RFI_Amendment 0001.pdf

PDF 93 KB Posted

Attached to
Keswick Station Service Transformer
Solicitation number
89503321QWA000082
Issued by

About this file

This document contains an amendment to a solicitation for a Keswick Station Service Transformer. The Western Area Power Administration, Sierra Nevada Region requires a custom 3 phase, 115/480-kV 2500 kVA ONAN transformer including mineral oil, transportation, offloading, and a five-year warranty. Additional requirements include one lot of tools, appliances, and spare parts, as well as erecting engineering services for assembly and travel. Drawings and data are also required. The solicitation is set aside for small businesses with a NAICS code of 335311 and size standard of 750 employees. The response due date was extended to May 12, 2021 per the amendment. The required delivery date was also changed to 45 weeks after award in the amendment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI for Keswick Station Service Transformer (Amendment 0001 to Solicitation 89503321QWA000082)

1. Is a Vapor phase required, or can a manufacturer use a heat and vacuum drying process?

Response: For this size transformer a heat and vacuum drying process would be acceptable.

2. Can the due date be extended to May 12, 2021?

Response: We are not able to accommodate an extension at this time.

Updated Response: Offer due date extended as stated in the solicitation amendment.

3. We are preparing a proposal for the subject solicitation and had a question regarding the requirement for vapor phase in paragraph 1.7.

In lieu of vapor phase, will Western consider an alternate dry out method/process for the windings?

Response: Yes, for this size transformer the alternate proposed in place of vapor phase drying is acceptable.

4. Also, is it possible to extend the bid due date for a week in order to finalize our proposal?

Response: We are not able to accommodate an extension at this time.

Updated Response: Offer due date extended as stated in the solicitation amendment.

5. Please can you confirm the voltage is 115,000?

Response: Yes, that is the voltage 115,000 V or 115-kV. This transformer is for station service and only a 115-kV primary source is available. Since 2.5 MVA capacity is needed for this installation, we weren’t able to use a power PT.

6. The required delivery date is 28-34 Weeks ARO, our factory standard now is pushing 45 weeks ARO. Will Western consider a delivery date 45 Weeks after award or is the 34 Weeks a drop dead date?

Response: The required delivery date has been changed to 45 weeks ARO, as stated in the solicitation amendment.