This addendum to the Brigham Road Water and Sewer Replacements contract documents issued by the Orange Water and Sewer Authority modifies the original bidding documents dated September 14, 2026. The project scope encompasses replacement of approximately 560 linear feet of existing 8-inch AC water mains with 370 linear feet of 8-inch ductile iron pipe and 150 linear feet of 2-inch PVC pipe, along with associated appurtenances, pavement, curb, and gutter replacement. The sanitary sewer component includes replacement of 1,480 linear feet of existing mains with approximately 325 linear feet of 16-inch ductile iron and 1,170 linear feet of 16-inch PVC sanitary sewer pipe, including three manhole replacements and four new manhole installations. A mandatory pre-bid meeting was held on September 30, 2026, at 2:00 p.m., with bids due October 20, 2026, at 2:00 p.m. Substantial completion is required within 180 calendar days from Notice to Proceed (anticipated April 2027), with final completion within 30 additional calendar days (anticipated May 2027). Liquidated damages are assessed at $1,500 per day for both substantial and final completion milestones.
Key modifications include deletion of Allowance A3 (Town of Chapel Hill Street Cut Allowance) and an increase in the estimated quantity of Asphalt Repair (Mill and Overlay) to 1,860 square yards. The addendum adds new requirements for water main testing and acceptance that exceed AWWA C651 standards, mandating pressure testing, disinfection, and day-one and day-two bacteriological testing before acceptance. New specification Section 33 01 30.72 addresses Cured-In-Place Pipe (CIPP) relining for sewers, with detailed requirements for product standards, quality assurance, installation methods, and field quality control. Pavement repair dimensions have been modified to conform to the Town of Chapel Hill Detail T-7.01. The asphalt open cut and replacement measurement maximum pay width was revised from six feet to five feet in the measurement specifications. Additional provisions address property coordination, tree identification and removal procedures, utility location responsibilities, existing structure protection, and specialized requirements for installations on private residential properties within easements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Brigham Road Water and Sewer Advertisement for Bids.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CIP NO.: 375-01 and 276-61
PROJECT: Brigham Road Water and Sewer Replacements
DATE: October 5, 2026
SECTION: 00 91 01 - Addenda
Orange Water & Sewer Authority 00 91 01 - 1 Brigham Road Water and Sewer Replacements
DOCUMENT 00 91 01
ADDENDA
ADDENDUM NUMBER 01
OWASA CIP NUMBER: 375 – 01 and 276 – 61
OWNER: ORANGE WATER AND SEWER AUTHORITY
ENGINEER: Freese and Nichols, Inc.
TO: All Prospective Bidders
This Addendum forms a part of the Contract Documents and modifies the Bidding Documents dated
September 14, 2026, with amendments and additions noted herein below.
Acknowledge receipt of this Addendum in the space provided in the Bid form. Failure to do so may disqualify the Bidder.
This Addendum consists of thirty-two (32) pages. This Addendum Includes:
• Pages 1 through 2 of this Addendum;
• Revised pages 8 through 12 of Section 00 41 44, which should completely replace the pages in your bid package;
• Revised Pages 7 through 10 of Section 01 29 01;
• Revised pages 1 through 4 of Section 01 35 00;
• Added pages 1 through 12 of Section 33 01 30.72;
• Four (4) pages of the Pre-Bid Meeting Minutes; and
• Revised Sheet DT-4 reflecting revisions to Detail 1.
PRE-BID MEETING MINUTES:
1. See the pages appended to this addendum for the mandatory pre-bid meeting minutes.
CHANGES TO THE SPECIFICATIONS:
1. Section 00 41 44 “Proposal – Unit Price”
a. DELETE Allowance A3 – Town of Chapel Hill Street Cut Allowance.
b. INCREASE estimated quantity of line item 31 – Asphalt Repair (Mill and Overlay) to
1,860 Square Yards
DATE: October 6, 2026
SECTION: 00 91 01 - Addenda
Orange Water & Sewer Authority 00 91 01 - 2 Brigham Road Water and Sewer Replacements
2. Section 01 29 01 “Measurement and Basis for Payment”
a. DELETE Paragraph 1.05 – C. The Town of Chapel Hill Street Cut Allowance has been removed from the current contract.
b. REVISE Paragraph 1.06 – L – 1. The measurement for Asphalt Open Cut and
Replacement (Trench Repair) shall be determined by measuring along the centerline of the pipe times a maximum pay with of five (5) feet.
c. REVISE Paragraph 1.06 – M – 2. The specified depth for Asphalt Repair (Mill and
Overlay) shall be 1.5-iches.
3. Section 01 35 00 “Special Procedures”
a. ADD the following paragraph 1.04:
1.04 WATER MAIN TESTING AND ACCEPTANCE
A. OWASA requirements exceed AWWA C651. Compliance with AWWA C651 alone does not constitute acceptance of installed water pipe.
B. All water main pipe installed, regardless of length installed, shall successfully complete each of the following in accordance with Section 02510 “Water
Distribution”:
1. Pressure testing, including repair and retesting as necessary until the installed pipe passes.
2. Disinfection.
3. Day 1 bacteriological testing.
4. Day 2 bacteriological testing.
C. The required sequence is pressure testing, disinfection, Day 1 bacteriological testing, and Day 2 bacteriological testing. No installed water pipe shall be accepted or placed into service until all required testing has passed and has been accepted by OWASA.
4. ADD specification section 33 01 30.72 “Relining Sewers - Cured-In-Place Pipe” to the Contract
Documents.
CHANGES TO THE DRAWINGS:
1. DRAWING SHEET DT-4
a. REVISE Detail 1 by removing the pavement repair dimensions shown. Pavement repair shall be performed in accordance with the modified Town of Chapel Hill Detail T-7.01 shown on Sheet DT-3, which governs the required pavement repair dimensions.
