Questions_and_Answers_050815.pdf
PDF 39 KB Posted
- Attached to
- Cascade Creek Trail Improvement Stewardship Project Federal contract opportunity
- Solicitation number
- AG-0116-S-15-0013
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 0116S150013_A0004.pdf | ||
| amend0003.pdf | ||
| amend0002.pdf | ||
| Questions_and_answers_051815.pdf | ||
| Amend0001.pdf | ||
| Questions_and_Answers_051415.pdf | ||
| PreProposalMeetingNotes_050615.pdf | ||
| 0116S150013SectionJAttachments.pdf | ||
| 0116S150013CascadeSTWD_041615.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-0116-S-15-0013 Cascade Creek Trail Improvement Stewardship
Questions and Answers
Dated: 05/08/2015
1. Where is the stone pitching paid for? Stone Pitching (SP) is paid according to Specification 906.02
2. What is the pay item Labor 15 ea? In reference to “Laboror Work” shown in the schedule of items as AQ paid by the unit “hour”, and in Specification 906.2. “Laboror Work” is also referenced in 956.03.
3. The retaining wall sizes are undefined. Can we get a pay item for retaining walls by the square foot?
SRW work is illustrated on Drawing Sheet 17. All work related to the construction of Rest Areas is incidental to the Lump Sum payment for the Rest Area, so no additional payment will be made for SRW.