831058roadFairfx.pdf

PDF 2 MB Posted

Attached to
Blenheim Blvd Bridge Deck Rehabilitation
Solicitation number
73929
Issued by
Fairfax County, Virginia

About this file

Blenheim Boulevard Bridge Deck Rehabilitation – Invitation for Bid

This is an Invitation for Bid (IFB 73929) issued by the City of Fairfax, Virginia Office of Procurement Services for construction services related to the Blenheim Bridge Deck Rehabilitation project (UPC 109811). The project scope includes milling the existing wearing surface, removing existing concrete median and sidewalks, performing localized repairs to precast prestressed voided slab units, sealing longitudinal joints to prevent moisture infiltration, installing a reinforced concrete bridge deck, casting new sidewalks, medians and parapets, eliminating deck joints by installing elastomeric expansion joints and link slabs, and performing localized repairs to the underside of the precast prestressed voided slab units. The bridge, originally constructed in 1976, carries four lanes of traffic over Accotink Creek on Route 6628 (Blenheim Boulevard) and measures 130 feet 9 inches in total length across three spans. An optional prebid conference is scheduled for July 11, 2026 at 11:00 a.m. at the project site. Sealed bids must be submitted electronically via the Virginia eVA website no later than August 5, 2026 at 2:00 p.m. The contractor must achieve substantial completion within 390 calendar days from the Full Notice to Proceed and final completion within 420 calendar days. The contract period commences upon award and issuance of the Full Notice to Proceed and extends until work is completed and accepted by the City.

This federally funded project is subject to compliance with Virginia Department of Transportation (VDOT) Standards & Specifications, FHWA Manual on Uniform Traffic Control Devices (MUTCD), and applicable federal regulations. All prospective bidders and joint venture members must be prequalified with VDOT and possess a certification of qualification prior to bidding. Bidders must submit a bid surety of five percent of the bid amount. The successful contractor must provide a 100 percent performance bond and 100 percent payment bond, both renewable annually. Liquidated damages are assessed at $1,350 per calendar day for non-completion beyond the contract time limit. A Virginia Contractor License is required prior to award, with the specific class depending on contract value. Allowable working hours are 7:00 a.m. to 6:00 p.m. on weekdays and 8:30 a.m. to 5:00 p.m. on Saturdays; work in active City streets is limited to 9:30 a.m. to 3:00 p.m. Monday through Thursday and 9:30 a.m. to 2:00 p.m. on Fridays. The project is funded through VDOT and federal sources (Federal Project CN No. RSTP-5B01(638)), with the City obtaining and paying for building permits and fees. All work must comply with applicable federal, state, and City requirements, with the federal or most conservative approach taking precedence in cases of conflict.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Fairfax, Virginia Office of Procurement Services

10455 Armstrong Street Fairfax, Virginia 22030

Title

Blenheim Blvd Bridge Deck Rehabilitation

Invitation for Bid

73929

Federal Project CN No.:

RSTP-5B01(638)

VDOT Project:

UPC 109811

Commodity Code(s)

91313, Construction Bridge 91366, Maintenance and Repair, Bridges

Procurement Officer

Patricia Innocenti, CPPO Patricia.innocenti@fairfaxva.gov

Issue Date June 30, 2026

Questions Deadline

July 22, 2026

Prebid Conference

July 16, 2026 @ 11:00 am Blenheim Blvd at Ridge Ave https://maps.app.goo.gl/mrudDZsu sE2eRso47

Due Date August 5, 2026 @ 2:00 p.m.

PAPER OR HAND-DELIVERED BIDS WILL NOT BE ACCEPTED IN RESPONSE TO THIS SOLICITATION. ALL BIDS MUST BE SUBMITTED ELECTRONICALLY VIA THE VIRGINIA PROCUREMENT SITE WHICH CAN BE FOUND AT HTTPS://EVA.VIRGINIA.GOV. ANY ASSISTANCE SUBMITTING BIDS THROUGH THIS SYSTEM

MUST BE DIRECTED SOLEY TO EVA SUPPORT/HELPDESK.

• Your business must be eVA registered and in active status.

• Start by clicking the Register Now link on the eVA website (www.eVA.virginia.gov).

mailto:Patricia.innocenti@fairfaxva.gov https://maps.app.goo.gl/mrudDZsusE2eRso47 https://www.fairfaxva.gov/?splash=http%3a%2f%2fwww.eVA.virginia.gov&____isexternal=true

The City of Fairfax does not discriminate against faith-based organizations in accordance with the Code of Virginia, § 2.2-

4343.1 or against a bidder or offeror because of race, religion, color, sex, national origin, age, disability, or any other basis prohibited by state law relating to discrimination in employment in the performance of its procurement activity.

