Asbestos Abatement
Solicitation number
IFB27000006
Issued by
Chesterfield County, Chatham Town, Virginia

About this file

This is an Invitation for Bids (IFB) issued by Chesterfield County Procurement Department on behalf of Chesterfield County and Chesterfield County Public Schools in Virginia for asbestos abatement services. The IFB seeks bids to establish a requirements contract for all labor, supplies, materials, permits, and equipment necessary to perform asbestos removal services. Sealed bids are due on August 10, 2026, at 2:00 p.m., with bid opening occurring 30 minutes thereafter via a virtual Microsoft Teams link. Prospective bidders are required to submit current Virginia Department of Professional and Occupational Regulations licenses for Asbestos Contractor, Asbestos Supervisor, Asbestos Worker, and Asbestos Analytical Laboratory work. The contractor must visit each job site to verify conditions prior to project commencement. Inquiries must be submitted to Ashley Hill, Senior Sourcing Officer, no later than July 30, 2026, at 4:00 p.m. The contract will be a requirements-based agreement with work performed at various Chesterfield County locations, with all pricing quoted on an F.O.B. Destination basis including freight, delivery, and incidental charges.

The IFB does not specify a maximum contract value, award date, or contract term in the document provided. All pricing must be submitted in units of quantity and/or work as specified in the pricing schedule, with unit prices governing in cases of discrepancy. The County reserves the right to negotiate with the lowest responsive bidder if the bid exceeds available funds, to reject any bid in whole or in part, or to waive any informality. Bids submitted in hard copy must be delivered to the Lane B. Ramsey Building at 9901 Lori Road, P.O. Box 51, Chesterfield, Virginia 23832, or submitted electronically through the County's eProcurement system. The contract is subject to appropriation and ratification by the Chesterfield County Board of Supervisors and School Board for each fiscal year. The contractor must maintain all required Virginia asbestos licenses throughout the contract term and comply with all federal, state, and local regulations, including OSHA, EPA, and Virginia Administrative Code requirements for asbestos abatement operations.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHESTERFIELD COUNTY

PROCUREMENT DEPARTMENT

CHESTERFIELD, VIRGINIA

Invitation for Bids IFB Number…………………………………………………………………………………………...IFB27000006 Title……………………………………………………………………………………………………Asbestos Abatement

Issue Date……………………………………………………………………………………………...July 13, 2026

Sealed Bids Due:……………………………………………………………………………………August 10, 2026, 2:00 P.M.

Sealed Bids Opening: 30 minutes after the Sealed Bids Due date and time specified above Bid Opening Location ................................................................. Chesterfield County Virtual Bid Opening Link

Inquiries: Questions which may arise as a result of this solicitation may be addressed to Ashley Hill, Senior Sourcing Officer, at (804) 748-1703, or by email to hillas@chesterfield.gov. Inquiries must be received no later than July 30, 2026 at 4:00 p.m. in order to be considered. Contact initiated by a bidder concerning this solicitation with any other County representative, not expressly authorized elsewhere in this document, is prohibited. Any such unauthorized contact may result in disqualification of the bidder from this transaction.

All prices shall be F.O.B. Destination: Various Chesterfield County locations Freight, delivery costs, and incidental charges shall be included.

My signature below certifies that:

• I agree to abide by all conditions of this bid and that I am authorized to sign this bid;

• the accompanying bid is not the result of, or affected by, any unlawful act of collusion with another person or company engaged in the same line of business or commerce, or any act of fraud punishable under § 18.2-498.1, et. seq. of the Code of Virginia. Furthermore, I understand that fraud and unlawful collusion are crimes under the Virginia Governmental Frauds Act, the Virginia Government Bid Rigging Act, the Virginia Antitrust Act, and Federal Law, and can result in fines, prison sentences, and civil damage awards;

• that the accompanying bid is in compliance with applicable provisions of the State and Local Government Conflict of Interests Act (§ 2.2-3100, et. seq. of the Code of Virginia). Specifically, without limitation, no County/School Board employee or a member of the employee’s immediate family shall have a proscribed personal interest in a contract; and

• that the accompanying bid is in accordance with applicable provisions of the Virginia Public Procurement Act, Art. 6 Ethics in Public Contracting (§ 2.2-4367, et. seq. of the Code of Virginia), and any other applicable law as set forth therein.

In compliance with this Invitation for Bids and to all conditions imposed therein the undersigned offers and agrees to furnish the goods/services in accordance with this signed bid.

Complete Legal Name of Firm:

Order From Address:

Remit To Address:

Signature: Email:

Name (type/print): Title:

Fed ID No.: Phone: ( ) Fax: ( )

This page must be returned with the Bid Form.

mailto:hillas@chesterfield.gov

TABLE OF CONTENTS

I. PURPOSE

II. ABBREVIATIONS, NAMES AND DEFINITIONS

III. SCOPE OF WORK/SPECIFICATIONS

IV. INSTRUCTIONS

V. TERMS AND CONDITIONS

VI. BID FORM

ATTACHMENT A - Virginia State Corporation Commission (SCC) Registration Information

I. PURPOSE

The purpose of this Invitation for Bids (IFB) is to solicit bids to establish a requirements contract for all labor, supplies, materials, permits and equipment necessary to perform asbestos removal services for Chesterfield County and Chesterfield County Public Schools.

II. ABBREVIATION, NAMES AND DEFINITIONS

A. The following acronyms or abbreviations referenced in Invitation for Bid documents are defined to mean the associated names. Both names and addresses are subject to change and are believed to be, but are not assured to be, accurate and up-to-date as of the date of the Invitation for Bid:

ACM Asbestos Containing Material

AIA American Institute of Architects

1735 New York Avenue, N.W.

Washington, DC 20006

(202) 626-7474

ANSI American National Standards Institute

1430 Broadway New York, NY 10018

(212) 354-3300

ASTM American Society for Testing and Materials

1916 Race Street Philadelphia, PA 19103

(215) 299-5400

CFR Code of Federal Regulations Available from Government Printing Office

Washington, DC. 20402 (Usually first Published in Federal Register)

DOT Department of Transportation 1200 New Jersey Avenue, Se Washington, DC 20590

(855) 368-4200

EPA Environmental Protection Agency

401 M Street, SW Washington, DC 20460

(202) 382-3949

MSHA Mine Safety and Health Administration

NIOSH National Institute for Occupational Safety and Health

NIST National Institute of Standards and Technology (U.S. Department of Commerce) Gaithersburg, MD 20234

(301) 921-1000

OSHA Occupational Safety and Health Administration

(U.S. Department of Labor) Government Printing Office Washington, DC 20402

TEM Transmission Electron Microscopy

VA DPOR Virginia Department of Professional And Occupational Regulation 3600 West Broad Street Richmond, Virginia, 23230-4917

(804) 367-8500

VDOT Virginia Department of Transportation

1401 E Broad St.

Richmond, VA 23219

(804) 786-2700

UL Underwriters Laboratories

333 Pfinngsten Road Northbrook, IL 60062

B. Definitions:

ACCREDITED/ACCREDITATION: When referring to a person, Abatement Contractor or laboratory, means that such person is accredited in accordance with Section 206 of Title II of the Toxic Substances Control Act (AHERA Regulations).

ACM: Asbestos-Containing Material(s).

AEROSOL: A system consisting of particles, solid or liquid, suspended in air.

AGGRESSIVE SAMPLING: High-activity level air sampling which results in all settled asbestos remaining airborne and uniformly disturbed through the use of special entrainment and mixing techniques. This makes any settled asbestos fibers accessible to the sampling filters for subsequent detection. The technique is described in 40 C.F.R. 763.90, Appendix A to Subpart E; and Guidance for Controlling ACM in Buildings, Appendix M; and Virginia Administrative Code (1VAC30-110) Aggressive Air Sampling Standards To Be Utilized In Final Clearance Inspections For Asbestos Projects In Local Education Agencies And Public Colleges And Universities In The Commonwealth Of Virginia.

AIR FILTRATION DEVICE (AFD): Air filtration device (AFD) is part of the pressure differential system in which the air is filtered. The AFD is to be equipped with HEPA filters.

AIR MONITORING: The process of measuring the fiber content of a specific volume of air.

NIOSH Method 7400 or TEM Method in 40 C.F.R. 763, Subpart E, Appendix A, shall be used for sampling and analysis.

AMENDED WATER: Water containing a wetting agent or surfactant.

APPROVE: Where used in conjunction with the QP's response to submittals, requests, applications, inquiries, reports, and claims by the Abatement Contractor, "approved" shall be held to limitations of QP's responsibilities and duties and does not release the Contractor from responsibilities to fulfill requirements of the Contract Documents. Approved shall also mean consent by U.S. EPA of training programs and the like.

ASBESTOS: The asbestiform varieties of serpentinite (chrysotile), riebeckite (crocidolite), cummingtonite-grunerite (asmosite), anthophyllite, and actinolite-tremolite. Both the asbestiform and non-asbestiform varieties of the above minerals and any of these materials that have been chemically treated and/or altered shall be considered to be asbestos.

ASBESTOS-CONTAINING MATERIAL (ACM): Any material containing more than 1% by weight of asbestos of any type or mixture of types.

ASBESTOS-CONTAINING WASTE MATERIAL: Any material, which is or is suspected of being or any material contaminated with an asbestos-containing material, which is to be removed from a Work Area for disposal.

AUTHORIZED VISITOR: Personnel authorized by the Project Officer, testing lab personnel, or a representative of any Federal, State or local regulatory agency having authority over the project are considered authorized visitors.

BARRIER: Any surface that seals off the Work Area to inhibit the movement of fibers.

BREATHING ZONE: A hemisphere forward of the shoulders with a radius of approximately 6 to 9 inches.

BRIDGING ENCAPSULANT: An encapsulant that forms a discrete layer on the surface of an in situ asbestos matrix.

CEILING CONCENTRATION: The concentration of an airborne substance that shall not be exceeded.

CLEAN ROOM: An uncontaminated room having facilities for the storage of employees' street clothing and uncontaminated materials and equipment.

COMPLETION OF WORK - The event that occurs when (1) the work has been completed, successfully tested and approved in accordance with the contract, (2) all submittals required by the contract (including operation and maintenance manuals) have been made, and (3) all punch list items and restoration work required by the contract documents has been completed.

CONSULTANT – Shall mean a representative designated by the County as consultant for the project, to act as such and designated to be in charge of the work, acting directly through duly authorized representatives of the County.

CONTRACTOR: Refers to the person, firm, or corporation providing the goods and services for this contract and/or sub-contract - "Asbestos Removal Project Design."

CRITICAL BARRIER: Two layers of 6 mil polyethylene sheeting on wall or three layers on floor;

spray foam or duct tape used to completely seal off the Work Area to prevent spread of fibers to surrounding areas.

DECONTAMINATION (DECON) AREA: An enclosed area adjacent and connected to the regulated area and consisting of an equipment room, shower room and a clean room which is used for the decontamination of workers, materials and certain equipment contaminated with asbestos. This shall serve as the only entrance or exist to the Work Area.

DEMOLITION: The wrecking or taking out of any building component, system, finish or assembly of a facility together with any related handling operations.

DISPOSAL BAG: A 6-mil thick, leak-proof polyethylene bag used for transporting asbestos waste from the work area to the disposal site. Each is labeled in compliance with OSHA

1926.1101 as follows:

DANGER

CONTAINS ASBESTOS FIBERS

AVOID CREATING DUST

CANCER AND LUNG DISEASE HAZARD

And U.S. DOT ORM-E label for Asbestos-Hazardous Material (including Asbestos Waste Manifest) and statements as required.

