 15
Site 16 (T.30 N. R.19E, Sec 20)
15756(c) Erosion Control, Geotextile, Type
IV.A
12’ Wide Rolls Required B.
25202(c) Special Rock Embankment, Erosion Control Treatment TW Modified, Treatment Zone E, F. Total length 280’
Site 16
Site 17 (T.30 N. R.19E, Sec 20)
15756(b) Erosion Control, Permanent Excelsior Fiber Wattles Zones A, B & C.
15756(d) Erosion Control, Log (Horizontal Large Woody Debris). Five (5) pieces in Zone A. Thirteen (13) pieces in Zone B. Seven (7) pieces in Zone C. Wood is Government Furnished at Prince Creek, Contractor haul.
Each
Erosion Control Treatment T3, Treatment Zone A, B, C and D.
Site 17
15101 Mobilization Lump Sum
1 $________ $________
PROJECT
B-2 - NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
Include bond payments under 151.01 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
Project consists of furnishing the construction and materials necessary to complete shoreline erosion control treatments at four sites on the north shoreline of Lake Chelan in
Chelan County, Washington. Construction consists of furnishing and installing special rock embankment, large woody debris, erosion control products as well as other incidental items in a variety of configurations called treatments at locations staked on the ground by the Government prior to commencing work. This work is being done to fulfill the requirements of an Article (1) Forest Service Erosion Control Plan to the license issued by the United States of America Federal Energy Regulatory Commission (FERC) to Public
Utility District No. 1 of Chelan County (Chelan PUD) for Lake Chelan Hydroelectric
Project No. 637 located on the Chelan River near the city of Chelan, Washington.
C.2 PROJECT LOCATION
The proposed Lake Chelan Shoreline Erosion Control Phase 7 work is located at four sites on the north shoreline of Lake Chelan on the Lake Chelan Ranger District of the Okanogan and Wenatchee National Forest. The primary access to this site is by boat or barge. The
Lady of the Lake private commercial ferry does not have scheduled stops at Graham
Harbor Campground or at Graham Harbor Creek Campground. The boat ramp nearest the project sites is located at Twentyfive Mile Creek State Park. Other boat ramps are available at Shrine Beach, Lake Chelan State Park, Chelan Riverwalk Park, Old Mill Park and Lake
Shore Marina. Commercial barge service is available on Lake Chelan from Mountain
Barge Services LLC, 1222 W. Woodin Ave, Chelan, WA 98816 phone (509)682-2493. The availability of boat ramps varies depending on the water level of Lake Chelan. This project requires work on Lake Chelan at two time periods. The first is during high-pool lake levels
(October to December) to pre-position rock at the project sites and the second is during low-pool lake levels (December to March) to complete the erosion control work.
Prospective offers are advised to verify the availability of planned boat launches during low-pool periods.
The work sites are Site No. 14, 15, 16 and 17. Sites are located in Section 20, Township 30
North, Range 19 East, Willamette Meridian (WM) in Chelan County, Washington. The project site may be reached from Chelan, Washington by traveling up Lake Chelan approximately 38 miles from the Lady of the Lake boat dock. The project site is approximately 11 miles up-lake from the Twentyfive Mile Creek State Park boat ramp.
C.3 PRICE RANGE
The Government's estimate is: Between $25,000 and $100,000
C.4 DESCRIPTION OF WORK
The construction of erosion control measures required by this contract at Site Nos. 14, 15
16 and 17 are required as part of the license issued by FERC for the Lake Chelan
Hydroelectric Project No. 637-041 to the Chelan PUD.
Erosion Control Treatments for Site 14
3.1.1 Erosion Control Work for Site 14 – Graham Harbor Campground
This site is Graham Harbor Campground and dock. It is 100 feet long with a wood wall protecting the site. The wall consists of four log courses with the bottom course approximately 8- 12 inches above the 1,100-foot high water line. The wall has a wood boardwalk along the top for pedestrian use.
