A1 Penoke Bike Trail Task Order 2022_2023.docx

DOCX document 20 KB Posted

Attached to
Allegheny National Forest Spring ATV Heavy Trail Maintenance
Solicitation number
12445522Q0212
Issued by

View the file

Other files

File Type Posted
A4 Penoke Maint section B.jpg JPG image
A5 Penoke Maint site 1.jpg JPG image
A13 Questions and answers for Allegheny Spring ATV Heavy Trail Maintenance.docx DOCX document
A11 Penoke Maint site 7.jpg JPG image
A12 DBA Wage Determination PA2022002 Elk Forest Mckean and Warren Counties.pdf PDF
A6 Penoke Maint site 2.jpg JPG image
A7 Penoke Maint site 3.jpg JPG image
A2 ANF ATV trails maintenance SOW revised.docx DOCX document
A3 Penoke Maint section A.jpg JPG image
A9 Penoke Maint site 5.jpg JPG image
12445522Q0212.pdf PDF
A10 Penoke Maint site 6.jpg JPG image
A8 Penoke Maint site 4.jpg JPG image
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Penoke Bike and ATV Trail Maintenance BPA Task Order Schedule of Items June 15, 2022

Scope of Work:

Work section A, can be accessed from Forest Rd 226 Goat farm Rd and Duhring Rd.

Work section B, can be accessed from state route 66 trail crossing and Duhring Rd.

Works sites section 1-7 from state route 66 trail crossing and Duhring Rd Forest Rd 226 Goat farm Rd.

Normal Tread Maintenance: Maintain trail tread, including pulling in material from undesirable berms and reincorporating into tread, correcting damage that corrupts drainage pattern. The work will include reshaping the rail to the original insloped /outsloped condition and controlling surface drainage to prevent further degradation of the trail and compact all disturbed areas. All dips will be reconstructed. Maintain all existing ditches, dips and leadoff ditches as part of the trail tread maintenance. Normal maintenance will include reconditioning of trails with not more than 6” deep ruts or holes in the tread surface. The depth will be measured using a 60” straight-edge across the drivable surface and measuring the depth of ruts/holes from the bottom of the straight edge to the deepest depth of the ruts or holes. If more than 20% of the ruts in a section are over 6” deep, the section will be evaluated under heavy tread maintenance.

Heavy Tread Maintenance: This item will be used for heavily damaged trail tread that would require more than normal maintenance to return to original shape. Heavy maintenance will include areas that are deeply rutted, have large waterholes and drainage has been significantly changed and where more than normal amount of work is needed to repair. In all cases the trail is still defined but has significant reshaping to be performed. Heavy tread maintenance will include the following: Remove and reshape berms as needed, pulling in material from undesirable berms and reincorporating into tread and compacting, correcting damage that corrupts drainage pattern, reshaping the trail to the original insloped/outsloped condition and controlling surface drainage to prevent further degradation of the trail. All dips will be reconstructed as directed by the COR. Maintain all existing ditches, dips, and leadoff ditches as part of the heavy trail tread maintenance. Use Heavy Tread maintenance if the ruts/holes are more than 6” and less than 18” deep as measured with a 60” straight-edge, and less than 30 CY of material needs to be moved over a 150’ length of trail

Work Description:

Section A Penoke Bike and ATV trail:

00+00 Start Normal Maintenance.

00+25872 End Normal Maintenance Section B Penoke Bike and ATV trail:

00+00 Start Normal Maintenance.

00+ 12672 End Normal Maintenance Section A Site 1:

00+00 Start Heavy Maintenance.

Start rip rap (R3) limestone. 22 tons.

Start 2A limestone. 22tons.

00+122 End Heavy Maintenance End rip rap (R3) limestone.

End 2A limestone.

Section A Site 2:

00+00 Start Heavy Maintenance.

00+150 End Heavy Maintenance

Section A Site 3:

00+00 Start Heavy Maintenance.

00+150 End Heavy Maintenance

Section A Site 4:

Start rip rap (R3) limestone 22 tons.

Start 2A limestone 10 tons.

Cover culvert with stone.

00+150 End Heavy Maintenance End rip rap (R3) limestone.

End 2A limestone.

Section A Site 5:

Section A Site 6:

Start rip rap (R3) limestone. 66 tons.

Start 2A limestone. 22tons.

End rip rap (R3) limestone.

Section B Site 7: