Boat Dock

PROJECT:BergerABAM Job No.:PAGE:
Hells Canyon Boat Launch Assessment1.0OF1
A15.0253.00
OPERATION:ESTIMATOR:DATE:
Estimate of Probable Construction Cost - Boat Dock Facility
TAD/BDB26-May-11
ITEMUNITQUANTITYUNITTOTAL
NO.COSTCOST
$0
1.0Mobilization *LS1$ 15,800.00$ 15,800.00
2.0Sediment Fence for In-water WorkLS1$ 4,000.00$ 4,000.00
3.0Clear Rock and DebrisLS1$ 2,100.00$ 2,100.00
4.0Replace Gravel BeddingLS1$ 2,000.00$ 2,000.00
5.0Re-align Steel FrameLS1$ 3,200.00$ 3,200.00
6.0Repair and Replace Steel Framing MembersLS1$ 9,200.00$ 9,200.00
7.0Repair and Replace Access StairsLS1$ 11,000.00$ 11,000.00
8.0New Floating Dcok (Incl. Dock Engineering)LS1$ 73,700.00$ 73,700.00
9.0Install Floating DockLS1$ 22,000.00$ 22,000.00
10.0Site Access Premium **LS1$ 12,800.00$ 12,800.00
11.0Permitting and EngineeringLS1$ 25,000.00$ 25,000.00
$0
$0
$0
$0
$0
$0
$0
$0
* 15% of total of items 2 through 9$0
(varies depending on estimate)$0
** 10% of items 2 through 9$0
(accounts for remote location of project)$0
$0
$0
SUB TOTAL$180,800
30% Construction Contingency$54,300
$0
TOTAL ESTIMATE ROUNDED$235,100

Boat Ramp - Alt A

PROJECT:BergerABAM Job No.:PAGE:
Hells Canyon Boat Launch Assessment1.0OF2
A15.0253.00
OPERATION:ESTIMATOR:DATE:
Estimate of Probable Construction Cost - Boat Ramp - Alternative A
TAD/BDB26-May-11
ITEMUNITQUANTITYUNITTOTAL
NO.COSTCOST
1.0Mobilization *LS1$ 7,100.00$ 7,100.00
2.0Sediment Fence for In-water WorkLS1$ 4,000.00$ 4,000.00
3.0Grout Bag InstallationLS1$ 27,800.00$ 27,800.00
4.0Install Engineered RiprapLS1$ 15,000.00$ 15,000.00
5.0Site Access Premium **LS1$ 4,700.00$ 4,700.00
6.0Permitting and EngineeringLS1$ 25,000.00$ 25,000.00
* 15% of total of items 2 through 4
(varies depending on estimate)
** 10% of items 2 through 4
(accounts for remote location of project)
SUB TOTAL$83,600
30% Construction Contingency$25,100
TOTAL ESTIMATE ROUNDED$108,700

Boat Ramp - Alt B

PROJECT:BergerABAM Job No.:PAGE:
Hells Canyon Boat Launch Assessment2.0OF2
A15.0253.00
OPERATION:ESTIMATOR:DATE:
Estimate of Probable Construction Cost - Boat Ramp - Alternative B
TAD/BDB26-May-11
ITEMUNITQUANTITYUNITTOTAL
NO.COSTCOST
1.0Mobilization *LS1$ 7,300.00$ 7,300.00
2.0Sediment Fence for In-water WorkLS1$ 4,000.00$ 4,000.00
3.0Remove Panels and Replace Gravel BeddingLS1$ 19,200.00$ 19,200.00
4.0Grout Bag InstallationLS1$ 10,000.00$ 10,000.00
5.0Install Engineered RiprapLS1$ 15,000.00$ 15,000.00
6.0Site Access Premium **LS1$ 4,900.00$ 4,900.00
7.0Permitting and EngineeringLS1$ 25,000.00$ 25,000.00
* 15% of total of items 2 through 5
(varies depending on estimate)
** 10% of items 2 through 5
(accounts for remote location of project)
SUB TOTAL$85,400
30% Construction Contingency$25,700
TOTAL ESTIMATE ROUNDED$111,100

Quantities and cost background

Boat Dock (Alt. A and B)Boat Ramp (Alt. A Only)
Floating Dock:Grout Bag Installation:
Area = (26' x 31') - (18' x 9' x 2) = 482 sfVolume (ramp end) = 1.5' deep x 6' Wide x 6' Long = 54 cf
Cost = $153/sf (RSMeans 35 51 13.24 + 30% for Engineering/Geometry)Volume (ramp end) = 1.5' deep x 2.5' Wide x 12' Long = 45 cf
Lump Sum = $73,700Cost = $73.50/cf (RSMeans 31 43 13.13)
Sub Total = $7,300
Repair and Replace Access Stairs:Diving = 1.5 times the effort of inspection
Cost = $20,250
Stringers = 2 Stringers x 80' = 160'Lump Sum = $27,800
Cost = $45/ft (RSMEans 05 12 23.75)
Sub Total = $7,200Boat Ramp (Alt. A and B)
Treads = 18 replaced
Cost = $150/eaInstall Rip Rap:
Sub Total = $2,700
Treads = 52 reatachedVolume = 30' long x 3' wide x 5' deep = 17 cy
Cost = $20/eaCost = $300/cy (WSDOT small quantitiy increased for Site Complexity and In-Water)
Sub Total = $1,040Lump Sum = $5,100
Lump Sum = $11,000
Boat Ramp (Alt. B Only)
Repair and Replace Steel Framing Members:
Replace Gravel Bedding:
Repair members = 8 hrs.Volume (ramp end) = 1.5' deep x 6' Wide x 6' Long = 3 cy
Cost = $89/hr (RSMeans Crew E-3 Steel Worker)Volume (ramp end) = 1.5' deep x 2.5' Wide x 12' Long = 3 cy
Sub Total = $712Cost = $52/cy (WSDOT State Average x 4 for complexity)
Replace Diagonal Braces = Up to (6) L3x3x5/16 @ 24' ea = 879 lbsRemoving and Resetting Concrete Panels = 24 hrs
Cost = $9.65/lb (RSMeans 05 12 23.40)Disconnect/reconnect end panel stop (below water) = 10000
Sub Total = $8,482Cost = $330/hr (RSMeans Crew E-3 + Crane)
Lump Sum = $9,200Lump Sum = $19,168
Replace Gravel Bedding:Engineering (Boat Dock Alt. A/Boat Ramp Alt. A and B):
WSDOT Crushed Surfacing Base Course = 40' x 9' x 0.75' = 10 cyProject Engineer = 40 hrs
Cost = $200/cy (WSDOT State Average increased for Site Complexity and In-Water)Cost = $125/hr
Lump Sum = $2,000Designer = 24 hrs
Cost = $85/hr
Clear Rock and Debris:Manager = 16 hrs
Cost = $165/hr
Excavation = 2' deep x 16' long x 18' wide = 21 cyLum Sum = $9,680
Cost = $100/cy (WSDOT State Average Excavation Incl. Haul increased for site Complexity and In-Water)
Lump Sum = $2,100Engineering (Boat Dock Alt. B Only):
Realigh Steel Frame:Project Engineer = 80 hrs
Realign = 8 hrs.Cost = $125/hr
Cost = $89/hr (RSMeans Crew E-3 Steel Worker) x 3 = $267/hrDesigner = 40 hrs
Jack rental$ 1,000.00Cost = $85/hr
Sub Total = $3200Manager = 24 hrs
Cost = $165/hr
Lum Sum = $17,360