THIS PROJECT IS FEDERALLY FUNDED

AS SUCH, THIS PROJECT SHALL BE SUBJECT TO COMPLIANCE WITH THE FEDERAL AND VDOT

REGULATIONS CONTAINED IN THIS DOCUMENT AND ELSEWHERE. THE CITY, VDOT’S CIVIL RIGHTS DIVISION OR OFFICE OF GENERAL INSPECTOR, GENERAL AUDITING DIVISION OF FHWA WILL PERFORM AUDITS TO ENSURE COMPLIANCE WITH ALL APPLICABLE TERMS AND CONDITIONS AND GUIDELINES

CONTAINED IN THIS DOCUMENT OR ELSEWHERE.

PREQUALIFICATION REQUIRED

All prospective bidders, including all members of a joint venture, shall be prequalified with the Virginia Department of Transportation and shall have received a certification of qualification (ref. Part Two, paragraph 14).

The City of Fairfax is committed to complying with the provisions of the Americans with Disabilities Act. This document will be made available in alternate format upon request – please contact the City’s Finance Department for more information.

PART ONE STATEMENT OF WORK

1. PROJECT BACKGROUND & INFORMATION

2. PROJECT IDENTIFICATION

3. SPECIFICATIONS

4. OPTIONAL PREBID CONFERENCE

5. PLANS AND SPECIFICATIONS

6. POINTS OF CONTACT

7. PERMITS AND LICENSES

8. PRICING

9. PLACE AND TIME OF PERFORMANCE

10. KEY PERSONNEL

11. CONTRACT PERIOD

12. TIME FOR COMPLETION AND LIQUIDATED DAMAGES FOR NON-COMPLETION:

13. BID SUBMISSION:

14. QUALIFICATION OF BIDDERS

15. DISTRIBUTION OF SOLICITATION DOCUMENTS

16. ADDITIONAL INFORMATION

17. CLARIFICATION OF TERMS:

18. ETHICS IN PUBLIC CONTRACTING:

19. ANTI‐DISCRIMINATION:

20. DEBARMENT STATUS:

21. ANTITRUST:

22. MANDATORY USE OF CITY FORM AND TERMS AND CONDITIONS:

23. PURCHASE ORDER:

24. PAYMENT:

25. UNREASONABLE CHARGES

26. PRECEDENCE OF TERMS:

27. CHANGES TO THE CONTRACT:

28. ANNOUNCEMENT OF AWARD:

29. SUBCONTRACTS:

30. E‐VERIFY PROGRAM:

31. DEFECTIVE SOLICITATION DOCUMENTS

32. COMPETITION INTENDED

33. EXCEPTIONS

34. EXPENSES INCURRED IN PREPARING BID

35. SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK

36. DEBARMENT STATUS

37. NEW MATERIAL

38. INFORMALITIES

39. CITY OF FAIRFAX BUSINESS LICENSE

40. VIRGINIA CONTRACTOR LICENSE

41. SURETY REQUIRED BID SURETY:

PART TWO – GENERAL CONDITIONS OF THE CONTRACT

42. PARKING

43. FAILURE TO EXECUTE:

44. PERFORMANCE SURETY:

45. FAILURE TO COMPLETE ON TIME GENERAL

46. VDOT AND/OR FEDERAL GOVERNMENT CONTRACTOR REQUIREMENTS

47. EXECUTION OFAGREEMENT

48. CIVILITY IN CITY WORKPLACES:

PART THREE– SPECIAL CONDITIONS OF THE CONTRACT

49. DEFINITIONS

50. COMMENCEMENT OF CONTRACT TIME; NOTICE TO PROCEED

51. STARTING THE PROJECT

52. BEFORE STARTING WORK

53. PRECONSTRUCTION CONFERENCE

54. INITIAL AND FINAL ACCEPTANCE OF SCHEDULES

55. CONTRACT DOCUMENTS AND INTENT

56. REFERENCED STANDARDS

57. REPORTING AND RESOLVING DISCREPANCIES

58. AMENDING AND SUPPLEMENTING CONTRACT DOCUMENTS

59. REUSE OF DOCUMENTS

60. DOCUMENTS ON THE JOB SITE

61. SUBMITTALS

62. TESTS

63. MATERIALS AND EQUIPMENT LIST

64. SURVEYS AND CONTROLS

65. AS‐BUILT DRAWINGS

66. AVAILABILITY OF LANDS

67. SUBSURFACE AND PHYSICAL CONDITIONS

68. DIFFERING SUBSURFACE OR PHYSICAL CONDITIONS

69. PROJECT OFFICER'S REVIEW

70. UNDERGROUND FACILITIES

71. REFERENCE POINTS

72. HAZARDOUS ENVIRONMENTAL CONDITION AT SITE

73. LIMITED RELIANCE BY CONTRACTOR ON TECHNICAL DATA AUTHORIZED

74. PROGRESS SCHEDULE

75. SUBSTITUTES OR "OR‐EQUAL" ITEMS

76. SUBSTITUTE ITEMS

77. SUBCONTRACTS

78. SUBCONTRACTOR PAYMENT

79. LAWS AND REGULATIONS

80. TAXES

81. USE OF SITE AND OTHER AREAS

82. LOADING STRUCTURES

83. RECORD DOCUMENTS

84. SAFETY AND PROTECTION

85. DAMAGES

86. Safety – (Contractor’s Safety Program)

87. SAFETY REPRESENTATIVE