ENCAPSULANT: A material that surrounds or embeds asbestos fibers in an adhesive matrix to prevent release of fibers.

ENCAPSULATION: Treatment of ACM with an encapsulant.

ENCLOSURE: The construction of an airtight, impermeable, permanent barrier around asbestos-containing material to control the release of asbestos fibers into the air.

EQUIPMENT ROOM (CHANGE ROOM): A contaminated room located within the decontaminated area that is supplied with impermeable bags or containers for the disposal of contaminated protective clothing and equipment.

EXTRA WORK - Shall mean work other than that required, either expressed or implied, by the contract in its present form.

FILTER: A media component used in respirators to remove solid or liquid particles from the respired air.

FINAL ACCEPTANCE - The event that occurs when the Consultant issues to the County or the County issues to the Contractor a written statement that the Contractor has completely performed all punch list items, has made all necessary submittals to the County and/or Consultant and has satisfied all of the Contractor’s obligations under the contract documents.

FINAL PAYMENT - Payment by the County to the Contractor after completion of the work so that the Contractor has received all payments due him under the terms of the contract documents for performing and completing the work.

FRIABLE ASBESTOS MATERIAL: Material that contains more than 1.0% asbestos by Polarized Light Microscopy (PLM), and that can be crumbled, pulverized, or reduced to powder by hand pressure when dry. This includes previously non-friable material which becomes damaged to the extent that, when dry, may be crumbled, pulverized or reduced to powder by hand pressure.

FURNISH: Except as otherwise defined in greater detail, the term "furnish" is used to mean supply and deliver to project site, ready for unloading, unpacking, assembly, installation, etc., as applicable in each instance.

GENERAL SUPERVISOR: Site Superintendent, Foreman: is the Abatement Contractor's representative at the work site. This person can be the Competent Person required by OSHA, 29 C.F.R. 1926.1101.

GLOVEBAG: A sack (typically constructed to 6 mil transparent polyethylene) with two inward projecting long sleeve gloves, which are designed to enclose an object from which an asbestos-containing material is to be removed.

HEPA FILTER: A high efficiency particular air (HEPA) filter that removes from air 99.97% or more of monodispersed dioctyl phthalate (DOP) or dioctyl sebacate (DOS) particles having a mean particle diameter of 0.3 microns.

HEPA FILTER VACUUM COLLECTION EQUIPMENT (OR VACUUM CLEANER): HEPA

filtered vacuum collection equipment with a filter system capable of collecting and retaining asbestos fibers. Filters shall be 99.97% efficiency for retaining fibers of 0.3 microns or larger.

INDICATED: The term "Indicated" is a cross-reference for Notes or Schedules on Drawings, to other paragraphs or Schedules in the Specifications, and to similar means of recording requirements in Contract Documents.

INSPECTOR - The person designated and authorized by the County to carry out instructions given by the County and to inspect the work performed and the materials supplied by the Contractor.

INSTALL: Unless defined in greater detail, "install" is used to describe operations at the project site including unloading, unpacking, assembly, erection, placing, anchoring, applying, working on dimension, finishing, curing, protecting, cleaning and similar operations, as applicable in each instance.

INSTALLER: The "installer" is defined as the entity (person or firm) engaged by the Abatement Contractor or Sub-Contractor to perform a particular trade at the work site, including installation, erection, application and similar required operations. Such entities (installers) shall be expert in operations they perform.

LANDFILL RECEIPT: Document signed by a landfill operator acknowledging the receipt of ACM waste.

MANIFEST: A document detailing chain of custody for ACM waste hauled.

NEGATIVE PRESSURE GLOVEBAG: A glove bag that is composed of flexible plastic that can be subjected to negative pressure without collapsing.

NEGATIVE PRESSURE ENCLOSURE: Pressure differential of a minimum of -0.02 column inches of water as related to outside pressure. Utilization of a manometer shall be used as evidence.

NEGATIVE PRESSURE RESPIRATOR: A respirator in which the air pressure inside the respiratory-inlet covering is positive during exhalation in relation to the air pressure of the outside atmosphere and negative during inhalation in relation to the air pressure of the outside atmosphere.

PENETRATING ENCAPSULANT: An encapsulant that is absorbed by the in situ asbestos matrix without leaving a discrete surface layer.

PERMISSIBLE EXPOSURE LIMIT (PEL): The Abatement Contractor shall ensure that no employee is exposed to an airborne fiber concentration of asbestos in excess of 0.1 fiber/cc expressed as an 8-hour TWA as determined by the OSHA Reference Method of 29 C.F.R.

1926.1101

PERSONAL SAMPLING MONITORING: Air samples taken in the breathing zone of workers as required by OSHA 29 C.F.R. 1926.1101.

PLASTICIZE: Means to cover floors and walls with polyethylene sheeting as herein specified and in accordance with the temporary Enclosure Section.

PRESSURE DIFFERENTIAL: Air pressure lower than surrounding areas, caused by exhausting air from a sealed space (Work Area).

PRESSURE DIFFERENTIAL SYSTEM: A local exhaust system, utilizing HEPA filtration, capable of maintaining a pressure differential inside the Work Area and a constant airflow from adjacent areas into the Work Area and exhausting that filtered air outside the Work Area.

PROJECT MANAGER (CONTRACTOR): The Abatement Contractor's employee responsible for the total oversight of the project.

PROJECT MONITOR: Means the individual(s) representing the "County/Schools" to make inspections, conduct monitoring, observe progress, approve schedules, and accept services under the terms of the contract.

PROJECT OFFICER: The County/Schools employee responsible for overall contract administration.

