AG-0261-S-16-0044.pdf
PDF 952 KB Posted
- Attached to
- 2016 East Branch Weiser River AOP Federal contract opportunity
- Solicitation number
- AG-0261-S-16-0044
About this file
instructions and SF1442
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SOW.pdf | ||
| ID86.pdf | ||
| Construction_Cost_Estimate_Breakdown_00.xls | XLS spreadsheet | |
| maps_ _Drawings.pdf | ||
| Construction_Cost_Estimate_Breakdown_00.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AT A MINIMUM PROVIDE THE FOLLOWING
1. SF-1442, Complete, date, and sign.
Provide your DUNS NUMBER. Block 14
2. Fill out the pricing schedule for all items Attachment 3
3. Representations and Certifications (R&Cs) Section K 52.204-8. You MUST complete your
R&Cs in SAM. 52.204-7 is included and paragraph (d) applies. 52.209-11 was recently added to SAM. Please ensure it is completed along with all other required R&Cs. I will not need a response to the rest of 52.204-8 unless there are deviations from your from your on-line R&Cs. See paragraph (d).
4. Provide Liability insurance verification with proposal
5. Complete Idaho workers comp form www.iic.idaho.gov/forms/ic_wc_verification.pdf
6. Provide Past performance for like projects
7. Submit proposal based on section L&M.
8. Complete Determination of responsibility (attached)
Submit your information to:
USFS ATTN: Matt Morris 1249 S Vinnell Way, Ste 200 Boise, ID 83709-1663
CONTRACTORS ARE REQUIRED TO REGISTER WITH SYSTEM FOR AWARD MANAGEMENT (SAM)
WEBSITE at https://www.acquisition.gov WHICH NOW INCLUDES ORCA (ANNUAL REPRESENTATIONS AND
CERTIFICATIONS) PRIOR TO CONSIDERATION FOR AWARD OF ANY CONTRACTS WITH THE
GOVERNMENT. THE NAICS LISTED ON THE SOLICITATION MUST BE ON YOUR COMPANYS PROFILE.
SPECIAL NOTICE:
CONTRACTOR IS RESPONSIBLE FOR UPDATING SAM WITH ANY CHANGES THAT ARE MADE THAT
COULD AFFECT PAYMENTS (change in bank account or address). SAM NOW AUTOMATICALLY UPDATES
YOUR INFORMATION AT THE NATIONAL FINANCE CENTER.
There is a site visit scheduled for 21 Jun 2016. See 52.236-27
Solicitation Closes 28 Jun 2016
SET ASIDE for HUBZone small business concerns http://www.iic.idaho.gov/forms/ic_wc_verification.pdf https://www.acquisition.gov/
United States Department of Agriculture
Forest Service
SW Idaho/Nevada Acquisition Center
1249 South Vinnell Way Suite 200 Boise, ID 83709
Caring for the Land and Serving People Printed on Recycled Paper
File Code: 6320
Date: 27-May-16
RE: AG-84M8-S-16-0044
2016 E Branch Weiser River AOP
Dear Perspective Contractor:
During the evaluation process of any received proposals and prior to the award of any contract, the Government must conduct a Determination of Responsibility on the perspective contractor in order to determine their capacity and capabilities. In order to accomplish this task, I review data from various sources. Therefore, I seek your assistance in obtaining this data on your firm. To assist you in providing the information required, I have enclosed a form for your use. Please provide the information listed as a minimum.
Any additional information you have demonstrating the capabilities of your firm would also be appreciated.
Please note that in the case of most banks, factoring companies, financial institutions and often time’s suppliers, they need your express permission to release any information concerning your accounts. I appreciate your cooperation in coordinating with these establishments to enable me to obtain the required information. You would need to provide my name to them, as well as the type of contract that you have submitted a proposal on.
In the case of references for suppliers, please provide the name and phone number for the person most knowledgeable with your firm’s reputation. i.e., in some cases a Project Manager for instance may be more knowledgeable of your contributions than say an owner.
Please include this information with your business proposal. Thank-you for your cooperation. If you have any questions please don’t hesitate to call me at (208) 373-4166.
