SOW.pdf
PDF 1 MB Posted
- Attached to
- 2016 East Branch Weiser River AOP Federal contract opportunity
- Solicitation number
- AG-0261-S-16-0044
About this file
Attach 1 SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ID86.pdf | ||
| Construction_Cost_Estimate_Breakdown_00.xls | XLS spreadsheet | |
| AG-0261-S-16-0044.pdf | ||
| maps_ _Drawings.pdf | ||
| Construction_Cost_Estimate_Breakdown_00.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
27-May-16
DESCRIPTION/ SPECIFICATIONS/ STATEMENT OF WORK EAST BRANCH
WEISER RIVER AOP 2016
C.1 SCOPE OF CONTRACT
Work consists of removal of existing culverts and replacement with AOP structures at two locations, NFSR#557 at MP 0.01 and NFSR#074 at MP 6.5. Replacement at NFSR#557 will be a 16’W x 5’3”R x 50’L open bottom structural plate arch. Replacement at NFSR#074 will be 18’W x 8’H x 24’L precast concrete box culvert with a 15 degree skew.
Work includes surveying and staking, dewatering, removal of existing metal culverts, excavation and embankment, placing riprap, installing structural plate arch with footings, developing streambed, placing crushed aggregate, and reinstalling salvaged gate. Project will also include the design, fabrication, transport and installation of precast box culvert.
GENERAL ITEMS COMMON TO ALL AOP’s:
1) Submit an erosion control plan that will show the stream diversion plans.
2) Remove and dispose of existing pipes.
3) Set and maintain survey control staking by referencing Government supplied control points.
4) Place stream simulation rock salvaged from excavation to construct a natural stream channel.
5) Backfill new structures.
6) Salvage rock for riprap on the fill slopes.
7) Haul any excess material to the disposal sites shown on the plans.
8) Haul and place government supplied crushed aggregate.
9) Scatter slash, mulch and spread government supplied seed on disturbed areas.
10) Supply and place Type III traffic barriers and ROAD CLOSED AHEAD signs.
C.2 PROJECT LOCATION
The project sites are located in the New Meadows Ranger District near the Price Valley Guard Station. Head west from New Meadows on Highway 95 to Price Valley Road/NFSR#074. Turn north onto NFSR#074, through Price Valley, for approximately 6.5 miles to reach site 074-MP 6.5. To reach the second site head north on NFSR#101 from the junction with NFSR#074 for approximately two miles to the junction of NFSR#557 and NFSR#101. The site 557-MP 0.01 is located near the intersection of the NFSR#101 and NFSR#557.
See map in project plans.
C.3 DESCRIPTION OF WORK
Installation of the open bottom structures shall be installed in the dry. Creating dry conditions will require capturing the flow of the East Branch Weiser River upstream of the project and diverting the flow past the work area in a manner which protects the natural flow from any additional turbidity. Seepage flow will be captured in a sump and pumped away from any flowing water to allow for infiltration so no muddy water reaches a flowing channel. The streambed simulation material will be placed as directed by the COR to approximate the drawings.
After placement the simulation material will be “washed in” utilizing the onsite dewatering pumps. The inlet and outlet of the structures will be protected by installing rip rap. Borrow material and surface aggregate should be obtained from Yantis Ditch Pit. Any material not available on site or at Yantis Ditch Pit shall be obtained for a commercial source. The culvert structure must meet HL-93 loading.
The material consists of unclassified Borrow and approximately 90 cy crushed road surfacing. Contractor must verify quantity.
AG-0261-S-16-0044 Attach 1 Page 1 of 52
Mobilization is considered the initial moving of equipment and incidentals to the project area on the Ranger District prior to the beginning of on-site work activities and includes subsequent demobilization off National Forest lands.
For assigned activities, the Contractor shall present a schedule of completion including anticipated hours per day, days per week and dates.
C.4 PROJECT CONTROL
There are time restrictions for road closure durations. The maximum consecutive days of closure are limited to 10 days and not more than 1 weekend. There are no in stream work window requirements.
