ADDENDUM 3, 25-WASTEWATER-01.pdf

PDF 104 KB Posted

Attached to
Wastewater Treatment Facility Upgrades - Design RFP State and local contract opportunity
Solicitation number
25-WASTEWATER-01
Issued by
Boulder County, Colorado

About this file

Addendum No. 3 is a contract document issued by the Town of Lyons for the Wastewater Treatment Facility Upgrades Project (Project Number: 25-WASTEWATER-01), dated July 1, 2025. The addendum provides clarifying information for potential bidders, including responses to three specific questions about the project. The document emphasizes that bidders must acknowledge receipt of all addenda, and failure to do so may result in bid rejection.

The addendum addresses key information requests from potential bidders, including providing updated influent wastewater flow and loading information via an Excel file on Bidnet, and directing bidders to record plans contained in the Site Location Application from October 18, 2018. Additionally, the document confirms that there is currently no integrator for the project. The second page of the document includes a form for bidders to acknowledge receipt of the addendum, requiring company name, authorized representative's signature, printed name, and title.

View the file

Other files for this state and local contract opportunity

Other files attached to Wastewater Treatment Facility Upgrades - Design RFP, newest first.
File Type Posted
2018 SITE LOCATION APPLICATION.pdf PDF
2686.9c - PDR Submission to CPDHE 2020.04.24.pdf PDF
ADDENDUM 1, 25-WASTEWATER-01.pdf PDF
Lyons Influent BOD Data 2025.xlsx XLSX spreadsheet
2011 WASTEWATER FEASIBILITY STUDY.pdf PDF
General Permit Certification.pdf PDF
2013 PRELIMINARY ENGINEERING REPORT.pdf PDF
25-WASTEWATER-01_RFP 05302025.pdf PDF
ADDENDUM 2, 25-WASTEWATER-01-Final.pdf PDF
Wastewater Treatment Facility Master Plan by JVA Oct 2024.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 3

TO THE CONTRACT DOCUMENTS FOR

TOWN OF LYONS

WASTEWATER TREATMENT FACILITY UPGRADES PROJECT

TOWN PROJECT NUMBER: 25-WASTEWATER-01

THIS ADDENDUM IS HERBY MADE A PART OF THE CONTRACT DOCUMENTS TO

THE SAME EXTENT AS THOUGH IT WERE ORIGINALLY INCLUDED THEREIN.

BIDDERS MUST ACKNOWLEDGE RECEIPT OF ALL ADDENDA. BIDS THAT FAIL TO

ACKNOWLEDGE ALL ADDENDA MAY BE CONSIDERED IRREGULAR AND MAY BE

REJECTED.

ISSUED: 07/01/2025

ITEM NO. 1

Questions and answers from email.

Q1. To help us better prepare our proposal, are you able to send updated influent wastewater flow and loading information for 2025?

A1: Yes, see attached Excel file on Bidnet.

Q2. Can the Town provide us with a set of record plans of the WWTF for review?

A2: The Site Location Application for the Town of Lyons, Wastewater Treatment Facility, dated October 18, 2018, on Bidnet as part of Addendum #1 contains the record plans.

Q3. Is there an integrator? If so, who is providing those services?

A3: There is no current integrator.

Acknowledge Receipt of Addendum #3

PRINT OR TYPE YOUR INFORMATION AND INCLUDE ANY AND ALL

ADDENDUMS.

Name of Company:

Authorized Representative’s Signature: Date:

Printed Name: Title:

File details come from the government source that posted it. Updated .