Harford County Library Administration Office Renovations
Solicitation number
26-124
Issued by
Harford County, Maryland

About this file

This is a construction project manual and specification document for the Harford County Library Administration Office Renovations, a capital improvement project managed by the Harford County Department of Public Works in Maryland. The project encompasses comprehensive interior and exterior renovations including demolition and installation of new acoustic ceiling systems, floor finishes, doors, windows, and interior walls; creation of new offices and a training room; renovation of restrooms; installation of new mechanical ductwork and electrical systems; and selective plumbing replacements and additions. The contractor is responsible for furnishing and installing all HVAC equipment with complete labor, materials, equipment, supervision, startup, testing, and balancing in accordance with contract documents. Seven alternates are offered for optional inclusion: aluminum storefront systems (SF1 and SF1A), roof hatch and ladder installation, fence extension, operable gate into parking lot, new exterior hollow metal doors and frames, exterior soffit/fascia along the front building, and new glazed exterior window systems (SF-2 and SF-3). The construction documents were prepared by Frederick Ward Associates, Inc., with a permit/bid construction set dated June 17, 2026, and project manual dated June 22, 2026.

The contract is structured as a single prime contract with detailed specifications across multiple divisions covering general requirements, demolition, concrete, metals, wood and plastics, thermal and moisture protection, openings, finishes, specialties, furnishings, fire suppression, plumbing, HVAC, electrical, and exterior improvements. The project operates under an alteration work framework, requiring the contractor to maintain partial owner occupancy during construction, coordinate with existing utility services, implement fire prevention and dust control measures, and protect existing materials and finishes. Payment procedures utilize AIA Document G702 and G703 forms with Applications for Payment submitted according to an established schedule of values. The contractor must submit a detailed submittal schedule, coordinate drawings for multi-trade integration, and maintain compliance with specialized procedures for lead-safe work practices and fire prevention outlined in Section 013516 for alteration projects.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LIBRARY ADMINISTRATION OFFICE

