21. Attachment A - Specifications.pdf

PDF 1 MB Posted

Attached to
Stegall-Wayside OPGW Installation
Solicitation number
89503220BWA000022
Issued by

About this file

This is a project specification for a federal contract opportunity to install optical ground wire and fiber optic cable on a transmission line. The contractor will remove existing overhead ground wire and install 25.8 miles of 48-fiber optical ground wire and 0.3 miles of all dielectric self-supporting cable to construct a fiber path. Additional work includes furnishing and installing fiber optics at two substations. The agency is the Department of Energy's Western Area Power Administration. Submittals are due within 14 days of the notice to proceed. Construction must be completed by September 30, 2020. The contractor will be responsible for obtaining any necessary temporary easements and complying with all environmental and safety requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

21 November 2019

Attachment A

Stegall-Wayside OPGW Installation Specifications

89503220BWA000022

Stegall-Wayside OPGW Installation

Specification No. 972

SECTION C

DESCRIPTION/SPECIFICATIONS

NEBRASKA

SECTION C

DESCRIPTION/SPECIFICATIONS

STEGALL-WAYSIDE OPGW INSTALLATION

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT

B. DESCRIPTION OF WORK

1. REMOVE EXISTING OVERHEAD GROUND WIRE

2. SUBSTATION ELECTRICAL

3. TRANSMISSION LINE ELECTRICAL

C. DESCRIPTION OF BIDDING SCHEDULE ITEM

1. Bidding Schedule item “Mobilization and preparatory work”

D. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

1. SUBMITTAL APPROVAL TIME

2. OUTAGE AND CONSTRUCTION SCHEDULE RESTRICTIONS

3. MAXIMUM AVAILABLE FAULT CURRENT

E. CONSTRUCTION SCHEDULE

1. SUBMITTAL TIME

F. MATERIAL

G. RIGHTS-OF-WAY

1. GENERAL

2. ACCESS EASEMENTS

3. WORK ON THE RIGHT-OF-WAY

H. GEOLOGIC INVESTIGATIONS

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES

J. WATER FOR CONSTRUCTION PURPOSES

K. EXPLOSIVES AND BLASTING

L. CONTRACTOR COMMUNICATIONS FOR WAPA USE

M. EMPLOYEE REQUIREMENTS

N. ELECTRICAL MINIMUM APPROACH DISTANCES

O. SUBMITTALS AND CORRESPONDANCE

1. GENERAL

2. TRANSMITTAL

3. SUBMITTAL RESPONSE

4. PHYSICAL SAMPLE SUBMITTALS

5. PROJECT PROTOCOL

DIVISION 2 – SITEWORK

A. GENERAL

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Remove existing overhead ground wire”

2. Bidding Schedule item “Seeding”

3. Bidding Schedule does not contain separate items

DIVISION 4 – TRANSMISSION LINE LATTICE STRUCTURES

A. DESCRIPTION OF BID ITEM

1. Bidding Schedule item “Furnish and install OPGW deadend steel plate on lattice steel structure 105/4”

B. LATTICE TOWER DRAWINGS

DIVISION 7 – WOOD POLE STRUCTURES

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule item “Furnish and install wood poles”

2. Bidding Schedule item “Furnish ADSS cable support on existing wood poles”

DIVISION 10 – ELECTRICAL TRANSMISSION LINE

A. DESCRIPTION OF BID ITEMS

1. Bidding Schedule items for “Furnish and install optical overhead ground wire assemblies, complete with suspension clamp or bolted dead end, suitable for 0.465-inch-diameter optical overhead ground wire with armor rods”

2. Bidding Schedule item for “Furnish and install one (1) 0.465-inch-diameter, forty-eight (48) fiber optical overhead ground wire”

3. Bidding Schedule item for “Furnish and install All Dielectric Self Supporting (ADSS) fiber optic cable assemblies, complete with tangent trunnion clamp or formed wire dead end, suitable for 0.512-inch-diameter ADSS cable with structure reinforcing rods”

4. Bidding Schedule item for “Furnish and install one (1) 0.512-inch-diameter, forty-eight (48) ADSS fiber optic cable”

5. Bidding Schedule item for “Furnish and install spiral-type vibration dampers for 0.465-inch-diameter optical overhead ground wire”

6. Bidding Schedule item “Spare parts”

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. DESCRIPTION OF BID ITEM

1. Bidding Schedule does not contain a separate item for “Environmental Quality Protection”

DIVISION 14 – COMMUNICATION FACILITIES

A. DESCRIPTION OF BID ITEMS:

1. Bidding Schedule item “Furnish and install fiber optic cable and associated equipment”

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT:

Construct and complete the Stegall-Wayside OPGW Installation, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; WAPA’s Construction Standards, including Standard 1 – General Requirements (September 2016), Standard 2 – Sitework (September 2016), Standard 4 – Transmission Line Lattice Structures, Standard 7 – Wood Poles (September 2016), Standard 10 – Transmission Line – Electrical (September 2016), Standard 13 – Environmental Quality Protection (September 2016), Standard 14 – Communication Facilities (September 2016) Standard 15 – Drawings (September 2016); Standard Drawings; and these Project Specifications and Drawings.

If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.

WAPA’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.

WAPA Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.

B. DESCRIPTION OF WORK:

The principal components of work include removing 25.8-miles of overhead ground wire on the East side of the Stegall–Wayside 230-kV transmission line; furnishing, installing 25.8-miles of 48-fiber Optical Ground Wire (OPGW), installing 0.3-miles of All Dielectric Self Supporting (ADSS) cable, to construct a fiber path from Stegall-Wayside lattice structure 105/4 to Black Hills Energy (BHE) Crawford Fiber Repeater Site on two (2) single wood poles and attaching to existing Northwest Rural Public Power District (NRPPD) Crow Butte Distribution Line poles and installing conduit and fiber optic cable in the Wayside Substation and Crawford Fiber Repeater Site Building, terminating the fiber and testing the completed fiber optic installation.