PROTECTION FACTOR: The ratio of the ambient concentration of an airborne substance to the concentration of the substance inside the respirator at the breathing zone of the wearer. The protection factor is a measure of the degree of protection provided by a respirator to the wearer.

PROVIDE: Except as otherwise defined in greater detail, the term "provide" means furnish and install, complete and ready for intended use, as applicable in each instance.

QUALIFIED PERSON (QP): A Registered Architect, Professional Engineer, Certified Industrial Hygienist, or Industrial Hygienist who has successfully completed training and is therefore accredited under a legitimate State Model Accreditation Plan as described in 40 CFR 763 as a Building Inspector, Management Planner, Project Monitor, and Asbestos Project Designer. The QP must be qualified to perform visual inspections as indicated in ASTM E 1368-11. The QP shall be appropriately licensed in the State of Virginia as a Project Monitor and Project Designer.

REGULATED ACM: Means friable ACM, non-friable ACM that has become friable, non-friable ACM that shall be or has been subjected to sanding, grinding, cutting or abrading or non-friable ACM that has a high probability of becoming or has become crumbled, pulverized or reduced to powder by the forces expected to act on the ACM during renovation or demolition.

REGULATED AREA: An area where asbestos removal operations are performed which is isolated by physical boundaries to prevent entry of unauthorized persons or the spread of asbestos dust, fibers or debris. Within this area, the airborne concentration of asbestos could reasonably be expected to exceed the PEL.

REMOVAL: The taking out or stripping of all ACM from a damaged area or associated area or space.

REMOVAL ENCAPSULANT: A penetrating encapsulant specifically designed for removal of asbestos-containing materials rather than for in situ encapsulation.

RESPIRATOR: A device designed to protect the wearer from the inhalation of harmful atmospheres.

SHORT-TERM EXPOSURE LIMIT (STEL): A "ceiling" concentration, identified in OSHA regulations, of an airborne substance that shall not be exceeded for the duration of any 30-minute period (Current STEL for asbestos is 1.0 fiber/cc.).

SUBMITTAL: Items that is required to be presented to the Project Officer and/or the QP for review, consideration or decision.

SURFACING MATERIAL: Material in a building that is sprayed-on, trowelled-on or otherwise applied to surfaces or structural members for acoustical, fireproofing or other purposes.

SURFACTANT: A chemical wetting agent added to water to improve penetration, thus reducing the quantity of water required for a given operation or area.

TESTING LABORATORY: The "testing laboratory" is an independent entity to perform specific air sampling and analysis at the work site and associated areas, to report and (if required) interpret results. Analysis shall be performed by a laboratory accredited by the American Industrial Hygiene Association (AIHA) and having demonstrated a proficient rating in AIHA's Proficiency Analytical Testing (PAT) Program. The laboratory shall be licensed by the Virginia Department of Commerce as an Asbestos Analytical Laboratory. The laboratory shall also be accredited by the National Institute of Standards and Technology (NIST) through the National Voluntary Laboratory Accreditation Program (NVLAP) for bulk sample analysis and air sample analysis by TEM (TEM Method of 40 C.F.R. 763, Subpart E, Appendix A).

TIME WEIGHTED AVERAGE (TWA): The average concentration of a contaminant in air during a specific time period.

VISIBLE EMISSIONS: Any emissions containing particulate asbestos material that are visually detectable without the aid of instruments. This does not include condensed water vapor.

WASTE SHIPMENT RECORD: Means the original shipping document, originated and signed by the waste generator (Abatement Contractor) used to track and substantiate the disposal of ACM waste as described in 40 C.F.R. Part 61.

WASTE GENERATOR: Means the licensed Asbestos Abatement Contractor removing ACM waste from the property.

WET CLEANING: The process of eliminating asbestos contamination from building surfaces and objects by using cloths, mops, or other cleaning utensils that have been dampened with amended water or diluted removal encapsulant and afterwards thoroughly decontaminated or disposed of as asbestos-containing waste.

WORK AREA: The area where asbestos-related work or removal operations are performed; the Work Area is defined and/or isolated to prevent the spread of asbestos dust, fibers, or debris, and entry by unauthorized personnel. The Work Area is a Regulated Area as defined by 29 C.F.R. 1926.1101.

WORK SITE: The term "work site" is defined as the space available to the Contractor for performance of the work either exclusively or in conjunction with others performing other work as part of the project. The extent of project site is shown on the Drawings, and may or may not be identical with the description of land upon which the project is to be built.

III. SCOPE OF WORK/SPECIFICATIONS

A. GENERAL

1. IN ORDER TO BE CONSIDERED RESPONSIVE TO THIS BID, THE CONTRACTOR

MUST INCLUDE WITH THEIR BID SUBMITTAL THE FOLLOWING LICENCES

ISSUED BY THE COMMONWEALTH OF VIRGINIA DEPARTMENT OF

PROFESSIONAL AND OCCUPATIONAL REGULATIONS FOR ASBESTOS

ABATEMENT WORK/SPECIALTY AS FURTHER DESCRIBED HEREIN:

a. Asbestos Contractor’s License

b. Asbestos Supervisor’s License

c. Asbestos Worker’s License

d. Asbestos Analytical Laboratory License

THE ABOVE LICENSES MUST BE MAINTAINED THROUGHOUT THE TERM OF THE

CONTRACT.

2. The Contractor shall furnish all labor, materials, equipment, supplies, and mobilization, necessary to remove and dispose of all asbestos-containing materials (ACM).

