About this file

This document is Addendum No. 2 issued by the City of Mountain View, California, for the Citywide Trash Capture, Phase II, Project 22-40. The addendum revises Page II-PF-2 of Exhibit A in the original contract documents and specifications. The project involves procuring and installing 207 Triton™ Perf-Full Trash Capture Devices in designated storm drain catch basins throughout the city, with the contractor responsible for providing labor, materials, equipment, and installation according to manufacturer specifications and regulatory requirements.

The bid schedule includes a base bid item for the 207 trash capture devices and an optional alternate bid item for traffic control and general safety measures. The bidding notes indicate that submittal of alternate bid items is optional, and the lowest bid will be determined by the base contract pricing without considering the optional alternate. The city reserves the right to add the optional alternate to the contract after identifying the lowest responsible bidder. The addendum was distributed on April 7, 2025, via BidNet Direct and Prints Charles to existing and subsequent plan holders.

View the file

Other files

File Type Posted
copy_955-03-28-25F130.pdf PDF
Addendum No. 1_signed.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF MOUNTAIN VIEW

MOUNTAIN VIEW, CALIFORNIA

ADDENDUM NO. 2

TO SPECIFICATIONS

FOR

Citywide Trash Capture, Phase II

Project 22-40

The following addition and/or changes hereinafter set forth shall apply to the Specifications for this project and shall be made a part hereof and subject to all the requirements thereof, as if originally specified and/or shown:

Revision to the following page of the contract documents and specifications:

1. Replace: Page II-PF-2 of Exhibit A with the attached revised page.

This Addendum No. 2 contains a total of 2 pages, including attachments. All other provisions remain in effect.

Bidders shall acknowledge receipt of this Addendum No. 2 in Proposal Form, page II-PF-4

Edward Arango

Assistant Public Works Director/City Engineer

Date: April 7, 2025

Distributed via BidNet Direct and Prints Charles to existing and subsequent plan holders on April 7, 2025 cc: PCE – Tseng, PCE – Shah, SCE – Chou, ACE – Husaini

EXHIBIT A

CITY OF MOUNTAIN VIEW

CITYWIDE TRASH CAPTURE, PHASE II, PROJECT 22-40

BID SCHEDULE

ITEM

NO.

ITEM DESCRIPTION QTY. UNIT

UNIT

PRICE

EXTENSION

Furnish and Install Triton™ Perf-Full Trash Capture Devices

207 EA $ $

TOTAL BASE BID:

(price in words) (price in numbers)

OPTIONAL ALTERNATE BID ITEM SCHEDULE

ITEM

NO.

ITEM DESCRIPTION QTY. UNIT

UNIT

PRICE

EXTENSION

1A Traffic Control and General Safety Measures at Special Areas

1 LS $

TOTAL BASE BID PLUS OPTIONAL BID ALTERNATE (OPTIONAL BID ALTERNATE 1A):

(price in numbers)

(price in words)

NOTES:

1. Submittal of bids for alternate bid items is optional.

2. The lowest bid shall be the lowest total of the bid prices on the base contract without consideration of the prices of the optional bid alternate item.

3. The City may add the Optional Bid Alternate to the contract after the lowest responsible bidder has been determined.

File details come from the government source that posted it. Updated .