88. EMERGENCIES

89. SHOP DRAWINGS AND SAMPLES

90. CONTINUING THE WORK

91. THE CONTRACTOR’S GENERAL WARRANTY AND GUARANTEE

92. DELEGATION OF PROFESSIONAL DESIGN SERVICES

93. OBLIGATION TO MITIGATE COSTS

94. ACCESS TO RECORDS

95. RELATED WORK AT SITE

96. COMMUNICATIONS TO THE CONTRACTOR

97. FURNISH DATA AND PAY WHEN DUE

98. LANDS & EASEMENTS; REPORTS & TESTS

99. INSPECTIONS, TESTS AND APPROVALS

100. LIMITATIONS ON THE CITY’S RESPONSIBILITIES

101. CITY’S REPRESENTATIVES

102. CITY’S REPRESENTATIVES

103. VISITS TO THE SITE

104. AUTHORIZED VARIATIONS IN WORK

105. REJECTING DEFECTIVE WORK

106. DETERMINATIONS FOR UNIT PRICES

107. PROJECT OFFICER AUTHORITY

108. LIMITATIONS ON PROJECT OFFICER’SAUTHORITY AND RESPONSIBILITIES

109. AUTHORIZED CHANGES IN THE WORK

110. UNAUTHORIZED CHANGES IN THE WORK

111. EXECUTION OF CHANGE ORDERS

112. NOTIFICATION TO SURETY

113. REQUESTS FOR PROPOSALS, PROPOSAL RESPONSES AND CHANGE ORDERS

114. COSTS INCLUDED

115. COSTS EXCLUDED

116. CONTRACTOR’S FEE

117. DOCUMENTATION

118. ALLOWANCES

119. CASH ALLOWANCES

120. CONTINGENCY ALLOWANCES

121. UNIT PRICE WORK

122. CHANGE OF CONTRACT PRICE

123. CONTRACTOR’S FEE

124. CHANGE OF CONTRACT TIME

125. DELAYS FOR PROJECTS REQUIRING CRITICAL PATH METHOD SCHEDULING

126. DELAYS FOR PROJECTS NOT REQUIRING CRITICAL PATH METHOD SCHEDULING

127. NOTICE OF DEFECTS

128. ACCESS TO WORK

129. TEST AND INSPECTION

130. UNCOVERING WORK

131. CITY MAY STOP THE WORK

132. CORRECTION OR REMOVAL OF DEFECTIVE WORK

133. CORRECTION PERIOD

134. ACCEPTANCE OF DEFECTIVE WORK

135. CITY MAY CORRECT DEFECTIVE WORK

136. SCHEDULE OF VALUES

137. PROGRESS PAYMENT

138. CONTRACTOR’S WARRANTY OF TITLE

139. REVIEW OF APPLICATIONS FOR PROGRESS PAYMENTS

140. REDUCTION IN PAYMENT

141. SUBSTANTIAL COMPLETION

142. PARTIAL UTILIZATION

143. FINAL INSPECTION

144. FINAL APPLICATION FOR PAYMENT

145. REVIEW OF FINAL APPLICATION AND ACCEPTANCE

146. FINAL COMPLETION DELAYED

147. WAIVER OF CLAIMS

148. CITY MAY SUSPEND WORK:

149. CITY MAY TERMINATE FOR CAUSE

150. CITY MAY TERMINATE FOR CONVENIENCE

151. CONTRACTOR MAY STOP WORK OR TERMINATE

152. CLAIMS, COUNTER CLAIMS AND DISPUTES

153. WHEN NOTICE AND CLAIM SUBMITTAL BECOME DUE

154. REQUIREMENTS FOR CONTRACTOR CLAIMS

155. DETERMINATION ON A CLAIM

156. VENUE

157. GIVING NOTICE

158. COMPUTATION OF TIME

159. GENERAL

160. CUMULATIVE REMEDIES

161. SURVIVAL OF OBLIGATIONS

162. CONTROLLING LAW ANTITRUST

163. HEADINGS

164. LIEN

165. OSHA REQUIREMENTS

PART FOUR – CITY OF FAIRFAX INSURANCE REQUIREMENTS

General Decision Number: VA20260116 05/18/2026

FHWA 1273 ……………………………………………………………………………………………………………………………………………………65

BID TABLE (USE SEPARATE EXCEL BID TABLE FOR SUBMISSION) …………………………………………………………………….79

IFB 73929

PART ONE STATEMENT OF WORK

1. PROJECT BACKGROUND & INFORMATION

The City of Fairfax is accepting bids for the construction services for the Blenheim Bridge Deck Rehabilitation (UPC 109811). The Blenheim Boulevard over the Accotink Creek Bridge was originally constructed in 1976.

The bridge carries four lanes of traffic in the North-South direction (two lanes in each direction) and is comprised of three spans for a total length of 130’-9”. Each span consists of 28 longitudinal 3’-0” wide precast voided slab units which have been post-tensioned with 1¼” lateral ties.

