Attachment_3_nf_grouse_special_project_specifications.doc
DOC document 482 KB Posted
- Solicitation number
- AG-02RC-S-10-0027
About this file
Attachment 3 - Special Project Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| amendment_2_schedule_corrections.doc | DOC document | |
| amendment_1_nf.grouse.ck_extension.doc | DOC document | |
| attachment_2_nf_grouse_ck_plans_sheets.pdf | ||
| return_forms_sol_nf_grouse_ck.doc | DOC document | |
| attachment_4_Idaho_wrk_comp_cert_.doc | DOC document | |
| Attachment_1_wage_rate.docx | DOCX document | |
| complete_sol_nf_grouse_ck.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N.F. GROUSE CREEK CULVERT REPLACEMENT
SPECIAL PROJECT SPECIFICATIONS
Section 101 - Abbreviations, Acronyms, & Terms
101.01 Terms, Organizations, & Standards.
(a) Acronyms. Add the following:
BMP
Best Management Practice
EPA
Environmental Protection Association
FPL
Forest Products Laboratory
ICRI
International Concrete Repair Institute
SSPC
Steel Structures Painting Council
WCLIB
West Coast Lumber Inspection Bureau
WWPA
Western Wood Products Association
USN
United States Navy”
101.02 – Abbreviations
Delete in its entirety and substitute the following:
And
AC
Acre
AGG …………………………Aggregate
AL.
Aluminum
ASP
Asphalt
AQ……………………………Actual Quantities
AVAIL
Available
BARR
Barrier
BKN
Broken
BST
Bituminous Surface Treatment
CATTLEGD
Cattle guard
CLEAR (CLG)
Clearing
CLEAR/GRUB
Clearing & Grubbing
CMP
Corrugated Metal Pipe
CMPA………………………..Corrugated Metal Pipe Arch
COMP
Compaction
CO……………………………Contracting Officer
CONC
Concrete
CONST
Construction (Construct) CSP…………………………..Corrugated Steel Pipe
CTD
Coated (Coating)
CUSH
Cushion
CY (CU YD)
Cubic Yard
CY MI (CYM)
Cubic Yard Mile
DIA
Diameter
DL
Double Lane
DQ……………………………Design Quantities D/S…………………………...Downstream
DWGS
Drawings
EA
Each
EMB
Embankment
EXC
Excavation F&I Furnish & Install
FDN
Foundation
FT
Foot (Feet)
FUNC
Function
GAL
Gallon
GR.
Grade
GRUB
Grubbing
HDPE
High Density Polyethylene
96 SPS 101-1 (07/12/10)
Ha… .…………………… Hectare HOR………………………….Horizontal
HR
Hour
HT
Height I Install
IN
Inches
INCL
Including (Includes)
IND
Individual
JCT
Junction
Kg ……………………………Kilogram
Kl..……………………………Kiloliter
Kl km...…………………….…Kiloliter Kilometer L Logs l ……………………………...Liter
L……………………………...Length
LBS
Pounds
LDG
Loading
LF (LIN FT)
Linear (lineal) Foot LS…………………………….Lump Sum
LSL…………………
Lower Specification Limit LSQ…………………………..Lump Sum Quantities
MAT'L
Material M Metal m……………… Meter mm……… Millimeter
MAX
Maximum
MBF
One Thousand Feet Board Measure
MGALS
One Thousand Gallons
MHD
Method
MI
Mile
MIN
Minimum
MISC
Miscellaneous
MP
Mile Post
MSF
One Thousand Square Feet
OTBC
Open Top Box Culvert
PI……………………………..Plasticity Index P M Placement Method
PVC
Polyvinyl chloride
RD
Road
RECOND
Reconditioning
RECONST
Reconstruction (Reconstruct)
REFL
Reflectorized
RT
Right
STMP (STP)
Stump(s)
SB
Self Balance
SEC
Section
SF
Square Foot (Feet)
SL
Single Lane
SLD
Solid
SQ……………………………Staked Quantities
ST
Slash Treatment
STA
Station (100 Feet)
STA YD
Station Yard
STL
Steel
STR (STRUC)
Structural
SY (SQ YD)
Square Yard
SZ
Size
T………………………… Ton (1,000 kg)
T km.…….
Ton Kilometer T&L Tops & Limbs
TBR
Timber
TH
Thickness
TM
Ton Mile
TV……………………………Target Value
TO
Turnout
TOL
Turnout Left
TOR
Turnout right
TRS
Trees
UOT
Utilization of Timber
U/S……………………………Upstream
USL…………………………..Upper Specification Limit
VERT
Vertical W Width W/ With W/O Without
X-SEC
Cross Section
YD
Yard”
96 SPS 101-2 (07/12/10)
Section 102 - Definitions Add the following:
"Noxious Weeds or Weeds. Any exotic plant species established or that may be introduced in the State which may render land unfit for agriculture, forestry, livestock, wildlife, or other beneficial uses and which is designated by the State's Department of Agriculture, or by the County's weed management district, or by other appropriate agencies having jurisdiction, or as listed on the current ‘All States Noxious Weed List.’
Shop Drawings. Incidental design sheets and/or drawings the Contractor is required to submit to the Forest Service. Shop drawings shall conform to the contract requirements, but they are not part of the contract drawings. They may be drawings, diagrams, schedules, performance charts, brochures, and similar data prepared by the Contractor, subcontractor, manufacturer, suppliers, or distributors that illustrate how specific portions of the work are to be fabricated or installed.
Weed Management District. A weed management district is any area of land identified for the purpose of weed management or control. Such an identified land area may be, but is not limited to one of the following: a project or job site, a County, two or more Counties, or a National Forest.
