Addendum 1 - RFB-UC26-146C WAWARSING PUBLIC SAFETY RADIO TOWER SITE PROJECT.pdf

PDF 216 KB Posted

Attached to
WAWARSING PUBLIC SAFETY RADIO TOWER SITE PROJECT
Solicitation number
2136796
Issued by
Ulster County, New York

About this file

This addendum to Bid No. RFB-UC26-146C is a specification document issued by Ulster County for the Wawarsing Public Safety Radio Tower Site Project, prepared by Tectonic Engineering Consultants. The addendum details requirements for furnishing and installing a complete interior overhead cable ladder rack and cable tray system within a prefabricated telecommunications equipment shelter. The work scope includes cable rack system fabrication and installation, coordination with shelter design and equipment layout, grounding and bonding of the ladder rack system, and cable management accessories and fittings. The system must support routing of RF feeders, hybrid/power cabling, and fiber optic cabling while accommodating a minimum of four equipment cabinets with provisions for future expansion. The cable rack system components shall include straight ladder sections, tees and intersections, splice hardware, trapeze supports, radius drop-out fittings, end caps, and bonding jumpers. Installation specifications require the ladder rack to be constructed from aluminum or corrosion-resistant equivalent material with minimum 12-inch width and 50 lb/ft distributed load capacity, with support spacing not to exceed 5 feet or per manufacturer requirements.

The system shall be installed as part of the prefabricated shelter assembly at elevations of 8 feet 0 inches to 8 feet 6 inches above finished floor, maintaining minimum 12-inch clearance above cabinet tops and adequate separation from HVAC and ceiling systems. All cable rack sections must be bonded to maintain electrical continuity and connected to the Interior Master Ground Bar using minimum #6 AWG copper bonding conductors with listed lugs and connectors. Installation must comply with ANSI/TIA-569, NFPA 70 Article 392, NEMA VE-1, and NEMA VE-2 standards. The shelter manufacturer is responsible for furnishing and installing the complete cable rack system as part of the prefabricated shelter, while the contractor must coordinate with the manufacturer, verify compliance with specifications, and connect the system to the site grounding network. Submittals required prior to shelter fabrication include product data with manufacturer specifications and load ratings, and shop drawings showing cable rack layout, elevations, support details, and grounding provisions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ulster County Public Radio System

Wawarsing Tower Site Project CABLE TRAY / LADDER RACK SYSTEMS

Tectonic Engineering Consultants, Geologists & Land Surveyors, D.P.C. 275036 - 1

BID NO: RFB-UC26-146C July 15, 2026

SECTION 270536

CABLE TRAY / LADDER RACK SYSTEMS (INTERIOR – TELECOM SHELTER)

PART 1 – GENERAL

1.01 SUMMARY

A. This section includes requirements for the interior overhead cable ladder rack / cable tray system within the prefabricated telecommunications equipment shelter.

B. Work includes:

• Furnishing and installation of complete cable rack system

• Coordination with shelter design and equipment layout

• Grounding and bonding of ladder rack system

• Cable management accessories and fittings

C. System shall support routing of:

• RF feeders

• Hybrid/power cabling

• Fiber optic cabling

1.02 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this section.

B. Coordinate with:

• C-3 Compound Plan (equipment layout and shelter configuration)

• C-7 Antenna and cable entry details

• G-2 Interior Grounding Plan

• Any other applicable design specifications

1.03 REFERENCES

Comply with latest editions of:

• ANSI/TIA-569 – Telecommunications Pathways and Spaces

• NFPA 70 (NEC), Article 392 – Cable Trays

• NEMA VE-1 – Metal Cable Tray Systems

• NEMA VE-2 – Installation Guidelines

1.04 SYSTEM DESCRIPTION

A. Provide a complete integrated overhead cable rack system within the shelter.

B. The system shown on the drawings is schematic; provide a complete system meeting performance requirements herein.

C. System shall extend from the cable entry port to all equipment cabinets including any future expansion.

Tectonic Engineering Consultants, Geologists & Land Surveyors, D.P.C. 275036 - 2

1.05 RESPONSIBILITIES

A. Shelter Manufacturer shall:

• Furnish and install the complete cable rack system as part of the prefabricated shelter