A summary of work includes the following:

1. REMOVE EXISTING OVERHEAD GROUND WIRE:

a. Removing 25.8-miles of overhead ground wire.

b. Removing overhead ground wire assemblies and vibration dampers for overhead ground wire on East side of transmission line.

2. SUBSTATION ELECTRICAL:

a. Furnishing and installing fiber optics at Wayside (WS) and Crawford Fiber Repeater Site building.

3. TRANSMISSION LINE ELECTRICAL:

a. Furnishing and installing optical overhead ground wire assemblies, 25.8-miles of optical overhead ground wire, vibration dampers for optical overhead ground wires, ADSS assemblies, 0.3-miles of ADSS cable and miscellaneous transmission line hardware, including grounding, on wood pole and steel lattice structures.

Paragraphs “Description of Bid Items” in Divisions – 1, 2, 4, 7, 10, 13 and 14 describe the work to be performed.

The work is located in Dawes County, Nebraska, as shown on Drawings WS 7100 and SG-WS 0001 and SG-WS 0002.

C. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Mobilization and preparatory work” includes the following:

a. Performing mobilization and preparatory work in accordance with Section H of the contract clauses.

b. Prepare and submit a Construction Schedule and furnish a Safety and Health Program.

c. The Black Hills Energy Crawford Fiber Repeater Site and the Northwest Rural Public Power

District poles are located on Cameco Resources, Crow Butte Operation Site. The following requirements must be met for all personnel working on the Cameco property:

(1) Eating, drinking, smoking and chewing are only allowed in clean areas.

(2) All personnel working on site must first check in with the Cameco office and initially sit for a short safety orientation briefing.

(3) Work can only occur while a Cameco Resources employee is present.

D. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK: See FAR 52.211-10 in

Section F of the solicitation/contract.

1. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 14-calendar days for review of drawings or data submitted for approval.

2. OUTAGE AND CONSTRUCTION SCHEDULE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following Outage and Construction Schedule restrictions shall apply:

a. The Contractor’s work hours shall not exceed 60-hours in one calendar week without prior approval from the Contracting Officer’s Representative (COR).

b. The Contractor shall complete OPGW and ADSS Cable installation by September 30, 2020.

Any site work to be completed after this date will require a 60-day notice, COR approval and additional Environmental review will be required (see Division 13).

c. Stringing operations will not be permitted in cultivated fields while crops are active without written consent from affected landowners and COR.

d. All transmission line outages shall occur between May 15th and September 15th.

e. The Contractor shall inform the COR 14-calendar days prior to splicing and testing.

f. See additional restrictions in Divisions 10 and 13

g. The electrical operation of the transmission lines are under the jurisdiction of WAPA’s Operations Office. All outage requests by the Contractor shall be subject to the approval of the COR. Approval or denial of an individual outage request will be based on transmission system electrical loads, system operating configurations and weather conditions at the time the outage is scheduled to begin. At any time because of transmission system electrical loads, transmission system operation or reliability, WAPA may deny an outage request or direct the Contractor to return facilities to operating conditions and release the applicable Special Work Permit.

Make all outage requests in writing to the COR a minimum of 30-days in advance.

Meeting the minimum advance notice requirement of 30-days does not guarantee an outage will be approved. To improve the chances of an outage being approved, all outages should be submitted with as much advance notice as practicable. Weather conditions and other system conditions such as other scheduled and nonscheduled (forced) outages must be evaluated against an outage request before approval can be granted.

3. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:

a. The maximum available fault current on the Stegall-Wayside 230-kV transmission line is

5864 amps and the X/R ratio is 12.6 prior to and after completing construction.

b. A minimum of one (1) 1/0 ground shall be used on the Stegall-Wayside 230-kV transmission line.

c. Protective Ground Leads: Each protective ground lead shall have a permanent identification tag with unique identification number, certified wire size and test date. Each protective ground lead shall be tested complete with connectors, in accordance with ASTM F 2249. Protective ground leads shall be retested and recertified annually. A protective ground lead without an identification tag to relate it to the annual certification of that protective ground lead shall not be used. No protective ground lead shall be longer than 36-feet, unless approved by COR. Test results shall be submitted to the COR for approval prior to use of the grounds. When using the DC test method, the Contractor shall submit testing information in the format shown below in the Personal Protective Grounds Test Report. When using the AC test method, the Contractor shall submit testing information in accordance with the test set manufacturers recommendations.

CABLE

ID

CABLE

SIZE

CABLE

CONDITION

CABLE

LENGTH

ASTM

RESISTANCE

(MΩ)

MEASURED

RESISTANCE

(MΩ)

PASS/FAIL

FT IN

Tester’s Signature

Test Temperature ______

Test Date ___________________

E. CONSTRUCTION SCHEDULE:

1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the COR within 14-calendar days after date of Notice to Proceed.

F. MATERIAL: All material shall be provided by the Contractor.

G. RIGHTS-OF-WAY:

1. GENERAL: Transmission line right-of-way is 125-feet-wide. WAPA does not represent that the Contractor can gain access to every structure site or travel continuously along the transmission line. NRPPD easement is 30-feet-wide.

Orient construction methods and equipment to utilize Government-furnished rights-of-way, or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired by the Contractor shall be submitted to the COR 60-days prior to use for environmental review and approval, since several areas of the transmission line have travel restricted areas. During the contract period, WAPA reserves the right to use Contractor-obtained access.

The Contractor is responsible for obtaining staging, storage areas and pulling sites. Provide COR with landowner agreements.

