AG-0109-S-17-0073_LaunchingInformation.pdf

PDF 271 KB Posted

Attached to
Bridge Replacement - Excursion Inlet Federal contract opportunity
Solicitation number
AG-0109-S-17-0073
Issued by
Department of Agriculture Forest Service R10-Alaska Region

About this file

Launching Information

View the file

Other files for this federal contract opportunity

Other files attached to Bridge Replacement - Excursion Inlet, newest first.
File Type Posted
AG-0109-S-17-0073_Amend3.pdf PDF
AG-0109-S-17-0073_Amendment2.pdf PDF
AG-0109-S-17-0073_Amend01.pdf PDF
Questions_and_Answers_2.pdf PDF
Packing_Lists_for_Barged_materials_Barged_08182017_via_AML.pdf PDF
FinalOrderNeva.pdf PDF
Questions_and_Answers_1.pdf PDF
FSSS_Excursion_Inlet.pdf PDF
AG-0109-S-17-0073_Excursion-Inlet-Bridge.pdf PDF
Excursion_Inlet_cannery_photo.pdf PDF
WageDetermination_AK7.pdf PDF
Excursion_Bridge_Plans_REV_2017_Final.pdf PDF
Excursion_Bridge_Plans_REV_2017_Final.pdf PDF
Excursion_Inlet_cannery_photo.pdf PDF
FSSS_Excursion_DRAFT.pdf PDF
Excursion_Inlet_Bridge_Parts.docx DOCX document
Excursion_Bridge_DrawingPackage_Unsigned.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-0109-S-17-0073 8/23/2017

Excursion Inlet Bridge Replacement

1 | P a g e

The Contractor will be responsible for preparing the launching area in accordance with the following:

The launching area in advance of the bridge needs to be 100 feet long, no more than 2% grade, and 24 feet clear width. Rollers in the launch area are

Bailey bridge plain rollers (photo shown at right ---------------------------------is approximate rendition of these rollers). They need to be supported every

25 feet on both sides of the bridge/launch nose (approximately 19 feet apart).

The launching sequence for a 130 foot bridge with 100 feet of launching approach will utilize an 80 foot long launching nose (6 bays single-single, 2 bays double-single) preceding the 130 foot triple-single bridge. Advance rocking rollers (shown below) will be placed 125 feet apart (beginning of bridge and end of bridge).

Advance

Rocking

Rollers

NOTE: Final Launching Plan will not be provided until after award. However, the anticipated launching sequence is provided below: (Assumption is center of gravity is 10 feet behind the lead roller)

Stage 1 Construct launching nose (6 SS+2 DS) + 20 feet of bridge (undecked) Launch 50 feet forward. 50 feet will be back

Stage 2 Construct 40 feet of bridge (undecked) Launch 75 feet forward. 65 feet will be back

Stage 3 Construct 20 feet of bridge (undecked) plus 10 feet of bridge with 1 row of decking. Launch 85 feet forward. 85 feet will be back

Stage 4 Construct 10 feet of bridge with 1 row of decking.

Launch 100 feet forward. 80 feet will be back.

Stage 5 Construct 20 feet of bridge with 2 rows decking +2 stacks (10) decking counterweight. Launch 115 feet forward. 85 feet will be back.

Stage 6 Construct 10 feet of bridge with 2 rows decking + 4 stacks (20) of curbing counterweight. Launch 125 feet forward and catch lead roller.

The Approved Launching Plan will be finalized after award with the successful contractor and Acrow.