-END OF DOCUMENT-
Proposal – Unit Price Contract Bid Form Brigham Road Water
00 41 44-8 and Sewer Replacement Orange Water & Sewer Authority
BID FORM – OWASA CIP #375-01
BRIGHAM ROAD WATER LINE REPLACEMENT
NOTE TO BIDDERS: DO NOT REMOVE THIS BID FORM
FROM THE CONTRACT DOCUMENTS
UNIT PRICE BID CONTRACT
Item
No.
Description Units
Estimated
Quantity Bid Unit Price Extended Total
Items in Base Bid (excluding Allowances) per Section 01 29 01 "Measurement and Basis for Payment"
8" Class 350 DIP Water Main, Restrained Joint
LF 370
2 2" SDR 11 PVC Water Line LF 150
3 Transition to 2" Water Line EA 1
4 8" Gate Valve with Valve Box EA 5
5 Ductile Iron Bends and Fittings LBS 920
6 Blow Off Assembly EA 1
Connection to Existing 8" Water
Main
EA 2
¾-inch Single Service Meter – Short
Side
EA 4
Pipe Abandonment with Low-
Density Cellular Grout
CY 7.2
Asphalt Open Cut and Replacement
(Trench Repair)
SY 350
11 Valve Abandonment EA 3
12 Traffic Control LS 1
13 Curb Inlet Protection EA 4
14 Synthetic Log LS 1
15 Trench Borrow (Select Fill) CY 100
16 Stone Bedding Material CY 50
17 Undercut Excavation CY 75
18 Rock Excavation CY 50
Total Base Bid Items Amount (Sum of Extended Amounts for each Base Bid Line
Item)
Allowances in Base Bid per Section 01 23 10 "Alternates and Allowances"
A1 Contingency Allowance LS 1 - $50,000
00 41 44-9 and Sewer Replacement Orange Water & Sewer Authority
Item
No.
Description Units
Estimated
Quantity Bid Unit Price Extended Total
A2 Town of Chapel Hill Permit Fee
Allowance
LS 1 - $9,500
Total Allowance Amount (Sum of Extended Amounts for Each Allowance Line
Item)
Subtotal – CIP #375-01 Base Bid with Allowances $
Bidder acknowledges that (1) each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and (2) estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit
Price Bid items shall be based on actual quantities, determined as provided in the Contract Documents.
TOTAL UNIT PRICE BID for the Project described in Sub-Article 5.01, complete as indicated by the Contract
Documents (in words and numerals):
Dollars and Cents ($ )
00 41 44-10 and Sewer Replacement Orange Water & Sewer Authority
BID FORM – OWASA CIP #276-61
BRIGHAM ROAD SEWER REPLACEMENT
NOTE TO BIDDERS: DO NOT REMOVE THIS BID FORM
FROM THE CONTRACT DOCUMENTS
UNIT PRICE BID CONTRACT
Item
No.
Description Units
Estimated
Quantity
Bid Unit
Price Extended Total
Items in Base Bid (excluding Allowances) per Section 01 29 01 "Measurement and Basis for Payment"
Mobilization/Demobilization, (Max
5% of Total Base Bid)
LS 1
20 Temporary Bypass Pumping LS 1
21A 16" C900 PVC Sanitary Sewer Main
(0'-6' of Cover)
LF 970
21B 16" C900 PVC Sanitary Sewer Main
(6'-9' of Cover)
LF 40
22A 4' ID Manhole, All Depths, Watertight
EA 4
22B 4' ID Manhole, All Depths EA 1
22C 5' ID Manhole, All Depths EA 2
23 Stainless Steel Vent Piping VF 11
24 Anti-Flotation Collar EA 25
25 Connect to Existing SSMH 88542 EA 1
Abandon Existing Sanitary Sewer
Manhole
EA 2
Remove Existing Sanitary Sewer
Manhole
EA 3
Remove Existing 12" VCP Sewer
Main
LF 750
Pipe Abandonment with Low-
Density Cellular Grout
CY 40
Asphalt Open Cut and Replacement
(Trench Repair)
SY 210
31 Asphalt Repair (Mill and Overlay) SY 1,860
32 Trench Borrow (Select Fill) CY 80
33 Stone Bedding Material CY 30
34 Undercut Excavation CY 20
35 Rock Excavation CY 20
00 41 44-11 and Sewer Replacement Orange Water & Sewer Authority
Item
No.
Description Units
Estimated
Quantity
Bid Unit
Price Extended Total
36 Erosion and Sediment Control Plan LS 1
37 Project Sign EA 1
Remove and Replace Concrete
Drive (1404 Brigham Road)
SY 115
Pavement Removal and
Replacement
SY 385
40A 1407 Brigham Road Special
Conditions
LS 1
40B 1404 Brigham Road Special
Conditions
LS 1
40C 1402 Brigham Road Special
Conditions
LS 1
40D 815 Churchill Drive Special
Conditions
LS 1
40E 817 Churchill Drive Special
Conditions
LS 1
40F 821 Churchill Drive Special
Conditions
LS 1
40G 823 Churchill Drive Special
Conditions
LS 1
40H 825 Churchill Drive Special
Conditions
LS 1
Subtotal - CIP #276-61 Base Bid with Allowances $
TOTAL BASE BID (CIP # 375-01 and # 276-61) with Allowances $
Alternates to be considered for inclusion per Section 01 23 10 "Alternates and Allowances"
Alt-I 16" Class 350 DIP Sanitary Sewer
Main (0'-6' of Cover)
LF 325
Alt-I CIPP Lining of 16” DIP Sanitary
Sewer Main
LF 325
Total ADD or DEDUCT for Alternate-I Bid Items Amount (Sum of Extended
Amounts for Each Allowance Line Item)
Alt-II 16” Stainless Steel Sanitary Sewer
Main (0'-6' of Cover)
LF 325
Total ADD or DEDUCT for Alternate-II Bid Items Amount (Sum of Extended
Amounts for Each Allowance Line Item)
For bid evaluation purposes, the Owner will determine the lowest responsive and responsible Bidder based on the lowest total of either (1) Total Base Bid plus Alternate No. 1 or (2) Total Base Bid plus Alternate No. 2. Orange Water
00 41 44-12 and Sewer Replacement Orange Water & Sewer Authority and Sewer Authority reserves the right to select either Alternate No. 1 or Alternate No. 2 and will determine the lowest evaluated bid based on the combination that is in the best interest of the Project.