2. ACCESS EASEMENTS:

a. WAPA has not acquired access easements from existing public roads to the transmission line, and some off right-of-way access along the transmission line. This off right-of-way access route is to provide access to the transmission line structure sites not accessible by traveling the transmission line.

b. The Contractor, at no cost to the Government, is responsible for working directly with the landowner to obtain a temporary easement/agreement to utilize, improve, or create roads not shown on project drawings. Each easement/agreement should specifically detail the reclamation to be completed after use. Upon obtaining this easement the Contractor shall send a copy of the easement, photos and videos of the initial condition to the COR.

3. WORK ON THE RIGHT-OF-WAY:

a. General: Perform work on the rights-of-way necessary for access to or along the transmission line. Only that excavation, dozing, or blading absolutely necessary will be allowed. Excavation, dozing, and blading for ease of travel may only be performed after field review and approval by the COR in accordance with Division 13. Unauthorized excavation, dozing, blading shall immediately be repaired, or WAPA will have the damage repaired and backcharge the Contractor for all costs involved.

b. Ease of Travel and Crane Landings: Excavation, dozing, or blading done for ease of travel on any easement or for crane landings shall be restored to the original contour of the land and shall be compacted to a dry density not less than the natural in-place dry density of the surrounding earth. The use of water may be required to obtain the required density. Topsoil shall be stockpiled and spread on cuts prior to completion of work.

c. Drawings WS-SG T760-T768 show the access roads that are available for the Contractor to use. Prior to the use of access roads for this project, the Contractor shall submit time-stamped photographs and videos of the initial condition of all roads to the COR. All access roads used during this project shall be reclaimed to the same or better condition than before use, or as state in the easement/agreement without additional cost to the Government. After reclamation of these roads is complete, the Contractor shall submit time-stamped photographs and videos of the roads to the COR.

d. The Contractor shall provide to WAPA proof of insurance, traffic control plan(s) and any other necessary documents to perform work over State or Federal Roadways 90-calendar days prior to performing work.

H. GEOLOGIC INVESTIGATIONS:

Geologic information has not been obtained for this project, and none is known to exist. The Contractor shall determine the nature of the material to be excavated, the difficulties of making and maintaining required excavations and doing other work affected by geology and ground water elevations at the worksite.

I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:

Make arrangements and provide all electric power for construction purposes. Provide necessary transmission lines, distribution circuits, transformers, and other electrical equipment for distributing the power to the places of use. At contract completion, remove temporary electrical equipment and distribution lines.

J. WATER FOR CONSTRUCTION PURPOSES:

Furnish water for construction purposes. Make arrangements for obtaining the water, and provide for conveying the water to the points of use.

K. EXPLOSIVES AND BLASTING:

Explosives shall not be used.

L. CONTRACTOR COMMUNICATIONS FOR WAPA USE:

Furnish and maintain up to three (3) Contractor mobile radio units to WAPA’s inspectors. The radio units shall be provided for WAPA’s use for the duration of the field work and shall be ready for use at the beginning of the Contractor’s field work. The radios shall operate on the Contractor’s normal radio frequencies; be complete with appropriate accessories, adjusted and maintained in good working condition; provide reliable 2-way communication with the Contractor’s office and field crews. When the Contractor’s field work is completed, the radios will be returned to the Contractor.

M. EMPLOYEE REQUIREMENTS:

In addition to the requirements listed in WAPA Construction Standard 1.4.3 all employees are restricted from wearing a headset, headphone, or other listening device, other than a hearing aid or instrument for the improvement of defective human hearing, hearing protection worn as the hazard exists, or for communication purposes while on a WAPA jobsite.

N. ELECTRICAL MINIMUM APPROACH DISTANCES:

In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects, or personnel, shall not be brought closer to energized facilities than the electrical minimum approach distances established by OSHA 1926.958(b), “Materials, Handling, and Storage”. The less stringent equipment clearance distances established by OSHA 1926.960, “Working On or Near Exposed Energized Parts”, Table V-5 and Table V-6, may only be used after the Contractor has completed and submitted WAPA’s Electrical Clearance Variance form and has received the signed form in return from the COR.

O. SUBMITTALS AND CORRESPONDANCE:

1. GENERAL: The Contractor shall furnish submittals as specified in the Construction Standards and this Project Specification via the email address listed below.

a. Submittals shall be in standard PDF, Microsoft Word (.doc/.docx), Microsoft Excel (.xls/.xlsx), Electronic CAD”*.dwg” (AutoCAD 2016 or newer) formats. All submittals in .dwg format shall also be submitted in .pdf format.

b. All submittals shall include the WAPA Contract number with the three digit Specification

Number if applicable, (895032-XXC-WA000XXX-972), WAPA project title, Bidding Schedule Contract Line Item Number (CLIN) and applicable division number.

c. Multiple CLIN’s on a single submittal are not permitted.

d. A cover transmittal letter in Microsoft Word or PDF format shall be included with each email transmittal.

2. TRANSMITTAL: The Contractor shall submit all correspondence (Request for Information, Submittals, etc.) to the following email address care of the COR.

ATTN: J5600

Email: RMR-J5600-CS@wapa.gov

3. SUBMITTAL RESPONSE: WAPA will provide a response to all submittals in accordance with

Division 1.D.2 of these Specifications with an “Acceptable for Use” or “Not Acceptable” status, with comments as appropriate, to the email address where the submittals originated.

4. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e., brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a Submittal-digital cover letter outlining the physical sample submittal prior to sending the sample (including tracking data when applicable) and shall deliver such physical specimens to:

Western Area Power Administration

ATTN: A7900

12155 W. Alameda Parkway Lakewood, CO 80228-2802

5. PROJECT PROTOCOL:

a. Electronic Correspondence:

EMAIL SUBMITTAL FORMAT:

Subject Line in Email Submittal number, Subject, CLIN Number, Project Name/Number, Contract Number, and Specification Number if applicable.