Sincerely, Matt Morris
Contracting Officer, Boise & Payette National Forest
Attachment
DETERMINATION OF RESPONSIBILITY INQUIRY
CONTRACTOR ______________________________________________________________
FINANCIAL INSTITUTIONS, FACTORING COMPANIES, BANKS:
FIRM INDIVIDUAL PHONE #
LINE OF CREDIT AVAILABLE OBLIGATED
LISTING OF ALL DEFAULTED LOANS OR JUDGEMENTS IN THE LAST 5 YEARS
OF BUSINESS AND/OR ALL OWNERS OR SHAREHOLDERS OF SUBMITTED
BUSINESS OR OTHER BUSINESSES PREVIOUSLY OWNED OR OPERATED BY
THIS INDIVIDUAL(S) OR CORPORATION(S)
COMPANY NAME LOAN/JUDGEMENT NO. PHONE/NAME
BONDING COMPANY CAPACITY COMMITTED
INSURANCE COMPANY TYPE AMT/LIMITS
IDAHO STATE WORKER’S COMP POLICY NUMBER: _____N/A_________________
SUPPLIERS:
FIRM INDIV TO CONTACT PHONE #
PREVIOUS PROJECTS SIMILAR TO THIS SOLICITATION:
OWNER/FIRM INDIV TO CONTACT PHONE #
LOCATION/SIZE
CURRENT PROJECTS:
OWNER/FIRM INDIV TO CONTACT PHONE #
LOCATION/SIZE
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
798566
SW IDAHO-NEVADA ACQUISITION CENTER
ATTN
1249 S VINNELL WAY STE 200
BOISE ID 83709-1663
MATTHEW MORRIS (208)373-4166
1x 05/27/2016
AG-0261-S-16-0044
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
2016 East Branch Weiser River AOP
This project is set aside for (Small Business) HUBZone
Magnitude of this project is between $100,000 and $250,000
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 90 calendar days and complete it within ________________ ________________ calendar days after receiving
06/28/2016
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
SW IDAHO-NEVADA ACQUISITION CENTER
ATTN
1249 S VINNELL WAY STE 200
BOISE ID 83709-1663
MATTHEW A. MORRIS
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
DUNS: Email:
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 21
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
AG-0261-S-16-0044
2016 East Branch Weiser River AOP
Delivery: 90 Days After Notice to Proceed
Delivery Location Code: 02WW
PAYETTE NATIONAL FOREST
800 WEST LAKESIDE AVE
MCCALL ID 83638 US
FOB: Destination
Period of Performance: 06/13/2016 to 09/30/2017
001 East Branch Weiser River AOP 2016 $__________________
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SECTION C - Description/specifications/Statement of Work
452.211-73 Attachments to Statements of Work/Specifications. (FEB 1988)
452.211-72 Statement of Work/Specifications. (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
(End of Clause)
AG-0261-S-16-0044 Page 4 of 21
SECTION E - Inspection and Acceptance
52.246-12 Inspection of Construction. (APR 1996)
AG-0261-S-16-0044 Page 5 of 21
SECTION F - Deliveries or Performance
52.242-14 Suspension of Work. (APR 1984)
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) - Alternate I (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 Sep 2017. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 1 Aug 2016. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of clause)
AG-0261-S-16-0044 Page 6 of 21
SECTION H – Special Contract Requirements
452.236-77 Emergency Response. (NOV 1996)
(a) Contractor's Responsibility for Fire Fighting. (1) The Contractor, under the provisions of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work. (2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents or employees.
(b) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.
(c) Contractor's Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to firefighting). An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.
(End of clause)
H.1 No separate payment will be made for traffic control. Traffic control is an indirect pay item with 151.-1 Mobilization. See supplemental specification 156 - Public Traffic.
H.2 TECHNICAL REQUIREMENTS
The Forest Service will obtain 404 Stream Channel Alteration Permits from the U.S. Army Corps of Engineers and Idaho Department of Environmental Quality. The permits are required to discharge fill material into rivers, including placement of rock, dirt, or sand necessary for the construction of the arch and stream simulation material. Copies of the permits will be made available to the Contractor at the time of the Contract award.
H.3. Weed-Free Equipment
In order to prevent the potential spread of noxious weeds into the project area, the Contractor shall be required to furnish the Contracting Officer with proof of weed-free equipment.