3. The Contractor shall perform limited floor, wall and ceiling demolition throughout the proposed demolition area of the project site in coordination with general architectural, plumbing, electrical, mechanical work to adequately expose piping and/or any other materials that may contain asbestos for inspection. The Qualified Person shall conduct asbestos testing of suspect pipe insulation materials and/or any other materials discovered during the renovation and/or demolition. The Contractor’s scope of work shall be adjusted accordingly based on the results of testing if additional materials are uncovered. The Contractor shall conduct all asbestos removal within negative pressure containment. Where thermal system insulation and surfacing materials have fallen off behind walls, the Contractor shall clean and decontaminate these areas. Where ceiling materials (plaster, drywall, and acoustical tile) has been contaminated with asbestos, the Contractor shall be responsible for the removal and disposal of this material as asbestos-containing waste. All debris generated from the demolition of the walls/ceilings and pipe chases shall be treated as asbestos containing materials (ACM) and the areas shall be decontaminated as part of the work. Tasks which require full demolition will be bid separately.

4. The Contractor shall be required to vent negative air exhaust to the outdoors in order to provide the required -0.02“ w.c. negative pressure at all times throughout the negative pressure enclosure (work area). The Contractor shall coordinate with the General Contractor and/or County/School representative to determine the best method of venting negative air exhaust.

5. The Contractor shall coordinate with the General Contractor and the County representative selected for this project to verify that the structure will support the planned activities and comply with local building codes and OSHA requirements.

6. The Contractor shall visit each job site to verify all conditions prior to start of any project.

Visits can be scheduled by calling the designated County representative.

7. Air Monitoring

a. Collection of all OSHA required air sampling to determine personnel asbestos exposure levels t o shall be conducted by a representative of the Contractor.

Sampling and analysis costs shall be borne by the Contractor.

b. Air monitoring samples shall be analyzed by a microscopist who has successfully completed the NIOSH 582 course - Sampling and Evaluating Airborne Asbestos Dust.

c. Samples for air monitoring shall be collected by a person in accordance with methods prescribed in Chapter X of the Federal OSHA Industrial Hygiene Field Operations Manual or by equivalent procedures.

d. Air monitoring shall be in compliance with 1910.1001 (f) of the OSHA standards.

e. Air monitoring (protection of the Abatement Contractor's employees) shall be provided throughout the removal and cleaning operations. Air monitoring shall be conducted and evaluated by a testing laboratory employed by the Contractor to ensure compliance with applicable EPA and OSHA regulations. The Abatement Contractor shall bear all cost associated with Contractor’s employee testing.

f. Environmental samples outside of containment and clearance sampling shall be performed by the Qualified Person/Project Monitor.

g. Area samples shall be collected outside the containment in areas of highest risk of contamination.

h. Samples shall be collected on a daily basis outside the containment.

i. All analytical results shall be presented as a signed "Certificate of Analysis" form, and shall include the following information:

Date and time sampling began.

Flow rate of samples.

Sampling time elapsed.

Concentration of fibers.

Site/individual sampled.

Signature of Analyst.

j. All analytical results shall be posted at the work site entrance within

24 hours of sampling. Results shall be designated as to sample type (area or personal) and location.

k. If fiber contaminations outside the containment area are found to be in excess of

0.01 fibers/cc, the Contractor shall immediately stop work and notify the building manager and Project Monitor. Work shall not be resumed until corrective action has been engaged.

l. The Project Monitor may conduct air sampling at critical barriers other than those designated to the Contractor. Operations shall be discontinued immediately at any time visible emissions are observed emanating from the containment.

m. Collection of all OSHA required air monitoring shall be conducted in accordance with all applicable State and Federal regulations, and shall be the sole responsibility of the Contractor. The laboratory to be used shall be qualified to perform the NIOSH Method 7400, have an established quality control program, be licensed in the Commonwealth of Virginia and, in all respects, conform with the requirements under the OSHA standard.

8. Inspections

a. The Project Monitor shall conduct inspections throughout the project. Each step of the abatement project shall require his inspection/approval before proceeding to the next step.

b. Environmental and clearance sampling shall be conducted by a project monitoring firm retained by the County.

c. Materials and workmanship shall be subject to examination by the project monitor at all times during the construction and use of the asbestos containment. The Project Monitor shall have authority to reject defective material and workmanship and require its correction.

d. The Project Monitor may immediately suspend any work which is being conducted in an unsafe manner, (i.e., the potential for personal injury or property damage exists).

e. The Project Monitor shall ensure that the Contractor and their employees are licensed by the Commonwealth of Virginia Department of Professional and Occupational Regulations for Asbestos Abatement Work/Specialty.

9. Labeling

a. The Contractor shall post signs and ensure labels are affixed to all asbestos materials, scrap, waste, debris, etc. Signs shall be posted at all entrances to the work area.

b. The signs and labeling shall be of sufficient size to be clearly legible, and display the following:

DANGER

CONTAINS ASBESTOS FIBERS

AVOID CREATING DUST

CANCER AND LUNG DISEASE HAZARD

B. Personal Protection/Safety

1. Proper respiratory equipment in accordance with 29 CFR 1910.134, as suitable for the asbestos exposure in the work area, shall be provided by the Contactor used for the duration of the project. Sufficient filters for replacement of disposable filters shall be provided by the Contractor.

2. Workers shall wear disposable, full body coveralls, gloves, disposable head covers, and disposable footwear in the work area.

3. Respirators shall be sanitized daily by the Contractor or between shifts if employees share usage.

4. Eating, drinking, and chewing of gum or tobacco shall not be permitted in the work area, equipment room or shower area.

5. All individuals, without exception, shall wear an approved respirator, disposable coveralls, gloves, head cover, and footwear to enter the work area. Disposable clothing worn into the containment area shall not be transferred out until it is properly sealed within two separate six (6) mil asbestos disposal bags.