RENOVATIONS

FOR

HARFORD COUNTY PUBLIC WORKS

Project Manual

June 22, 2026

PERMIT/BID CONSTRUCTION SET

June 17, 2026

HARFORD COUNTY

TABLE OF CONTENTS 000002-1

SECTION 000002 – TABLE OF CONTENTS

DIVISION 1 – GENERAL REQUIREMENTS

011000 SUMMARY

012300 ALTERNATES

012600 CONTRACT MODIFICATION PROCEDURES

012900 PAYMENT PROCEDURES

013100 PROJECT MANAGEMENT AND COORDINATION

013300 SUBMITTAL PROCEDURES

013516 ALTERATION PROJECT PROCEDURES

014000 QUALITY REQUIREMENTS

015000 TEMPORARY FACILITIES AND CONTROLS

017300 EXECUTION

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

017823 OPERATION AND MAINTENANCE DATA

017839 PROJECT RECORD DOCUMENTS

017900 DEMONSTRATION AND TRAINING

DIVISION 2 – DEMOLITION

024119 SELECTIVE DEMOLITION

DIVISION 03 - CONCRETE

032000 CONCRETE REINFORCING

033000 CAST-IN-PLACE CONCRETE

DIVISION 05 - METALS

051200 STRUCTURAL STEEL FRAMING

055000 METAL FABRICATIONS

DIVISION 6 – WOOD & PLASTIC

061000 ROUGH CARPENTRY

064116 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

074646 FIBER-CEMENT SIDING

076200 SHEET METAL FLASHING AND TRIM

077200 ROOF ACCESSORIES

079200 JOINT SEALANTS

DIVISION 08 - OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES

081416 FLUSH WOOD DOORS

083513 CUSTOM WOOD FRAME WITH ACRYLIC PANEL DOORS

084113 ALUMINUM FRAMED ENTRANCES AND STOREFRONTS

087100 DOOR HARDWARE

088000 GLAZING

DIVISION 09 - FINISHES

092216 NON-STRUCTURAL METAL FRAMING

092900 GYPSUM BOARD

093013 CERAMIC TILING

TABLE OF CONTENTS 000002-2

095123 ACOUSTICAL TILE CEILINGS

096513 RESILIENT BASE AND ACCESSORIES

096519 RESILIENT TILE FLOORING

096813 TILE CARPETING

098116 ACOUSTIC BLANKET INSULATION

099124 INTERIOR PAINTING (MPI STANDARDS)

DIVISION 10 - SPECIALTIES

101423.16 ROOM-IDENTIFICATION PANEL SIGNAGE

102113.19 PLASTIC TOILET COMPARTMENTS

102800 TOILET, BATH, AND LAUNDRY ACCESSORIES

104413 FIRE PROTECTION CABINETS

104416 FIRE EXTINGUISHERS

DIVISION 12 - FURNISHINGS

123661.16 SOLID SURFACING COUNTERTOPS

DIVISION 21 - FIRE SUPPRESSION

210518 ESCUTCHEONS FOR FIRE-SUPPRESSION PIPING

210553 IDENTIFICATION FOR FIRE-SUPPRESSION PIPING AND EQUIPMENT

211313 WET-PIPE SPRINKLER SYSTEMS

DIVISION 22 – PLUMBING

220517 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING

220518 ESCUTCHEONS FOR PLUMBING PIPING

220519 METERS AND GAGES FOR PLUMBING PIPING

220523 GENERAL-DUTY VALVES FOR PLUMBING PIPING

220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

220719 PLUMBING PIPING INSULATION

221116 DOMESTIC WATER PIPING

221119 DOMESTIC WATER PIPING SPECIALTIES

221316 SANITARY WASTE AND VENT PIPING

221319 SANITARY WASTE PIPING SPECIALTIES

224100 PLUMBING FIXTURES

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

230548.13 VIBRATION CONTROLS FOR HVAC

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

230713 DUCT INSULATION

230800 COMMISSIONING OF HVAC

230900 INSTRUMENTATION AND CONTROL FOR HVAC

230993 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

231123 FACILITY NATURAL-GAS PIPING

232300 REFRIGERANT PIPING

233113 METAL DUCTS

233300 AIR DUCT ACCESSORIES

233423 HVAC POWER VENTILATORS

233713 DIFFUSERS, REGISTERS, AND GRILLES

235113.16 VENT DAMPERS

TABLE OF CONTENTS 000002-3

235123 GAS VENTS

235416.13 GAS-FIRED FURNACES

237416.11 PACKAGED, SMALL-CAPACITY, ROOFTOP AIR-CONDITIONING UNITS

238126 SPLIT-SYSTEM AIR-CONDITIONERS

238216.13 REFRIGERANT AIR COILS

DIVISION 26 – ELECTRICAL

260505 SELECTIVE DEMOLITION FOR ELECTRICAL-06-18-2025

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES-06-18-2025

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS-06-18-2025

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS-06-18-2025.PDF

260533.13 CONDUIT FOR ELECTRICAL SYSTEMS-06-18-2025

260533.16 BOXES FOR ELECTRICAL SYSTEMS-06-18-2025

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS-06-18-2025

260923 LIGHTING CONTROL DEVICES-06-18-2025

262200 LOW-VOLTAGE TRANSFORMERS-06-18-2025

262416 PANELBOARDS-06-18-2025

262726 WIRING DEVICES-06-18-2025

265100 INTERIOR LIGHTING-06-18-2025

DIVISION 32 – EXTERIOR IMPROVEMENTS

323113 CHAIN LINK FENCES

END OF SECTION 000002

Harford County Library Administration Office Renovations

Frederick Ward Associates, Inc.

Permit/Bid Construction Set

SUMMARY 011000 - 1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Work covered by Contract Documents.

2. Contractor's use of site and premises.

3. Coordination with occupants.

4. Specification and Drawing conventions.

5. Miscellaneous provisions.

B. Related Requirements:

1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.3 DEFINITIONS

A. Work Package: A group of specifications, drawings, and schedules prepared by the design team to describe a portion of the Project Work for pricing, permitting, and construction.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:

1. Demolition and new work to acoustic ceiling systems, floor finishes, doors, windows, interior walls, the installation of new offices and training room and renovation of restrooms. New mechanical ductwork and electrical systems with selective plumbing replacements and additions.