There are needs for range permitees to cross the subject pipes to access their range allotments this access will be coordinated by the COR to minimize the impact to both the contractor and permitee.
Contractor is responsible for protecting workers from injury. Refer to FAR 52.236-13, Accident Prevention, for full text.
The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Government is not responsible for loss of or damage to equipment, materials, or supplies stored on-site during performance of this contract.
C.5 TERMINOLOGY
The term “Engineer”, when used in the contract documents, shall refer to the Contracting Officer’s Representative (COR)
The term “Owner”, when used in the contract documents, shall refer to the Federal Government (U.S. Forest Service)
C.6EXISTING CONDITIONS
Contractor shall verify all existing dimensions and conditions before proceeding with the work. All dimensions must be verified and/or determined in the field. Protect all improvements including existing culverts and roadway from damage during construction.
C.7 TRAFFIC CONTROL & MAINTENANCE
Refer to Forest Service Supplemental Specifications (FSSS) Section 156 Public Traffic for requirements regarding traffic control.
C.8 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS
U.S. Department of Transportation, “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects: FP-03 U.S. Customary Units,” hereafter refered to as FP-03, are included by reference. The requirements contained in Section 101 through 158 are hereby made a part of this solicitation and any resultant contract. Special Project Specifications (SPS) that amend FP-03 can be found in this contract.
AG-0261-S-16-0044 Attach 1 Page 2 of 52
Standard Specifications (FP-03) and Forest Service Supplemental Specifications (FSSS) contained in the following list are applicable to this contract. All specifications not included in the specification listing but referenced by listed specifications, are applicable.
FP-03 101 Terms, Format, and Definitions FSSS 101 Terms, Format, and Definitions FSSS 102 Bid, Award, and Execution of Contract FP-03 103 Scope of Work FSSS 103 Scope of Work FP-03 104 Control of Work FSSS 104 Control of Work FP-03 105 Control of Material FSSS 105 Control of Material FP-03 106 Acceptance of Work FSSS 106 Acceptance of Work FP-03 107 Legal Relations and Responsibility to the Public FSSS 107 Legal Relations and Responsibility to the Public FSSS 108 Prosecution and Progress FP-03 109 Measurement and Payment FSSS 109 Measurement and Payment FP-03 151 Mobilization FSSS 151 Mobilization FP-03 152 Construction Survey and Staking FSSS 152 Construction Survey and Staking FP-03 153 Contractor Quality Control FSSS 153 Contractor Quality Control FSSS 155 Schedules for Construction Contracts FSSS 156 Public Traffic FP-03 157 Soil Erosion Control FSSS 157 Soil Erosion Control FP-03 201 Clearing and Grubbing FSSS 201 Clearing and Grubbing FP-03 203 Removal of Structures and Obstructions FSSS 203 Removal of Structures and Obstructions FP-03 209 Structure Excavation and Backfill FSSS 209 Structure Excavation and Backfill FP-03 251 Riprap FSSS 251 Riprap FSSS 308 Minor Crushed Aggregate FP-03 552 Concrete FSSS 552 Structural Concrete for Precast Footings FSSS 553 Precast Box Culvert FP-03 602 Culverts and Drains FP-03 603 Structural plate Structures FSSS 603 Structural Plate Structures FP-03 619 Fences, gates and cattle guards FP-03 625 Turf Establishment FSSS 625 Turf Establishment FSSS 648 Stream Simulation FP-03 705 Rock FSSS 705 Rock
AG-0261-S-16-0044 Attach 1 Page 3 of 52
NOTE:
Bidders are cautioned to carefully review these Standard and Supplemental Project Specifications prior to submission of bids. All specifications in the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units are binding on the parties signing the contract, including any that may be omitted above.
The attachments to the Statement of Work/Specifications listed in Sections F, G and J are hereby made part of this solicitation and any resultant contract.