C. Decontamination

1. Greater than 25 linear feet or 10 square feet of TSI (thermal system insulation) or surfacing materials shall be removed, enclosed or encapsulated and a decontamination unit shall be constructed as follows:

a. The Contractor shall establish a decontamination unit to include an equipment room, clean room, and a shower outside each work area. The decontamination unit shall be continuous with the work area. The area shall include a clean room connected by a double poly barrier to a walk-through shower which is also connected by a double poly barrier to an equipment room. There shall also be a double poly barrier separating the equipment room and the work area.

b. The clean room shall contain boxes or lockers for each worker's street clothes. These items shall be provided by the Contractor.

c. Portable showers shall be used. No "facsimile" showers are allowed, (i.e., hose put through a poly slit with poly flooring). The shower shall have hot and cold water with separate controls for each.

d. Soap, shampoo, disposable towels, etc., shall be provided by the Contractor.

e. The decontamination unit chambers shall be cleaned daily.

f. The clean room, shower, and equipment room shall be sealed completely to ensure that the sole source of air flow through these areas originates from uncontaminated areas outside the asbestos removal, demolition, or renovation enclosure. The shower shall be drained and filtered to retain particles 5.0 microns or larger after each use to ensure that contaminated water is not released to uncontaminated areas. If waste is inadvertently released, it shall be cleaned up as soon as possible to prevent any asbestos in the water from drying and becoming airborne in areas outside the work area.

g. All workers shall use the following procedure. Remove street clothes in the clean room and put on the coveralls and all other protective equipment before entering the work area. Before exiting the work area all coveralls, head covers, boots, etc., shall be cleaned with a HEPA vacuum and removed. The respirator shall be properly fitted and provide an effective seal. Hoods, associated with disposable garments, shall be worn on the outside of the respirator-no clothing shall be permitted on the head and neck area beneath the respirator. After completely disrobing, with the exception of respirators, the workers shall proceed to the shower room. Under the shower, respirators shall be rinsed thoroughly then removed and cleaned. Used filters shall be placed in suitable plastic bags on the contaminated side of the shower, sealed, and labeled for disposal. All boots, shoes, etc., shall remain in the equipment room until the project is completed. Upon project completion, such items shall be bagged and moved to the next asbestos removal project as contaminated equipment or disposed of as asbestos waste. At no time are they to be worn through the shower to the clean room or outside of the containment area.

2. Decontamination: If materials that are not TSI (thermal system insulation) or surfacing materials, or if less than 25 linear feet or 10 square feet of TSI or surfacing materials will be removed, enclosed or encapsulated, then a decontamination unit shall be constructed as follows:

a. The Contractor shall establish a decontamination unit to include a clean room. T he decontamination unit shall be continuous with the work area.

The area shall include a clean room connected by a double poly barrier to the work area. The decontamination unit shall include a HEPA vacuum.

b. A HEPA vacuum shall be included in the decontamination unit.

D. Work Area Preparation/Instructions

1. Heating, Ventilation, and Air Conditioning (HVAC)

a. The Contractor shall notify the County at least five days in advance of project commencement so that the County may make the necessary modifications to the HVAC system.

b. The Contractor shall be responsible (coordinate with County) for ensuring that the HVAC system is isolated for the asbestos removal work area.

The HVAC system shall be locked and tagged out to ensure the system is not activated until the completion of the project.

c. The Contractor shall cover/isolate the HVAC duct grills (return and supply) inside the work area with two separate layers of 6 mil polyethylene sheeting. Each layer shall extend a few inches above the first layer and shall be sealed with duct tape.

d. The isolation of the HVAC system shall be inspected and approved by the Project Monitor before the project can proceed.

2. Clean and Remove Non-Stationary Items from the Work Area

Non-stationary items (i.e., furniture) which have been pre-determined to be contaminated with asbestos fibers, shall be HEPA vacuumed and/or wet-wiped to remove any asbestos-containing dust. The individuals performing the cleaning shall wear respiratory protection and disposable clothing. Once this has been accomplished, all non-stationary items shall be removed from the work area or covered and staged properly to prevent further contamination.

3. Seal Stationary Items

Items not being removed from the work area (i.e., large machinery, water fountains, etc.)

shall be wet-wiped and/or HEPA vacuumed, and then sealed with two layers of 6 mil fire retardant polyethylene and duct tape. Electrical outlets shall be covered with two layers of 6 mil polyethylene and duct tape.

4. Tape and Seal Windows with Fire Retardant Polyethylene

a. The edges of all windows shall be sealed with duct tape. Once the edges are sealed, the windows shall be covered with two layers of 6 mil fire retardant polyethylene and duct tape.

b. Windows which shall serve as outlets for the negative air machine exhaust shall be boarded with fire retardant plywood. The plywood shall be cut to proper dimensions to allow enough room for the negative air machine duct to exhaust to the outside of the building. The exhaust duct shall be secured to the plywood by with duct tape.

5. Isolating Access Areas/Critical Barriers

a. All access areas (i.e., doors, halls, etc.) which are not part of the work area shall be sealed off from public access. All doors, halls, or other areas not directly needed for work place access, shall be sealed with plywood (fire retardant) barriers and then covered with a minimum of two layers of 6 mil fire retardant polyethylene.

b. The County/Schools may choose to padlock boarded access doors in areas where security is a concern.

6. Sealing All Penetrable Areas

All penetrations of the floor, walls and ceilings shall be sealed with a minimum of two layers of 6 mil fire retardant polyethylene and duct tape to prevent airborne asbestos from escaping into the area outside the work area or from lodging in cracks around the penetration.