2. Furnish and install all HVAC equipment, including all labor, materials, equipment, supervision, startup and testing and balancing required for a complete and operations systems, accordance with the contract documents.

3. Add alternates to for the exterior storefront, windows, rear doors, new automatic swing gate and fencing, new soffit/fascia board and a new roof hatch and ladder..

Frederick Ward Associates, Inc.

SUMMARY 011000 - 2

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.5 CONTRACTOR'S USE OF SITE AND PREMISES

A. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Driveways, Walkways and Entrances: Keep driveways loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

B. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.6 COORDINATION WITH OCCUPANTS

A. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated

1.7 WORK RESTRICTIONS

A. Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.

B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging for temporary utility services according to requirements indicated:

1. Notify Owner not less than two days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

C. Smoking and Controlled Substance Restrictions: Use of tobacco products , alcoholic beverages, and other controlled substances on Owner's property is not permitted.

Frederick Ward Associates, Inc.

SUMMARY 011000 - 3

D. Employee Identification: Provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.

E. Employee Screening: Comply with Owner's requirements for background screening of Contractor personnel working on Project site.

1. Maintain list of approved screened personnel with Owner's representative.

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.

3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.

4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.

C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

Frederick Ward Associates, Inc.

SUMMARY 011000 - 4

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

Harford County Department of Public Works Library Administration Office Renovations

Frederick Ward Associates, Inc.

ALTERNATES 012300 - 1

SECTION 012300 - ALTERNATES

1.1 SUMMARY

A. Section includes administrative and procedural requirements for alternates.

1.2 DEFINITIONS

A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if the Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.

1. Alternates described in this Section are part of the Work only if enumerated in the Agreement.

2. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternates into the Work. No other adjustments are made to the Contract Sum.

1.3 PROCEDURES

A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.

1. Include, as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation, whether or not indicated as part of alternate.

B. Execute accepted alternates under the same conditions as other Work of the Contract.

C. Schedule: A Part 3 "Schedule of Alternates" Article is included at the end of this Section. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SCHEDULE OF ALTERNATES

A. Alternate No. 1 : Aluminum Storefront System - SF1 and SF1A .

1. Base Bid: There is no work for this alternate under the base bid.

Harford County Library Administration Office

ALTERNATES 012300 - 2

2. Alternate: Demolition of existing and installation of new aluminum storefront openings and doors, along the front of the building. New door hardware shall match the operations of the existing doors. Door 151B must have egress hardware. Total quantity of new aluminum storefront doors is four (4). Aluminum storefront shall be thermally broken with insulated glazing.

B. Alternate No. 2: Roof hatch and ladder

1. Base Bid: There is no work under the base bid

2. Alternate: Selective demolition for new roof opening, reinforcing of new opening, new roof hatch with curbs flashed to existing metal roof, new ladder and wall reinforcing, as showing on sheet S1-1 and A1.1

C. Alternate No. 3: Fence Extension

1. Base Bid: There is no work for this alternate under the base bid

2. Alternate: Modify the existing chain link fence by extending the existing fence as shown on sheet A6.1. This alternate includes a double 3' swing gate with latch hardware, a single 3' wide gate with egress hardware and new chain link fencing to match the existing in size and height.

D. Alternate No. 4: Operable Gate into Parking Lot

1. Base Bid: There is no work for this alternate under the base bid.

2. Alternate: Demolish the existing gate and provide a new gate as shown on sheet

A6.1. Provide a new operator equal to the Liftmaster RSW12UL. Install new island to protect a new post mounted access control keypad equal to the Liftmaster MK500GS. Cut and patch existing asphalt for connection of the keypad to the operators and to install an underground pressure plate/sensor for the exit lane of the parking lot. Install new conduit and wiring back to building, as required by the manufacturer of the gate operators. Modify the existing fencing to transition smoothly into the new gate.

E. Alternate No. 5: New Exterior Hollow Metal Doors, Frames and Hardware

1. Base Bid: There is no work for this alternate under the base bid.

2. Alternate: Demolition of the existing hollow metal doors and frames and add new exterior hollow metal doors, frames and hardware for the following doors: 119B, 125C, 131B, 132B, 143A and 154.