C.9 LANDSCAPE PRESERVATION
All heavy equipment shall be cleaned and thoroughly inspected prior to mobilization to the work site. Once on site all equipment shall be inspected daily and all visible oil, grease, and hydraulic fluid will be removed.
Needed repairs will be implemented immediately before resuming work.
All machinery shall be refueled outside of the riparian reserve area. If refueling does occur within the riparian reserve area, spill control measures shall be installed around the machinery prior to refueling operations.
Unless otherwise agreed, to prevent the introduction of seeds of noxious weeds onto National Forest land, Contractor shall ensure all equipment moved onto National Forest land is free of soil, seeds, vegatative matter or other debris that could contain or hold seeds. Contractor shall employ whatever cleaning methods necessary to insure compliance with this provision, and shall notify the Forest Service prior to moving each piece of equipment onto National Forest land. Upon request of Forest Service, arrangements will be made for Forest Service to inspect each piece of equipment prior to being moved onto National Forest land.
C.10 GOVERNMENT-FURNISHED PROPERTY (FAR 52.245-4) (APR 1984)
Govt furnished property is limited to the aggregate available at Yanits Ditch Pit. The material consists of unclassified Borrow and approximately 90 cy crushed road surfacing.
The govt will also be providing seed mix.
C.11 TECHNICAL REQUIREMENTS
Specific construction drawings and Supplemental Project Specifications are included in Section J. Per FP-03, Section 109.05(b); all items shown or noted on plans, which are not specifically bid items, are considered indirect payment items. The cost of furnishing and installing all indirect payment items will not be paid for separately, but shall be included in the unit price bid for other items unless noted otherwise.
C.12 ORDER OF PRECEDENCE - CONSTRUCTION
Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:
1) The Schedule of Items
2) Representations and other instructions
3) Contract clauses
4) Other documents, exhibits, and attachments
AG-0261-S-16-0044 Attach 1 Page 4 of 52
5) Forest Service Supplemental Specifications(FSSS)
6) Standard Specifications(FP-03)
7) Plans, figured dimensions over scaled dimensions
8) Plans, large scale contract plans over small scale contract plans
9) Schedules on contract plans over any conflicting notations on contract plans
10) Shop drawings
AG-0261-S-16-0044 Attach 1 Page 5 of 52
FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS
For
East Branch Weiser AOP 2016
074-MP 6.5
557-MP 0.01
U.S.D.A. FOREST SERVICE, REGION 4
PAYETTE NATIONAL FOREST, NEW MEADOWS RANGER DISTRICT
ADAMS COUNTY, IDAHO
AG-0261-S-16-0044 Attach 1 Page 6 of 52
Contents Preface Section 101. - Terms, Format, and Definitions Section 102. - Bid, Award, and Execution of Contract Section 103. - Scope of Work Section 104. - Control of Work Section 105. - Control of Material Section 106. - Acceptance of Work Section 107. - Legal Relations and Responsibility to the Public Section 108. - Prosecution and Progress Section 109. - Measurement and Payment Section 151. - Mobilization Section 152. - Construction Survey and Staking Section 153. - Contractor Quality Control Section 155. - Schedules for Construction Contracts Section 156. - Public Traffic Section 157. - Soil Erosion Control Section 201. - Clearing and Grubbing Section 203. - Removal of Structures and Obstructions Section 209. - Structure Excavation and Backfill Section 251. - Riprap Section 308. - Minor Crushed Aggregate Section 552. - Structural Concrete – Precast Footings Section 553. - Precast Concrete Box for 074- MP 6.5 Section 603. – Structural Plate Structures Section 625. – Turf Establishment Section 648. - Streambed Simulation Section 705. - Rock
AG-0261-S-16-0044 Attach 1 Page 7 of 52
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
AG-0261-S-16-0044 Attach 1 Page 8 of 52
Section 101. - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
AG-0261-S-16-0044 Attach 1 Page 9 of 52 http://www.nist.gov/
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
AG-0261-S-16-0044 Attach 1 Page 10 of 52
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
AG-0261-S-16-0044 Attach 1 Page 11 of 52
Section 102. - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
Delete Section 102 in its entirety.