The following is considered proof of weed-free equipment:
The Contractor will be required to clean all construction equipment (equipment that operates off existing roads) prior to entry on the project area. This cleaning shall remove all dirt and plant parts and material that may carry noxious weed seeds into the project area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within the project area. All subsequent move-ins of construction equipment shall be treated the same as the initial move-in.
Prior to initial move-in of all construction equipment, and all subsequent move-ins, the Contractor shall make equipment available for inspection at an agreed location.
H.4 Barricades, Warning Signs, and Other Devices
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
AG-0261-S-16-0044 Page 7 of 21
SECTION I - Contract Clauses
52.252-2 Clauses Incorporated by Reference. (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/ or https://www.acquisition.gov/Far/ or www.usda.gov/procurement/policy/agar.html (End of clause)
52.202-1 Definitions. (NOV 2013) 52.203-3 Gratuities. (APR 1984) 52.203-5 Covenant Against Contingent Fees. (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government. (SEP 2006) 52.203-7 Anti-Kickback Procedures. (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights. (APR 2014) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (OCT 2015) 52.204-13 System for Award Management Maintenance. (JUL 2013) 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015) 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015) 52.211-18 Variation in Estimated Quantity. (APR 1984) 52.215-2 Audit and Records - Negotiation. (OCT 2010) 52.219-3 Notice of HUBZone Set-Aside or Sole Source Award. (NOV 2011) 52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011) 52.219-8 Utilization of Small Business Concerns. (OCT 2014) 52.219-14 Limitations on Subcontracting. (NOV 2011) 52.219-28 Post-Award Small Business Program Rerepresentation. (JUL 2013) 52.222-3 Convict Labor. (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards - Overtime Compensation. (MAY 2014) 52.222-6 Construction Wage Rate Requirements. (MAY 2014) 52.222-7 Withholding of Funds. (MAY 2014) 52.222-8 Payrolls and Basic Records. (MAY 2014) 52.222-9 Apprentices and Trainees. (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) 52.222-11 Subcontracts (Labor Standards). (MAY 2014) 52.222-12 Contract Termination - Debarment. (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards. (FEB 1988) 52.222-15 Certification of Eligibility. (MAY 2014) 52.222-21 Prohibition of segregated facilities. (APR 2015) 52.222-26 Equal Opportunity. (APR 2015) 52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015) 52.222-35 Equal Opportunity for Veterans. (OCT 2015) 52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014) 52.222-37 Employment Reports on Veterans. (FEB 2016) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (DEC 2010) 52.222-50 Combating Trafficking in Persons. (MAR 2015) 52.222-54 Employment Eligibility Verification. (OCT 2015) 52.222-55 Minimum Wages Under Executive Order 13658. (DEC 2015) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011) 52.223-6 Drug-Free Workplace. (MAY 2001) 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts (May 2008) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
AG-0261-S-16-0044 Page 8 of 21 http://farsite.hill.af.mil/ https://www.acquisition.gov/Far/ http://www.usda.gov/procurement/policy/agar.html
52.228-2 Additional Bond Security. (OCT 1997) 52.228-5 Insurance - Work on a Government Installation. (JAN 1997) 52.228-11 Pledges of Assets. (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014) 52.228-14 Irrevocable Letter of Credit. (NOV 2014) 52.228-15 Performance and Payment Bonds - Construction. (OCT 2010) 52.229-3 Federal, State, and Local Taxes. (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014) 52.232-17 Interest. (MAY 2014) 52.232-23 Assignment of Claims. (MAY 2014) 52.232-27 Prompt payment for construction contracts. (MAY 2014) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013) 52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013) 52.233-1 Disputes. (MAY 2014) 52.233-3 Protest after Award. (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) 52.236-2 Differing Site Conditions. (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) 52.236-5 Material and Workmanship. (APR 1984) 52.236-6 Superintendence by the Contractor. (APR 1984) 52.236-7 Permits and Responsibilities. (NOV 1991) 52.236-8 Other Contracts. (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984) 52.236-10 Operations and Storage Areas. (APR 1984) 52.236-11 Use and Possession Prior to Completion. (APR 1984) 52.236-12 Cleaning Up. (APR 1984) 52.236-13 Accident Prevention. (NOV 1991) 52.236-14 Availability and Use of Utility Services. (APR 1984) 52.236-15 Schedules for Construction Contracts. (APR 1984) 52.236-17 Layout of Work. (APR 1984) 52.236-21 Specifications and Drawings for Construction. (FEB 1997) 52.236-26 Preconstruction Conference. (FEB 1995) 52.242-13 Bankruptcy. (JUL 1995) 52.243-4 Changes. (JUN 2007) 52.246-21 Warranty of Construction. (MAR 1994) 52.248-3 Value Engineering - Construction. (OCT 2015) 52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) 52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) - Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction). (APR 1984) 52.253-1 Computer Generated Forms. (JAN 1991) 452.236-72 Use of Premises. (NOV 1996) 452.236-73 Archaeological or Historic Sites. (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution. (NOV 1996) 452.236-76 Samples and Certificates. (FEB 1988)
52.223-9 -- Estimate of Percentage of Recovered Material Content for EPA Designated Items.