At site 14 approximately 57 lineal feet will be treated with T3S Modified – Single
Row Rock Placement. There will be no LWD because rock can be placed directly on the flat shoreline without any ground disturbance. This treatment will inhibit materials being washed out underneath the bottom log course as the rock will block wave action especially when lake levels are nearly equal to the bottom elevation of this wall.
Work at Site 14 will need to be done from the barge due to potential lithic scatter being present. No ground disturbance will be allowed at this site and equipment will not be allowed to operate on dry shoreline. Mobilization cost should include all barge work the contractor anticipates.
Due to the limited and simple nature of this site a shoreline profile or site sketch was unnecessary to determine treatments for this site. Treatment zones are identified in the photos for this site.
Table 1: Treatments for Site 14 – Graham Harbor Campground
Treatment
Zone
Length
(Feet)
Treatment Type
(See Drawings)
Treatment Description
A 37 T3S Single Row Rock Placement. No LWD.
B 20 T3S Single Row Rock Placement. No LWD.
3.1.1 Erosion Control Work for Site 15 – Between Graham Harbor
Campground and Graham Harbor Creek Campground
This site is located between Graham Harbor Campground and Graham
Harbor Creek Campground. The site consists of four steep chutes of relatively narrow width.
At site 15 approximately 59 lineal feet will be treated at four separate locations with T3
Modified
– Double Row Rock Placement.
Due to the limited nature of this site a shoreline profile or site sketch was unnecessary. Treatment areas are illustrated on photos for this site.
Table 2: Treatments for Site 15
Length
(Feet)
Treatment Type
(See Drawings)
Treatment Description
A 15 T3 Double Row Rock Placement. Include 1 piece
LWD
B 16 T3 Double Row Rock Placement. Include 1 piece
LWD
C 10 T3 Double Row Rock Placement. Include 1 piece
LWD
D 18 T3 Double Row Rock Placement. Include 1 piece
LWD
Site 15 Description 1982 Site 15, By MGY, 4/13/99, Relatively exposed U/S, long fetch Limited by bedrock each end 0’-30’ Erosion from foot traffic, 0’-20’ repaired, working well
Moderate slope
Till, 30%-40% cobbles to 2’ boulders, angular More rocks at toe
Moss, grass, face healing (+) 30’-75’ very little activity
75’-160’ bedrock, no erosion
160’ end at 220’ As at 30’-75’
3.1.1 Erosion Control Work for Site 16 – Graham Harbor Creek Campground
This site is located in front of Graham Harbor Creek Campground and directly downlake of the Graham Harbor Creek Fixed dock. It has a 185-foot-long crib wall protecting the site. The four- pole vertical wall needs toe protection to reduce wave energies from pulling materials out and initiating wall failures. Additionally, the entire wall needs to be faced with rock in order to provide long term protection of the shoreline in this location.
Approximately 185 feet will be treated with enhanced placed rock (TW Modified).
This will be the only treatment for this homogenous site. No excavation work will be needed in the drawdown zone to key in the first course of rock due to the flat nature of the shoreline at the interface with the existing wall. Therefore, no large woody debris is required or will be incorporated into the treatment.
Table 3: Treatments for Site 16 – Graham Harbor Creek Campground
Length
(Feet)
Treatment Type
(See Drawings)
Treatment Description
A 185 TW Modified Enhanced Placed Rock with Wood Crib Wall. No
LWD.
Site 16 Description 1982 Site 16, By MGY, 4/13/99, 0’-30’
SL
undercut toe Very little activity
30’+ Log bulkhead
Old erosion face above logs (+) Grass, moss, shrubs, sm trees 192’+
Bedrock
204’ CL of dock
Site 16 Sketch
CRIB
WALL
Zone A – 185 ’ – TW Modified -
3.1.1 Erosion Control Work for Site 17– Directly Uplake from Graham Harbor
Creek Fixed Dock
This site is directly up lake from the Graham Harbor Creek Fixed Dock. Two areas totaling approximately 123 feet would be treated with T3 – Double Row Rock Placement.