Bidder acknowledges that (1) each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and (2) estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit
Price Bid items shall be based on actual quantities, determined as provided in the Contract Documents.
TOTAL UNIT PRICE BID PLUS ALTERNATIVE 1 for the Project described in Sub-Article 5.01, complete as indicated by the Contract Documents (in words and numerals):
TOTAL UNIT PRICE BID PLUS ALTERNATIVE 2 for the Project described in Sub-Article 5.01, complete as indicated by the Contract Documents (in words and numerals):
Bidder
(Print Name)
Bidder
(Signature)
Measurement and Basis for Payment
Orange Water & Sewer Authority 01 29 01 - 7 Brigham Road Water and Sewer Replacements
1.05 MEASUREMENT AND BASIS FOR PAYMENT FOR ALLOWANCES – CIP 375-01
A. Item A1 – Contingency Allowance
1. This allowance shall cover the cost of any items not included under other pay items that may arise from unforeseen circumstances or conditions. The Contractor must obtain approval from the Engineer and Owner for use of this contingency allowance prior to any Work associated with the contingency allowance being performed.
B. Item A2 – Town of Chapel Hill Permit Fee Allowance
1. This allowance is intended to cover the cost of obtaining any required permits from the Town of Chapel Hill other than street cut permits. This pay item will allow for the reimbursement of costs which have been paid by the Contractor to the Town of
Chapel Hill. The Contractor must supply receipts for review and approval by the
Engineer. Payment will be for the actual cost as shown on submitted invoices, along with a 5% markup to cover the Contractor’s labor associated with coordination of the work.
C. Item A3 – Town of Chapel Hill Street Cut Allowance – REMOVED FROM PROJECT MANUAL
1. This allowance will cover the cost of obtaining street cut permits from the Town of
Chapel Hill, including any street cut fees levied. This pay item will allow for the reimbursement of costs which have been paid by the Contractor to the Town of
Chapel Hill. The Contractor must supply receipts for review and approval by the
Engineer. Payment will be for the actual cost as shown on submitted invoices, along with a 5% markup to cover the Contractor’s labor associated with coordination of the work.
1.06 MEASUREMENT AND BASIS FOR PAYMENT FOR BASE ITEMS – CIP 276-61
A. Item 19 – Mobilization/Demobilization:
1. Measurement for payment is on a lump sum basis and shall not exceed 5% of the total bid amount. Payment for mobilization will be based on the earned value of Work completed.
2. Payment for mobilization shall be 50% of the total at the beginning of the project, with the remaining 50% paid by percentage based on the earned value of Work completed.
3. Mobilization/Demobilization costs are intended to assist with the cost of bonds, insurance, utility investigations, construction staking, construction signage, mobilization of equipment, and the cost of operations, but is not intended to cover the full amount of these costs. Cost in excess of the allowable mobilization percentage shall be included in other unit prices items as needed.
B. Item 20 – Temporary Bypass Pumping
1. Measuring for payment is on a lump sum basis for the entire bypass pumping operation.
CURRENT CONTRACT
Orange Water & Sewer Authority 01 29 01 - 8 Brigham Road Water and Sewer Replacements
2. Temporary bypass pumping will be paid for at the contract lump sum price and will include all labor and materials necessary to bypass the existing gravity sewer for the duration of construction activities. This item will include all efforts involved in coordination, mobilization, setup, and breakdown of bypass pumping operations as described in Section 02530, 3.5 – Bypass Pumping. Payment for temporary bypass pumping shall be 50% of the total at the beginning of the project, with the remaining
50% paid by percentage based on the earned value of Work completed
C. Item 21 – 16” Sanitary Sewer, All Depths and Materials
1. Measurement for payment shall be per linear foot of Class 350 Ductile Iron Pipe or
C900 PVC Pipe installed through bends, fittings, valves, and manholes.
2. The accepted quantities of sanitary sewer pipe will be paid for at the contract unit price per linear foot of the various types, depths, and size pipe specified, complete in place. This price shall include labor, equipment, materials, trench excavation
(excluding select fill and rock), shoring, or use of trench box, support and bracing of other existing utilities as needed, installation, dewatering of trenches, backfilling, compaction, testing of failed trenches, disposal of excess material, pressure testing, cleaning, pre-construction video and other graphic documentation of existing conditions, and all other work incidental to the complete installation of the mains in accordance with these specifications. The cost must also include metallic detection tape.
D. Item 22 – XX’ ID Manhole, All Depths
1. Manholes will be measured by the number of each size and type of manhole installed.
2. Manholes will be paid for at the contract unit price, complete in place, per manhole for the type and size specified, complete in place. This price shall include all labor, equipment, and materials necessary for installing the manhole, rim and cover, footing
(if applicable), backfilling, testing, sterilizing and all other work incidental to the complete installation of the manhole, in accordance with the specifications.
E. Item 23 – Stainless Steel Vent Piping
1. Measurement for payment for Vent Piping will be per vertical foot of stainless steel piping installed at the contract unit price.
2. Vent piping will be paid for at the contract unit price, complete in place. This price will include all labor, equipment and materials necessary for installation of the steel vent pipe in accordance with Section 02530 of the specifications and Detail 532.05 of the contract drawings. The unit price provided will also include the cost of coating both inside and outside the steel pipe.
F. Item 24 – Anti-Flotation Collar
1. Anti-Flotation Collars will be measured by the number of each installed.
2. Anti-Flotation Collars will be paid for at the contract unit price, complete in place. This price must include all labor, equipment, and materials necessary for installing and setting the Anti-Flotation Collar as shown on Detail 2 of Sheet DT-11 of the contract drawings. Costs for the Neoprene Pad and stainless-steel anchor bolts are to be
Orange Water & Sewer Authority 01 29 01 - 9 Brigham Road Water and Sewer Replacements included in price of the anti-flotation collar. Stone bedding will be considered a separate pay item.