F. Alternate No. 6: Exterior soffit/fascia along the front of the building.

1. Base Bid: There is no work for this alternate under the base bid.

2. Alternate: Selective demolition of the existing sloped soffit/fascia over the storefront openings along the front of the building. New cementitious siding and exterior plywood sheathing shall be installed, along with trim and flashing. See detail 6/A3.2 for partial section. See specification section 074646 - Fiber-cement siding.

G. Alternate No. 7: New Glazed Exterior Window System - SF-2, SF-3

Harford County Library Administration Office

ALTERNATES 012300 - 3

1. Base Bid: There is no work for this alternate under the base bid.

2. Alternate: Selective demolition of the existing glazed openings and the installation of new thermally broken aluminum storefront system with 1" thick glazed fixed unit. Replace flashing/add flashing at head and sills.

END OF SECTION 012300

Harford County Library Administration Office

Frederick Ward Associates, Inc.

Permit/Bid Construction Set

June 17, 2026

CONTRACT MODIFICATION PROCEDURES 012600 - 1

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

B. Related Requirements:

1. Section 013100 "Project Management and Coordination" for requirements for forms for contract modifications provided as part of web-based Project management software.

1.3 MINOR CHANGES IN THE WORK

A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

Frederick Ward Associates, Inc.

Permit/Bid Construction Set

June 17, 2026

CONTRACT MODIFICATION PROCEDURES 012600 - 2

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Work Change Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Architect may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

1.7 WORK CHANGE DIRECTIVE

A. Work Change Directive: Architect may issue a Work Change Directive on EJCDC

Frederick Ward Associates, Inc.

Permit/Bid Construction Set

June 17, 2026

CONTRACT MODIFICATION PROCEDURES 012600 - 3

Document C-940. Work Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Work Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012600

Frederick Ward Associates, Inc.

Permit/Bid Construction Set

June 17, 2026

PAYMENT PROCEDURES 012900 - 1

SECTION 012900 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.3 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.

1.4 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule. Cost-loaded Critical Path Method Schedule may serve to satisfy requirements for the schedule of values.

1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule.

2. Submit the schedule of values to Owner at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

3. Subschedules for Phased Work: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values coordinated with each phase of payment.

4. Subschedules for Separate Elements of Work: Where the Contractor's construction schedule defines separate elements of the Work, provide subschedules showing values coordinated with each element.

B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the schedule of values:

Frederick Ward Associates, Inc.

Permit/Bid Construction Set

June 17, 2026

PAYMENT PROCEDURES 012900 - 2

a. Project name and location.

b. Owner's name.

c. Owner's Project number.

d. Name of Architect.

e. Architect's Project number.

f. Contractor's name and address.

g. Date of submittal.

2. Arrange schedule of values consistent with format of AIA Document G703.

3. Arrange the schedule of values in tabular form, with separate columns to indicate the following for each item listed:

a. Related Specification Section or division.

b. Description of the Work.

c. Name of subcontractor.

d. Name of manufacturer or fabricator.

e. Name of supplier.

f. Change Orders (numbers) that affect value.

g. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent. Round dollar amounts to whole dollars, with total equal to Contract Sum.

1) Labor.

2) Materials.

3) Equipment.

4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum.

5. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between items stored on-site and items stored off-site.

6. Allowances: Provide a separate line item in the schedule of values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.

7. Purchase Contracts: Provide a separate line item in the schedule of values for each Purchase contract. Show line-item value of Purchase contract. Indicate Owner payments or deposits, if any, and balance to be paid by Contractor.

8. Overhead Costs, Proportional Distribution: Include total cost and proportionate share of general overhead and profit for each line item.

9. Overhead Costs, Separate Line Items: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items.

10. Temporary Facilities: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items.

Frederick Ward Associates, Inc.

Permit/Bid Construction Set

June 17, 2026

PAYMENT PROCEDURES 012900 - 3

11. Schedule of Values Revisions: Revise the schedule of values when Change Orders or Construction Change Directives result in a change in the Contract Sum. Include at least one separate line item for each Change Order and Construction Change Directive.