Table 4: Treatments for Site 17
Length
(Feet)
Treatment Type
(See Drawings)
Treatment Description
A 40 T3 Double Row Rock Placement. Include 2 pieces
LWD
B 83 T3 Double Row Rock Placement. Include 5 pieces
LWD
Site 17 1982 Site 17, By MGY, 4/13/99
Moderately protected U/S
Bedrock limits both ends 0’-40’
Little activity
40’-60’
Face, more bare soil, less vegetation Till with cobbles to 1.5’ subrounded
Downslope grades to fine-med gravel near water 60’-120’ More rocks, less activity
120’+ Past point, more exposed
160’ End at bedrock, fresh face area adjacent to bedrock
Compare to 1982 photos, Site 16 & 17, 1/1: 1982 photo shows D/S half of site. Other half in better condition. D/S half appears unchanged except shrubs and Trees are larger.
Site 17 Profile
S17P1
Site 17 Sketch
A – 83 ’ – T3 -
DRR
A – 40 ’ – T3 -
DRR
3.2 Mitigation Measures Included
Of the group of sites in this site-specific plan, sites 14 and 16 are defined as group 1 sites in the Settlement Agreement, indicating they are located in high-use recreation areas
(e.g., campgrounds). Sites 15 and 17 are not defined as being group 1 sites, but are listed as being scheduled for treatment along with sites 14 and 16. Sites 1 and 2 are defined as being group 3 sites in the Settlement Agreement, selected for treatment based on visual impact of the erosion occurring at the sites.
Noxious weed control will be addressed by: 1) limiting foreign soils being brought into the sites;
2) limiting ground disturbance to areas below elevation 1,100 feet, the normal maximum lake level; and, 3) obtaining large rock from a weed-free certified pit. Every effort will be made to keep existing slopes and vegetation as stable as possible during treatment.
These sites all have fairly good natural vegetation that will fill in once toe erosion is stabilized. However, spot shoreline plantings may be completed by Forest Service personnel at select sites where plantings are needed.
Large Woody Debris (LWD) will be used to benefit fish and address wave action where possible at a ratio (1/1) of disturbed shoreline as agreed to with permitting agencies. This set of treatment allows for LWD placement to be incorporated into approximately 792 linear feet of shoreline treatments. It will not be a continuous treatment but a selected piece anchored occasionally until we reach the appropriate amount. It will be done so that it does not interfere with dock access or other recreational shoreline to water access at the campgrounds. T1 treatments include excavation that is used in the LWD calculation. We have calculated 792 lineal feet of these treatments with excavation disturbances of approximately 1.5 feet, so we have a square footage of required LWD of approximately 1,188 square feet. With “average” pieces of LWD being a 20-foot log and 14-16 inches in diameter, each log would represent about 25 square feet of mitigation. Thus we are planning to place approximately 48 “average” logs within the treatment areas that allow for LWD.
3.3 Implementation and Effectiveness Monitoring
The effectiveness monitoring schedule is based on when each site will be treated. The timelines for site treatment are outlined in Chapter 1 of the Lake Chelan
Comprehensive Management Plan. The monitoring will be focused on the evaluation of four distinct focus areas:
1. Slope stabilization with an objective of reaching a 90-percent success rate in the treated areas.
2. Presence of native vegetation with an objective of reaching ratio of native to non- native vegetation similar to that found on nearby on undisturbed slopes on 90 percent of treated area. This will take into account the percentage of rock, and bare spots as this is a very dry hostile natural environment.
3. Presence of noxious weeds with an objective of not introducing any new noxious weeds through the course of treatment. Implementation methodologies are designed to exclude the introduction of noxious weeds. Treated areas will be monitored on an ongoing basis to determine if the methodologies employed are sufficient to meet the project objectives.
Lake Chelan Project No. 637 USDA FS Site Specific Erosion Plan (Sites 1, 2, 14, 15, 16 and 17)
F/N 40815 Page 30 June
14, 2013
4. Stability of LWD with an objective of minimizing movement. Large loose objects could become hazardous to the site users.