G. Item 25 – Connection to Existing Sanitary Sewer
1. Connections to existing sanitary sewer mains will be measured by the number of each connection made as shown on the drawings.
2. Payment for connections to existing sewer main shall include all materials, equipment, and labor necessary to locate the existing sewer main, connect the existing sewer main to the proposed sewer manholes including, but not necessarily limited to excavation of trenches, backfilling trenches as required, disposal of surplus excavated materials, removal of existing fittings, and any specialty items required to connect to the existing system. Any special fittings and/or blocking required to make the connection are included in the cost of this item. Applies to all connections.
H. Item 26 – Abandon Existing Sanitary Sewer Manhole
1. Measurement and basis for payment will be for each Sanitary Sewer Manhole abandoned as shown on the contract drawings.
2. Abandonment of existing sanitary sewer manholes will be paid for at the contract unit price per manhole abandoned. The unit price must include all labor, materials and equipment required to abandon the existing sewer manhole in place as shown on
Detail 536.05. This price shall include, but is not necessarily limited to, removal of the upper portion of the manhole within 36 inches of the proposed finished grade, or as determined by OWASA’s Engineer, #57 stone dumped into the manhole, the stone vibrated to consolidate the stone with the remainder of void or space between the top of the manhole and the finished subgrade backfilled as follows. Backfill with #57 stone and consolidate. The unit price must include filter fabric to be placed over the stone and suitable material of a compactable nature which will be placed over the concrete manhole pad for all manholes to be abandoned outside roadway right of ways.
I. Item 27 – Remove Existing Sanitary Sewer Manhole
1. Measurement and basis for payment will be for each Sanitary Sewer Manhole removed as shown on the contract drawings.
2. Removal of existing sanitary sewer manholes will be paid for at the contract unit price per manhole removed. The unit price must include all labor, materials, and equipment required to completely remove and dispose of the existing sewer manhole.
J. Item 28 – Remove Existing 12” VCP Sewer
1. Removal of existing 12” VCP Sewer will be measured by the linear foot of existing VCP sewer removed.
2. Payment for this item will cover the cost of all labor and equipment necessary for removal and disposal of the existing 12” VCP Sewer as shown on the contract drawings.
Orange Water & Sewer Authority 01 29 01 - 10 Brigham Road Water and Sewer Replacements
K. Item 29 – Pipe Abandonment with Low Density Cellular Grout
1. Measurement and payment shall be by the cubic yard of cellular grout required to fill the existing pipe. Vendor of the low-density cellular grout shall provide tickets which will be supplied to the Engineer as part of the pay application.
2. Payment of this item shall include excavation around existing fittings, valves, valve boxes, manholes, and any other appurtenance associated with the line being abandoned and filling the pipe and void spaces with flowable fill. Payment shall also include all materials, labor, and equipment as may be required for the execution of this work, and disposal of any removed items.
L. Item 30 – Asphalt Open Cut and Replacement (Trench Repair)
1. Measurement for Asphalt Open Cut and Replacement (Trench Repair) repair shall be per square yard of pavement patch installed. The measurement for this pay item shall be determined by measuring along the centerline of the pipe times a maximum pay width of six (6) feet.
2. Payment for Asphalt Open Cut and Replacement (Trench Repair) shall be made at the contract unit price per square yard of pavement patch installed including, but not limited to, cutting and removing existing pavement, hauling, properly disposing of materials, furnishing and installing base course, intermediate course, surface course, re-marking of pavement lines, replacing traffic sensors, testing of all asphalt and subbase material, and shall be full compensation for pavement repair per the Town of
Chapel Hill detail included in the contract drawings.
M. Item 31 – Asphalt Repair (Mill and Overlay)
1. Measurement for Asphalt Milling and Overlay shall be made per square yard of pavement milled and overlaid. The measurement for this pay item shall be determined by the actual area of pavement milled and overlaid as directed by the Engineer and accepted by the Owner.
2. Payment for Asphalt Milling and Overlay shall be made at the contract unit price per square yard of pavement milled and overlaid. The unit price shall include, but not be limited to, milling the existing asphalt surface to the specified depth of 1.5-inches, loading, hauling and disposal of milled materials, cleaning and preparation of the milled surface, furnishing and applying tack coat, furnishing, placing and compacting asphalt overlay, adjustment of pavement markings as required, and all labor, equipment, tools, materials, and incidentals necessary to complete the Work.
N. Item 32 – Trench Borrow (Select Backfill)
1. Offsite Trench Borrow material will be measured and paid for paid for based upon the cubic yards of select backfill material provided for areas where the excavated material is unsuitable and does not meet the requirements of the Contract Documents.
2. This item will cover the cost of delivery, handling, placement, compaction, testing, and any other costs associated with Offsite trench borrow material brought in from offsite.
The Contractor must obtain approval from the Engineer and Owner for use of Trench
Borrow prior to any Work associated with this item being performed. The unit price for five (5) feet.
CIP NO.: 276-61
DATE: September 30, 2026
Special Procedures Brigham Road Water
Orange Water & Sewer Authority 01 35 00 - 1 and Sewer Replacements
DOCUMENT 01 35 00
SPECIAL PROCEDURES
1.00 GENERAL
1.01 SUMMARY
A. This section describes requirements for maintaining, protecting, and restoring the easement during construction, including landscaping features, trees, fences, sheds, retaining walls, and utilities.
B. Work includes:
1. Coordination with the Engineer and Owner prior to removal of any landscape or site features.
2. Identification and flagging of trees proposed for removal.
3. Field walk procedures with the Owner and Engineer.
4. Requirements for handling existing fences, sheds, and similar structures.
5. Replanting and relocation activities outside the easement as part of restoration.
6. Responsibilities for locating, protecting, and maintaining existing electrical and gas utilities.
7. Restrictions on communication with Property Owners.
8. Water main testing and acceptance requirements that exceed the minimum requirements of AWWA C651.
1.02 EASEMENT MAINTENANCE COORDINATION
A. General Requirements
1. The Contractor shall maintain the easement area in a safe, orderly, and accessible condition throughout construction.
2. No landscape feature, structure, or utility within the easement shall be removed, disturbed, or altered without prior coordination and written approval from both the
Engineer and the Owner.