Engineer. The Contracting Officer’s Representative (COR) responsible for onsite administration of the contract.”
96 SPS 102-1 (07/12/10)
Section 103 – Intent of Contract Add the following:
“This project involves the removal of an existing 10 foot diameter CMP and construction of a new 67’ span bridge with a prestressed concrete bulb-tee beam superstructure on a precast concrete grade beam foundation.
The project work includes, but not limited to; removal of existing CMP structure, minor clearing and grubbing, structural excavation, furnish and placement of riprap, furnish and install precast concrete grade beams and wingwalls, furnish and install precast prestressed concrete bulb-tee beams, excavation and embankment, crushed aggregate surfacing, equipment rental stream realignment and structures work, stream diversion(s), soil erosion and pollution control, contractor construction quality control and associated minor work items
In-stream work will only be allowed between July 15th and September 1st of any construction year without approval by the Contracting Officer. Approved BMP’s for sediment containment must be utilized through the entire reach of the construction site. Stream diversion(s) and de-watering will be required so that bridge construction and stream channel simulation work is accomplished in a manner to control construction generated stream turbidity.”
96 SPS 103-1 (07/12/10)
Section 104 – Maintenance for Traffic
104.01 Roads to be Constructed - Schedule A: Detour Road and Detour Bridge Option Delete the last two paragraphs of this subsection and add the following:
“The Contractor will not be allowed to close Road No. 280 to public traffic during construction work under this contract. Furnish, install, maintain and remove a portable prefabricated detour bride as specified under Section 558 and sown on the project drawings. Construct, maintain and remove a detour road as specified in the project drawings, and in Section 680 of the Special Project Specifications. Maintain detour for safe public traffic around the bridge construction site for the duration of construction activities until the new bridge structure can be opened to public traffic.
The contractor shall be responsible for providing, maintaining and removal of all barricades, night time delineation lighting and signs required for the road closure. The traffic control plan must include provisions to safely accommodate and guide public traffic on the detour road at all hours of the day, and through the section of Road 280 designated as the excess material waste site.
At the contractor’s written request, traffic delays, as outlined below, will be approved should the project work necessitate short traffic delay periods.
Time Periods Maximum Delays
Monday – Friday (8:00 a.m. – 4:00 p.m.) ------------------------ 60 Minutes
Monday – Friday (4:00 p.m. – 8:00 a.m.) ------------------------ Open to Traffic
Weekends – (Sat. & Sun) and Holidays -------------------------- Open to Traffic
Traffic delay periods (60 minutes) between 8:00 a.m. and 4:00 p.m. begin when the first traffic vehicle arrives at the closure site. This traffic delay period is the maximum delay traffic should experience within the entire construction area.
Other delay periods up to 4 hours may be authorized upon receipt of a written approval from the Contracting Officer. Prior notification by the contractor is required for public notice of the contractor’s intent to delay traffic. The Contractor shall submit a written request outlining the longer traffic delays required at least 7 days prior to starting construction operation that necessitates the longer traffic delays. The contractor must open the bridge and road as rapidly as possible to allow passage of emergency vehicles.”
96 SPS 104-1 (07/12/10)
The following is added to this subsection:
“The Contractor shall be responsible for the safe passage of vehicle traffic over the bridge and through the construction site when Road No. 280 is open to public traffic during construction and outside work hours.
Develop a construction sign plan that reflects the Contractor’s plan of operation and submit to the Contracting Officer for approval 14 days prior to commencement of on-site project work. Install construction signs prior to and consistent with the site work being performed.”
104.01 Roads to be Constructed - Schedule B: Pedestrian By-Pass & Footbridge Option Delete the last two paragraphs of this subsection and add the following:
“The Contractor will be allowed to close that segment of Road No. 280 affected by bridge and approach road construction activities to public traffic during construction as outlined below. No temporary detour or work bridge will be allowed under this Schedule B award option.
Forest Development Road No. 280 may be closed to public traffic within the construction area during bridge construction work under this contract for one(1) closure period consisting of up to a sixteen(16) consecutive day closure period.
The sixteen(16) consecutive day closure period will only be approved starting on a Saturday of one week and concluding on a Sunday sixteen days later. Within this closure period, the Contractor will be responsible for removal of the existing culvert structure and installation of the new replacement bridge ready for public use. This will allow a Contractor 10 week days and 6 weekend days to complete this portion of the project work. Weekend construction may be required in order to meet this construction schedule.
This sixteen(16) day closure period will fall sometime between July 15th and September 1st of 2011. Contractor shall provide the Contracting Officer at least 14 days advanced written notice prior to any road closure period to provide residence, public and Forest Service administrative user’s notice of the approved closure period. The contractor shall be responsible for providing, maintaining and removal of all barricades and signs required for the road closure.
96 SPS 104-2 (07/12/10)
There are several private residences located beyond the bridge construction site with the only access being Road No. 280 through the project area. To provide limited access for residents, the Contractor will construct a temporary foot path and temporary pedestrian bridge to provide residence with a safe pedestrian access during this road closure period. During this closure period, residence will have the option of parking vehicles on one or both sides of the construction area. Government will work with Contractor to designate a parking area for residents to leave vehicles outside the bridge construction area.
At the contractor’s written request, traffic delays, as outlined below, will be approved outside the road closure period should the project work necessitate short traffic delays outside the approved closure period.
Time Periods Maximum Delays
Monday – Friday (8:00 a.m. – 4:00 p.m.) ------------------------ 60 Minutes
Monday – Friday (4:00 p.m. – 8:00 a.m.) ------------------------ Open to Traffic
Weekends – (Sat. & Sun) and Holidays -------------------------- Open to Traffic
Traffic delay periods (60 minutes) between 8:00 a.m. and 4:00 p.m. begin when the first traffic vehicle arrives at the closure site. This traffic delay period is the maximum delay traffic should experience within the entire construction area.
