Addendum #1 - SUNY IFB #990313.pdf

PDF 268 KB Posted

Attached to
SUNY Purchase College - Interior Painting Services
Solicitation number
2136850
Issued by
Westchester County, New York

About this file

This is Addendum #1 to SUNY Purchase College's Invitation for Bid (IFB) #990313 for Interior Painting Services, issued by the State University of New York on August 3, 2026. The addendum provides clarifications to the original IFB through a question-and-answer section addressing bidder inquiries. The scope of work encompasses interior painting services for college dormitories, apartment complexes, and other campus buildings under a three-year contract term. Sealed bids were due by 2 p.m. on Wednesday, August 12, 2026, and a non-mandatory site visit was held on Tuesday, July 28, 2026 at 11:00 a.m. at the Facilities Management Building conference room on the Purchase College campus in Purchase, New York. Bids must be submitted as two signed paper copies in sealed packages and cannot be submitted electronically.

All bidders must complete required forms by hand and submit them with their proposal packages, including SUNY MWBE Forms 104 and 107, regardless of whether subcontractors have been selected. The painting work requires one primer coat and two paint coats, with colors provided by SUNY from Sherwin Williams. Work hours and project deadlines are determined on a per-job basis and typically include residential areas painted during summer months and academic buildings during fall and spring. The project is subject to New York State prevailing wage requirements under Prevailing Wage Case number PRC# 2026018427. SUNY Purchase will provide on-campus storage space; trailers are not permitted. Scaffolding and lift costs are quoted separately on a per-need basis, and SUNY assumes responsibility for any asbestos found on site. The College did not provide a proposed budget, expecting bidders to submit their best pricing, which will determine the final contract amount.

View the file

Other files

File Type Posted
IFB-990313 SUNY Purchase College - Painting.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB #990313 Painting Services Addendum #1 * August 3, 2026

To: Prospective Bidders No. of Pages: 3 page

SUNY Purchase wishes to make the following clarifications to IFB #990313.

Please be sure to sign the end of this Addendum (as acknowledgement that your firm received it) and submit it with your proposal package, which is due by Wednesday, August 12, 2026 at 2pm

EDT.

Item 1:

SUNY Purchase received a number of questions during the Q & A period. Answers with additional clarification are provided on the follow 2 pages. The Q&As are not listed in any kind of order that is significant.

Please note that as the bidder, you must sign THIS ADDENDUM and submit it with your bid package.

Respectfully, Elizabeth Pleva Director, Procurement and Accounts Payable

Acknowledgement of ADDENDUM #1

Signature Date

Typed printed name and title

Company name

SUNY Purchase College IFB #990313 Interior Painting Services

Addendum #01 - Bidder’s Questions & Answers

Q1. Do you provide a storage space on campus or can we bring in a trailer?

A1. We will provide a storage space with a lock on campus. No trailers are allowed.

Q2. What is the estimated contract amount?

A2. The College is not providing a proposed budget and expects Bidders who meet the requirements to provide their best pricing which will determine the contract amount.

Q3. Should scaffolding costs be included in our estimate number?

A3. No. Scaffolding and lifts for complex, large areas are considered an extra cost, and will be quoted separately on a per need basis.

Q4. How are colors chosen?

A4. We provide the colors. They are from Sherwin Williams.

Q5. Does this project require asbestos removal?

A5. No. If asbestos is found, SUNY Purchase College takes care of it.

Q6. Is sheetrock included?

A6. Only sheetrock repair is included for any small area, as part of surface preparation.

Q7. How many coats are required?

A7. One primer and two coats paint. If skim coat is needed, that is part of surface prep costs.

Q8. Do all forms included in the IFB need to be filled out and submitted with the proposal?

A8. Yes. All forms with fill-in boxes should be completed and submitted with your proposal.

Q9. How is the price determined for each project?

A9. A Painting Estimate Sheet is submitted beforehand for each project and signed by the contractor and SUNY supervisors.

Q10. What are the work hours?

A10. This is determined per job, and once agreed upon, it can be days, nights, weekends.

Q11. Is this a prevailing wage job?

A11. Yes. All work done on campus must be a New York State prevailing wage rates. The Prevailing Wage Case number for this contract is PRC# 2026018427.

SUNY Purchase College IFB #990313 Interior Painting Services

Addendum #01 - Bidder’s Questions & Answers

Q12. What are the deadlines for each painting project?

A12. Deadlines are discussed and determined prior to the start of a project, and depends on the urgency. Residential areas are mostly done in the summer months, and Academic buildings in the fall and spring.

Q13. Can I submit my bid electronically? Can forms be completed electronically?

A13. No. Bids cannot be emailed, and forms should be completed by hand. Submit two (2) signed paper bids in a sealed package, addressed to the contact’s name found in the IFB, Section 6e: Bid Submission Requirement, which details what should be included in your submission. Your sealed envelope can be hand delivered or mailed.

Q14. We have not selected our MWBE subcontracts. Should we leave that section blank for now?

A14. No, as noted on page 11 of the IFB, SUNY MWBE Forms 104 & 107 must be submitted with all bids.

Q15. Is it acceptable to provide our five project references on our company letterhead?

A15. Yes.