AG-0261-S-16-0044 Attach 1 Page 12 of 52
Section 103. - Scope of Work
103_nat_us_2_16_2005
Delete all but subsection 103.01 Intent of Contract.
AG-0261-S-16-0044 Attach 1 Page 13 of 52
Section 104. - Control of Work
104.00_nat_us_06_16_2006 Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005 Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
The contractor shall confine his operation of equipment and trucks to existing road surfaces and the cleared areas that are shown on the site plans for each culvert installation.
AG-0261-S-16-0044 Attach 1 Page 14 of 52
Section 105. - Control of Material
105.02_R04F12_3_24_2012
105.02 Material Sources
Add the following before Subsection 105.02(a):
Sources have been designated for the East Branch Weiser AOPs 2016 as follows:
Crushed Aggregate Government furnished aggregate, obtain from the existing stockpile that is in the borrow pit near Yantis Ditch, which is near the junction with NFSR#083 and NFSR#074 in Section 10.
T.20 N, R1W.
Riprap and stream simulation– On-Site. Contractor will utilize material from the excavations. Material may also be obtained from the Yantis Ditch borrow pit. Riprap may also be obtained from a commercial source.
Material Disposal Site – Government furnished. A waste site for excess and unsuitable material :
Excess material may also be hauled to the Yantis Ditch borrow pit, and set it on edge of the cut slope of the borrow pit.
105.02_R04f12_2_27_2013
(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material from the project site unless otherwise designated. Place all unsuitable and excess material at the designated waste-disposal sites.
When required, re-establish vegetation in disturbed areas according to section 625.
(b) Contractor-located sources.
Prior to any pit development or use of materials, provide a State certification or have the pit site approved by the CO as being free of noxious weeds as listed on the All States Noxious Weeds List.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
AG-0261-S-16-0044 Attach 1 Page 15 of 52
Section 106. - Acceptance of Work
106.01_nat_us_07_31_2007
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more stringent.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request.
Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
AG-0261-S-16-0044 Attach 1 Page 16 of 52
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Partial and Final Acceptance
Delete subsection 106.07.
AG-0261-S-16-0044 Attach 1 Page 17 of 52
Section 107. - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph:
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_R04F12_02-15-2011
107.10 Environmental Protection.
Add the following:
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract.
Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill.
Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information.
Describe how the contractor will comply with the following three methods to minimize fuel/oil leakage from construction equipment into the stream channel. Include the following:
i. Clean all equipment used for in-stream work so that it is free of external oil, grease, dirt and mud, and repair leaks, prior to arriving at the project site. All equipment will be inspected by the Contracting Officer’s Representative before unloading at site. Correct any leaks or accumulations of grease before entering streams or areas that drain directly to streams or wetlands.
ii. Fuel and service equipment used for in-stream or riparian work (including chainsaws and other hand power tools) in an established staging area (site-specifically designated by CO). When not in use, store vehicles in the designated staging area. The staging area should be in an area that will not deliver fuel, oil, etc., to streams.
iii. Oil-absorbing floating booms, and other equipment such as pads and absorbent “peanuts” appropriate for the size of the stream, shall be available on site during all phases of construction. For very small streams with few pools or slack water, booms may not be effective. More pads and straw bales to anchor booms may be necessary. Place booms in a location that facilitates an immediate response to potential petroleum leakage.
Immediately notify the CO of all hazardous material spills. Provide a written narrative report no later than 24 hours after the initial report, and include the following:
AG-0261-S-16-0044 Attach 1 Page 18 of 52
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA- or State-reportable, and if so whether it was reported, and to whom.
Follow Federal and Idaho State regulations regarding spills. Report any spills resulting in a detectable sheen on water to the EPA National Response Center (1-800-424-8802). Report any spills over 25 gallons to the IDEQ (1-800-632-800), and initiate cleanup within 24 hours of the spill.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, State and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site, including final disposition and disposal location of spill residue.