Other delay periods may be authorized upon receipt of a written approval from the Contracting Officer. Prior notification by the contractor is required for public notice of the contractor’s intent to delay traffic. The Contractor shall submit a written request outlining the traffic delays required at least 7 days prior to starting construction operation that necessitates the traffic delays. The contractor must open the bridge and road as rapidly as possible to allow passage of emergency vehicles.”
The following is added to this subsection:
“The Contractor shall be responsible for the safe passage of vehicle traffic over the bridge and through the construction site when Road No. 280 is open to public traffic during construction and outside work hours.
Develop a construction sign plan that reflects the Contractor’s plan of operation and submit to the Contracting Officer for approval 14 days prior to commencement of on-site project work. Install construction signs prior to and consistent with the construction work being performed. The traffic control plan must include provisions to safely guide public traffic through the section of Road 280 designated as a waste site all hours of the day.
96 SPS 104-3 (07/12/10)
With award of Schedule B, in addition to the typical MUTCD construction zone signing and road closure devices (type III barricades), the contractor shall install public information signs on Road No. 280 on both sides of the closure area to notify residence and public of bridge construction and road closures ahead as follows:
| Road/Bridge Closure |
| # Signs |
| Location |
| NF Grouse Creek Bridge |
| 1 |
| Road No. 280 at M.P. 0.0 – US Forest Service Boundary (T59N, R1E, Section 30) |
| NF Grouse Creek Bridge |
| 1 |
| Road No. 280 at M.P. 2.8 – (T59N, R1E, Section 20) |
Sample road closure sign follows:
104.02 Use of Roads by Contractor
The following is added to this subsection:
“Commensuate with use, the Contractor shall be responsible to any damage to roads under the jurisdiction of the Forest Service used by the Contractor as haul routes for delivery materials to the project site. Commenserate use road damage repairs will be the responsibility of the contactor.”
The following is added to this subsection:
“PAYMENT
Measurement
104.03 Use the method of measurement that is DESIGNATED IIN THE SCHEDULE OF ITEMS.
96 SPS 104-4 (07/12/10)
Measure traffic control for Schedule A- Detour Road Option on a lump sum basis. Include all materials, equipment, and work necessary to develop a traffic control plan, furnish, install, maintain, and remove construction signing.
No payment will be made for this item under Schedule B- Pedestrian By-Pass Option. Include all costs associated with road closures, furnishing, erecting, maintaining and removing traffic control construction signing in the unit price bid for Mobilization.
Payment
215.04 Basis. The accepted quantities will be paid for at the contract unit price for each PAY ITEM DESIGNATED IN THE SCHEDULE OF ITEMS.
Pay Item
Pay Unit 104(01) Traffic Control Lump Sum”
96 SPS 104-5 (07/12/10)
Section 105 – Control of Materials
105.06 Material Sources
(a) Designated Sources.
Add the following:
“Riprap Source – Commercial Source: There is no designated Government source for for Item 251(01) Placed Riprap, Class 5 under this contract.
Crushed Aggregate Source- Commercial Source: There is no designated Government source for crushed surfacing material under Item 304(11)A or Item 304(11)B under this contract.
Coarse Granular Backfill- Commercial Source: There are no designated Government sources for course granular backfill designated under Item 260(01) – Geocell Abutment Stabilization or 204(09) – Sediment Basin under this contract.
Streambed Simulation Material- Commercial Source: There is no designated Government source for Item 304(23) - Streambed Simulation Material under this contract.
Individual Boulders- Commercial Source: There is no designated Government source for Item 251(14) Large Boulders to be used for stream channel restoration. Suitable boulders encountered during excavation will be conserved and incorporated into the work.
Waste Area (Excess Material) – Government Provided: Suitable excess material will be used to raise the roadbed on Road 280 from Mile Post 0.9 to Mile Post 1.1. Dispose of excess material by hauling, spreading, shaping and compacting the material to an approximate thickness of 12” over the full width of the existing roadway, but not to exceed a 25’ subgrade width.
Waste Area (Unsuitable Material) – Government Provided: Unsuitable material that can not be incorporated into the new stream simulation work or utilized as excess waste material to raise the roadbed shall be disposed of at the designated waste site approximately 2.6 miles from the project site on Road No. 2656.
Logs with Root Wads – Government Provided: Logs for stream structures will be available at the Government pit located approximately 1/4 mile south of the Priest Lake Ranger Station at the end of Forest Road 789 in Section 10, T.60N., R. 5W.
96 SPS 105-1 (07/12/10)
Borrow Source: No Government source borrow material is anticipated under this Contract”
(b) Contractor-Furnished Sources.
Add the following:
“Prior to any pit development or use of materials from contractor-furnished sources, have the pit site approved by the Contracting Officer that it is free of noxious weed as listed on the “All States Noxious Weeds List.”
96 SPS 105-2 (07/12/10)
Section 106 – Measurement & Payment
106.03 Units of Measurement
Delete this subsection and add the following:
“Forest Service Specifications for Construction of Roads and Bridges (Revised August 1996) are based on Modern Metric units of measurement. The dimensions and units of measure SHOWN ON THE DRAWINGS and used to develop SPECIAL PROJECT SPECIFICATIONS for this contract, utilize U.S. Standard English units of measure. All measurements referenced in the August 1996 Forest Service Standard Specifications (EM-7720-100) shall be converted to U.S. Standard English units of measure. Appendix A – Engineering Conversion Factors and Appendix B – SI (Modern Metric) Conversion Factors, are included on pages 611 – 614 of the Standard Specification Appendices to assist with any required conversions.