All sites will be monitored 1, 3 and 5 years following treatment at the sites. For efficiency, some sites monitoring may be conducted when additional vegetation is being planted following the initial stabilization. LWD inspections and slope stability inspections will be conducted during drawdown times to allow inspection of anchoring devices. Noxious weed and vegetation inspections will occur after leaf-out, typically in the May-to-June time period. These inspections will be coordinated with other erosion control implementation steps to provide travel and time efficiencies when possible.
C.5 NATIONAL ENVIRONMENTAL POLICY ACT and PERMITTING
4.1 NEPA
The Forest Service accepted the Final Environmental Assessment (FEA) for
Hydropower for Lake Chelan Hydroelectric Project, FERC Project No. 637, FERC, October 2003, for erosion control treatments. Materials included in the FEA detailed all previously conducted survey work, and proposed site-specific treatment areas that were measured and mapped at 10-foot increments. The proposed specific treatments have not materially changed since the date of issuance of the FEA and, as such, will be consistent with the intent of the original proposed treatments.
4.2 Permitting
To ensure that site-specific permitting requirements are met, Project Files, including biological evaluation data, cultural resources, and consultation, will be created or updated, to provide additional site-specific information in a timely manner over the life of the License. Project Files include the Biological Evaluation (BE) data and U.S. Fish and Wildlife Service (USFWS) concurrence letters, the Cultural Resources information, and the Joint Aquatic Resources Permit Application (JARPA).
The USFWS concurred with the Forest Service findings of “may affect not likely to adversely affect” the northern spotted owl (Strix occidntalis caurina), gray wolf (Canis lupus), and grizzly bear (Ursus arctos) in the Biological Evaluation for Lake Chelan
Erosion Sites in letters dated August 15, 2007 and April 8, 2008. These letters were included as part of the Site-Specific Erosion Control Plan (Sites 24, 25, 26 and 27) submitted to the FERC on November 18, 2009. The proposed treatments at the sites covered in this site-specific plan are consistent with the BE and a programmatic consistency form will be completed to document meeting requirements in the BE. The
USFWS will review annual site specific program consistency analysis forms (PCF), which are tied to a larger programmatic analysis of the entire project over the 25 years of erosion control treatment.
A JARPA is being submitted to the Washington Department of Fish and Wildlife
(WDFW), Washington Department of Ecology (Ecology), USFWS, and the Army
Corps of Engineers (Corps). The JARPA is the formal request for Nationwide Permit 13
Bank Stabilization from the Corps. It also addresses Ecology’s 401 Water Quality
Certification permit and the WDFW’s Hydraulic Project Application (HPA) addressed under the 2005 HPA Memorandum of Understanding.
4.3 Cultural Resources
The project area was surveyed for cultural resources during the relicensing project. A project description has been submitted to Powys Gadd, Okanogan-Wenatchee National
Forest Archaeologist, for review. A report will be submitted to the Washington State
Historic Preservation Office and concurrence documented prior to commencing project activities. Nation-to-Nation letters will be sent to the Confederated Tribes of the
Colville Reservation and the Confederated Tribes and Bands of the Yakama Indian
Nation in June 2013.
C.6 MATERIAL SOURCES
The Contractor is responsible for finding sources of rock and other materials such as LWD needed for this contract. The nearest local source of rock is Tunnel Hill Granite, 9 Howard Flats Road, Chelan, WA 98816 phone (509)682-2569.
C.7 PERFORMANCE PERIOD
It is anticipated that contract award will be made in early September, 2016. Award will be made in accordance with Section M of this solicitation.
The estimated starting date for on-site work is Fall (October 1, 2016). All work shall be completed during the winter/spring drawdown period for 2016-2017 with all work completed not later than March
31, 2017 or the end of the drawdown period, whichever occurs first. The Contractor shall maintain progress at a rate which shall assure completion within the contract time.
Do not submit a proposal unless you can complete all work within this established timeline.
C.8 WORK PROCEDURES
All work related to this project shall be performed in accordance with the following:
All applicable OSHA Safety Regulations and all applicable federal, state, county and local laws and regulations.
US Army Corps of Engineers Section 404 Permit (Nationwide No.13) with attached special conditions.
Final USDA Forest Service Site-Specific Erosion Control Plan as a requirement of the FERC license granted to the Chelan PUD for the Lake Chelan Hydroelectric Project No. 637-041.