When available, provide copies of all spill-related clean-up and closure documentation and correspondence from regulatory agencies.
AG-0261-S-16-0044 Attach 1 Page 19 of 52
Section 108. - Prosecution and Progress
108.00_nat_us_02_16_2005
Delete Section 108 in its entirety.
AG-0261-S-16-0044 Attach 1 Page 20 of 52
Section 109. - Measurement and Payment
109.02 Measurement Terms and Definitions.
109.02_nat_us_06_16_2006
(b) Contract quantity.
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
109.00_nat_us_02_17_2005
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
AG-0261-S-16-0044 Attach 1 Page 21 of 52
Section 151. - Mobilization
151.01_0114_R04F12_3_6_2012
Description
151.01 Add the following:
This work includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands.
Wash the sides, tops, and undercarriages of all construction equipment with a high-pressure washing system.
Perform all work at a location designated on the plans or other locations approved in writing. Provide the CO with an opportunity to monitor the washing and inspection.
Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment cleaned and inspected will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, dump trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.
Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment or components, or the need for specialized inspection tools, is not required.
Notify the CO in writing at least 7 days before moving any construction equipment onto the National Forest, and at least 24 hours before changing locations within the project area. Include an agreed-upon location where the equipment will be available for inspection. Inspection is required after every cleaning.
Use methods of cleaning and locations for cleaning approved by the C.O.
For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds offsite in a legal and approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
For work at a commercial washing facility, use an approved facility.
New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or Forest Service, on the Project Area or on the haul route, shall be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office. A list of known infestations along roads to be reconstructed will be available to the Contractor before work begins.
AG-0261-S-16-0044 Attach 1 Page 22 of 52
Section 152. - Construction Survey and Staking
152_R04F12_3_24_2012
152.01 Add the following:
The Government has set survey control stakes at both sites. Coordinates and/ or elevations are shown on the drawings.
Set and maintain adequate horizontal and vertical control and reference points for the projects.
(c) Material.
Delete the entire subsection.
Construction Requirements
152.02 General.
Delete the first two sentences.
Add the following:
When indicated on the plans, a preliminary survey line has been established on the ground. The project location line is established by offsets from this preliminary line.
Delete second sentence in second paragraph and replace with the following:
Reestablish missing reference, control lines, or stakes as necessary to control subsequent construction staking operations.
Delete the following entire subsections:
152.03 Survey and Staking Requirements
AG-0261-S-16-0044 Attach 1 Page 23 of 52
Section 153. - Contractor Quality Control Add the following.
153.07. Project Submittals
At a minimum the contractor shall provide project submittals as shown on the below Submittal Log. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.
Submittal Log
Log No.
Incidental to
Pay Item(s) Description of Submittal
Type of Submittal
Requirement found in
Specification No.
/Drawings
Additional Specification References
1 151 Weed Free Material Source Certification
Material Certification FSSS 105.02(b)
2 151 Hazardous Spill Plan Plan FSSS 107.10
3 151 Contractor Quality Control Plan Plan 153.02 552.09
4 151 Road Closure dates Plan FSSS 156.05
5 157 Soil Erosion and Pollution Control Plan Plan FSSS 157.03
6 209 Material Moisture/Density Testing Test Results Table 209-1 106
7 209 Structural Backfill Compaction Testing Test Results 209.11 106
8 552 Precast Footings Plans and calculations 552.01
9 552 Structural Concrete: Mix Design Mix Design 552.03 553, 553A, Drawings
10 552 Structural Concrete: Testing Test Results 552.19 106, Drawings
11 553 Reinforcing Steel and Wire Rope Material Certification 709.01
12 553 Precast Concrete Box Plans and calculations FSSS 553
13 553 Precast Concrete Structures: Testing Test Results FSSS 553A.02 106, 554, 562
14 625 Weed Free Straw Material Certification 625.02
AG-0261-S-16-0044 Attach 1 Page 24 of 52
Section 155. - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
Delete Section 155 in its entirety.