Work required by the contract will be paid based on the PAY UNIT (U.S. Standard English measure) as DESIGNATED IN THE SCHEDULE OF ITEMS.
Under each Specification Section with PAY ITEMS of work DESIGNATED IN THE SCHDULE OF ITEMS for measurement and payment under this contract, the last subsection “Payment - Basis”, shall have the following format:
Pay Item - Numbering system and work description to remain the same.
Pay Unit - Pay unit(s) DESIGNATED IN THE SCHEDULE OF ITEMS have been changed from metric to the corresponding unit of U.S.
Standard English measure.
Payment will be by units defined and determined according to U.S. Standard English measure and by the following:
(a) Cubic Yard in Place. Measure solid volumes by the average end area method as follows:
(1) Measure cross sections of the original ground and use with design or staked templates, or take other comparable measurements to determine the end area. Do not measure work outside of the established lines or slopes.
96 SPS 106-1 (07/12/10)
(2) If any portion of the work is acceptable, but is not completed to the established lines and slopes, remeasure cross sections or comparable measurements of that portion of the work. Deduct any quantity outside the designated or staked limits. Use these measurements to calculate new end areas.
(1) Compute the quantity using the average end areas multiplied by the horizontal distance along a centerline or reference line between the end areas. Deduct any quantity outside the designed or staked limits.
Where it is impractical to measure material by the average end area method, other approved methods involving three-dimensional measurements may be used.
Measure liquid volumes in accordance with SPS Subsection 106.03(h).
(b) Cubic Yard in the Hauling Vehicle. Measure the cubic yard volume in the hauling vehicle using three-dimensional measurements at the point of delivery. Use vehicles bearing a legible identification mark with the body shaped so the actual contents may be readily and accurately determined. Before use, mutually agree in writing upon the volume of material to be hauled by each vehicle. Vehicles carrying less than the agreed volume may be rejected or accepted at the reduced volume.
Level selected loads. If leveling reveals that the vehicle was hauling less than the approved volume, reduce the quantity of all material received since the last leveled load by the same ratio as the ratio of the current leveled load volume to the agreed volume. Payment will not be made for material in excess of the agreed volume.
Material measured in the hauling vehicle may be weighed and converted to cubic yards for payment purpose if the conversion factors are mutually agreed to in writing.
Compute quantity by using measurements of material in the hauling vehicles at the point of delivery. Load vehicles to at least their water-level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
(c) Cubic Yard Mile. A combination of linear and volumetric measurement meaning the movement of a cubic yard of material one(1) mile.
(d) Hour. Measurement will be for the actual number of hours ordered and performed by the Contractor.
96 SPS 106-2 (07/12/10)
(e) Each. One complete unit, which may consist of one or more parts.
(f) Lump Sum. Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.
(g) MBF. One thousand feet board measure based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminate timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
(h) Gallon. The quantity may be measured by any of the following methods:
a. Measured volume container.
b. Metered volume. Use an approved metering system.
c. Commercially packaged volumes.
(i) Station. One hundred linear feet measured horizontally.
(j) Station Yard. A combination of linear and volumetric measurement meaning the movement of a cubic yard of material one station.
(k) Square Yard. Measure on a plane parallel to the surface being measure or horizontal.
(l) Thousand Gallons Mile. A combination of linear and volumetric measurement meaning the movement of 1,000 gallons of material one(1) mile.
(h) Ton. Short ton consisting of 2,000 pounds. Use net certified scale weights based on certified volumes.
(m) Ton Mile. A combination of linear and weight measurement meaning the movement of one(1) ton of material one(1) mile.”
96 SPS 106-3 (07/12/10)
Section 160 - Quality Control & Quantity Measurement Construction
160.02 Quality Control and Quantity Measurement System
Under (a) Quality Control Plan, add the following:
"(3) Description of the testing facilities and information on when and where each of the required materials tests will be performed.
(4) Random sampling and/or measurement plan prepared in accordance with requirements in Table 160."
(5) A log of all samples that are taken by the Contractor shall be maintained for the duration of the contract, and provided to the Contracting Officer upon request. Test results on all samples shall be given directly to the Contracting Officer within 8 hours of test completion."
160.03 Sampling, Testing, Inspection, and Measurement of Quantities Add the following:
"Minimum sampling and testing FREQUENCY is defined in Table 160.
Sampling and testing by the contractor shall meet the applicable AASHTO and ASTM Standards.”
96 SPS 160-1 (07/12/10)
TABLE 160
SAMPLING, TESTING AND MEASUREMENT REQUIREMENTS
A soil type is defined such that all soil in the represented volume shall have the same group symbol in the Unified Soil Classification system (ASTM D 2487) and the percent passing the No. 4 sieve shall not vary more than 10 percent between samples.
Wherever a AASHTO T99 or T180 moisture density curve is required, gradation data will be provided as shown below. The moisture density sample shall maintain the same percentage of coarse material (passing 50 mm and retained on a number 4 sieve) as in the original field sample. Field density testing of soil will normally require the use of AASHTO T224, Coarse Particle Correction.
Field Sample
Moisture Density Test Material
Percent plus 19 mm
Percent plus No. 4
Percent 19 mm to No. 4 sieve
Percent minus No. 4 sieve
Where random sample or random measurement is specified, it shall be a stratified statistically random sample. Random numbers are to be determined by ASTM D3665 Section 5.1 thru 5.7, or a computer generated random number program approved by the Contracting Officer. The sampling must be stratified to eliminate the possibility of sample points being "clustered". Stratification is calculated by dividing the total quantity for the applicable bid item by the sample FREQUENCY. This process divides the total project quantity of one lot into sublots. The random number is used to obtain a random sampling point within each sublot. The contractor may terminate a lot, and start a new lot when approved by the Contracting Officer. Once a lot is terminated it may not be combined with any other lot. If material within a sublot fails to meet specification requirement, the Contracting Officer may allow the contractor to rework the sublot materials and resample at a different randomly selected location.
