FERM_Q&A_Fremont_Wiinema_May_19_2009.doc

DOC document 47 KB Posted

Attached to
Forest Engineering and Road Maintenance Federal contract opportunity
Solicitation number
AG-04N0-S-09-0004
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

Questions and Answers for (2) The Klamath Falls Meeting

View the file

Other files for this federal contract opportunity

Other files attached to Forest Engineering and Road Maintenance, newest first.
File Type Posted
FERM_Awards_Attachment_09.pdf PDF
Road Side Brushing Detail Map Revision #1.pdf PDF
FERM_Q&A_Deschutes_Ochoco_May_13_2009.doc DOC document
Amendment 01 Continuation.pdf PDF
Attachment 02A Road Side Brushing Revision #1.doc DOC document
Attachment 02B Road Side Brushing Example.doc DOC document
I_FERM_8_of_11_Area_#8_District_Maintenance.pdf PDF
L_FERM_11_of_11_Area_#11_District_Maintenance.pdf PDF
C_FERM_2_of_11_Area_#2_North_Deschutes.pdf PDF
R_FERM_General_Decision_Number.doc DOC document
N_FERM_Attachment_01_Road_Surface_Maintenance_Detail_Map.pdf PDF
P_FERM_Attachment_02_Road_Side_Brushing_Detail_Map.pdf PDF
K_FERM_10_of_11_Area_#10_District_Maintenance.pdf PDF
D_FERM_3_of_11_Area_#3_Chemult_Crescent.pdf PDF
O_FERM_Attachment_02_Road_Side_Brushing.doc DOC document
J_FERM_9_of_11_Area_#9_District_Maintenance.pdf PDF
M_FERM_Attachment_01_Road_Surface_Maintenance.doc DOC document
B_FERM_1_of_11_Area_#1_Ochoco_NF.pdf PDF
A_FERM_Solicitation.doc DOC document
E_FERM_4_of_11_Area_#4_Paisley_Silverlake.pdf PDF
H_FERM_7_of_11_Area_#7_District_Maintenance.pdf PDF
G_FERM_6_of_11_Area_#6_Bly_Lakeview.pdf PDF
Q_FERM_Service_Contract_Act_Wage_Rates.doc DOC document
F_FERM_5_of_11_Area_#5_Chiloquin_Klamath.pdf PDF
A_FERM_Notice.doc DOC document
S_FERM_Contractor_Performance_Data_Sheet.doc DOC document
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FERM Pre-Quote Meeting Q&A

FOREST ENGINEERING AND ROAD MAINTENANCE

AG-04N0-S-09-0004

PRE-QUOTE MEETING

MAY 19, 2009

FREMONT-WINEMA NATIONAL FORESTS

Q1: What if the equipment that is listed on the Schedule of Items does not include equipment that I have?

A1: The equipment that is listed on the Schedule of Items is to get a base line price to use to evaluate for the award. As long as the contractor stays in the perimeter of the contract the contractor may use any equipment to accomplish the project.

Q2: What does the Asterisk (*) mean on the Schedule of Items?

A2: The Asterisk (*) means that item is under the Service Contract Wage, if it does not have a * than it is under the Davis Bacon Wage. It is necessary for each contractor to burden their rates accordingly.

Q3: Will Delivery/Task Orders be negotiated?

A3: Yes.

Q4: How many awards are estimated?

A4: Up to 12 per item, depending on qualifying contractors.

Q5: When competing Delivery/Task Orders are the Contractors required to bid?

A5: No, but need to send a hard copy of reason for not bidding to the Contracting Officer.

Q6: If Delivery/Task Order is awarded under Davis Bacon Wage will we have time to get bonded?

A6: The contractor should already have a bond company.

Q7: If the Forest Service is not happy with the vendor pool, will the Forest Service open it back up in the future?

A7: While not definite, the Forest Service may re-open competition in the future if additional capacity is needed. As businesses fold or folks retire and we don’t have enough vendors left in a certain category, we may re-solicit at that time.

Q8: If after the contract is awarded, will the Forest Service allow other contractors in the pool?

A8: The Forest Service is hopeful that we will have a good pool of contractors to use for future projects, unless the contractor goes out of business.

Q9: Is there a reason why this wasn’t this a Hub Zone set aside?

A9: There is not a large enough pool of Hub Zone contractors.

Q10: Does each bid item stand on its own?

A10: Yes

Q11: Why is the unit of measurement different for Hazard Tree Falling from the Ochoco N.F., Deschutes N.F. and the Fremont-Winema N.F.?

A11: The Amendment these Q&As are attached to has corrected the Units.

Q12: What budget year will F.E.R.M. be in?

A12: Budget Year FY09 which ends September 30, 2009.

Q13: Does the Forest Service want the contractors to include a Safety Plan for this solicitation?

A13: We are not requiring a Safety Plan to be provided in response to the initial solicitation. We will be asking for them at the first Task Order’s pre-work meeting. Any unique hazards for the project will be addressed at that time as well.

Q14: Can Project and Site Manager be the same person?

A14: Yes, there is no reason they can not be the same person.

Q15: Can a computer print out be used for equipment availability?

A15: Yes

Q16: Is there any estimate of how many miles of road?

A16: No, this will be to each individual Delivery/Task Order.

Q17: Do we need to update personnel if it changes in the future?

A17: In accordance with the clauses set forth in the solicitation, the Government must be notified of key personnel changes and that can be done on Delivery/Task Orders.

Q18: Can you use Sub contractor when Sub contractor is bidding on same Delivery/Task Order?

A18: Yes, they will be evaluated separately and will need to know the specific equipment being used on the Contractor Data Performance Sheet.

Q19: All Specs will be FP-O3?

A19: Yes, for construction unless otherwise noted as a lump sum item for all work on a project.

Q20: Will bid items be unit cost or lump sum?

A20: How ever the engineer puts them out but the Delivery/Task Orders will be unit cost.

Q21: Will this contract be funded with Stimulus funds only or does the Forest Service have project funds available this year too?

A21: Yes, we have project funding right now and we should also use Stimulus funding.

Q22: If we do not receive an award will there be another opportunity?

A22: The Forest Service may re-open competition in the future if additional capacity is needed.

Q23:

Do we need to submit a Contractor Performance Data Sheet for each bid item?

A23:

Yes, at least one but preferably three Contractor Performance Data Sheets shall be submitted for each work activity (e.g. Roadside Brushing). However, if your business is proposing on roadside brushing or similar work activities in several performance areas, those three will suffice for all Areas you are interested in performing.

Q24: Do we need to submit a Resume for each personnel on each bid item?

A24: No, will need to submit for key personnel only and can be submitted for groups of work activities and Areas of performance as long as that information is provided in your proposal.

Q25: Do we need to fill out the boxes in Representations and Certifications?

A25: No, not if you have registered and updated your information in ORCA. However, remember to state in the representations and certifications clause that you are registered in ORCA.

File details come from the government source that posted it. Updated .