AG-0261-S-16-0044 Attach 1 Page 25 of 52
Section 156. - Public Traffic
156.00_R04F12_03_01_2007
Delete Section 156 in its entirety and replace with the following:
156.01 This work consists of controlling and protecting public traffic adjacent to and with the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Construction sign panels 633 Retroreflective sheeting 718.01 Temporary concrete barrier 618 Temporary plastic fence 710.11 Temporary traffic control devices 718.22
156.03_R04F12_3_26_2012
156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic.
This contract will allow closure of each road at the point of the stream crossing.
Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic-control plan has been approved. Post construction signs and traffic-control devices in conformance with MUTCD. Have all required signs in place and approved prior to beginning work on project.
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic-control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic-control devices adjacent to and within the project as required by the approved traffic-control plan and the MUTCD. Install and maintain traffic-control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic-control devices clean.
(h) Remove all temporary traffic-control devices upon contract completion, or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services Association, the
National Safety Council, the International Municipal Signal Association, a State agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retro-reflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high-visibility safety apparel as required by MUTCD 6E.02.
AG-0261-S-16-0044 Attach 1 Page 26 of 52
156.05_R04F12_3_24_2012
156.05 Temporary Closures
Prior to closing roads during construction, give written notice to the Contracting Officer at least 14 days in advance, so the Forest Service can post a notice in the local newspapers. The written notice shall include a complete work schedule showing stages of construction and planned completion and re-opening of the road to the public.
On each site where construction is occurring, install a Type III barricade on each side of the work area, with a white and black sign that says ROAD CLOSED. Barricades are needed at both sides of the work area to warn motorized traffic as well as people on foot or horse who could approach from the back side.
Site 557 MP 0.01 is adjacent to NFSR#101. Construction will require temporary closure of NFSR#101 during construction. When a closure occurs on NFSR#101 additional signage must be placed. See addition signage for 557 MP 0.01 in this section.
Temporary Road Closures Road Number
From Terminus To Terminus Maximum
Consecutive Days of Closure
Minimum Consecutive Days Open
074 Intersection of 074 and 101
Instersection of 074 and 128
10 days Not more than 1 weekend
To be approved in work schedule
556 At intersection with 101
At the Site To be approved in work schedule
Same as above
101 At intersection with 556
At intersection with 556
10 days Not more than one weekend
Same as above
In addition to the signs at each work site install the following advance warning signs:
When working on the 074_ 6.5 E. Branch Weiser River- Approx 500 feet in front of the Type III barricades at each work site, install this sign on a post that Says in black letters on orange background:
ROAD CLOSED
500 FEET
AG-0261-S-16-0044 Attach 1 Page 27 of 52
Install a Type III barricade on NFSR#074 at the junction of NFSR#074 and NFSR#128 in Section 10 Township 20 North Range 1 West, with a sign mounted on the barricade that says in black letters on white background
4 MILES AHEAD
LOCAL TRAFFIC ONLY
AG-0261-S-16-0044 Attach 1 Page 28 of 52
When working on 557 MP 0.01 E. Branch Weiser River, Site 557 MP 0.01 is adjacent to NFSR#101. Construction will require temporary closure of NFSR#101 during construction. When a closure occurs on NFSR#101 addition signage must be placed. Closure of NFSR#101 will be limited to 10 consective days and not more than one weekend.
Install a Type III barricade on each side of the work area on NFSR#101, with a white and black sign that says
ROAD CLOSED.
Install approximatlly 500 feet in front of the Type III barricades, place this sign on a post that says in black letters on orange background:
156.06 Acceptance
Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Measurement and Payment
Do not measure Public Traffic for payment. Compensation is incidental to 151- Mobilization.
500 FEET
AG-0261-S-16-0044 Attach 1 Page 29 of 52
Section 157. - Soil Erosion Control
157_nat_us_08_23_2004 Material
157.02
Provide bales, wattles, logs, rolls, and erosion-control mats from a certified noxious-weed-free source.