Key to symbols used in table:
CT: Sampling and testing by contractor's personnel identified by name on the approved contractor's Q/C plan. Interim approval of personnel submitted will be based on specified training or experience requirements. Final approval will be based on observation of work performance on the project.
PE: Sampling and testing under the direction of and certification by a registered engineer retained by the contractor and specifically identified on the approved contractor's Q/C plan.
FS: Sampling, testing, measuring and/or data to be furnished by the Forest Service.
96 SPS 160-2 (07/12/10)
Note: The minimum FREQUENCY shown in this table is for contractor Quality Control sampling and testing. The contractor can run additional samples over the minimum number specified in the table. These additional samples can be taken in any manner, at any time desired by the contractor. Quality assurance sampling and testing by the Forest Service may be done at any time or location.
SUBSECTION REFERENCE
Required Sampling, Testing and
Measurements Responsibility For
Sampling/Testing Minimum Frequency
203.16 Embankment Placement
Field Density
| CT/CT |
| One certification per bridge approach. Certify that subgrade is at a uniform moisture content suitable for compaction and compacted in accordance with Method 3 |
203.17 Construction Tolerances
Measurement of Construction Tolerances
CT/CT
For non-highway projects: 10 tests per campground loop, access road, bridge approach or administrative site (construction tolerance class A)
206.10 & 206.11 Backfill & Embankment for Structures
Field Density
| CT/CT |
| One certification per bridge abutment and wingwall. Certify that backfill is at a uniform moisture content suitable for compaction and compacted in accordance with SPS subsection 206.10, SPS subsection 206.11 and SPS subsection 203.16(b), Method 3 |
96 SPS 160-3 (07/12/10)
SUBSECTION REFERENCE
Required Sampling, Testing and
Measurements Responsibility For
Sampling/Testing Minimum Frequency
251.02 Requirements (Riprap)
Gradation
| CT/CT |
| As required in specification (subsection 705.02) |
304.03 Gradation
Gradation and percent fracture (Section 703.05)
| CT/CT |
| For material in stockpile - Three test per source or submit test results taken at time of crushing operations (AASHTO T27 and T11). At the request of the Contracting Officer, provide a QA sample split for Government testing. For material being specifically crushed for this project, one statistically random test per 1,000 tons of crushed product. |
304.08 Preparation of Roadbed
Per Section 306.02 and SPS Section 306.02
CT/CT
Certify that roadbed has been completed in accordance with Section 304 and 306 prior to request for approval in writing from Contracting Officer.
304.10 Compaction
Field Density
CT/CT
Certify that pit run aggregate and crushed aggregate is at a uniform moisture content suitable for compaction and materials are compacted in accordance with Compaction Method B.
96 SPS 160-4 (07/12/10)
Required Sampling, Testing and
Measurements Responsibility For
Sampling/Testing Minimum Frequency
304.12 Thickness & Width Requirements
Measurements of Aggregate Thickness and Width
CT/CT
Random measurements: minimum 10 per mile or 3 per bridge approach.
304.13 Measurement Method
Moisture content determination Per SPS 106.02
CT/CT
Random measurements: minimum of 1 test per 1,000 tons or a least 1 per shift when aggregate is being weighed (AASHTO T255). This requirement may be waived by the Contracting Officer for a crusher operation when initial tests show moisture content is consistently 5% percent or less.
553.03 Method Approval
Submittals and Inspection
| --/PE |
| As required in specification |
(Submit shop drawings 21 days prior to starting prestressing and notify CO a minimum 10 days prior to fabrication)
553.05 Concrete
Concrete cylinder fabrication and testing
PE/PE
As required in specification
553A.02 Requirements Concrete slump and air content
Concrete cylinder fabrication and testing
PE/PE
PE/PE
As required in specification
As required in specification
96 SPS 160-5 (07/12/10)
Section 170 – Construction Staking, L-Line Description
170.01 Work.
Replace the last sentence of the first paragraph with the following:
“In addition, set grade-finishing stakes, stake major structures and the associated riprap locations.”
Survey Requirements
170.17 Staking Major Structures.
Add the following to paragraph (c):
“Consult with the CO prior to staking final riprap locations.”
Measurement
170.21 Method.
Replace the first sentence of the last paragraph with the following:
“Include all work necessary to establish lines and grades for the construction of the structures, including staking the locations of all riprap in the pay item for Construction Staking.”
Payment
Add the following pay items:
“Pay Item
170(07) Construction Staking; Bridge Structure Precision A, Centerline …….
L.S.
Precision A, Slope Staking Precision B”
96 SPS 170-1 (07/12/10)
Section 201 – Clearing & Grubbing Construction
201.03 Utilization of Timber
Delete this section and add the following:
“Minor clearing required for this project does not include any merchantable timber.”
201.05 Slash Treatment.
Delete the first sentence of this section and add the following:
“Treat construction slash larger than 3 inches in diameter and 3 feet in length by (8) Decking Unmerchantable Material, (10) Removal and (11) Piling.”
Change the second paragraph to read:
"Small pieces of wood less than 3 inches in diameter and 3 feet in length may be scattered outside the roadway or clearing limits."
(b) Specific Methods.
(8) Decking Unmerchantable Material.
