Questions_and_Answers_for_Anan_Observation_AG.docx

DOCX document 14 KB Posted

Attached to
Anan Bay Wildlife Observatory Recreational Facilities Construction
Solicitation number
AG-0116-S-16-0026
Issued by

About this file

Questions and Answers

View the file

Other files

File Type Posted
Amended_DRWG_SET_-_08-17-2016.pdf PDF
Amendment_001.pdf PDF
Amended_SPECS_08-17-2016.pdf PDF
Question_and_Answers__2.docx DOCX document
Photo_Log.pdf PDF
Solicitation_-_AG-0116-S-16-0026.pdf PDF
Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers for Anan Observation AG-0116-S-16-0026

Q 1. Is there cell coverage in the area?

A. No cell service near Anan

Q 2. Would the Forest Service be willing to offer one of the FS Structural Engineers to stamp submittal drawings?

A. The structural engineer needs to be provided by the Contractor. See the contract provisions.

Q 3. Is there enough rip-rap/boulders materials on site and available to complete this solicitation?

A. The contractor must make their own determination whether there are enough boulders onsite that can be used in conformance with the specifications. See the contract provisions in this regard

Q 4. Is there an approved area to burn old structures or must all materials be barged out?

A. Some small burning may be allowed as approved. No burning of treated wood is allowed, it shall be removed offsite and disposed of. See the contract provisions in this regard.

Q 5. Will a temporary barge beach landing require permitting while unloading?

A. The beach landing locations are to be approved in advance. See the contract provisions in this regard.

Q 6. Will D-1 crushed rock suffice for the E-1 spec?

D-1 is not a suitable replacement for E-1.