A-E Supplement B Submissions and Schedule.doc

DOC document 50 KB Posted

Attached to
C1DA--523A5-21-002 design Fuel Pump Replacements
Solicitation number
36C24121R0210
Issued by

About this file

This notice requests SF330 qualification packages from firms for Architect/Engineer design services to replace fuel pumps at the Brockton VA Medical Center in Massachusetts. Firms should provide design, specifications, cost estimates, and construction administration. Submissions are due August 30, 2021 and will be evaluated based on professional qualifications, reputation, experience with healthcare and fuel system projects, team qualifications, capacity, past performance, and location. The small business set-aside contract value is estimated between $100,000 and $250,000. Firms must be an SDVOSB and meet limitations on subcontracting. The selected firm will provide design reviews and submissions at 30%, 90%, 100% completion. The scope includes surveys, drawings, specifications, cost estimates, and as-built documents.

View the file

Other files

File Type Posted
SDVOSB Compliance Statement.pdf PDF
SOW Replace Fuel Pumps Brockton-523A5-21-002.docx DOCX document
PAST PERFROMANCE QUESTIONAIRE.docx DOCX document
A-E Supplement C Submissions.doc DOC document
West Roxbury Drawing Set 523A4-12-205.pdf PDF
West Roxbury Specifications 523A4-12-205.pdf PDF
36C24121R0210.docx DOCX document
A-E Supplement A Scope and Site Visits.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace Fuel Pumps, Brockton

Project #523A5-21-002

SUPPLEMENT “B”

A/E SUBMISSIONS

OF DESIGN REVIEW MATERIAL

FIRST REVIEW

(Conceptual – Preliminary User Group Meetings & Field Surveys)

2 CDs each containing the following:

· AutoCAD and PDF conceptual/preliminary drawings

· Preliminary Investigation Report with Recommendations and Alternates

· Conceptual/preliminary estimates with proposed alternates 1 Set of full size conceptual/preliminary layout plans/details - 30 inches by 42 inches

1 Set of Preliminary Investigation Report with Recommendations and Alternates

SECOND REVIEW

(30% Submittal – Schematics)

2 CDs each containing the following:

· AutoCAD and PDF schematic drawings with phasing plans

· Set of design analysis, narrative report and phasing plans

· MS Word draft specifications in electronic format

· Schematic estimates with proposed alternates in electronic format

1 Set of full size bound schematic layout plans/details with phasing plans– 30 inches by 42 inches

1 Set of design analysis

1 Set of spiral bound draft specifications 1 Set of schematic estimates with proposed alternate

THIRD REVIEW

(90% Submittal – “CD” Construction Documents)

2 CDs each containing the following:

· AutoCAD and PDF construction drawings with phasing plans

· Set of design analysis, narrative report

· MS Word construction documents specifications

· Construction documents estimates

1 Set of full-size bound construction documents plans/details with phasing plans– 30 inches by 42 inches

1 Set of design analysis, narrative report 1 Set of spiral bound construction documents specifications

1 Set of MS Word construction documents specifications 1 Set of construction documents estimates

FOURTH REVIEW

(100% Submittal – Bid [Final] Documents)

2 CDs each containing the following:

· AutoCAD and PDF bid drawings

· MS Word/PDF final specification sections

· MS Word/PDF final specification sections merged

· Final estimates

· Final Phasing Schedule

1 Set of approved full-size bid documents with Registered Architect (RA) and Professional Engineer (PE) stamps - 30 inches by 42 inches

1 Set of 3-ring bound final specifications paginated front to back

1 Set of final estimates

1 Set of final phasing schedules

FIFTH REVIEW

(Project Close Out Submittal – “As-Built” Construction Documents)

2 CDs each containing the following:

· AutoCAD and PDF as-built drawings

1 Set of approved full size As-Built Mylar drawings with RA and PE stamp

ID
Milestone Task Description
Duration
Schedule

Date Actual

Date

1
User Group Preliminary Mtg (Review Scope, Site Survey Investigation)
1 Day
NTP + 1
2
Preliminary Investigation of Existing Conditions
As Needed
3
Submit Conceptual Layout Schemes with Proposed Alternates
---
4
User Group Mtg (Review Proposed Schemes)
1 Day
NTP + 15
5
Submit Revised Conceptual Layout Plans with Proposed Alternates
---
6
User Group Mtg (Review Conceptual Plans)
1 Day
NTP + 20
7
Submit Revised Conceptual Layout Design for Approval
---
8
User Group Mtg (Review/Approve Conceptual Plans)
1 Day
NTP + 30
9
Prepare 30% Schematic Design Submissions
---
Survey Existing Conditions, Coordinate Design with Consultants & VA Comments
As Needed
10
Submit 30% Schematic Design Package
---
VA Engineering 30% Review
7 Days (Min)
11
User Group 30% Schematic Design Review Meeting
1 Day
NTP + 60
12
Prepare 90% “CD” Construction Document Submissions
---
Coordinate Design with Consultants, Existing Conditions & VA Comments
As Needed
13
Submit 90% “CD” Construction Documents Package
---
VA Engineering 90% Review
14 Days (Min)
14
User Group 90% “CD” Review Meeting
1 Day
NTP + 90
15
Prepare 100% Bid Final Documents
---
Finalize Coordination with Consultants, Existing Conditions & VA Comments
As Needed
16
Submit 100% Bid Final Documents with RA and PE Stamps
---
NTP + 120