g.Opinion_of_Probable_Construction_Cost_-_Boat_Dock_Facility.xls
XLS spreadsheet 52 KB Posted
- Attached to
- Hells Canyon Boat Launch Design
- Solicitation number
- AG-04M3-S-16-0087
About this file
G. Opinion of Probable Construction Cost - Boat Dock Facility
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Boat Dock
| PROJECT: | BergerABAM Job No.: | PAGE: | |||||
| Hells Canyon Boat Launch Assessment | 1.0 | OF | 1 | ||||
| A15.0253.00 | |||||||
| OPERATION: | ESTIMATOR: | DATE: | |||||
| Estimate of Probable Construction Cost - Boat Dock Facility | |||||||
| TAD/BDB | 26-May-11 | ||||||
| ITEM | UNIT | QUANTITY | UNIT | TOTAL | |||
| NO. | COST | COST | |||||
| $0 | |||||||
| 1.0 | Mobilization * | LS | 1 | $ 15,800.00 | $ 15,800.00 | ||
| 2.0 | Sediment Fence for In-water Work | LS | 1 | $ 4,000.00 | $ 4,000.00 | ||
| 3.0 | Clear Rock and Debris | LS | 1 | $ 2,100.00 | $ 2,100.00 | ||
| 4.0 | Replace Gravel Bedding | LS | 1 | $ 2,000.00 | $ 2,000.00 | ||
| 5.0 | Re-align Steel Frame | LS | 1 | $ 3,200.00 | $ 3,200.00 | ||
| 6.0 | Repair and Replace Steel Framing Members | LS | 1 | $ 9,200.00 | $ 9,200.00 | ||
| 7.0 | Repair and Replace Access Stairs | LS | 1 | $ 11,000.00 | $ 11,000.00 | ||
| 8.0 | New Floating Dcok (Incl. Dock Engineering) | LS | 1 | $ 73,700.00 | $ 73,700.00 | ||
| 9.0 | Install Floating Dock | LS | 1 | $ 22,000.00 | $ 22,000.00 | ||
| 10.0 | Site Access Premium ** | LS | 1 | $ 12,800.00 | $ 12,800.00 | ||
| 11.0 | Permitting and Engineering | LS | 1 | $ 25,000.00 | $ 25,000.00 | ||
| $0 | |||||||
| $0 | |||||||
| $0 | |||||||
| $0 | |||||||
| $0 | |||||||
| $0 | |||||||
| $0 | |||||||
| $0 | |||||||
| * 15% of total of items 2 through 9 | $0 | ||||||
| (varies depending on estimate) | $0 | ||||||
| ** 10% of items 2 through 9 | $0 | ||||||
| (accounts for remote location of project) | $0 | ||||||
| $0 | |||||||
| $0 | |||||||
| SUB TOTAL | $180,800 | ||||||
| 30% Construction Contingency | $54,300 | ||||||
| $0 | |||||||
| TOTAL ESTIMATE ROUNDED | $235,100 |
Boat Ramp - Alt A
| PROJECT: | BergerABAM Job No.: | PAGE: | |||||
| Hells Canyon Boat Launch Assessment | 1.0 | OF | 2 | ||||
| A15.0253.00 | |||||||
| OPERATION: | ESTIMATOR: | DATE: | |||||
| Estimate of Probable Construction Cost - Boat Ramp - Alternative A | |||||||
| TAD/BDB | 26-May-11 | ||||||
| ITEM | UNIT | QUANTITY | UNIT | TOTAL | |||
| NO. | COST | COST | |||||
| 1.0 | Mobilization * | LS | 1 | $ 7,100.00 | $ 7,100.00 | ||
| 2.0 | Sediment Fence for In-water Work | LS | 1 | $ 4,000.00 | $ 4,000.00 | ||
| 3.0 | Grout Bag Installation | LS | 1 | $ 27,800.00 | $ 27,800.00 | ||
| 4.0 | Install Engineered Riprap | LS | 1 | $ 15,000.00 | $ 15,000.00 | ||
| 5.0 | Site Access Premium ** | LS | 1 | $ 4,700.00 | $ 4,700.00 | ||
| 6.0 | Permitting and Engineering | LS | 1 | $ 25,000.00 | $ 25,000.00 | ||
| * 15% of total of items 2 through 4 | |||||||
| (varies depending on estimate) | |||||||
| ** 10% of items 2 through 4 | |||||||
| (accounts for remote location of project) | |||||||
| SUB TOTAL | $83,600 | ||||||
| 30% Construction Contingency | $25,100 | ||||||
| TOTAL ESTIMATE ROUNDED | $108,700 |
Boat Ramp - Alt B
| PROJECT: | BergerABAM Job No.: | PAGE: | |||||
| Hells Canyon Boat Launch Assessment | 2.0 | OF | 2 | ||||
| A15.0253.00 | |||||||
| OPERATION: | ESTIMATOR: | DATE: | |||||
| Estimate of Probable Construction Cost - Boat Ramp - Alternative B | |||||||
| TAD/BDB | 26-May-11 | ||||||
| ITEM | UNIT | QUANTITY | UNIT | TOTAL | |||
| NO. | COST | COST | |||||
| 1.0 | Mobilization * | LS | 1 | $ 7,300.00 | $ 7,300.00 | ||