Example: Submittal 017, Suspension Assemblies-CLIN 0001, Stegall-Wayside OPGW

Installation, 895032-XXC-WA0000XX-972

b. Payment Requests:

EMAIL PAYMENT REQUEST FORMAT:

Invoice number, Project Name/Number, and Contract Number Example: Invoice 01, Stegall-Wayside OPGW Installation, 895032-XXC-WA0000XX-972

c. Certified Payrolls-Prime and Sub-Contractors:

EMAIL CERTIFIED PAYROLL FORMAT:

Certified Payroll (CP), Week ending (WE), Project Name/Number, Contract Number and Specification Number if applicable Example: CP-WE 09/12/20 & 09/19/20, Stegall-Wayside OPGW Installation, 895032-XXC-

WA0000XX-972

d. Request for Information:

EMAIL (REQUEST FOR INFORMATION) FORMAT:

Request for Information (RFI), Project Name/Number, Contract Number and Specification Number if applicable Example: RFI-003, Labeling Info, Stegall-Wayside OPGW Installation, 895032-XXC-

WA0000XX-972

DIVISION 2 – SITEWORK

A. GENERAL:

A portion of the transmission line will be in cultivated fields.

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Remove existing overhead ground wire” includes the following:

a. Removing Electrical Items: Locations described by station are on the existing Stegall-Wayside 230-kV transmission line. The existing Stegall-Wayside 230-kV transmission line is shown on the existing plan and profile Drawings SG-WS 4000 through SG-WS 4025. Items removed from the existing line shall become the property of the Contractor, shall be removed promptly from the right-of-way and may not be reused in constructing the new line.

b. Approximate quantities are listed in Table 2-1. The Contractor shall determine the actual quantities to be removed and regardless of the quantities removed, payment will only be made for the lump sum price bid in the Bidding Schedule.

c. Remove the East overhead ground wire, overhead ground wire assemblies and vibration dampers for overhead ground wire, complete with accessories, listed in Table 2-1 located on the Stegall-Wayside 230-kV transmission line. The overhead ground wire shall be removed from Station 10992+50 (Take-off Structure (TOS) at Wayside Substation) to Station 12343+00 (SG-WS Structure 105/4).

d. The Contractor shall include any credit to the Government for salvage of the equipment and/or materials in this bid item.

TABLE 2-1 – ELECTRICAL ITEMS TO BE REMOVED

MATERIAL UNIT QUANTITY

One (1) 1/2-inch, HS, 7-strand Steel Overhead Ground Wire MI 25.8 Overhead Ground Wire Suspension Assemblies on East Side of structures EA 102

Overhead Ground Wire Tension Assemblies on East Side of structures EA 45

Vibration Dampers – OGW on East Side of structures EA 440

2. Bidding Schedule item “Seeding” includes providing material, preparing areas to be seeded, spreading commercial fertilizer, sowing and maintaining grass seed and protecting seeded areas.

Areas to be seeded include:

a. Disturbed areas around structures, pulling and tensioning sites, except those to receive gravel surfacing.

b. Disposal areas, borrow areas and all other disturbed areas.

c. Seed: Use regionally native plant seed. Seed mix shall be submitted to the COR for approval.

d. Perform seeding during the period March 1 to June 1 or August 1 to October 1, except during unfavorable weather conditions or when soil conditions are suitable as determined by the COR.

3. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items:

a. Clearing as directed by the COR.

b. Grading for structure and tower sites and line clearance as directed by the COR.

c. Excavations for foundations.

d. Disposing of excavated material.

DIVISION 4 – TRANSMISSION LINE LATTICE STRUCTURES

A. DESCRIPTION OF BID ITEM:

1. Bidding Schedule item “Furnish and install OPGW deadend steel plate on lattice steel structure 105/4” includes furnishing and installing a new OPGW attachment plate in accordance with Drawing 43-21S 2205 at Structure number 105/4 on plan and profile Drawing SG-WS 4025.

B. LATTICE TOWER DRAWINGS:

1. Tower names on the plan and profile drawings are referenced with Original Tower Names. New Tower names and drawing numbers are identified in table 4.1.

TABLE 4-1—LATTICE TOWER DRAWINGS

NEW

TOWER

NAME

ORIGINAL

TOWER

NAME

DRAWING NUMBERS

21S SH 43-21S 2200, 43-21S 2205

21X SHX 43-21X 2200

21A SAH 43-21A 2200, 43-21A 2201

21T TH 43-21T 2200

21R STRH 43-21R 2200 (Transposition Structure)

DIVISION 7 – WOOD POLE STRUCTURES

A. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule item “Furnish and install wood poles” includes furnishing and installing two (2) 35-foot Class 2 wood poles, 105/4A and 105/4B, with 5/8-inch eye-bolts including washer, double coil lockwasher and square nut attached 6-inches from the top of the pole to accommodate formed wire dead – end assemblies, ADSS-TH, as shown on WAPA standard Drawing 41 1036, SG-WS 7300 and SG-WS 7301. Also include hardware, 7/16 HS guy strand, and anchors for one (1) single guy on 105/4A and one (1) single guy on 105/4B in accordance with WAPA standard Drawing 41 6047.

2. Bidding Schedule item “Furnish ADSS cable support on existing wood poles” includes furnishing and installing 5/8-inch eye-bolts including washer, double coil lockwasher and square nut attached 12-inches from lowest existing wire to accommodate formed wire dead – end assemblies, ADSS-TH, on structures 105/4C, 105/4H and 105/4J and 5/8-inch square head bolts including washer, double coil lockwasher attached 12-inches below the lowest existing wire to accommodate tangent trunnion support assemblies, ADSS-TRUN, as shown on WAPA standard Drawing 41 1036, SG-WS 7300 and SG-WS 7301 on existing Northwest Rural Public Power District (NRPPD) Crow Butte Distribution Line poles 105/4D, 105/4E, 105/4F, 104/4G, 105/4I.