As prescribed in 23.406(d), insert the following clause:
Estimate of Percentage of Recovered Material Content For EPA Designated Items (May 2008)
(a) Definitions. As used in this clause— “Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”
“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall—
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of postconsumer material content; and
(2) Submit this estimate to ___TDB________ [Contracting Officer complete in accordance with agency procedures].
AG-0261-S-16-0044 Page 9 of 21 http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/23.htm#P195_22650
52.225-9 Buy American - Construction Materials. (MAY 2014)
(a) Definitions. As used in this clause- Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if-
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
AG-0261-S-16-0044 Page 10 of 21
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description Unit of Measure Quantity Price
(Dollars)*
Item 1:
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
Item 2:
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
(End of clause)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)
(a) Upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract, to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, after receipt of a proper invoice and all other required documentation from the small business subcontractor.
(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.
(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial items.
52.244-6 Subcontracts for Commercial Items. (FEB 2016)
(a) Definitions. As used in this clause- Commercial item has the meaning contained in Federal Acquisition Regulation 2.101, Definitions.
AG-0261-S-16-0044 Page 11 of 21
Subcontract includes a transfer of commercial items between divisions, subsidiaries, or affiliates of the Contractor or subcontractor at any tier.
(b) To the maximum extent practicable, the Contractor shall incorporate, and require its subcontractors at all tiers to incorporate, commercial items or nondevelopmental items as components of items to be supplied under this contract.
(c)(1) The Contractor shall insert the following clauses in subcontracts for commercial items:
(i) 52.203-13, Contractor Code of Business Ethics and Conduct (OCT 2015) (41 U.S.C. 3509), if the subcontract exceeds $5.5 million and has a performance period of more than 120 days. In altering this clause to identify the appropriate parties, all disclosures of violation of the civil False Claims Act or of Federal criminal law shall be directed to the agency Office of the Inspector General, with a copy to the Contracting Officer.
(ii) 52.203-15, Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5), if the subcontract is funded under the Recovery Act.
(iii) 52.219-8, Utilization of Small Business Concerns (OCT 2014) (15 U.S.C. 637(d)(2) and (3)), if the subcontract offers further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds $700,000 ($1.5 million for construction of any public facility), the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.
(iv) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
(v) 52.222-26, Equal Opportunity (APR 2015) (E.O. 11246).
(vi) 52.222-35, Equal Opportunity for Veterans (OCT 2015)(38 U.S.C. 4212(a));
(vii) 52.222-36, Equal Opportunity for Workers with Disabilities (JUL 2014) (29 U.S.C. 793).
(viii) 52.222-37, Employment Reports on Veterans (FEB 2016) (38 U.S.C. 4212).
(ix) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O. 13496), if flow down is required in accordance with paragraph (f) of FAR clause 52.222-40.
(x)(A) 52.222-50, Combating Trafficking in Persons (MAR 2015) (22 U.S.C. chapter 78 and E.O. 13627).
(B) Alternate I (MAR 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).
(xi) 52.222-55, Minimum Wages under Executive Order 13658 (DEC 2015).
(xii) 52.225-26, Contractors Performing Private Security Functions Outside the United States JUL 2013) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
(xiii) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (DEC 2013), if flow down is required in accordance with paragraph (c) of FAR clause 52.232-40.
(xiv) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C.
App. 1241 and 10 U.S.C. 2631), if flow down is required in accordance with paragraph (d) of FAR clause 52.247-64.
(2) While not required, the Contractor may flow down to subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.