157.03_nat_us_02_24_2005
157.03 General
Delete the first two paragraphs and replace with the following:
Submit an Erosion Control Plan for each site, detailing permanent and temporary erosion-control measures to minimize erosion and sedimentation during and after construction, in accordance with the plans and storm-water permits. Do not modify the type, size, or location of any control or practice without approval. Submit the erosion-control plan proposal at least 7 days before operations begin to the CO for approval.
Reflect in the Erosion Control Plan special concerns and measures necessary to protect resources and government improvements. Include:
1. The construction activities and sequence of implementation relating to specific erosion control measures.
2. The location and type of permanent controls to be implemented during construction.
3. The location and type of temporary controls to be implemented during construction.
157.03_R04F12_03_27_2012
4. For work in stream channels with running water, submit a detailed dewatering plan. Convey water around the construction area during the operating season and higher flows in the event of a storm. Notify the COR at least 10 days in advance of any stream work or dewatering. The COR will notify the District Fish biologist who will be available during dewatering to move fish from the dewatering area using a combination of dip-netting and electrofishing. Schedule the start of dewatering to occur in the mid-morning, so the fish crew will have the afternoon to remove the fish. After the COR approves the stream simulation placement, re-water the area slowly to prevent loss of surface water downstream as the construction-site streambed absorbs water and to minimize a sudden increase in turbidity.
157.03_0510_11_10_2004
In perennial channels, which includes the two sites on this contract, pre-wash the reconstructed stream channel into a reach equipped with sediment-capture devices such as Sedimat, or settling pond prior to reintroduction of flow to the stream. Remove the turbid water by pumping to an infiltration area, or letting the sediment settle in the settling pond.
Re-water the construction site slowly to prevent loss of surface water downstream as the construction-site streambed absorbs water and to minimize a sudden increase in turbidity.
Use in-channel sediment-abatement barriers such as Sedimat to capture sediment that is liberated during re-watering of dewatered channels. Clean out and remove barriers, and dispose of captured sediment so it is not reintroduced into stream channels. Maintain such barriers throughout the related construction and remove only when construction is complete and erosion control is assured.
AG-0261-S-16-0044 Attach 1 Page 30 of 52
5. The location of each temporary stockpile site for the excavated material, and location of erosion control measures to prevent sediment from washing off of stockpile.
6. Keep a supply of erosion-control materials (e.g. silt fence, straw bales, and/or straw wattles) on hand to respond to sediment emergencies. Use only sterile straw or certified “weed-free” straw to prevent introduction of noxious weeds.
157.03_R04F12_03_07_2012
Add to the third paragraph:
Upon completion of construction at the site, remove all temporary dewatering materials and equipment from Government property. This includes items such as pumps, pipes and hoses, and sandbags.
Add the following:
Adhere to the following practices:
a) In order to protect aquatic organisms, insure that drafting hoses are fitted with screens with a 3/32 inch mesh and the appropriate surface area for the pump to achieve a mazimum water velocity of 0.4 ft/ sec at the screen surface, consistent with NOAA guidelines.
b) Centrifugal pumps used for drafting water from live streams or removing water from structure excavation (if needed) shall sit in a secondary spill container with sufficient capacity to contain the quantity of fuel in the pump fuel tank.
c) Construct the Dewatering and Sediment Control according to the Contractor’s approved plan.
d) Maintain the roads and stockpiles of material in a manner that prevents direct entry of sediment into the stream, by either preventing the erosion of sediments or collecting the sediments before it reaches the stream.
e) Construct permanent and temporary control features to intercept sediments. A settling basin will be constructed, or a portable one used, that is able to handle the volume of water anticipated, and that provides filtering capability. Dewatering of the excavation site, (of ground water from the excavation) will be done by pumping water to the settling basin, and the basin shall be cleaned out when full of sediments.
f) Any sanitation facilities established by the Contractor shall be located as designated by the CO.
g) Cease all project operations, except efforts to minimize storm or high-flow erosion, under precipitation and high-flow conditions that result in uncontrollable erosion in the construction area.