1.5 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments, as certified by Architect and paid for by Owner.

B. Payment Application Times: The date for each progress payment is indicated in the Owner/Contractor Agreement. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.

1. Other Application for Payment forms proposed by the Contractor may be acceptable to Architect and Owner. Submit forms for approval with initial submittal of schedule of values.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.

2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.

3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.

E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.

b. Value of previously stored materials put in place after date of previous

Frederick Ward Associates, Inc.

Permit/Bid Construction Set

June 17, 2026

PAYMENT PROCEDURES 012900 - 4

Application for Payment and on or before date of current Application for Payment.

c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.

F. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Certification of completion of final punch list items.

3. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

4. Updated final statement, accounting for final changes to the Contract Sum.

5. AIA Document G706.

6. AIA Document G706A.

7. AIA Document G707.

8. Evidence that claims have been settled.

9. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

10. Final liquidated damages settlement statement.

11. Proof that taxes, fees, and similar obligations are paid.

12. Waivers and releases.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012900

PROJECT MANAGEMENT AND

COORDINATION

013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project, including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

3. RFIs.

4. Digital project management procedures.

5. Web-based Project management software package.

6. Project meetings.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

C. Related Requirements:

1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

2. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.

1.3 DEFINITIONS

A. BIM: Building Information Modeling.

B. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.4 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, telephone number, and email address of entity performing

Harford County Library Administration Office

013100 - 2 subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

1.5 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.

Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results, where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and scheduled activities of other contractors and direction of Project coordinator to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

1.6 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to

Harford County Library Administration Office

013100 - 3 indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Use applicable Drawings as a basis for preparation of coordination drawings. Prepare sections, elevations, and details as needed to describe relationship of various systems and components.

b. Coordinate the addition of trade-specific information to coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.

c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

f. Indicate required installation sequences.

g. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternative sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

2. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

3. Electrical Work: Show the following:

a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.

c. Panel board, switchboard, switchgear, transformer, busway, generator, and motor-control center locations.

d. Location of pull boxes and junction boxes, dimensioned from column center lines.

4. Review: Architect will review coordination drawings to confirm that, in general, the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If Architect determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Architect will so inform Contractor, who shall make suitable modifications and resubmit.

5. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 013300 "Submittal Procedures."

C. Coordination Drawing Process: Prepare coordination drawings in the following manner:

Harford County Library Administration Office

013100 - 4

1. Electrical Installer will indicate service and feeder conduit runs and equipment in green color. Electrical Installer shall forward drawing files to Communications and Electronic Safety and Security Installer.

2. Communications and Electronic Safety and Security Installer will indicate cable trays and cabling runs and equipment in purple color. Communications and Electronic Safety and Security Installer shall forward completed drawing files to Contractor.

3. Contractor shall perform the final coordination review. As each coordination drawing is completed, Contractor will meet with Architect to review and resolve conflicts on the coordination drawings.

D. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

1. File Preparation Format:

a. Same digital data software program, version, and operating system as original Drawings.

2. File Submittal Format: Submit or post coordination drawing files using PDF format.

3. Architect will furnish Contractor one set of digital data files of Drawings for use in preparing coordination digital data files.

a. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.

1.7 REQUEST FOR INFORMATION (RFI)

A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Owner name.

3. Owner's Project number.

4. Name of Architect.

5. Architect's Project number.

6. Date.

7. Name of Contractor.

8. RFI number, numbered sequentially.

9. RFI subject.

Harford County Library Administration Office

013100 - 5

10. Specification Section number and title and related paragraphs, as appropriate.

11. Drawing number and detail references, as appropriate.

12. Field dimensions and conditions, as appropriate.

13. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

14. Contractor's signature.

15. Attachments: Include sketches, descriptions, measurements, photos, Product

Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Architect.

1. Attachments shall be electronic files in PDF format.

D. Architect's Action: Architect will review each RFI, determine action required, and respond. Allow seven days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt by Architect of additional information.

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect n writing within 5 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect.