If Archeological features or items are discovered during excavation, operations will stop until a qualified archeologist or other qualified professional archeologist approved by the
Contracting Officer can review the site.
C.9 TECHNICAL SPECIFICATIONS
The following listed specifications and SPECIAL PROJECT SPECIFICATIONS are hereby made a part of this Request for Proposals and any resultant contract award:
a. Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 U.S. Customary Units, U.S. Department of Transportation, Federal Highway Administration, 2003. The full FHWA specifications are available for downloading at the following URL:
http://www.wfl.fha.dot.gov/design/specs/fp03.htm.
Copies of these specifications are available from the U.S. Government Printing Office, Superintendent of Documents, Congressional Sales Office, U.S. Government Printing Office, Washington, DC 20402. The following sections are included in the contract by reference:
DIVISION 100 GENERAL REQUIREMENTS
Section 101 Terms, Format, and Definitions
Section 102 Bid, Award, and Execution of Contract
Section 103 Scope of Work
Section 104 Control of Work
Section 105 Control of Material
Section 106 Acceptance of Work
Section 107 Legal Relations and Responsibility to the Public
Section 108 Prosecution and Progress
Section 109 Measurement and Payment
DIVISION 150 PROJECT REQUIREMENTS
Section 151 Mobilization
Section 153 Contractor Quality Control
Section 156 Public Traffic
Accommodation Traffic During Work
Limitation on Construction Operations http://www.wfl.fha.dot.gov/design/specs/fp03.htm
Nighttime Operations
Traffic and Safety Supervisor
Section 157 Soil Erosion Control
DIVISION 200 EARTHWORK
Section 207 Earthwork Geotextile
DIVISION 250 SLOPE REINFORCEMENT AND RETAINING WALLS
Section 252 Special Rock Embankment and Rock Buttress
DIVISION 600 INCIDENTAL CONSTRUCTION
Section 620 Stone Masonry
Section 624 Topsoil
DIVISION 700 MATERIALS
Section 705.03 Rock for Masonry Structures
Section 705.04 Rock for Special Rock Embankment
Section 722.03 Rock Bolts
Section 713.13 Erosion Control Bales, Wattles, Logs and Rolls, Type 5.C
Section 713.18 Permanent Rolled Erosion Control Products
Section 714.01 Geotextile- Table 714.4 type IV-A
Specifications referenced under the Standard Specifications may be obtained from the following sources:
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO) Publications. For sale by AASHTO, P.O. Box 96716, Washington, DC 20090-6716, telephone (800)231-3475, fax (800)525-5562, Web site at www.aashto.orgb. The following SPECIAL
PROJECT REQUIREMENTS:
SECTION D--PACKAGING AND MARKING
D.1 MARKING REQUIRED ON OFFICIAL CORRESPONDENCE
The government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The government issued contract number shall be be referenced by the contractor on all official communications to the government, e.g. letters, certified payrolls, e-mails, submittals, etc., starting upon notice of contract award.
SECTION E--INSPECTION AND ACCEPTANCE
E.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/?q=browsefar
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
F.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
52.242-14 Suspension of Work (APR 1984)
F.2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than March 31, 2017 or the end of the drawdown period, whichever occurs first. The time stated for completion shall include final cleanup of the premises.
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held after the date of contract award. The conference will be held at a location mutually agreed upon between parties.
G.2 GOVERNMENT-FURNISHED PROPERTY
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the
Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.
Property to be Furnished Delivery Point Time of Delivery
Large Woody Debris Available at Prince Creek N/A
The government will furnish the following materials and information:
Large Woody Debris (LWD) at Prince Creek – the Government has accumulated a limited stockpile of LWD logs at Prince Creek campground on Lake Chelan that is available for the
Contractor’s use. The Contractor is responsible to load, transport and unload the logs from
Prince Creek to the applicable work site. The Government makes no warranty that the LWD log materials at Prince Creek meet contract specification. The Contractor shall select and use only LWD logs that meet contract specifications.