157.04 Controls and Limitations on Work.
Add the following to the second paragraph:
Place temporary erosion-control measures at the end of each day’s operation if greater than 30 percent chance of rainfall is predicted. Earthwork operations may be temporarily suspended by the CO if significant rainfall is forecast.
157.08 Water Crossings.
Add the following:
When there is water flowing through a channel crossing, dewater that site by rerouting the flow around the site before and during excavation and embankment operations that have the potential for sediment delivery to the live stream. If pumps are used, install screens on pump intakes with maximum openings of 3/32 inch and the appropriate surface area for the pump to achieve a maximum water velocity of 0.4 ft/sec at the screen surface, AG-0261-S-16-0044 Attach 1 Page 31 of 52 consistent with NOAA guidelines to protect aquatic organisms.
157.13_R04F12_2_8_2012
157.13 Maintenance and cleanup
Delete the third paragraph and insert the following:
Remove any Sedimat used from the stream channel after sediment-producing activities have ended. Place Sedimat on stream bank as an erosion-control measure. Erosion-control materials, such as hay bales, silt fences, and straw wattles, will be removed by the Forest Service when the sites have revegetated.
AG-0261-S-16-0044 Attach 1 Page 32 of 52
Section 201. - Clearing and Grubbing
201_R04F12_02_23_2010 Description
201.01 Replace with the following:
This work consists of clearing and grubbing within clearing limits and other designated areas.
201.02 Delete tree wound dressing material reference.
Construction Requirements
201.03 General.
Delete the first sentence.
Delete the last sentence.
201.04_nat_us_2_22_2005
201.04 Clearing.
Delete paragraph (c) and replace with the following:
(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground.
Delete subsection (d) and replace with the following:
(d) Do not cut vegetation less than 3 feet tall and less than 3 inches in diameter, that is within the clearing limits but beyond the roadway and not in a decking area, and that does not interfere with sight distance along the road.
(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs flush with the truck with a clean saw cut. Tree wound dressing is not required.
201.04_R04F12_3_7_2012
(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage; and will not roll. Keep logs in log decks free of brush and soil.
(g) Remove dead trees over 6 inches in diameter measured at 12 inches above the ground that lean toward the road and are tall enough to reach the roadbed. Deck as specified in (f) above.
201.05 Grubbing
Delete entire paragraph and replace with the following:
Grub all embankment areas. Undisturbed stumps may be left in place if they protrude less than 6 inches above the original ground and will be covered with more than 2 feet of embankment.
AG-0261-S-16-0044 Attach 1 Page 33 of 52
201.06_R04F12_3_7_2012
201.06 Disposal.
Delete the section and add the following:
Dispose of limbs, tree trunks, and stumps using 203.05 (l) placing slash on construction slopes.
201.06_R04F12_12_1_2012
201.07 Acceptance.
Delete the second and third sentences that applied to tree wound dressing and backfilling of stump holes.
201.09 Payment.
Delete the section and add the following:
Work under this item will be incidental to pay item 203, Removal of Structures and Obstructions.
AG-0261-S-16-0044 Attach 1 Page 34 of 52
Section 203. - Removal of Structures and Obstructions
203.01_R04F12_06_11_2012
203.01 Description.
Add the following:
Dispose of the existing culverts by method (a) remove from project.
The existing corrugated metal pipe culvert and related appurtenances shall be removed and disposed of away from Forest land according to all applicable local, state and federal regulations and 203.05 (a). Temporary soil erosion control measures shall be in place prior to commencing.
203.01_nat_us_2_18_2005
203.05 Disposing of Material.
Add the following:
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toe line of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks in windrows of at least 15 feet at least every 200 feet and at every draw and ridge and for wildlife trails. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.
(f) Scattering. Scatter construction slash outside the clearing limits without damaging trees. Limb all logs.
Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.
(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04, as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.