DIVISION 10 – ELECTRICAL TRANSMISSION LINE

A. DESCRIPTION OF BID ITEMS:

1. Bidding Schedule items for “Furnish and install optical overhead ground wire assemblies, complete with suspension clamp or bolted dead end, suitable for 0.465-inch-diameter optical overhead ground wire with armor rods” include furnishing material and performing work to provide optical overhead ground wire assemblies shown on Drawing 41 1031. An estimate of material quantities for each type of structure is shown on Drawing SG-WS 1000.

a. Optical overhead ground wire assemblies shall comply with the characteristics detailed on

Drawing SG-WS 1000.

b. Optical overhead ground wire assemblies shall include armor rods.

c. The Contractor is responsible for determining fiber splice locations. All fiber splice points (by structure number) shall be submitted to the COR at the same time the Construction Program is submitted. The Contractor shall locate fiber splice enclosures based on access roads, reel lengths and set-ups.

Fiber splices and fiber splice enclosures shall be located on structures that currently have tension overhead assemblies, types 21X and 21T, where possible.

Where fiber splice enclosures are required to be located on type 21S structures with an existing suspension overhead assembly, a floating deadend assembly (OPGW-FDB) shall be used with the new 0.465 OPGW in accordance with standard Drawing 41 1031. Reduce existing quantity of OPGW-SL assemblies by new number of OPGW-FDB assemblies as needed. Add any additional cost for OPGW-FDB assemblies to OPGW-SL bid item.

A fiber splice and fiber splice enclosure is required on Stegall-Wayside structure 105/4. Two

(2) OPGW-TH assemblies in accordance with standard Drawing 41 1031 shall be installed with an OPGW dead end attachment plate in accordance with Drawing 43-21S 2205.

Fiber splice enclosures shall not be located on running angle structures, type 21A.

The Contractor shall observe all restrictions identified in Table 10-2.

TABLE 10-2 – AREAS WHERE PULLING/TENSIONING IS RESTRICTED

STRUCTURE NUMBERS

80/2 to 80/4 96/2 to 96/3

2. Bidding Schedule item for “Furnish and install one (1) 0.465-inch-diameter, forty-eight (48) fiber optical overhead ground wire” includes furnishing, stringing, sagging and clipping in the optical overhead ground wires, as described; and furnishing and installing material to complete the optical overhead ground wire installations, except for material furnished and installed as a part of suspension and tension assemblies for optical overhead ground wires and accessories.

a. Optical overhead ground wire shall be installed on the East side of the line from the North

TOS at Wayside Substation to Structure 105/4 as shown on the plan and profile Drawings SG-WS 4000 through SG-WS 4025.

b. It is the responsibility of the Contractor to determine reel lengths, pulling lengths and pulling locations for the entire project. Each reel length shall take into account the distance between the splice locations, amount needed to route down the structure from the OPGW attachment to the optical splice enclosures, amount coiled at the optical splice enclosure, pulling length and pulling locations. No pulling/tensioning sites shall be located in any environmentally sensitive areas. OPGW pulling/tensioning sites shall be within the transmission line right-of-way. If the Contractor wishes to use a pulling location that is outside of WAPA’s right-of-way, then the Contractor shall allow WAPA a minimum of 60-days, after receipt of the proposed site, to review and environmentally clear the area. All pulling locations and pulling lengths shall be submitted to the COR at the same time the Construction Program is submitted. The Contractor shall observe all restrictions identified in Table 10-2.

c. The OPGW shall contain forty-eight (48) single-mode optical fibers and shall be AFL Catalog

No. CC-57/465, AFL Specification DNO-9782 (CentraCore Optical Ground Wire), or equivalent.

d. The OPGW shall have the following characteristics:

(1) Overall diameter not greater than 0.465-inches.

(2) Rated breaking strength not less than 16,250-pounds.

(3) Weight not greater than 0.314-pounds per-foot.

(4) Fault current rating not less than 43 (kA^2)sec.

(5) Meets IEEE Standard 1138 requirements. Test reports from an independent testing company shall be provided to verify the OPGW meets the requirements of IEEE Standard 1138.

(6) Compliant with Standard ITU-T-G.652.D and equivalent to Corning SMF-28e single-mode fiber.

(7) Sag chart number 1-1421.

e. Stringing shall strictly adhere to procedures recommended by the manufacturer. Ensure that the allowable bending radius of the fiber optic cable is not exceeded at any time.

f. At splice locations, the OPGW shall be routed down and attached to lattice steel structures as shown on Drawing 41 1027.

g. For fiber splice enclosures on the transmission line refer to Division 14 of this specification, bidding schedule item “Furnish and install fiber optic cable and associated equipment”.

3. Bidding Schedule item for “Furnish and install All Dielectric Self Supporting (ADSS) fiber optic cable assemblies, complete with tangent trunnion clamp or formed wire dead end, suitable for 0.512-inch-diameter ADSS cable with structure reinforcing rods” include furnishing material and performing work to provide ADSS assemblies shown on Drawing 41 1036. An estimate of material quantities for each type of structure is shown on Drawing

SG-WS 1000.

a. ADSS assemblies shall comply with the characteristics detailed on Drawing SG-WS 1000.

b. Vibration Dampers will not be required on ADSS Fiber Optic Cable.

