Amendment_3.pdf

PDF 696 KB Posted

Attached to
Starkey EFR Big Game Fence Construction & Maintenance
Solicitation number
AG-04M3-S-17-0058
Issued by

View the file

Other files

File Type Posted
Amendment_2.pdf PDF
Amendment_1.rtf RTF text file
d.Return_This_Copy.docx DOCX document
a.AG-04M3-S-17-0058.docx DOCX document
b.Section_J_Attachments.pdf PDF
c.Starkey_Task_Order.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1 CONTRACT ID CODE

I PA~E r PA;ES 04M3

2. AMENDMENT/MODIFICATION NO. 13. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO.

PROJECT NO. (If app/icable)

Amendment 3 May 24,2017

6. ISSUED BY CODE I 04M3 7. ADMINISTERED BY (If other than Item 6) CODE I 04M3

Contracting East Acquisition Area Wallowa-Whitman National Forest

Same1550 Dewey Ave.

Baker City, OR 97814

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) ~ 9A AMENDMENT OF SOLICITATION NO.

AG-04M3-S-17 -0058

~ 9B. DATED (SEE ITEM 11)

May 4,2017

10A MODIFICATION OF CONTRACTIORDER NO.

D 10B. DATED (SEE ITEM 13)

CODE I DUNS NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

~ The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers D is extended.

~ is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X) A THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

D

D D

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor D is not, ~ is required to sign this document and return 1 copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

Amendment 3 is to provide page 2 of the Task Order package that was inadvertely omitted from the original solicitation.

Exce t as rovided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore chan ed, remains unchan ed and in full force and effect.

15A NAMEAND TITLE OF SIGNER (Type or print) 16A NAMEAND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED

Sue Domina, Contracting Officer i'

(Signature of person authorized to sign)

16C. DATE SIGNED

~atureo

5/24/2017

NSN 7540-01-152-8070

Previous edition unusable

30-105

Solicitation No. AG-04M3-S-17-0058 Task Order

DESCRIPTION

This project is for the replacement of rotted wood fence posts, replacing broken steel posts, straightening bent steel posts, tightening wire, removing electrical single strand wire and re-establishing the ROW on the outside perimeter of the fence.

The Contractor shall be required to check each post, wooden & steel.

PROJECT ESTIMATE

This project is estimated at $25,000 - $150,000. Davis Bacon Wage Rates apply.

COMPLETION TIME

Project shall start within 14 days of award and shall be completed within 90 calendar days from date on Notice to Proceed.

SPECIFICATIONS

Contractor is to use their proposal to accomplish the work. Maps and drawings attached are for reference purposes to show how the fence is currently installed.