4. RFI number, including RFIs that were returned without action or withdrawn.

Harford County Library Administration Office

013100 - 6

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect's response was received.

8. Identification of related Minor Change in the Work, Construction Change

Directive, and Proposal Request, as appropriate.

9. Identification of related Field Order, Work Change Directive, and Proposal

Request, as appropriate.

F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within seven days if Contractor disagrees with response.

1.8 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Use of Architect's Digital Data Files: Digital data files of Architect's CAD drawings will be provided by Architect for Contractor's use during construction.

1. Digital data files may be used by Contractor in preparing coordination drawings, Shop Drawings, and Project Record Drawings.

2. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.

B. PDF Document Preparation: Where PDFs are required to be submitted to Architect, prepare as follows:

1. Assemble complete submittal package into a single indexed file, incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier.

3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.

1.9 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times a minimum of seven days prior to meeting.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Architect is responsible for recording significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner, , and General Contractor, within three days of the meeting.

B. Preconstruction Conference: Owner will schedule and conduct a preconstruction

Harford County Library Administration Office

013100 - 7 conference before starting construction, at a time convenient to Owner and Architect, but no later than 15 days after execution of the Agreement.

1. Attendees: Authorized representatives of Owner, Architect, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Responsibilities and personnel assignments.

b. Tentative construction schedule.

c. Critical work sequencing and long lead items.

d. Designation of key personnel and their duties.

e. Lines of communications.

f. Procedures for processing field decisions and Change Orders.

g. Procedures for RFIs.

h. Procedures for processing Applications for Payment.

i. Submittal procedures.

j. Preparation of Record Documents.

k. Use of the premises and existing building.

l. Work restrictions.

m. Working hours.

n. Owner's occupancy requirements.

o. Responsibility for temporary facilities and controls.

p. Procedures for disruptions and shutdowns.

q. Construction waste management and recycling.

r. Parking availability.

s. Office, work, and storage areas.

t. Equipment deliveries and priorities.

3. Minutes: Architect is responsible for recording and distributing meeting minutes.

C. Progress Meetings: Conduct progress meetings at monthly intervals.

1. Coordinate dates of meetings with preparation of payment requests.

2. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Review and correct or approve minutes of previous progress meeting.

Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule.

Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule

Harford County Library Administration Office

013100 - 8 revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

4. Minutes: Architect will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting, where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)

END OF SECTION 013100

Harford County Library Administration Office

Frederick Ward Associates, Inc.

Permit/Bid Construction Se

June 17, 2026

SUBMITTAL PROCEDURES 013300 - 1

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

B. Related Requirements:

1. Section 012900 "Payment Procedures" for submitting Applications for Payment and the schedule of values.

2. Section 013100 "Project Management and Coordination" for submitting coordination drawings and subcontract list and for requirements for web-based Project software.

3. Section 014000 "Quality Requirements" for submitting test and inspection reports, and schedule of tests and inspections.

4. Section 017700 "Closeout Procedures" for submitting closeout submittals and maintenance material submittals.

5. Section 017823 "Operation and Maintenance Data" for submitting operation and maintenance manuals.

6. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.

7. Section 017900 "Demonstration and Training" for submitting video recordings of demonstration of equipment and training of Owner's personnel.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Architect's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

Frederick Ward Associates, Inc.

Permit/Bid Construction Se

June 17, 2026

SUBMITTAL PROCEDURES 013300 - 2

1.4 SUBMITTAL SCHEDULE

A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Architect and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.

2. Initial Submittal Schedule: Submit concurrently with startup construction schedule.

Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

3. Final Submittal Schedule: Submit concurrently with the first complete submittal of Contractor's construction schedule.

a. Submit revised submittal schedule as required to reflect changes in current status and timing for submittals.

4. Format: Arrange the following information in a tabular format:

a. Scheduled date for first submittal.

b. Specification Section number and title.

c. Submittal Category: Action; informational.

d. Name of subcontractor.

e. Description of the Work covered.

f. Scheduled date for Architect's final release or approval.

g. Scheduled dates for purchasing.

h. Scheduled date of fabrication.

i. Scheduled dates for…