| 2.0 | Sediment Fence for In-water Work | LS | 1 | $ 4,000.00 | $ 4,000.00 | ||
| 3.0 | Remove Panels and Replace Gravel Bedding | LS | 1 | $ 19,200.00 | $ 19,200.00 | ||
| 4.0 | Grout Bag Installation | LS | 1 | $ 10,000.00 | $ 10,000.00 | ||
| 5.0 | Install Engineered Riprap | LS | 1 | $ 15,000.00 | $ 15,000.00 | ||
| 6.0 | Site Access Premium ** | LS | 1 | $ 4,900.00 | $ 4,900.00 | ||
| 7.0 | Permitting and Engineering | LS | 1 | $ 25,000.00 | $ 25,000.00 | ||
| * 15% of total of items 2 through 5 | |||||||
| (varies depending on estimate) | |||||||
| ** 10% of items 2 through 5 | |||||||
| (accounts for remote location of project) | |||||||
| SUB TOTAL | $85,400 | ||||||
| 30% Construction Contingency | $25,700 | ||||||
| TOTAL ESTIMATE ROUNDED | $111,100 |
Quantities and cost background
| Boat Dock (Alt. A and B) | Boat Ramp (Alt. A Only) | ||
| Floating Dock: | Grout Bag Installation: | ||
| Area = (26' x 31') - (18' x 9' x 2) = 482 sf | Volume (ramp end) = 1.5' deep x 6' Wide x 6' Long = 54 cf | ||
| Cost = $153/sf (RSMeans 35 51 13.24 + 30% for Engineering/Geometry) | Volume (ramp end) = 1.5' deep x 2.5' Wide x 12' Long = 45 cf | ||
| Lump Sum = $73,700 | Cost = $73.50/cf (RSMeans 31 43 13.13) | ||
| Sub Total = $7,300 | |||
| Repair and Replace Access Stairs: | Diving = 1.5 times the effort of inspection | ||
| Cost = $20,250 | |||
| Stringers = 2 Stringers x 80' = 160' | Lump Sum = $27,800 | ||
| Cost = $45/ft (RSMEans 05 12 23.75) | |||
| Sub Total = $7,200 | Boat Ramp (Alt. A and B) | ||
| Treads = 18 replaced | |||
| Cost = $150/ea | Install Rip Rap: | ||
| Sub Total = $2,700 | |||
| Treads = 52 reatached | Volume = 30' long x 3' wide x 5' deep = 17 cy | ||
| Cost = $20/ea | Cost = $300/cy (WSDOT small quantitiy increased for Site Complexity and In-Water) | ||
| Sub Total = $1,040 | Lump Sum = $5,100 | ||
| Lump Sum = $11,000 | |||
| Boat Ramp (Alt. B Only) | |||
| Repair and Replace Steel Framing Members: | |||
| Replace Gravel Bedding: | |||
| Repair members = 8 hrs. | Volume (ramp end) = 1.5' deep x 6' Wide x 6' Long = 3 cy | ||
| Cost = $89/hr (RSMeans Crew E-3 Steel Worker) | Volume (ramp end) = 1.5' deep x 2.5' Wide x 12' Long = 3 cy | ||
| Sub Total = $712 | Cost = $52/cy (WSDOT State Average x 4 for complexity) | ||
| Replace Diagonal Braces = Up to (6) L3x3x5/16 @ 24' ea = 879 lbs | Removing and Resetting Concrete Panels = 24 hrs | ||
| Cost = $9.65/lb (RSMeans 05 12 23.40) | Disconnect/reconnect end panel stop (below water) = 10000 | ||
| Sub Total = $8,482 | Cost = $330/hr (RSMeans Crew E-3 + Crane) | ||
| Lump Sum = $9,200 | Lump Sum = $19,168 | ||
| Replace Gravel Bedding: | Engineering (Boat Dock Alt. A/Boat Ramp Alt. A and B): | ||
| WSDOT Crushed Surfacing Base Course = 40' x 9' x 0.75' = 10 cy | Project Engineer = 40 hrs | ||
| Cost = $200/cy (WSDOT State Average increased for Site Complexity and In-Water) | Cost = $125/hr | ||
| Lump Sum = $2,000 | Designer = 24 hrs | ||
| Cost = $85/hr | |||
| Clear Rock and Debris: | Manager = 16 hrs | ||
| Cost = $165/hr | |||
| Excavation = 2' deep x 16' long x 18' wide = 21 cy | Lum Sum = $9,680 | ||
| Cost = $100/cy (WSDOT State Average Excavation Incl. Haul increased for site Complexity and In-Water) | |||
| Lump Sum = $2,100 | Engineering (Boat Dock Alt. B Only): | ||
| Realigh Steel Frame: | Project Engineer = 80 hrs | ||
| Realign = 8 hrs. | Cost = $125/hr | ||
| Cost = $89/hr (RSMeans Crew E-3 Steel Worker) x 3 = $267/hr | Designer = 40 hrs | ||
| Jack rental | $ 1,000.00 | Cost = $85/hr | |
| Sub Total = $3200 | Manager = 24 hrs | ||
| Cost = $165/hr | |||
| Lum Sum = $17,360 |