(d) The Contractor shall include the terms of this clause, including this paragraph (d), in subcontracts awarded under this contract.
(End of clause)
452.232-70 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts. (NOV 1996) The Contract Price includes the total amount for premiums that the Contractor attributes to the furnishing of performance and payment bonds required by the contract. Reimbursement for bond premiums under the clause at FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not cover any amount therefor not included in the contract price.
AG-0261-S-16-0044 Page 12 of 21
SECTION J - List of Documents, Exhibits, and Other Attachments
List of Documents, Exhibits, and Other Attachments Attachment
Number Title Date
1 SOW 25 May 2016 2 Maps and Drawings 25 May 2016 3 Construction Cost Estimate Breakdown (pdf & xls) 25 May 2016 4 Wage Determination ID86 01/08/2016
AG-0261-S-16-0044 Page 13 of 21
SECTION K - Representations, Certifications, and Other Statements of Offerors
52.204-16 Commercial and Government Entity Code Reporting. (JUL 2015) 52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)
52.204-8 Annual Representations and Certifications. (APR 2016) (a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237310.
(2) The small business size standard is $36.5m.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
___ (i) Paragraph (d) applies.
___ (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless-
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures;
or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions.
This provision applies to solicitations expected to exceed $150,000.
(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include provision at 52.204-7, System for Award Management.
(iv) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that-
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(v) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations-Representation.
(vi) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(vii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(viii) 52.214-14, Place of Performance-Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(ix) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(x) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(xi) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xiii) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
AG-0261-S-16-0044 Page 14 of 21
(xiv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xv) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xvi) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xvii) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xviii) 52.225-4, Buy American-Free Trade Agreements-Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $77,533, the provision with its Alternate II applies.
(D) If the acquisition value is $77,533 or more but is less than $100,000, the provision with its Alternate III applies.
(xix) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xx) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan-Certification. This provision applies to all solicitations.
(xxi) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications. This provision applies to all solicitations.
(xxii) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
(Contracting Officer check as appropriate.)
[ ] (i) 52.204-17, Ownership or Control of Offeror.
[ ] (ii) 52.204-20, Predecessor of Offeror.
[ ] (iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
[ ] (iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Certification.
[ ] (v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Certification.
[ ] (vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA- Designated Products (Alternate I only).
[ ] (vii) 52.227-6, Royalty Information.
[ ] (A) Basic.
[ ] (B) Alternate I.
[ ] (vii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The offeror has completed the annual representations and certifications electronically via the SAM Web site accessed through https://www.acquisition.gov. After reviewing the SAM database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below (offeror to insert changes, identifying change by clause number, title, date). These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR Clause No. Title Date Change
AG-0261-S-16-0044 Page 15 of 21
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
(End of provision)
452.219-70 Size Standard and NAICS Code Information. (SEP 2001) The North American Industrial Classification System Code(s) and business size standard(s) describing the products and/or services to be acquired under this solicitation are listed below:
Contract line item(s): 001
- NAICS Code 237310
- Size Standard $36.5 (End of provision)
AG-0261-S-16-0044 Page 16 of 21
SECTION L - Instructions, Conditions, and Notices to Offerors or Respondents
52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998) This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/ or https://www.acquisition.gov/Far/ or www.usda.gov/procurement/policy/agar.html (End of provision)
52.204-7 System for Award Management. (JUL 2013) 52.204-18 Commercial and Government Entity Code Maintenance. (JUL 2015) 52.215-1 Instructions to Offerors - Competitive Acquisition. (JAN 2004) 452.237-71 Pre-Bid/Pre-Proposal Conference. (FEB 1988) 52.236-28 Preparation of Proposals - Construction. (OCT 1997)
52.216-1 Type of Contract. (APR 1984) The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
(End of provision)
52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. (MAY 2014)
(a) (1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b) (1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
(End of Provision)
52.228-1 Bid Guarantee. (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $50,000, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for Minority Participation for Each Trade 4.4%
AG-0261-S-16-0044 Page 17 of 21 http://farsite.hill.af.mil/ https://www.acquisition.gov/Far/ http://www.usda.gov/procurement/policy/agar.html
Goals for Female Participation for Each Trade 6.9% These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative…
This is the start of the file's text. The full file is on GovTribe.