Delete this sentence and replace with the following:
“Remove or haul unmerchantable material to the Unsuitable Material Waste Site designated in Section 105 of these Special Project Specifications or as SHOWN ON THE DRAWINGS. Deck unmerchantable material at a location approved by the CO.”
(10) Removal.
Delete this sentence and replace with the following:
“Remove or haul construction slash to the Unsuitable Material Waste Site designated in Section 105 of these Special Project Specifications or as SHOWN ON THE DRAWINGS. Pile construction slash, stumps or logs at a location approved by the CO.”
96 SPS 201-1 (07/12/10)
Measurement
201.06 Method.
Add the following:
“No separate measurement will be made for transporting construction slash to the designated site. All labor, equipment and materials associated with this item will be considered incidental to other pay items shown on the SCHEDULE OF ITEMS.”
Payment
201.07 Basis.
“No separate measurement will be made for this item. All costs associated with this item will be considered incidental to other pay items shown on the SCHEDULE OF ITEMS.”
96 SPS 201-2 (07/12/10)
Section 202 – Removal of Structures and Obstructions Description
202.01 Work
Add the following:
“This work consists of the removal and disposal of the existing CSP culvert and fish ladder at the N.F. Grouse Creek crossing of Road No. 280 as SHOWN ON THE DRAWINGS.”
Construction
202.02 Salvaging Material
Add the following:
“There are no salvage requirements under this project associated with the removal of the CSP culvert or fish ladder. The removed structures becomes the property of the Contractor for removal from National Forest System Lands.”
202.04 Disposing of Material or Structures Not Designated for Salvage.
Delete the first sentence of this subsection and replace it with the following:
“Dispose of all materials designated for removal off of National Forest System Lands.”
(a) Removal From Project.
Replace this paragraph with the following:
“All materials designated for removal under this contract are considered unsalvageable and become the property of the Contractor. Dispose of all unsalvageable materials off of National Forest System Lands in an environmentally safe manner in accordance with all Local, State and Federal requirements.”
(b) Burning. Delete this subsection:
(c) Burying. Delete this subsection:
96 SPS 202-1 (07/12/10)
Section 203 – Excavation, Embankment, & Haul Construction
203.06 Utilization of Excavated Materials.
(a) Excess Excavation.
Delete the first sentence and replace with the following:
“Transport and deposit excess excavation from bridge construction or stream simulation work at the designated EXCESS MATERIAL waste site as specified in Section 105 of these Special Project Specifications or as SHOWN ON THE DRAWINGS. Spread, shape and compact suitable excess material to raise road grade as SHOWN ON THE DRAWINGS and as directed by the Contracting Officer.”
(d) Excavation of Unsuitable Material & Backfill.
Replace the first sentence of this section with the following:
“Transport and deposit unsuitable material from bridge construction or stream simulation work at the designated UNSUITABLE MATERIAL waste site as specified in Section 105 of these Special Project Specifications or as SHOWN ON THE DRAWINGS. Spread the material and shape to drain as directed by the Contracting Officer. Seed and mulch after final shaping.”
203.08 Sloping, Shaping, & Finishing.
Under subsection (d) Finishing, delete the last sentence and add the following:
“(d) Finishing. Finish bridge roadbed to tolerance Class A as shown in Table 203-1. Transition the approach road into the new bridge superstructure to provide a safe, uniform transition for a minimum of 100 L.F., and provide the proper road surface elevation to achieve the designed road surface drainage.”
203.16 Embankment Placement
(b) Specific Methods
(3) Method 3 – Layer Placement (Roller compaction)
96 SPS 203-1 (07/12/10)
Delete the last two sentences of this paragraph and add the following:
“Under Subsection 206.11 (embankment for major structures), establish the compactive effort required by the control strip method. Construct a control strip at the beginning of work on each type of material to be compacted. Ensure that the material used in the construction of the control strip meets the specification requirements and proper moisture content for maximum compaction. Use compaction equipment in the construction of the control strip designed for this purpose until visual displacement ceases. Replace any compaction equipment that fails to provide adequate compaction. Correct or remove unacceptable control strips and replace them at the Contractor’s expense.
Begin compacting the control strip immediately after the course has been placed to the specified thickness. Ensure that compaction is continuous and uniform over the entire surface. Continue compaction of the control strip with a minimum of three passes or until no discernible increase in density can be obtained by additional compactive effort as determined by the CO. Once the compactive effort has been established by the control strip method, apply this compaction process until soil type or other conditions change.”
Measurement
203.19 Method.
Add the following:
“No separate measurement will be made for transporting, spreading, compacting or shaping excess, or unsuitable excavated materials, and for seeding and mulching the material after shaping. All labor, equipment and materials associated with these items will be considered incidental to other pay items shown on the SCHEDULE OF ITEMS.”
96 SPS 203-2 (07/12/10)
Section 204 – Soil Erosion & Water Pollution Control Description
204.01 Work
Add the following:
“This work also includes project BMP’s implemented by Contractor for sediment containment through the entire reach of the constructions site.”
Materials
204.02 Requirements.
Add the following:
“Provide straw for erosion and water pollution control from a certified noxious weed free source.”
Construction
204.03 Performance.
Delete the first sentence and replace it with the following:
“Prior to the start of construction, submit a written plan for review that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Include methods to minimize disturbance to the stream, prevent runoff from the construction site entering directly into the stream, prevent the release of fuel and oil into the water and soil and to contain and control any spills that may occur.
Stream diversions and de-watering plan to control construction generated stream turbidity must be addressed with details and sketches to demonstrate how Contractor plans to perform work and control stream turbidity. Do not begin work until the necessary controls for that particular phase of work have been implemented.