4. Bidding Schedule item for “Furnish and install one (1) 0.512-inch-diameter, forty-eight (48)

ADSS fiber optic cable” includes furnishing, stringing, sagging and clipping in the cable, as described; and furnishing and installing material to complete the ADSS cable installations, except for material furnished and installed as a part of tangent and tension assemblies for ADSS fiber optic cable and accessories.

a. ADSS fiber optic cable shall be installed from Stegall-Wayside lattice structure number

105/4 to WAPA wood pole structure numbers 105/4A and 105/4B. From WAPA structure 105/4B, ADSS Fiber Optic Cable shall be installed on the North side of existing NRPPD poles 105/4C to 105/4H and on East side of 105/4 H to 105/4J. Refer to Division 14 for details from Splice box on Lattice Structure to wood pole structure 105/4A and 105/4J to Crawford Fiber Repeater Site. Refer to Drawing SG-WS 7301 for ADSS Fiber Optic details and path to Crawford Fiber Repeater Site.

b. It is the responsibility of the Contractor to determine reel lengths, pulling lengths and pulling locations. Each reel length shall take into account the distance between the splice locations, amount needed from splice on lattice structure 105/4 to wood Structure 105/4A, up 105/4A, continuing to Structure 105/4J and down structure 105/4J to Crawford Fiber Repeater Site, amount coiled at the optical splice enclosure, pulling length and pulling locations. No pulling/tensioning sites shall be located in any environmentally sensitive areas. ADSS pulling/tensioning sites shall be within the distribution line right-of-way. If the Contractor wishes to use a pulling location that is outside of right-of-way, then the Contractor shall allow WAPA and NRPPD a minimum of 60-days, after receipt of the proposed site, to review and environmentally clear the area. All pulling locations and pulling lengths shall be submitted to the COR at the same time the Construction Program is submitted. The Contractor shall observe all restrictions identified in Table 10-2.

c. The ADSS shall contain forty-eight (48) single-mode fiber optic fibers and shall be AFL

Catalog No. AE0489C521BA0, AFL Specification DNA-28262 (ADSS Fiber Optic Cable) or equivalent.

d. The ADSS Fiber Optic Cable shall have the following characteristics:

(1) Overall diameter not greater than 0.512-inches.

(2) Rated breaking strength not less than 2,713-pounds.

(3) Weight not greater than 0.087-lbs/ft.

(4) Meets IEEE 1222 requirements. Test reports from an independent testing company shall be provided to verify the ADSS Fiber Optic Cable meets the requirements of IEEE Standard 1222.

(5) Compliant with Standard ITU-T G.652D/G.657.A1, equivalent to Corning Optical single mode fiber.

e. Stringing shall strictly adhere to procedures recommended by the manufacturer. Ensure that the bending radius of the fiber optic cable is not exceeded at any time.

f. At Splice locations, the ADSS fiber optic cable shall be routed down and attached to wood pole structures as shown on Drawing 41 1029 and 41 1030.

g. For fiber splices on the transmission line, refer to Division 14 of this specification, bidding schedule item “Furnish and install fiber optic cable and associated equipment”.

5. Bidding Schedule item for “Furnish and install spiral-type vibration dampers for

0.465-inch-diameter optical overhead ground wire” includes determining the number of vibration dampers needed, furnishing material and performing all work, including testing, required to furnish and install vibration dampers for optical overhead ground wire.

a. Vibration damper Drawing SG-WS 1001 contains all the wire, span and tension data necessary for a damper manufacturer to provide recommendations for quantities and spacing for dampers. The Contractor should provide this specification paragraph and the damper drawing to the manufacturer for application recommendations and final spacing for attachments.

b. The Contractor shall provide spiral-type vibration dampers for the optical overhead ground wire.

6. Bidding Schedule item “Spare parts” includes furnishing the following material and delivery to the Gering, Nebraska, warehouse (1030 U Street) or as determined by the COR. Deliver the one (1) reel of 0.465-inch optical overhead ground wire to Loveland, Colorado, warehouse (5555 E. Crossroads Blvd):

a. Optical overhead ground wire assemblies suitable for 0.465-inch diameter optical overhead ground wire with armor rods as follows:

(1) Ten (10) Type OPGW-SL optical overhead ground wire assemblies.

(2) One (1) Type OPGW-TH optical overhead ground wire assemblies.

(3) One (1) Type OPGW-TV optical overhead ground wire assemblies.

(4) Four (4) Type OPGW-TLV optical overhead ground wire assemblies.

b. Twenty (20) fiber optic cable mounting downlead clamps as shown on Drawing 41 1030.

c. One (1) 5,280-foot reel of 0.465-inch-diameter, forty-eight (48) fiber CC-57/465 optical overhead ground wire on a steel reel as specified in Bidding Schedule item “Furnish and install one (1) 0.465-inch-diameter, forty-eight (48) fiber optical overhead ground wire.”

d. Spiral-type vibration dampers suitable for 0.465-inch-diameter optical overhead ground wire as follows:

(1) Ten (10) percent of the total quantity of spiral-type vibration dampers furnished and installed in Bidding Schedule item “Furnish and install spiral-type vibration dampers for 0.465-inch-diameter optical overhead ground wire”.

e. ADSS fiber optic cable assemblies suitable for 0.512-inch diameter ADSS as follows:

(1) Five (5) Type ADSS-TRUN all dielectric self supporting fiber optic cable assemblies.

(2) Two (2) Type ADSS-TH all dielectric self supporting fiber optic cable assemblies.

f. One (1) 2,700-foot reel of 0.512-inch diameter, forty-eight (48) fiber ADSS on a steel reel as specified in Bidding Schedule item “Furnish and install one (1) 0.512-inch-diameter, forty-eight (48) ADSS Fiber Optic cable.”

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. DESCRIPTION OF BID ITEM:

1. Bidding Schedule does not contain a separate item for “Environmental Quality Protection”. The cost of compliance with requirements of Division 13 shall be included in the applicable bidding schedule items. The Contractor shall review the latest version of WAPA’s Construction Standards Division 13 Environmental Quality Protection and comply with all requirements.

DIVISION 14 – COMMUNICATION FACILITIES

A. DESCRIPTION OF BID ITEMS:

1. Bidding Schedule item “Furnish and install fiber optic cable and associated equipment” includes determining lengths, furnishing and installing conduit, spare fiber coil brackets, splice enclosures, patch panels and LFMC (Liquid tight flexible metal Conduit), with preinstalled single-mode fiber optic duct cable (LFMC/FODC), removing LFMC from FODC at TOS and control building cable entry, splicing the FODC to OPGW and terminating FODC into the patch panels with pre-connectorized pigtails. Perform all end to end testing of installed fiber.

