A-E Supplement A Scope and Site Visits.doc
DOC document 35 KB Posted
- Attached to
- C1DA--523A5-21-002 design Fuel Pump Replacements
- Solicitation number
- 36C24121R0210
About this file
This document is a sources sought notice from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1 seeking qualifications packages from architectural and engineering firms. The notice requests SF330 forms and responses by August 30, 2021 at 4:00 PM EST to provide design services including drawings, specifications, cost estimates and construction administration for a fuel pump replacement project at the Brockton VA Medical Center in Brockton, Massachusetts with an estimated construction budget between $100,000 and $250,000. The contract is set aside for Service-Disabled Veteran Owned Small Businesses. Evaluation criteria include professional qualifications, reputation and experience of the firm, specialized experience in similar healthcare facility projects, team qualifications and experience, capacity, past performance, capability and commitment, and office location. Responses are limited to 85 pages and must include a completed SF330 and responses addressing each evaluation criteria.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SDVOSB Compliance Statement.pdf | ||
| SOW Replace Fuel Pumps Brockton-523A5-21-002.docx | DOCX document | |
| PAST PERFROMANCE QUESTIONAIRE.docx | DOCX document | |
| A-E Supplement C Submissions.doc | DOC document | |
| West Roxbury Drawing Set 523A4-12-205.pdf | ||
| A-E Supplement B Submissions and Schedule.doc | DOC document | |
| West Roxbury Specifications 523A4-12-205.pdf | ||
| 36C24121R0210.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace Fuel Pumps, Brockton Project #523A5-21-002
SUPPLEMENT “A”
General Scope of Work (SOW):
Provide all professional architectural and engineering (A/E) services necessary to develop complete drawings, specifications, cost estimates, design analysis and narrative reports, construction schedules, project phasing plans, investigations, environmental assessments and coordination efforts, site visits and construction period services associated with removing and replacing failed gasoline and diesel fuel pump stations/systems at Veterans Affairs’ Medical Center (VAMC), 940 Belmont Street, Brockton, MA. The intent of this project is to replace corroded and failed gasoline and diesel fuel pump systems to correct deficiencies like the West Roxbury Campus efforts. Conduct preliminary project scope meetings and site survey investigations to develop the necessary elements for conceptual layout schemes with proposed alternatives consistent with the VA’s project team goals as prioritized during preliminary project meetings, field surveys and studies.
Task Order
Task Order Construction Budget
#523A5-21-002 Replace Fuel Pumps
$990,000.00
Deduct Alternates} Shall be part of the design requirements to be utilized in case of market condition variations in order to maximize the use of available Government funds. The VA shall select the proposed alternates from the A/E recommendations. Deduct Alternates shall not be used to bring the projected project costs within construction funding; these alternates are designed to assure a contract award and to have a project design and estimate at or below construction funding.
General Statement of Task} The project scope includes but is not limited to demolition, concrete, asphalt, containment, fuel piping, fuel station, layout and location investigation and recommendations, canopy/cover, antistatic design, corrosion protection, environmental protection, heaters, fire alarm and detection, fire suppression systems, environmental assessment, environmental coordination, soil investigation/boring, topographical survey, security and anti-theft, utilities, electrical, lighting, emergency power, signage.
Services shall also include, but are not limited to the following:
1) On site visits to define the details of the project scope of work meeting the goals of the Veterans Affairs' (VA) project team, and presentation of preliminary layout plans with proposed alternatives.
2) Engage the services of all consultants in each discipline deemed to be necessary to fulfill the requirements of the project plan. Site investigations shall measure and record the conditions of the area to be renovated and/or impacted by the project. Each discipline shall document and investigate the relevant existing conditions found, review the availability of existing site information, and field verify all essential elements pertinent to their trade.
3) Based on meetings and site field surveys, prepare a proposed detailed project scope description report within the limits of the project construction budget consistent with the VA goals.
4) Representation during all design review and field survey meetings. Architect/Engineer (A/E) shall document the results of each meeting and provide the conclusions to the Contracting Officer and VA Project Engineer within one (1) week following each meeting.
5) Based on meetings and investigations prepare preliminary, schematic, working, and construction documents with the necessary engineering and design details for all architectural, mechanical (plumbing, fire protection and HVAC), electrical, structural, civil, and other specialty consultants elements within the limits of the project goals established.
6) 90% Design Submission: The 90% design submission shall be a complete 100% design. All plans, sections, details, etc. shall be complete at this time. The A/E shall ensure that the 90% design submittal is in fact his/her 100% product, and that it represents a total biddable package. An incomplete 90% design submittal may be rejected by the VA; a rejection will require the A/E to resubmit a 90% design with no additional cost to the A/E.
7) VA Design Review Comments: The A/E shall submit written responses to the VA's oral and written design review comments. These written responses shall be within seven (7) calendar days of the VA's comments; and these responses shall explain the action the A/E will take for each comment.
8) Verification and preparation of as-built drawings which the VA shall retain.
9) The design consultant must have a PDF writer program to electronically sign material submittals; all Material Submittal Forms will be processed via electronic format with digital signature which utilizes a PDF Writer Program such as Adobe Reader/Writer or Pro V Nuance.
10) Site visits (minimum of 7 design and 7 construction) or as required and/or requested by the VA Contracting Officer and Project Engineer for review and inspection of progress including final tests and inspections.
11) Documentation of all site visits shall be submitted in writing to the VA Contracting Officer and Project Engineer within one (1) week after each visit.
12) Review and comply with Design Alert – VA Project Design Principles – Foundation of Design. In summary, VA staff and consulting architects and engineers must help realize the VA missions through design and construction that honors and serves our Nation's Veterans by providing world class health care, benefits, and memorial facilities that embody optimum performance in functionality, flexibility, quality, safety, security, accessibility, wayfinding, resilience, sustainability, maintainability, and economy.