B. Coordination Requirements
1. All communication, notifications, and coordination with individual Property Owners must be routed exclusively through OWASA. The Contractor shall not contact Property
Owners directly unless specifically authorized in writing by OWASA.
2. The Contractor must provide the Engineer and Owner with a minimum of seven (7) calendar days’ notice prior to any proposed landscaping removals or field reviews. Work shall not proceed until all required approvals have been obtained.
1.03 SUBMITTALS
Orange Water & Sewer Authority 01 35 00 - 2 and Sewer Replacements
A. Documentation of proposed removals, including marked plans or annotated field maps.
B. The Contractor must maintain documentation of all coordination efforts, approvals, and field walk outcomes. Documentation shall be made available to the Engineer upon request.
1.04 WATER MAIN TESTING AND ACCEPTANCE
A. OWASA requirements exceed AWWA C651. Compliance with AWWA C651 alone does not constitute acceptance of installed water pipe.
B. All water main pipe installed, regardless of length installed, shall successfully complete each of the following in accordance with Section 02510 “Water Distribution”:
1. Pressure testing, including repair and retesting as necessary until the installed pipe passes.
2. Disinfection.
3. Day 1 bacteriological testing.
4. Day 2 bacteriological testing.
C. The required sequence is pressure testing, disinfection, Day 1 bacteriological testing, and
Day 2 bacteriological testing. No installed water pipe shall be accepted or placed into service until all required testing has passed and has been accepted by OWASA.
2.00 PRODUCTS (NOT APPLICABLE)
3.00 EXECUTION
3.01 TREE IDENTIFICATION AND FLAGGING
A. Prior to any tree removal activities, the Contractor shall clearly identify all trees proposed for removal within the limits of disturbance.
B. Each tree proposed for removal shall be flagged using high-visibility tape approved by the
Engineer. Flagging shall be placed at eye level and remain in place until removal is completed.
C. The Contractor shall notify the Engineer and Owner once all trees proposed for removal have been flagged.
D. No tree removal shall occur prior to verification and approval during the field walk.
3.02 FIELD WALK AND APPROVAL
A. After flagging is complete, the Contractor shall coordinate a field walk with the Owner and
Engineer to review all proposed landscape removals.
B. Only trees and landscape features explicitly approved during the field walk may be removed.
C. Document final decisions and maintain records in accordance with Section 01 33 00 –
Document Management for the duration of the project.
3.03 EXISTING FENCES, SHEDS, AND SITE STRUCTURES
Orange Water & Sewer Authority 01 35 00 - 3 and Sewer Replacements
A. Identification and Protection
1. Identify all existing fences, sheds, outbuildings, gates, and similar structures within or adjacent to the work area.
2. Protect all such structures from damage unless removal is specifically approved by the
Owner and Engineer.
B. Removal Requirements
1. No fence, shed, or similar structure shall be removed, relocated, or modified without prior written approval.
2. If removal is approved, coordinate timing and access requirements through OWASA.
3. Salvage, storage, or disposal procedures shall follow Owner direction.
C. Damage and Restoration
1. Any damage to fences, sheds, or other structures not approved for removal shall be repaired or replaced at the Contractor’s expense.
2. Restoration shall match existing materials, construction quality, and appearance unless otherwise directed.
3.04 REPLANTING TREES AND RELOCATION OF SITE FEATURES OUTISDE THE EASEMENT
A. General
1. As part of final restoration, the Contractor shall replant trees and relocate certain existing site features outside the permanent easement limits where directed by the
Owner and Engineer.
2. Work may include relocation of sheds, small outbuildings, retaining walls, or similar structures when necessary to restore property functionality or aesthetics.
B. Tree Species and Quality
1. Replacement trees shall be nursery grown, healthy, and free of defects.
2. Species shall match Owner direction and may include native or ornamental varieties appropriate to the site.
3. Minimum size requirements shall be as shown on the Drawings or as directed by the
Owner.
4. Provide backfill, mulch rings, staking (if required), and initial watering at the time of installation.
C. Relocation of Sheds and Outbuildings
1. The Contractor shall make reasonable efforts to install the sewer in a manner that avoids impacts to existing sheds and outbuildings located within the easement.
2. If avoidance is not feasible due to alignment, depth, access, or safety constraints, the
Contractor shall follow the relocation procedures described herein.
Orange Water & Sewer Authority 01 35 00 - 4 and Sewer Replacements
3. When relocation is required, carefully dismantle and remove the structures as needed.
After removing the structures, demolish any foundations or pads remaining in the easement.
4. Prepare new foundations or pads outside of the easement as directed by the Owner and
Engineer.
3.05 EXISTING UTILITIES
A. Utility Location Responsibilities
1. The Contractor is fully responsible for locating all existing electrical, gas, and other buried utilities within and adjacent to the easement prior to beginning work.
a. Note that the existing gas and electrical lines serving the greenhouse behind 825
Churchill Drive are shown on the drawings but are not shown in the profile.
2. Utility locating shall include coordination with NC 811, utility owners, and field verification methods such as potholing where required.
B. Protection and Maintenance
1. The Contractor shall protect all existing utilities from damage throughout construction.
2. Any utility damaged due to Contractor operations shall be repaired immediately at the
Contractor’s expense.