The total fiber optic installation, including OPGW, splice enclosures, LFMC/FODC, patch panels and single mode connectorized pigtails, will result in forty-eight (48) optical communication paths per Table 14-1.

TABLE 14-1

FIBER PATH NO. FIBERS

SG-WS 48

a. Material: All fiber optic communications equipment shall be commercially manufactured off-the-shelf items.

(1) Liquid tight Flexible Metal Conduit (LFMC): Manufactured/preinstalled with 48-count

Fiber Optic Distribution Cable (FODC): LFMC shall be part number OCC DX048DSLX9YRI2 (48 Strand single mode fiber, OCC DX Series Interlocked Armored Distribution, OFCR Riser, Singlemode 9/125, yellow jacket LFMC designating single mode fiber, with easily removable LFMC from FODC), or equivalent. The LFMC connector with grounding lug shall be Crouse-Hinds part no.

LT100G-SA or equivalent. The fibers shall have no factory splices in any continuous length. Each continuous length of cable shall be wound on a separate reel. The end of each length of cable shall be sealed so no moisture can enter the cable. The cable shall be wound onto the reel so it can be pulled off without binding, kinking, or other problems. All optical fibers shall be compliant with or exceed the requirements of ITU-T G.652.D (e.g., SMF-28e).

(2) Fiber Optic Conduit, Buried: Buried conduit system shall be SDR-11, 2-inch, tone-able, high density polyethylene (HDPE) conduit, orange in color, with pull-tape, smooth exterior wall and ribbed interior wall Carlon HDPE P/N A15BJ1JNNBxxxx, or equal, where xxxx is length. Conduit system shall have a complete, easily accessible, tone-able link (for locating purposes), from the TOS to the fiber optic vault. Conduit system includes overhead to underground transition risers (as applicable).

(3) Fiber Optic Patch Panel: In the control building at WS and the Crawford Fiber

Repeater Site, the Contractor shall provide and install fiber optic patch panel equivalent to AFL Xpress Fiber Management 4RU Model No. XFM-4U-B-0, with splice trays/cassettes and factory connectorized SC-APC pigtails equivalent to AFL PolyMod Patch and Splice Module Model No. PM-L-12-UST-0-S-01 for the termination of the FODC. The fiber optic patch panel shall have SC type connectors.

(4) Cable Storage Brackets: For fiber splice points at substation(s) and transmission line(s), provide one (1) new external coil bracket AFL CB-44-3AL, or equivalent at TOS for WS and on transmission line splice points. Reference Standard Drawing 31 1097.

(5) Fiber Optic Splice Enclosures: Provide and mount optical splice enclosures, equal to AFL Opti-Guard OG-03, on the coil brackets, as follows:

(a) Substation(s): TOS optical splice enclosures shall be equivalent to AFL

Opti-Guard OG-03 (no bullet guard) including all accessories required for the splicing of the 48-fiber OPGW to FODC. Optical splice enclosure accessories shall include, but not limited to: Connector kits, minimum forty eight (48) fiber capacity splice trays/organizers, splice protection sleeves, fiber routing kits and connector kits. The splice tray/organizer shall allow for sufficient bend radii as recommended by the cable/fiber manufacturer. Splice enclosures shall be airtight, moisture proof, re-enterable and re-sealable.

(b) Transmission Line: Fiber optic splice enclosures shall be equivalent to AFL bullet proof SB-01 splice enclosure, including all accessories required for the splicing of the 48-fiber, OPGW to OPGW and/or OPGW to ADSS. Optical splice enclosure accessories shall include, but not limited to: Connector kits, minimum 48-fiber capacity splice trays/organizers, splice protection sleeves, fiber routing kits and connector kits. The splice tray/organizer shall allow for sufficient bend radii as recommended by the cable/fiber manufacturer, with minimum 24-inches bare fiber in each splice tray. Splice enclosures shall be airtight, moisture proof, re-enterable and re-sealable.

(6) Grounding System: OPGW shall be bonded in accordance with specification and standard drawings.

(7) Signs:

(a) Substation Equipment Identification Signs: Signs shall be furnished and installed at TOS at WS and at Structure 105/4. Signs shall be in accordance with standard Drawing 31 1000 and located above the coil bracket and/or splice enclosure. Lettering on the signs shall be as follows:

48 FIBER OPGW CC-57/465

SG – WS

SPLICE ENCLOSURE

b. Installation (refer to Figure 14-1, for information only):

(1) At WS: Provide and install at TOS, OPGW cable storage racks and splice enclosures, as specified above. Placement and grounding as shown in Standard Drawing 31 1097 and configured as shown in Standard Drawing 41 1035. Completed installation shall have a minimum length of 60-feet of OPGW and 60-feet of LFMC/FODC on the coil bracket, or such that the coil bracket(s) is filled, whichever is greater.

(2) Install LFMC/FODC combination, as a continuous run, from splice enclosure at

TOS(s) to fiber optic patch panel in the control building. At TOS splice enclosure, remove the LFMC from the FODC, reserving sufficient length FODC for splicing.

Ground the LFMC per Drawing 31 1099. Using LFMC connector, terminate the LFMC into TOS splice enclosure, creating a watertight seal. Continuous length of LFMC/FODC from the TOS splice enclosure, shall be routed through 2-inch rigid conduit and HDPE, through fiber optic vaults and existing conduit, to control building cable entry. Reference Drawing WS 1700 and 31 1099.