Large Woody Debris (LWD available on-site - There is a limited supply of LWD logs and downed trees available on site. The Contractor may use any materials available on site with the written approval of the Contracting Officer.
Historic and Planned Lake Water Level Hydrographs – The USDA Forest Service has written records of the historic water level hydrographs for Lake Chelan that are available for inspection upon request. The USDA Forest Service also has planned water level hydrographs for the future operation of Lake Chelan during the anticipated contract period per the new hydroelectric project license that are available for inspection upon request.
A copy of the US Army Corps of Engineers Section 404 permit (NWS-2008-1401-CRC) with special conditions applicable to this project.
G.3 DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE
The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract).
On all matters that pertain to the contract terms the Contractor must communicate with the
Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,
EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984)
(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work sites, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.
(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made know to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
H.2 PRODUCT SUBSTITUTION
Any modification of other items, designs, materials, products or equipment (including
Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting
Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.
H.3 CONTRACTOR’S REPRESENTATION & RESPONSIBILITY
a. In making formal request for substitution the Contractor represents it:
1. Has investigated proposed product and determined that it is equal to or superior in all respects to that originally specified.
2. Will provide same warranties and bond for substitute as for originally specified product.
3. Will coordinate installation of accepted substitution into the work, and will make such changes as may be required for the work to be complete in all respects.
4. Will waive claims for additional costs caused by substitution, which may subsequently become apparent.
5. Cost data is complete and includes related costs under the contract, but not:
a) Costs under separate contracts.
b) Contracting Officer costs for redesign or revision of contract documents.
b. The Contractor assumes full responsibility that the substitution and/or alternate items or procedures proposed will meet the job requirements.
c. The Contractor is solely responsible for the cost of redesign and modifications to this and other parts of the work caused by the substitutions or alternates furnished.
H.4 LANDSCAPE PRESERVATION
The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.
a. Prevention of the Landscape Defacement. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or other natural features or any other improvements in the work area unless specifically authorized by the Contracting Officer.
Unless otherwise provided herein, the Contractor shall confine contract operations to within the areas designated in contract documents.
b. Protection of Streams, Lakes, and Reservoirs. The Contractor shall take sufficient precautions to prevent pollution of streams, lakes, small ponds, and reservoirs with fuels, oils, bitumens, calcium chloride, silt, or other harmful materials. Mechanical equipment shall not be operated in live streams without written approval of the Contracting Officer.
H.5 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
a. Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
b. The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
c. Government inspections and tests are for the sole benefit of the Government and do not—
1. Relieve the Contractor of responsibility for providing adequate quality control measures;
2. Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
3. Constitute or imply acceptance; or
4. Affect the continuing rights of the Government after acceptance of the completed work under paragraph (I) below.
d. The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
e. The Contractor shall promptly furnish, without additional charge, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the
Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
f. The Contractor shall, without charge, replace or correct work found by the
Government not to conform to contract requirements, unless in the public interest the
Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
g. If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the
Contractor or (2) terminate for default the Contractor's right to proceed.
h. If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
i. Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately.
Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
H.6 SUSPENSIONS FOR OTHER THAN GOVERNMENT’S CONVENIENCE
The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of: (1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project, or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to become muddy or unsuitable; or (2) Failure of the Contractor to comply with Specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements, or when conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by his/her operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR
52.242-14, Suspension of Work, and shall not qualify for equitable adjustment.
H.7 ACCIDENT PREVENTION (FAR 52.236-13) (NOV 1991)
(a) The Contractor shall provide and maintain work environments and procedures which will (1) safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities; (2) avoid interruptions of
Government operations and delays in project completion dates; and (3) control costs in the performance of this contract.
(b) For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall --
(1) Provide appropriate safety barricades, signs, and signal lights;
(2) Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910; and
(3) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.
(c) If this contract is for construction or dismantling, demolition or removal of improvements with any Department of Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers
Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.
(d) Whenver the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting Officer shall notify the
Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor's representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the
Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued under this clause.
(e) The Contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.