3. Maintain safe clearances and support exposed utilities as required.
C. Coordination
1. Notify the Engineer and Owner immediately if unknown utilities are encountered.
2. Do not disturb electrical or gas utilities without explicit approval from the utility owner.
3.06 PROTECTION OF REMAINING LANDSCAPE FEATURES
A. Install temporary fencing, barriers, or other protective measures as required to prevent damage.
B. Maintain protection throughout construction.
C. Restore or replace any damaged landscape features at no additional cost to the Owner.
END OF SECTION
Relining Sewers – Cured-In-Place-Pipe Brigham Road Water
Orange Water & Sewer Authority 33 01 30.72 - 1 and Sewer Replacements
DOCUMENT 33 01 30.72
RELINING SEWERS - CURED-IN-PLACE PIPE
1.00 GENERAL
1.01 SUMMARY
A. Provide all labor, material and equipment necessary for the rehabilitation of sanitary sewer mains and service connections by the installation of a flexible tube saturated with a thermosetting resin which is either inverted or pulled into the existing wastewater main.
The resin is cured using either hot water under hydrostatic pressure, or by steam pressure, or UV light, within the tube. The Cured-In-Place-Pipe (CIPP) will be continuous and tight fitting.
1.02 STANDARDS
A. The applicable provisions of the following standards shall apply as if written here in their entirety. Piping and fittings shall be in full compliance with the applicable standards and specifications for each type of pipe involved. Pipe may be rejected for failure to comply with any requirement of this Section.
1. ASTM International (ASTM) Standards:
ASTM F1216
Standard Practice for Rehabilitation of Existing Pipelines and
Conduits by the Inversion and Curing of a Resin Impregnated
Tube
ASTM F1743
Rehabilitation of Existing Pipelines and Conduits by Pulled-in-
Place Installation of Cured-in-Place Thermosetting Resin Pipe
(CIPP)
ASTM D5813 Cured In Place Thermosetting Resin Sewer Pipe
ASTM D638 Test Method for Tensile Properties of Plastics
ASTM D790
Test Method for Flexural Properties of Unreinforced and
Reinforced Plastics and Electrical Insulating Materials
ASTM D2990
Test Method for Tensile, Compressive, and Flexural Creep and
Creep-Rupture of Plastics
1.03 SUBMITTALS
A. Submittals shall be in accordance with Section 01 33 00 “Document Management” and shall include:
1. Shop Drawings:
a. Flow control implementation plan.
b. Odor control plan.
Orange Water & Sewer Authority 33 01 30.72 - 2 and Sewer Replacements
c. Quality Control Plan that includes a checklist documenting each critical step in the tube’s resin saturation, unhardened CIPP tube’s insertion into the subject reach of pipe, hardening process of the CIPP and a list of personnel and defined responsibilities during the installation process.
2. Product Data:
a. Method of rehabilitation and restoration of existing service connections.
b. Diameter, length, wall thickness and all structural design calculations for each sewer main segment. All design calculations shall be sealed by a professional engineer licensed in the state where the Project is located.
c. Type of resin or pipe material.
d. Method and materials for sealing liner at manholes.
e. Pre and Post-Installation CCTV.
f. Documentation of any corrective actions taken to address any defects. This will include stationing.
1.04 QUALITY ASSURANCE
A. For a product to be considered commercially proven, a minimum of ten successful wastewater collection system projects for host pipes equal to or greater than the diameter of the largest pipe in this Project and in excess of 100,000,00 linear feet total shall be performed in the U.S. and documented to the satisfaction of the Owner to assure commercial viability. All successful projects must be equal to or larger in host pipe diameter to that which is included within this Project. The manufacturing and installation processes shall operate under a quality management system which is third party certified to ISO 9000 or other recognized standards. Proof of certification shall be required for approval.
B. For an installing company to be considered as commercially proven, the installer must satisfy all insurance, financial, and bonding requirements of the Owner, and must have had at least 5 years active experience in the commercial installation. In addition, the installer must have successfully installed at least 500,000 linear feet of a cured-in-place product in wastewater collection systems in the U.S. for host pipe equal to or greater than the diameter of the largest pipe in this Project. Acceptable documentation of these minimum installations must be submitted to the Owner. Installer’s project manager assigned to this
Project must have a minimum of 5 years of CIPP installation experience with the exact product and installing company intended for use with this bid.
1.05 SYSTEM DESCRIPTION
A. If the inversion method is used, the tube is installed by utilizing an inversion standpipe and a hydrostatic head or air pressure. The resin is cured by circulating hot water or introducing controlled steam within the tube. If the tube is pulled into the existing wastewater main, it is placed flat and pressed out against the old pipe by inverting a calibrating hose through the center of the liner using water pressure. The resin is cured by circulating hot water through the liner. When cured and complete, the installed pipe shall extend from one manhole to the next in a continuous, tight-fitting, corrosion resistant, watertight pipe within a pipe.
B. Provide cleaning, televising, and flow control as specified herein.
Orange Water & Sewer Authority 33 01 30.72 - 3 and Sewer Replacements
2.00 PRODUCTS
2.01 COMPONENTS
A. Cured In Place Pipe:
1. Liner Hose:
a. Inversion Flexible Felt Tube: The tube shall consist of one or more layers of flexible needled felt material or an equivalent non-woven or woven material capable of carrying resin and withstanding installation pressures and curing temperatures. The felt tubular material shall be lined on one side with a translucent waterproof coating such as polyurethane or polyvinylchloride (PVC), and be fully impregnated with a liquid thermosetting polyester resin and catalyst system compatible with the inversion process. The resin must be able to cure in the presence of water and the initialization temperature for cure shall be less than 180 deg F (82.2 deg C). The tubing shall be properly sized to the diameter of the wastewater pipe and the length of the wastewater main to be rehabilitated, able to stretch to fit irregular pipe sections and bends, and of relatively uniform thickness.
b. Pulled-In Felt Hose Fabrication: The construction of the lining hose shall be as follows:
1). Resin absorbing first inner layer of polyester felt.
2). Impermeable second layer of thin film polyester.
3). Resin absorbing outer layer or layers of polyester felt.
c. The lining hose shall be capable of carrying resin, withstanding installation pressures and curing temperatures, and be able to stretch to fit irregular pipe sections and bends. The lining hose shall be prefabricated to the appropriate diameter and thickness and shall be cut to the length necessary for the line being rehabilitated.