(3) Route LFMC through building cable entry and ensure LFMC is sealed at the cable entry. At approximately 10-feet after the cable entry (inside the building), remove the LFMC from the FODC. Make sure there is sufficient length of FODC remaining for the following:

(a) Approximately 30-feet of reserve coil/FODC after entering building, per COR

(attach coil to wall, adhere to FODC minimum bend radius requirements),

(b) Routing through building to fiber optic patch panel, and

(c) Splicing as follows: 1-foot of fiber with buffer tube, inside fiber optic patch panel to splice tray and 16-inches of fiber inside splice tray. Terminate the end of LFMC with the appropriate sized, straight, LFMC fittings (with ground lugs), as specified above, and terminate the ground lug to the building ground with #6 AWG ground wire, using split bolt and apply corrosion protection per industry practice. Route remaining exposed FODC fiber cable to the patch panel and terminate with pigtails in the fiber optic patch panel. Reference Drawing WS 3500 for the location of communication rack. Lengths of LFMC and FODC shall be adjusted per the discretion of the COR.

(4) HDPE conduit (e.g., trenching) between Structure 105/4 and 105/4A shall be backfilled with at least 3-inches of a “1 sack” cementitious flowable fill and marker tape at 12-inches below finish grade, per industry standard and WAPA standards for buried conduit.

(5) At the Crawford Fiber Repeater Site: From the distribution pole, route ADSS into the building through cable duct and cable vault and coil approximately 30-feet of cable before terminating at the patch panel. Reference Drawings CFD 4050 and CFD 7050.

(6) Fiber Splicing/Termination: At WS and the Crawford Fiber Repeater Site, terminate/splice all fibers in the order of, and in accordance with, the industry standard color coding (ANSI/ITA-598-C-2005). All splicing shall be fusion splicing. This includes splicing FODC to pre-connectorized pigtails in the substation, splicing FODC-OPGW transition splices at the TOS. All splicing points shall be spliced straight through (e.g., Fiber 1 to 1, 2 to 2, etc.). See splice lengths in paragraph (3) above. Label patch panels indicating site name of distant end patch panel.

Figure 14-1: Wayside Substation TOS

c. Fiber Optic Testing: Perform fiber optic testing in accordance with the following:

(1) Factory Tests of FODC, OPGW, and ADSS: Factory tests shall be performed on each fiber of every reel at the factory. Results shall be recorded and included in the packaging with the cables. Product data sheets showing the cable characteristics including chromatic dispersion, index of refraction, dimensional quality and tensile strength shall be provided from the manufacturer.

(2) Pre-installation Field Tests of FODC, OPGW, and ADSS: Contractor shall notify COR at least 14-days prior to pre-installation field tests to enable WAPA observers to be present. The Contractor shall test all fibers of each reel of FODC, OPGW and ADSS upon delivery to insure the fiber was not damaged during shipment and handling.

(a) Contractor shall submit optical time domain reflectometer (OTDR) charts (on

CD: Raw test data and PDF formatted chart data) at 1310nm and 1550nm, showing launch conditions and all other parameters used in setup, time and date, as well as a diagram of the test setup. For these tests, each fiber, in turn, shall be mechanically spliced to a single-mode launch fiber, minimum of 1 km in length, which is connected to the OTDR (record length of launch cable). The OTDR charts shall illustrate and quantify the losses of each length of fiber and stress points on the fiber. Review the traces carefully and explain unusual discontinuities in detail. The OTDR testing waveforms, in native format from the test set, shall be stored on an optical disk and included with the required submittals, as well as, PDF formatted waveforms via email to WAPA-A7930. If OTDR testing is performed using equipment other than Wavetek or Tektronics, the Contractor shall supply WAPA with legitimate test set vendor software necessary to view and manipulate the native test set waveforms.

(3) Post-Installation Field Tests of FODC, OPGW and ADSS: Contractor shall notify

COR at least 7-days prior to the post-installation field tests to enable WAPA observers to be present. Perform end to end testing from each fiber patch panel appearance, at each end of the completed fiber path shown in Table 14-2. Perform and record results as shown in Table 14-3. These tests shall include:

(a) Contractor shall submit optical time domain reflectometer (OTDR) charts (on

CD: Raw test data and PDF formatted chart data) at 1310nm and 1550nm, showing launch conditions and all other parameters used in setup, time and date, as well as a diagram of the test setup. For these tests, each fiber, in turn, shall be mechanically spliced to a single-mode launch fiber, minimum of 1 km in length, which is connected to the OTDR (record length of launch cable).

These charts shall illustrate and quantify the losses at each splice, length of fiber and stress points on the fiber. These tests shall document all splices along the optical path. Contractor to review the traces carefully and explain unusual discontinuities in detail. OTDR measurements shall be made in both directions and the splice loss results bi-directionally averaged. Bidirectional averaged values shall be clearly displayed in a separate table that identifies each splice location by transmission line and structure number. Bi-directionally averaged splice loss shall not exceed 0.10dB. Submit OTDR results for every fiber of the completed fiber system. The OTDR testing waveforms, in native format from the test set, shall be stored on an optical disk and included with the required submittals, as well as PDF formatted waveforms via email to WAPA-A7930. If the OTDR testing is performed using equipment other than Wavetek or Tektronics, the Contractor shall supply WAPA with legitimate test set vendor software necessary to view and manipulate the test set waveforms.

(b) Optical loss testing (end to end): Perform continuity and attenuation tests at 1310nm and 1550nm, using an optical loss test set pair (power meter pair), on each complete fiber path. Testing shall demonstrate/verify continuity, fiber sequence integrity (i.e., fiber 1 to 1, fiber 2 to 2, etc.) and quantify overall end-to-end losses for each fiber. Total end-to-end losses, including fiber loss and splices shall not exceed the values in Table 14-2.

TABLE 14-2 – MAXIMUM LIMITS FOR FIBER PATH BIDIRECTIONAL AVERAGE LOSS

(4) Instrument Calibration: All test equipment shall be calibrated with certification traceable to the National Institute of Standards and Technology relative to their intended use. Vendor to provide test equipment model number, serial number and calibration dates of test equipment as part of the test data package.

(5) Qualifications of Splicing and Testing Personnel: The fiber optic tester shall have a minimum of 1-year testing and operations experience with the OTDR test equipment used for tests required in this specification and shall be…