H.8 FAR 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK
(APR 1984)
(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to
(1) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site; (4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the
Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/?q=/browse/far/52 www.usda.gov/procurement/policy/agar.html
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
(OCT 2015)
52.204-13 System for Award Management Maintenance (JUL 2013)
52.204-18 Commercial and Government Entity Code Maintenance (JUL 2015)
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015)
(Applicable if contract exceeds $35,000)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)
52.211-18 Variation in Estimated Quantity (APR 1984)
52.219-6 Notice of Total Small Business Set-Aside (NOV 2011)
52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013)
52.222-3 Convict Labor (JUN 2003)
52.222-6 Construction Wage Rates Requirements (MAY 2014)
52.222-7 Withholding of Funds (MAY 2014)
52.222-8 Payrolls and Basic Records (MAY 2014)
52.222-9 Apprentices and Trainees (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements (FEB 1988)
52.222-11 Subcontracts (Labor Standards) (MAY 2014)
52.222-12 Contract Termination - Debarment (MAY 2014)
52.222-13 Compliance with Construction Wage Rates Requirements and Related
Regulations (MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (MAY 2014)
52.222-20 Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000
(MAY 2014)
52.222-21 Prohibition of Segregated Facilities (APR 2015) (Applicable if contract exceeds
$10,000)
52.222-26 Equal Opportunity (APR 2015) (Applicable if contract exceeds $10,000)
52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015)
(Applicable if contract exceeds $10,000)
52.222-36 Equal Opportunity for Workers with Disabilities (JUL 2014) (Applicable if contract exceeds $15,000)
52.222-50 Combating Trafficking in Persons (MAR 2015) http://www.usda.gov/procurement/policy/agar.html
52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015)
52.223-6 Drug-Free Workplace (MAY 2001) (Applicable if contract is awarded to an individual)
52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving
(AUG 2011)
52.224-1 Privacy Act Notification (APR 1984)
52.224-2 Privacy Act (APR 1984)
52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)
52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)
52.228-2 Additional Bond Security (OCT 1997) (Applicable if contract exceeds $35,000)
52.228-11 Pledges of Assets (JAN 2012) (Applicable if contract exceeds $35,000)
52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) (Applicable if contract exceeds $35,000)
52.228-14 Irrevocable Letter of Credit (NOV 2014)(Applicable if contract exceeds $35,000)
52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014)
52.232-7 Payments under Time-and-Material and Labor-Hour Contracts (AUG 2012)
52.232-23 Assignment of Claims (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts (MAY 2014)
52.232-33 Payment by Electronic Funds Transfer – System for Award Management
(JUL 2013)
52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)
52.233-1 Disputes (MAY 2014)
52.233-3 Protest after Award (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)
52.236-2 Differing Site Conditions (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)
52.236-5 Material and Workmanship (APR 1984)
52.236-6 Superintendence by the Contractor (APR 1984)
52.236-7 Permits and Responsibilities (NOV 1991)
52.236-8 Other Contracts (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (APR 1984)
52.236-10 Operations and Storage Areas (APR 1984)
52.236-11 Use and Possession Prior to Completion (APR 1984)
52.236-12 Cleaning Up (APR 1984)
52.236-13 Accident Prevention (NOV 1991)
52.236-15 Schedules for Construction Contracts (APR 1984)
52.236-17 Layout of Work (APR 1984)
52.236-21 Specifications and Drawings for Construction (FEB 1997)
Alternate I (APR 1984)
Alternate II (APR 1984)
52.243-5 Changes and Changed Conditions (APR 1984)
52.244-6 Subcontracts for Commercial Items (FEB 2016)
52.246-21 Warranty of Construction (MAR 1994) Alternate I (APR 1984)
52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short From)
(APR 1984)
52.249-10 Default (Fixed-Price Construction) (APR 1984)
52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV
1996) (Applicable if contract is over $35,000)
452.236-72 Use of Premises (NOV 1996)
452.236-73 Archeological or Historic Sites (FEB 1988)
452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)
452.236-76 Samples and Certificates (FEB 1988)
452.236-77 Emergency Response (NOV 1996)
I.2 FAR 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. As used in this clause—
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means—
(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the…