2. Properties: The cured pipe material shall meet the minimum chemical resistance requirements of ASTM F1216, Appendix 2, and shall conform to the minimum structural standards listed below:
Cured Pipe Material Test Test Method Standard Results
Flexural Stress ASTM D790 4,500 psi
Flexural Modulus of Elasticity ASTM D790 215,000 psi
3. Tube Design:
a. The tube shall be designed in accordance with ASTM F1216 Appendix 1. The design shall be based on a partial-deteriorated gravity pipe condition.
b. Tube must be manufactured in the USA.
c. Tube must be marked for distance at regular intervals and include manufacturer’s name and any other identifiers such as a batch code.
d. Tube design shall withstand the following service requirements:
Tube Design - Service Requirements
Orange Water & Sewer Authority 33 01 30.72 - 4 and Sewer Replacements
Tube Design - Service Requirements
Soil Density 120 lb./cu. ft.
Live Loading 350 psi
Maximum Depth of Soil Cover 15 feet
Maximum Ground Water Level 5 feet
Ovality 2%
Modulus of Passive Soil Reaction 1,000 psi
Minimum Safety Factor 2
Creep Retention Factor 50%
Minimum Service Life 50 years
e. CIPP Wall Thickness: Contractor shall determine the required CIPP design wall thickness for each installation in accordance with ASTM F1216 and the design criteria specified herein. Submit calculations sealed by a Professional Engineer licensed in North Carolina. The calculated thickness shall be considered the minimum design thickness for acceptance unless a greater minimum thickness is otherwise indicated in the Contract Documents.
4. Allowable Hydrostatic Head: The liner shall have an allowable hydrostatic head which is greater than the depth of the host pipe invert. The allowable hydrostatic head shall be determined for each size of liner as follows:
a. The instantaneous critical buckling pressure of typical installed liner (having the physical properties specified herein) shall be measured by actual hydrostatic tests performed under the supervision of a licensed professional engineer. Engineer shall determine the allowable hydrostatic head by reducing the instantaneous buckling pressure with respect to the predicted installation affects, ovality factor, maximum dimension ratio and long-term (50-year) physical properties.
b. A sealed engineer’s report showing the analysis and determination of allowable hydrostatic head shall be provided to the Owner for each size of liner used.
2.02 SOURCE QUALITY CONTROL
A. Cured In Place Testing: While the Owner may perform testing at its own expense, Owner may also require the Contractor to provide one test sample for each design segment in according to the following restrained sampling method:
1. Materials: The sample form pipe shall be PVC pipe (SDR-25, C-900). Internal preparation should be made to the PVC form pipe using a release agent such as PVA
(polyvinyl alcohol solution) to facilitate sample removal without damage.
Cured-In-Place-
Pipe Thickness
Min. PVC
Pipe Length
3 to 7.5 mm 12”
9 mm & greater 20”
Orange Water & Sewer Authority 33 01 30.72 - 5 and Sewer Replacements
2. During the inversion or pulling of the cured-in-place-pipe, place the section of PVC pipe in a manhole or other access point.
3. Invert or pull the cured-in-place-pipe through the PVC pipe. An identification number assigned by the Engineer or Owner’s representative shall be marked on the outside of the PVC pipe.
4. The cured-in-place-pipe shall then be cured and cooled using standard methods.
5. After the cured-in-place-pipe has cooled and has been drained, cut at both sides of the
PVC pipe and remove the restrained sample. Trim the sample to the proper size. Label the sample with the proper I.D. number and submit for testing.
6. Tests for compliance with this Section shall be made according to the applicable ASTM specification. A certificate of compliance with this Section shall be provided by the manufacturer upon request for all material furnished under this Section.
B. Rejection: Failure to meet or exceed any of the requirements of ASTM F1216 based on the design parameters outlined in the Drawings and Specifications shall be cause for rejection.
3.00 EXECUTION
3.01 PREPARATION
A. Contractor shall plan its Work after review of previous television inspection tape and reports prior to commencement of the actual liner inversion process. All point repairs must be satisfactorily completed, equipment and material mobilized, and the Owner’s representative shall be informed of the work schedules for liner installations.
1. Safety:
a. Carry out operations in strict accordance with all OSHA and manufacturer’s safety requirements, including scaffolding provisions and proper entry into confined spaces.
b. Ensure workers are educated on the latest OSHA and NASSCO requirements for worker and public safety measures in regard to styrene gas emissions.
2. Cleaning:
a. Immediately prior to pre-installation CCTV inspection, thoroughly clean the newly installed host pipe and remove all debris, sediment, foreign material, protrusions, and other material that could interfere with installation or performance of the CIPP liner. Re-clean immediately prior to liner installation if required. Cleaning and pre-installation CCTV inspection shall be incidental to the CIPP bid item and no separate payment will be made.
3. Pre-Installation TV Inspection: After cleaning and immediately prior to CIPP installation, perform a continuous CCTV inspection of the full length of each pipe segment proposed for lining. CCTV inspection shall be performed by personnel holding current NASSCO
PACP certification and shall be coded in accordance with the current NASSCO PACP and
MACP.
Provide digital color video in MPEG-4 (MP4) format, together with the corresponding
PACP inspection report and database/export file. Clearly identify each inspection by
Orange Water & Sewer Authority 33 01 30.72 - 6 and Sewer Replacements
Project, upstream and downstream manhole, pipe diameter, inspection date, and direction of inspection.
CCTV inspection shall clearly document the entire inside circumference of the host pipe and identify joints, obstructions, debris, defects, service connections, and conditions that could interfere with CIPP installation.
Submit pre-installation CCTV records to the Engineer ten (10) working days before the proposed CIPP installation. Do not begin CIPP installation until the Engineer has reviewed the CCTV inspection and authorized installation to proceed.
4. Post-Installation CCTV Inspection: Following completion of CIPP installation, trimming, sealing, and service reinstatement, perform CCTV inspection of the entire length for each lined segment. Perform and document the inspection using the same video, PACP, identification, and reporting requirements specified for pre-installation CCTV.