7. Covering the Work Area with Fire Retardant Polyethylene

a. A minimum of two layers of 6 mil fire retardant polyethylene sheeting shall be used to cover the work area floors. Spray adhesive and duct tape shall be used to seam sheets of polyethylene together. The floor covering shall be cut to proper dimensions (12" overlap, or greater) to extend up the wall all the way around the room. The polyethylene floor covering shall be flexible enough to prevent damage from foot traffic.

b. After the first floor layer has been secured, a second layer shall be installed with the seams of the first and second layers offset. The second layer of polyethylene shall extend at least 12 inches above the first layer on the wall and shall be secured with duct tape.

c. After covering stationary objects and the floors, two layers of 6 mil fire retardant polyethylene shall be used to cover the walls. The sheets of polyethylene shall be hung from the top of the wall, 2 inches below the asbestos material and shall be long enough to overlap the floor sheets by approximately 24 inches. The vertical sheets shall be overlapped and seam-sealed with adhesive duct tape.

d. Where feasible, and at locations requested by the County representative, the Contractor shall install windows of clear plexiglass within the containment walls, to allow the County representative clear visibility into the contained area.

e. It may be necessary in some instances to use nails and wood blocks to secure the polyethylene when duct tape cannot support the weight of the polyethylene (as when humidity is excessive). The Contractor shall reinforce the containment structure as needed to provide proper negative pressure-gross containment conditions.

8. Emergency and Fire Procedures

a. The Contractor shall establish emergency and fire procedures for evacuation. Emergency and fire procedures shall have priority over decontamination procedures.

b. The Contractor shall have arrows marking the exits and fire extinguishers on site.

9. Negative Air Pressure Within the Enclosure

a. After construction of the enclosure is complete, a ventilation system shall be installed by the Contractor to create a negative pressure within the enclosure with respect to the area outside the enclosure. This system shall be equipped with HEPA filters meeting specifications established in ANSI Standard 29.2-79. The system shall be required to produce a negative pressure of 0.02 inches of water column within the enclosure. The system shall provide at least four (4) air changes per hour. Negative air exhaust shall not be vented into the building(s).

b. The negative pressure system shall be operated in accordance with Appendix

J., pages J-1 through J-8, of the EPA Guidance Manual No EPA 560/85-024, entitled "Recommended Specifications and Operating Procedures for the Use of Negative Pressure Systems for Asbestos Abatement".

c. If during the removal process negative pressure is not maintained in the work area, all removal operations shall be immediately suspended. The County shall be notified immediately.

NOTE: Mandatory Smoke Test of the Enclosure Area shall be performed in ALL OSHA Class I Asbestos Abatement operations. This test shall consist of a two stage smoke test operation. Stage one, shall be performed without negative pressure; to ensure that all seams and openings are completely sealed and no smoke migrates outside the Work Area. Once Stage one is accomplished stage two shall be performed to ensure that proper air movement is occurring within the Work Area and is acceptable by the Qualified Person or County representative

E. Removal Process

1. The removal process shall begin once the work preparations have been finished, inspected, and approved.

2. The Contractor shall have a licensed asbestos supervisor on the job at all times (during work hours) to ensure that the enclosure, engineering controls, work methods and personal protective equipment are in compliance with all governing regulations and these specifications. The supervisor shall ensure that unauthorized personnel do not enter the enclosure and that all personnel that do enter the enclosure observe proper protection and decontamination procedures.

3. All asbestos-containing materials shall be thoroughly wetted with amended water to enhance penetration prior to executing removal. Thorough wetting of the asbestos-containing materials shall continue throughout the removal operations.

4. At the beginning of each workday, all polyethylene barriers shall be checked to ensure that they are still intact. Corrections/reparations shall be made prior to resuming asbestos removal activities.

5. Upon removal, the asbestos material shall be thoroughly wetted again and placed directly into waste bags. Asbestos-containing waste shall not accumulate on the floor before bagging. Asbestos waste bags shall not be dropped, thrown or otherwise carelessly handled at any time.

6. The waste bags shall be properly sealed immediately after filling.

7. It is advantageous to the clearance process to conduct removal towards the HEPA-filtered negative air machines. Once the bulk (gross) asbestos-containing material has been removed, efforts can be directed toward cleaning operations.

8. Removal Via Mini-enclosure

a. Small scale-short duration abatement tasks (cleaning surfaces for wall and ceiling penetrations, drilling of holes, installing mounting for conduit etc.) may be performed under mini-enclosure conditions with the preapproval of the County.

b. Mini-enclosure construction and work methods shall follow guidelines established in 29 CFR 1926.1101 Appendix G.

c. Proper respiratory equipment in accordance with 29 CFR 1910.134, as suitable for the asbestos exposure in the work area, shall be used for the duration of the project. Sufficient filters for replacement of disposable filters shall be provided by the Contractor.

d. The Project Monitor shall perform a visual inspection on each mini enclosure prior to completion/removal of unit. The Project Monitor may also choose to conduct clearance sampling prior to granting final clearance. Airborne fiber counts less than .01 f/cc shall be required prior to achieving final clearance.

9. Removal Via Negative Pressure Glove-Bags

a. Removal of asbestos-containing materials via negative pressure glove-bag techniques (as specified in these documents and in OSHA 29 CFR 1926.1101) may be performed only in areas preapproved by project designer.

b. All glove-bag set-up and asbestos removal activities shall be performed by two workers wearing proper respiratory equipment in accordance with 29 CFR 1910.134, as suitable for the asbestos exposure in the work area. Workers performing asbestos removal via glove-bag shall also wear disposable protective coveralls and gloves.

c. Areas affected by glove-bag removal of asbestos- containing materials shall be thoroughly pre-cleaned utilizing wet-wiping and HEPA-vacuuming equipment. At least one layer of 6 mil fire retardant polyethylene shall be used under each glove-bag as a drop cloth.

d. Workers shall thoroughly wet asbestos-containing materials prior to, and during asbestos removal activities. A wetting agent shall be utilized if water repelling asbestos-containing materials is encountered.

e. Each individual glove-bag unit shall be inspected and granted visual clearance by the Project Monitor prior to tear-down. All interior areas of each glove-bag shall be thoroughly encapsulated prior to tear down.

