Schedule of Items RGFO

ITEMDESCRIPTION: Unit Price ItemsUNITBASE YEAR UNIT COSTYEAR 1 UNIT COSTYEAR 2 UNIT COST
151-1Mobilization -as a percentage of total cost of all other task order items (NOTE: equipment transport to be paid under 622).%
151-2Bonding, Task Order $30,000 and Higher (as % of total cost of all other tasks). No individual Task Order will exceed $500,000%
157Silt Fence with mesh supportLF
201-1Light to moderate clearing and grubbing, disposal of tops, limbs, logs, dispose of debris by windrowing or scattering.Acre
201-2Moderate to heavy clearing and grubbing, disposal of tops, limbs, logs, dispose of debris by windrowing or scattering.Acre
202-1Removal and Disposal of Trees less than 24" Diameter (remove from project)Each
202-2Removal and Disposal of Trees greater than 24" Diameter less than 36" - remove from prjectEach
203-1Removal of Culverts up to 25-inch diameter - (a) remove from projectFoot
203-2Removal of Culverts 25-inch to 48-inch diameter - (a) remove from projectFoot
203-3Removal of Structures and Obstructions (Off Site with disposal) (a) remove from projectTon
204-1Site Excavation (disposal on-site to embankment construction or waste)CY
204-2Embankment constructionCY
207Earthwork Geotextile Class 1SY
211-1Roadway Obliteration - Method 1: 24' wide or lessMile
211-2Roadway Obliteration - Method 2: 24' wide or lessMile
212-1Linear grading- new construction: Cut/fills less than 1-foot at centerline, travelled way 20-feet wide or lessMile
212-2Linear grading- new construction: Cut/fills less than 1-foot at centerline, travelled way 20-30 feet wideMile
212-3Linear grading - reconstruct existing road: cut/fills less that 1-foot at centerline, existing width 20' or lessMile
212-4Linear grading - reconstruct existing road: cut/fills less that 1-foot at centerline, existing width 20'-30'Mile
212A-1Routune Road Maintenance - existing travelled way width up to 20-feetMile
213Site grading - construct/reconstruct with drainage features. Cut/fills under 1-foot.SY
214Brushing (linear) 5-feet wide.Mile
251-1Supply and place riprap Class2 (price with no haul, use hourly rate for haul)Ton
251-2Supply and place riprap Class4 (price with no haul, use hourly rate for haul)Ton
251-3Supply and place 2'-3' Boulders (price with no haul, use hourly rate for haul)Ton
251-4Supply and place 3'-4' Boulders (price with no haul, use hourly rate for haul)Ton
301Aggregate surface course, commercial source (price with no haul - use hourly rate for haul )Ton
404-1Apply Dust Control using Calcium Chloride or approved other. (price includes blading, materials, application and compationMile
404-2Apply Base Stabization using Calcium Chloride or approved other. (price includes blading, materials, application and compationMile
602-118-inch corrugated HDPE drainage pipe, smooth inner wall, H20 loadingFoot
602-224-inch corrugated HDPE drainage pipe, smooth inner wall, H20 loadingFoot
602-336-inch corrugated HDPE drainage pipe, smooth inner wall, H20 loadingFoot
602-418-inch corrugated HDPE end sectionEach
602-524-inch corrugated HDPE end sectionEach
602-636-inch corrugated HDPE end sectionEach
607-1Cleaning culverts in place (up to 24-inch diameter)Foot
607-2Cleaning culverts in place (25-inch - 48-inch diameter)Foot
619Cattleguard 12-24 feet wide with precast concrete base.Each
619-1Clean cattlegaurd foundation of dirt, debris, etc.Each
622-1Motor Grader, Cat 12H, JD670D, or similar, with operator.Hour
622-2Backhoe/Loader, Cat 416E , JD 310G, or similar, 4-wheel drive, with extendable stick; with operatorHour
622-3Crawler Dozer, Cat D-3, Case 650K, JD 550J PAT, or similar, with tilt blade, with operatorHour
622-4Crawler Dozer, Cat D-6N, Case 1650, JD 700J or similar, w/rippers and tilt blade; with operatorHour
622-5Haul Vehicle, End Dump, 6 C.Y. or similar; with OperatorHour
622-6Haul Vehicle, End Dump, 10 C.Y. or similar; with OperatorHour
622-7Track-Mounted Excavator, JD 120C or similar, with thumb attachment; with operatorHour
622-8Skid Steer, Bobcat S220 or similar w/12” Auger and Loader; with operatorHour
622-8ASkid Steer, Bobcat S220 or similar w/hammer/breaker; with operatorHour
622-9Wheel Loader, Case 721E or similar, with operatorHour
622-10Compactor, Vibratory Steel wheel, 5-8 ton, with operatorHour
622-11Water Tender, 1,500 gallon (or similar) pressurized; with driver/operator. 8-hour minimum per job.Hour
622-12Hand-held compactor (whacker-packer) with operatorHour
622-13Chain Saw w/20” Bar or similar, with operatorHour
622-14Equipment TransportMile
623General LaborHour
629Furnish and install erosion blankets and seeding.SY
NOTE:Items 622: Equipment: COR may allow equipment substitution
at no cost if appropriate
*Denotes items potentially subject to Economic Price Adjustment for fuel
OPTIONAL ITEMS
AURGENT WORK (Within 14 days of NTP) Multiplier
BEMERGENCY WORK (Within 24 hours of NTP) Mulitiplier

&C&"Arial,Bold"SCHEDULE OF ITEMS: &KFF0000 ROYAL GORGE FIELD OFFICE BASE YEAR&K000000

CONTRUCTION IDIQ: ROAD/REC SITE/ADMIN SITE MAINTENANCE

Input PAY ITEM just as it is found in the Specification or Special Spec. The SPD is set up for 40 PAY ITEMS. More can be added by editing the format.

Row Height = 15 for single line of text 30 for two lines of text 45 for three lines of text Column Width is 12 VIEW is set at 70% Type in DESCRIPTION just as the Spec or SPS. This PAY ITEMS library is just for your project so you can make all the PAY ITEMS you want.

Column width is 52 Units of Measure.

This is where you input your unit costs for your particular project. Costs are determined by you, this is NOT a canned cost!

This is where you input your unit costs for your particular project. Costs are determined by you, this is NOT a canned cost!

This is where you input your unit costs for your particular project. Costs are determined by you, this is NOT a canned cost!

File details come from the government source that posted it. Updated .