CCTV shall demonstrate that the liner is continuous, fully cured, properly fitted to the host pipe, free of unacceptable defects, properly terminated and sealed at manholes, and that designated service connections have been completely and properly reinstated.
Submit the post-installation CCTV inspection and associated reports as part of the final
CIPP acceptance documentation.
5. Flow Control: Make provision for the flow of wastewater around the section or sections of pipe designated for inversion and effective TV inspection at a cost incidental to the insertion of the liner. Submit a flow control implementation plan for the Owner’s approval prior to construction. At no time shall wastewater be pumped into the streets, alleys or storm drain systems. The pump and bypass lines shall be of adequate capacity and size to handle the flow. Take all necessary steps to prevent flooding of any residence or business. Contractor shall be liable for any damages incurred as a result of this Work.
6. Line Obstructions: Identify point repairs required such as heavy solids, dropped joints, intruding service connections, collapsed pipe, or obstructions that must be removed to permit the inversion or lining process to be completed. This Work must be identified and approved in writing by the Owner’s representative prior to the Work being completed by the Contractor. Point repairs and removal of obstructions that require excavation of the pipe and removal of existing pipe sections shall be considered a separate pay item.
7. Water: Water for the rehabilitation work will be made available to the Contractor by the Owner from the nearest fire hydrant. Hauling, if required, will be at the Contractor’s expense. Contractor shall use a double-check valve assembly to prevent backflow in the event of pressure failure. The backflow prevention device must be approved by the
Owner’s representative.
8. Public Notification: Contractor shall make every effort to maintain service usage throughout the duration of the Project. In the event that an individual sanitary sewer connection or group of connections must be out of service to complete the Work, the maximum amount of time out of service for any property served by the sanitary sewer shall not exceed 8 hours. A public notification program shall be implemented by the
Contractor. Contractor shall, at a minimum, contact each home or business connected
Orange Water & Sewer Authority 33 01 30.72 - 7 and Sewer Replacements to the sanitary sewer and inform them of the Work to be conducted and when the sewer will be off-line. Contractor shall also provide the following:
a. Written notice delivered to each home or business the day prior to the beginning of work being conducted on the section, with a local telephone contact number for the
Contractor that the citizens can call to discuss the Project or any problems which could arise.
b. Contact, in person, any home or business owner that cannot be reconnected within the time stated in the written notice.
c. Contractor shall ensure public notification is made in accordance with the Odor
Control Plan and proper infographics and “door hangers” have been distributed to make the public aware of the possibility styrene gas emissions.
3.02 CONSTRUCTION
A. Cured In Place Pipe Insertion:
1. Inversion Method:
a. Wet-Out: Designate a location where the uncured resin in original containers and the fiber felt tube will be vacuum impregnated prior to installation. A resin/catalyst system compatible with the requirements of this method shall be used. The quantities of the liquid thermosetting material shall be sufficient to provide the thickness specified herein and to fill the volume of air voids in the tube with additional allowances for polymerization shrinkage and the loss of resin through cracks and irregularities in the original pipe wall. The tube shall be transported to the Site and maintained in a refrigeration truck until ready for installation.
b. Inversion using Hydrostatic Head: The resin-impregnated felt tube shall be inserted through an existing manhole by means of an inversion standpipe capable of applying the hydrostatic head required to fully extend the tube to the next designated manhole or termination point. The tube shall be inserted into the inversion standpipe with the impermeable plastic membrane side out. At the lower end of the inversion standpipe, the tube shall be turned inside out and attached to the inversion standpipe so that a leak-proof seal is created. The inversion head shall be adjusted to be of sufficient height to invert the tube from manhole to manhole and to hold it tight against the existing pipe wall, producing dimples at side connections and flared ends at the manhole. Care shall be taken to prevent damage or failure of the felt tube as a result of overstressing due to the elevated curing temperatures prior to completion of the final cure.
c. Inversion using Air Pressure: The resin impregnated tube shall be inserted thru an existing manhole by means of an inversion process utilizing air pressure sufficient to fully extend the tube to the next designated manhole or termination point. The tube end shall be connected by an attachment so that a leak-proof seal is created with the impermeable plastic membrane side out. The inversion pressure shall be adjusted to cause the impregnated tube to invert from manhole to manhole and hold the tube tight against the existing pipe wall, producing dimples at side connections and flared ends at the manhole. Care shall be taken to prevent damage
Orange Water & Sewer Authority 33 01 30.72 - 8 and Sewer Replacements or failure of the felt tube as a result of overstressing due to the elevated curing temperatures prior to completion of the final cure.
d. Curing using Circulating Heated Water:
1). After the inversion is completed, Contractor shall supply approved heat source and water recirculation equipment capable of delivering heated water throughout the section to uniformly raise the water temperature above the temperature required to achieve a final cure of the resin. This temperature shall be as recommended by the resin/catalyst system manufacturer. The heat source shall be fitted with suitable monitors to gauge the temperature of the incoming and outgoing water supply. An additional gauge shall be placed between the impregnated felt tube and the host pipe in the downstream manhole at or near the bottom to determine the temperatures during cure.
Water temperature in the line during the cure period shall not be less than 150 deg F nor more than 200 deg F as measured at the heat source return line.
Initial cure shall be completed when inspection indicates the exposed portions of the pipe to be hard and sound and the remote temperature sensor indicates that an exotherm has occurred. The recirculation of the water and cycling of the heat exchanger to maintain the water temperature shall continue for the duration of cure recommended by the resin manufacturer, modified for the specific installation process chosen.
2). After completion of the heated water cure, cool the hardened pipe to a temperature below 100 deg F before relieving the static head in the inversion standpipe. Cool-down shall be accomplished by the introduction of cool water into the inversion standpipe to replace water being drained from a small hole made in the downstream end. Care shall be taken in the release of the static head so that a vacuum will not be developed that could damage the newly installed pipe.
e. Curing using Steam:
1). After the inversion is completed, Contractor shall provide steam generating equipment to distribute steam throughout the section and uniformly raise the temperature within the…