B. Contractor shall:

• Coordinate with shelter manufacturer

• Verify compliance with this specification

• Connect system to site grounding network

1.06 SUBMITTALS

A. Product Data:

• Manufacturer specifications for ladder rack system

• Load ratings and material data

B. Shop Drawings:

• Cable rack layout within shelter

• Elevations and support details

• Alignment with entry ports and equipment

• Grounding/bonding provisions

C. Submit prior to shelter fabrication for approval.

1.07 QUALITY ASSURANCE

A. Installer shall have experience with telecommunications infrastructure installations.

B. All components shall be listed/labeled where applicable.

PART 2 – PRODUCTS

2.01 ACCEPTABLE MANUFACTURERS

A. Cable rack system shall be provided by the selected shelter manufacturer.

B. System components shall be standard, commercially available products designed for telecom applications.

2.02 MATERIALS

A. Ladder Rack System:

• Type: Ladder rack or integrated cable tray

• Material: Aluminum (preferred) or corrosion-resistant equivalent

• Finish: standard mill finish or equivalent

B. Dimensions:

• Width: 12 inches minimum

C. Structural Capacity:

• Minimum: 50 lb/ft distributed load

Tectonic Engineering Consultants, Geologists & Land Surveyors, D.P.C. 275036 - 3

2.03 COMPONENTS

Provide complete system including:

• Straight ladder sections

• Tees and intersections

• Splice hardware

• Trapeze supports or integrated support system

• Radius drop-out (waterfall) fittings

• End caps

• Bonding jumpers

2.04 CABLE MANAGEMENT ACCESSORIES

A. Provide:

• Radius drop-out fittings at all cable transitions

• Smooth edges and protective surfaces

B. Maintain bending radius requirements for fiber and hybrid cables.

2.05 GROUNDING MATERIALS

A. Bonding conductors:

• Minimum #6 AWG copper

B. Grounding hardware:

• Listed lugs and connectors compatible with ladder system

PART 3 – EXECUTION

3.01 INSTALLATION – GENERAL

A. Install cable rack system as part of prefabricated shelter assembly.

B. System shall be level, secure, and aligned with equipment layout.

C. Support spacing:

• Maximum 5 feet or per manufacturer requirements (whichever is more stringent)

3.02 PROJECT-SPECIFIC LAYOUT

A. Shelter Size: As defined in the Project Drawings

B. Equipment Configuration:

• Four (4) equipment cabinets minimum (to be confirmed with the Owner)

C. Provide:

1. Longitudinal and Transverse cable rack runs:

o Length: as needed to cover cabinet configurations and future expansion

2. Cable routing:

o Continuous path from cable entry port to ladder rack system o No sharp bends at entry

3. Cabinet access:

Tectonic Engineering Consultants, Geologists & Land Surveyors, D.P.C. 275036 - 4 o Four (4) cable drop locations aligned with cabinet centers

3.03 COORDINATION

A. Coordinate installation with:

• Cable entry ports

• Equipment cabinet layout

• HVAC equipment

• Lighting fixtures

• Fire suppression systems

B. Do not obstruct:

• Airflow

• Access aisles

• Equipment maintenance zones

3.04 ELEVATION AND CLEARANCES

A. Install at elevation coordinated with shelter design, typically:

• 8′-0″ to 8′-6″ AFF

B. Maintain:

• Minimum 12 inches above cabinet tops

• Clearance from HVAC and ceiling systems

3.05 CABLE MANAGEMENT INSTALLATION

A. Install radius drop-out fittings at:

• Each cabinet drop

• All directional transitions

B. Ensure:

• No exposed sharp edges

• Compliance with cable bend radius requirements

3.06 GROUNDING AND BONDING

A. Bond all ladder rack sections to maintain electrical continuity.

B. Provide bonding across all joints.

C. Connect cable rack system to the Interior Master Ground Bar (MGB) as shown on grounding plans.

D. Verify grounding continuity after installation.