About this file

This is Addendum One to the contract documents for the MTC Sidewalk Improvement/Granby Hall ADA Ramp project issued by the South Carolina procurement authority on November 24, 2020. The project involves sidewalk improvements and ADA ramp construction at Granby Hall, with bidders required to submit all bids via email to www.procurement.sc.gov by 11:00 am on December 8, 2020, under SCBO Solicitation Number 540020575. The project specifies a construction timeline of 90 calendar days from the date of commencement. All bidders must acknowledge receipt of this addendum in the space provided on the bid form, with failure to do so potentially resulting in bid rejection. The addendum includes modifications to the original contract documents, specifically noting that Drawing C5 is missing handrail details, with clarification provided in the attached bulletin drawing titled "Ramp/Walk Handrail Detail."

The estimated project budget ranges from $30,000.00 to $70,000.00. A bid bond is required only if the submitted bid equals or exceeds $50,000.00. Liquidated damages are assessed at $150.00 for each calendar day that actual construction time exceeds the specified contract time for substantial completion. The addendum clarifies that MTC does not maintain a plan holder list at this time. No plan holders list was available for distribution at the time of addendum issuance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum Number One

Date of Issue: 11/24/2020

Project: MTC Sidewalk Improvement/Granby Hall ADA Ramp

Project Number: MTC #20-07

This addendum modifies the Contract documents only in the manner and to the extent stated herein and shown on any accompanying drawings and will become part of the Contract Documents. Except as specified or otherwise indicated by this Addendum, all work shall be in accordance with the basic requirements of the Contract Documents.

BIDDERS SHALL ACKNOWLEDGE RECEIPT OF ADDENDUM IN THE SPACE

PROVIDED ON THE BID FORM. FAILURE TO DO SO MAY CONSTITUTE A REASON

TO REJECT THE BID.

General Information: Questions and Answers

1. Is there an estimated value or budget available?

Answer: $30,000.00 to $70,000.00

2. Also is there a list of plan holders available?

Answer: MTC does not have a plan holder list at this time.

3. Can you provide the following clarifications?

Bid Bond? Answer: Bid Bond is required if your Bid is $50,000.00 or more.

Liquidated Damages? Answer: $150.00 for each calendar day the actual construction time required to achieve Substantial Completion exceeds the specified or adjusted Contract Time for Substantial Completion.

Budget Estimation? Answer: $30,000.00 to $70,000.00 Construction Days? Answer: 90 Calendar days from the date of Commencement.

Changes to the Specifications:

1. Not used.

Changes to the Drawings:

1. Drawing C5 is missing Handrail details.

See Attached bulletin drawing “Ramp/Walk Handrail Detail”

BIDDER SUBMISSIONS:

All bids are to be submitted via e-mail to http://www.procurement.sc.gov by 11:00 am, December 8, 2020 per SCBO Solicitation Number 540020575, Request for Quote.