In-stream work will only be allowed between July 15th and September 1st of any construction year. Approved BMP’s for sediment containment must be utilized through the entire reach of the construction site.”
96 SPS 204-1 (07/12/10)
Add the following to this subsection:
“As part of the “Soil Erosion Control Plan”, Contractor to provide the following:
(a) Emergency Spill Kit. Keep sufficient quantities of absorbent materials on the project site to absorb accidental fuel, hydraulic oil, or other petroleum produce spills. Use absorbent materials that are biodegradable, non-water absorbing and designed specifically for the types of spills associated with the Contractor’s operations.
(b) Straw/Hay Bales. Contractor to stockpile five(5) straw/hay bales on the Jim Creek Bridge replacement project site for the discretionary use as directed by the Contracting Officer in addition to any bales or silt fence that the Contractor intends to incorporate into the project as a part of the permanent and temporary erosion control measures as required under this specification. These straw/hay bales are intended for unforeseen emergency use. As the straw bales are used from the stockpile, Contractor shall replace the used bales within 48 hours. Upon completion of the project, the straw/hay bales shall remain in place or removed as directed by the Contracting Officer. Removed bales and remaining stockpiled bales shall be uniformly spread over seed disturbed areas upon substantial completion of the project.
Upon completion of construction at the site, remove all temporary erosion control devices, dewatering materials and equipment from Government property.”
204.08 Water Crossings.
Add the following:
“Installation of a work bridge or detour bridge will not be allowed with award of Schedule B under this contract. Contractor will be required to stage equipment and materials on both sides of stream prior to the removal of the existing culvert to minimize the need for stream crossings with equipment. Any stream crossing with equipment after removal of the culvert structure must be requested by the Contractor and approved by the Contracting Officer.”
204.09 Diversions.
Add the following to this subsection:
“Stream diversions under this project may become a significant part of the contract work during construction of the bridge and completion of the stream simulation work to control construction generated stream turbidity.”
96 SPS 204-2 (07/12/10)
Measurement
204.14 Method.
Add the following:
“Do not measure stockpiled emergency use straw/hay bales or emergency spill kit as described under this section.”
Payment
204.15 Basis.
Add the following:
“Payment for straw bales, silt fence, dewatering, stream diversions or other BMP measures furnished and erected by the Contractor as a part of the Soil Erosion and Pollution Control Plan will be paid for under item 204(19) Soil Erosion and Pollution Control. No separate payment will be made for emergency spill kit or stockpiled emergency use straw/hay bales specified for discretionary use as directed by the Contracting Officer.”
96 SPS 204-3 (07/12/10)
Section 206 - Structural Excavation for Major Structures Construction
206.04 General.
Delete the second to last paragraph of this subsection and replace with the following:
"Suitable material may be used in the construction of the roadway embankment and for structural backfill. Field drain and dry excessively wet material that is otherwise suitable for embankment before placement. Dispose of unsuitable or excess material according to SPS Subsection 105.06, Subsection 203.06 or as SHOWN ON THE DRAWINGS.”
206.10 Backfill.
Replace the third paragraph with the following:
"Place backfill or embankment material on both abutments so that not more than 2 feet of elevation difference exists between the backfill or embankment of the two abutments. No embankment or backfill shall be place higher than 1 foot below the top of the abutment grade beam until after the grout and mortar for the prestressed deck slabs have been placed and cured. Ensure that the moisture content of backfill material is suitable for attaining the required compaction.”
206.11 Embankment.
Delete the second sentence of this paragraph and replace with the following:
“Compact backfill in accordance with Subsection 203.16(b), method 3, except approved hand operated mechanical tampers may be used for the required compaction. Due to the importance of good compaction behind bridge abutments, the contractor must demonstrate for Contracting Officer approval, capabilities of compaction equipment, proper moisture content of backfill material and compaction effort (passes) to obtain the specified compaction under Method 3 – Layer Placement (roller compaction).”
96 SPS 206-1 (07/12/10)
Measurement
206.12 Method
Replace the second paragraph with the following:
“Measure all structural excavation by Lump Sum. Includes all roadway, bridge, culvert, riprap and channel excavation, backfill, removal of unsuitable and excess material, haul and disposal of material for this project not specifically identified in related sections and included in the SCHEDULE OF ITEMS.”
96 SPS 206-2 (07/12/10)
Section 207 – Developing Water Supply & Watering Measurement
204.14 Method.
Delete this subsection and add the following:
“No separate measurement will be made for developing water supply and watering. All labor, equipment and materials associated with the item will be considered incidental to Section 304 pay items.”
Payment
204.15 Basis.
Delete this subsection and add the following:
“No separate measurement will be made for this item. All costs associated with this item will be considered incidental to other Section 304 pay items.”
96 SPS 207-1 (07/12/10)
Section 215. — Hauling Government-Furnished Logs Description
215.01 Work. Load, haul, unload, and stockpile Government-furnished logs with rootwads.
Construction
215.02 Performance. Load logs with rootwads from the Government source designated in Section 105 of these Special Project Specifications. Use equipment to load the logs that will not damage the root structure or the integrity of the log. Transport the logs in trucks that can safely accommodate the length of the logs and that will not damage the root structure during transport.
Unload and stockpile the logs at the bridge site.
Measurement
215.03 Use the method of measurement that is DESIGNATED IIN THE SCHEDULE OF ITEMS.
Measure the logs on a per each basis. Include all materials, equipment, and work necessary to load, haul and unload the logs without damaging the root structure.
Payment
215.04 Basis. The accepted quantities will be paid for at the contract unit price for each PAY ITEM DESIGNATED IN THE SCHEDULE OF ITEMS.