10. Removal of Asbestos-Containing Flooring Materials

a. Removal of asbestos-containing flooring and mastic materials shall be performed under negative pressure gross containment conditions as specified above, except that floors, walls and ceilings are not required to be covered with 6-mil polyethylene plastic. However, if floor mastic is being removed, a 3-foot tall “splash guard” consisting of 6-mil polyethylene plastic shall be constructed at the base of all walls within the contained area.

b. Nondestructive or “Armstrong” removal methods shall be permitted only in locations where quantities of asbestos-containing floor tile and/or mastic to be abated total 10 square feet or less.

c. Nondestructive or “Armstrong” removal of asbestos-containing floor tile and mastic shall be performed in accordance with the procedures outlined in the texts “Recommended Work Procedures For Resilient Floor Coverings” 1980/1987, and “Resilient Floor Tile, Asphaltic ‘Cutback’ Mastic, Sheet Vinyl Flooring, Instructions for Removal”, June 1993, issued by the Resilient Floor Covering Institute, 966 Hungerford Drive, Suite 12-B Rockville Maryland, 20850. Failure to follow the procedures as presented in the above listed texts shall result in the return to negative pressure gross containment conditions and/or work stoppage.

d. Construction activities with the potential for disturbing asbestos-containing flooring materials (drilling and/or driving of nails through asbestos-containing flooring materials et. al.) shall be performed by properly trained and protected personnel in accordance with these specifications.

F. Cleaning Operations

1. Upon completion of gross removal, the substrate shall be thoroughly brushed, and repeatedly wet-wiped with amended water.

2. The following steps shall be performed in sequential order:

a. All surfaces shall be thoroughly wet-wiped, allowed to dry, and wet-wiped again until all visual evidence of residual asbestos-containing materials has been eliminated (fine cleaning process).

b. Rags and water used for wet-wiping shall be continually changed. Rags utilized in the wet-wiping process shall be disposed of as asbestos-contaminated waste.

All asbestos - contaminated water shall be filtered (5.0 micron filtration) prior to being released in the sanitary sewer system.

c. The top (outer) floor layer of the equipment room shall be removed after fine cleaning has been completed to ensure that tracking of asbestos dust does not occur from this area.

d. Any visual debris shall be removed by HEPA vacuuming and/or wet-wiping.

e. Removal of gross contamination from all equipment in the work area shall be the final step of the fine cleaning process.

f. Equipment shall be wet-wiped, washed off in shower and removed from work area (except negative air machines). Tools such as scrapers, utility knives, brushes, etc., shall be sealed in plastic and transported to other jobs.

g. Following completion of fine cleaning, a thorough visual inspection will be conducted by the County. Lock down (encapsulation) of the work area may proceed only after visual clearance of the containment is granted by the Project Monitor. Failure of the visual inspection shall require the Contractor to provide additional labor until the work area is deemed acceptable by the County. An approved encapsulant material (provide SDS for review prior to application) shall be applied to the substrate and all other surfaces throughout the work area.

h. Following encapsulation, a period of 24 hours shall elapse to allow the encapsulant to dry, prior to initiating final air clearance procedures. Failure of air clearance sampling shall result in the re-execution of fine cleaning activities by the Contractor until satisfactory air sampling results are achieved.

i. Following the 24 hour waiting period, satisfactory air clearance monitoring and final visual inspection, removal of the inner (bottom) polyethylene layers shall take place.

j. All floors shall be wet-mopped. All walls shall be wet-wiped.

k. All critical barriers, decontamination unit, windows, HVAC system, electrical outlets, penetrations, and negative air machines shall be left in place until the project has been given final approval by the Project Monitor.

G. Waste Disposal

1. Asbestos debris shall be placed in a 44” x 60” 6-mil bag within the enclosure and sealed.

Upon removal from the enclosure, the bags shall be placed into a second, clear 6-mil bag.

2. Each asbestos waste bag shall be labeled with the warning sign along with all other pertinent information (including waste generator and generation site) in accordance with applicable federal and state regulations.

3. All asbestos waste bags shall be removed from the work area and stored in a properly prepared hauling container following the completion of each shift.

4. Sharp objects (i.e. plaster lathe, ceiling grid work, floor tiles, etc.) shall be bagged and placed into a labeled, fiber drum for disposal. Alternatively, they may be placed in a tear resistant container such as a box or canvas bag, the double-bagged as described above.

5. Asbestos shall be disposed of at an approved landfill.

6. A manifest shall accompany the asbestos waste and shall be signed by a responsible representative of the landfill.

7. Transportation of asbestos waste for disposal shall be in accordance with all Federal, State, Regional, and Local regulations.

8. If a temporary disposal receptacle (dumpster) is to be utilized, the following conditions shall be met:

a. The receptacle shall be fully covered.

b. Warning signs shall be placed on each side of the receptacle.

c. The receptacle shall be locked when not attended.

9. Workers unloading asbestos at the disposal site shall wear NIOSH approved respirators with HEPA filters. Bags shall be carefully unloaded by hand and placed on the ground.

10. An enclosed or covered vehicle shall be used to transport asbestos to the disposal site.

11. Copies of disposal manifests shall be submitted to the Project Manager within 45 days of the landfill receipt date.

12. In the event the Contractor is not licensed by the Commonwealth of Virginia to transport friable asbestos-containing materials, transportation services may be subcontracted to a transporter with a valid Commonwealth of Virginia Asbestos transporter license, subject to approval by Chesterfield County Risk Management Department, or General Services-Environmental Division. A copy of the transporters license shall be submitted to the Project Manager along with each applicable task quote.

H. Clearance Proceedings

1. Once all stages of preparation, removal, and clean-up have been completed satisfactorily, clearance…