215(01) Load & haul Government-furnished logs ………………………… Each”
96 SPS 215-1 (07/12/10)
Section 251 - Riprap Description
251.01 Work
Add the following:
“Work under this section includes minor structural excavation, haul, disposal of unsuitable material, temporary construction access, reshaping existing riprap and embankment required for placement of riprap.
Furnish individual boulders for stream structures and channel restoration.”
Construction
251.04 Placed Riprap.
Add the following to Subsection (a) Method A, Machined Placed:
“The minimum channel width under the new bridge structure as SHOWN ON THE DRAWINGS is a critical distance for construction control. The Contractor shall take the necessary measures to insure that the riprap is constructed to the designed dimensions and slope ratios to provide the designed stream width as SHOWN ON THE DRAWINGS to provide the desired Q2 channel widths.”
Add the following to Subsection (c) Stream Simulation Work:
“Furnish rocks meeting the dimensional requirements as SHOWN ON TH DRAWINGS and as directed by the Contracting Officer. Excavate and construct the rock vanes and place individual boulders as SHOWN ON THE DRAWINGS and as directed by the Contracting Officer.”
96 SPS 251-1 (07/12/10)
Measurement
251.12 Method
Add the following to this subsection:
“Construction of rock vanes and placement of individual boulders will be measured and paid under Section 637 – Equipment Rental. Boulders will be commercially supplied by the Contractor under Item 251(14).”
Payment
251.13 Basis.
Add the following:
"The cost of minor structural excavation, haul, disposal of excess or unsuitable material, temporary construction access, reshaping existing riprap, and embankment required for placement of riprap is incidental to this pay item and no separate payment will be made.
The cost of minor structural excavation, haul, disposal of excess or unsuitable material, temporary construction access and embankment required for stream simulation work will be measured for payment under Section 637 – Equipment Rental.”
251(14) Furnish individual boulders (size) Each”
96 SPS 251-2 (07/12/10)
Section 260 - Cellular Confinement System Description
260.01 Work. Construct geocell abutment stabilization at each abutment using Presto Geoweb Cellular Confinement System, Webtec TerraCell, or approved equal in accordance with the plans and manufacturers recommendations.
Materials
260.02 Requirements. Ensure that material conforms to specifications in the following subsections:
Coarse Granular Backfill
703.03
Geocell
Geotextile, Type IV (A,B,C.D,E, or F)
714.01
Construction
260.03 General. Perform the work specified in Section 206. Use ditches, grading or similar methods to prevent surface runoff that may occur during inclement weather from ponding in the foundation excavation.
260.04 Geotextile Installation. Place the geotextile according to Section 221 or AS SHOWN ON THE DRAWINGS. Ensure that the surface upon which the geotextile is to be placed is uniform and is reasonably smooth and free of obstructions, depressions, and debris that could damage the geotextile . Have the surface approved by the CO prior to placing geotextile.
Lay the geotextile without tension, stress, wrinkles or creases. Sew or overlap adjacent strips a minimum of 12” at joints. Insert securing pins through both strips of overlapped geotextile at minimum intervals of 3 feet, but no closer than 2 inches to each edge, to prevent the geotextile from being displaced.
Have the installed geotextile approved by the CO prior to setting the geocells.
96 SPS 260-1 (07/12/10)
260.05 Geocell Installation. Place the geocell sections directly on the prepared subgrade. Expand the geocell sections into position at the grades and lines AS SHOWN ON THE DRAWINGS. Hold the expanded geocell sections with suitable “stretcher frames”, steel stakes driven inside selected outer cell walls, or other similar methods as allowed by the geocell manufacturer prior to filling. Ensure that the individual cells have been expanded to the minimum dimensions required by the manufacturer. If necessary field cut sections as per the manufacturer’s recommendations to the lines SHOWN ON THE PLANS.
Connect geocell panels in accordance with the manufacturer’s recommendations.
260.06 Infill Placement. Furnish the CO with the manufacturer’s specific recommendations for backfilling prior to placement of the geocells.
Place coarse granular backfill meeting subsection 703.03 into the expanded cells with equipment appropriate for the site conditions such as a backhoe or a front-end loader. Do not drop infill material more than 3 feet to avoid damage or displacement of the cell walls.
Overfill the geocell cells and level to a minimum of 2 inches above the top of the cell walls. A front-end loader may be used to place the infill provided that it only traffics above geocell sections that have been filled and covered with the minimum 2 inches of additional material. Compact the infill material with a vibratory plate compacter. Operate compaction equipment over the full width of the geocell until visible deformation of the infill ceases. Make at least three complete passes. Grade the surface to be ½ inch above the top of the cells. Ensure that the cell walls are not exposed after fine grading is completed.
Use the geocell manufacturer’s specific recommendations for backfilling if they are more stringent than stated above.
Measurement
260.07 Method. Use the method of measurement that is DESIGNATED IN THE SCHEDULE OF ITEMS.
Payment will be based on the contract unit price of geocell material placed and accepted. This will be exclusive of wastage and material placed outside the neat lines SHOWN ON THE DRAWINGS.
96 SPS 260-2 (07/12/10)
Payment
260.08 Basis. The accepted quantities will be paid for at the contract unit price for the PAY ITEM DESIGNATED IN THE SCHEDULE OF ITEMS.
The cost for furnishing and placing the Coarse Granular Backfill required for geocell infill is incidental to this pay item and no separate payment will be made.
The cost for furnishing and placing geotextile for the geocell installation is incidental to this pay item and no separate payment will be made.
Payment will be made under:
260(01) Geocell Abutment stabilization, __inch depth ……………….………
This is the start of the file's text. The full file is on GovTribe.