The scope of repairs include: Mill existing wearing surface, remove existing concrete median and sidewalks, perform localized repairs to top surface of precast prestressed voided slab units, seal longitudinal joints between slab units to prevent moisture infiltration, install reinforced concrete bridge deck, cast new sidewalks medians and parapets. Eliminate deck joints by installing new elastomeric expansion joints at the abutments and link slabs at the piers. Perform localized repairs to the underside of the precast prestressed voided slab units.

This is a federally funded project subject to compliance with all applicable federal, state and City terms and conditions.

2. PROJECT IDENTIFICATION

A. Project Title: Blenheim Bridge Deck Rehabilitation B. Federal Project No: RSTP-5B01(638)

C. UPC: 109811

3. SPECIFICATIONS

All work shall conform to the latest editions of the Virginia Department of Transportation (VDOT) Standards & Specifications, VDOT Work Area Protection Manual, FHWA Manual on Uniform Traffic Control Devices (MUTCD), Virginia Erosion and Sediment Control Handbook & Regulations, in effect on the bid date, as applicable.

4. OPTIONAL PREBID CONFERENCE

An optional prebid conference will be held at 11:00 am on July 11, 2026 at Blenheim Blvd at Ridge Ave https://maps.app.goo.gl/mrudDZsusE2eRso47. The purpose of this conference is to allow potential bidders an opportunity to present questions and obtain clarification relative to any facet of this solicitation.

While attendance at this conference will not be a prerequisite to submitting a bid, bidders who intend to submit a bid are encouraged to attend. Bring a copy of the solicitation with you. Any changes resulting from this conference will be issued in a written addendum to the solicitation.

5. PLANS AND SPECIFICATIONS

a. All work shall be performed according to the City of Fairfax and the Virginia Department of

Transportation standards and specifications, most recent edition.

b. All work shall be performed in accordance with applicable federal, state and City requirements. To resolve conflict between state, local, and federal code. The federal-aid or most conservative approach must be taken.

c. The approved drawings for this project were prepared by Hardesty & Hanover and dated February 23, 2026.

6. POINTS OF CONTACT

During the performance of the project, the main point of contact is the project manager. Unless otherwise authorized, the Contractor shall not contact the A&E of Record or other representatives for any matter.

Project Team Department of Public Works Engineer of Record

Satoshi Eto, CPM Doug Neely, PE

7. PERMITS AND LICENSES

Unless otherwise provided in the Contract Documents, the City shall obtain and pay for the building permits and fees. The Contractor shall meet all requirements of the building permits and fees. Unless otherwise provided in the Contract Documents, the Contractor shall obtain and pay for all other construction permits, fees and licenses, and the Contractor shall meet all requirements of those permits, fees, and licenses. The City may assist the Contractor, when necessary, in obtaining such permits and licenses. The Contractor shall pay all governmental charges and inspection fees necessary for the performance of the Work, which are applicable at the time of Bid opening, or, if there are no Bids, on the Effective Date of the Agreement the City shall pay all charges for utility connections and for providing permanent utility service to the Work. The Contractor shall not include the cost of the building permit and fee in the bid price.

8. PRICING

The unit prices established in the Bid Quotation Sheet shall be applied to changes in the Work as additions or deletions, except as provided for in the bid documents.

9. PLACE AND TIME OF PERFORMANCE

a. The project will be performed at Route 6628 (Blenheim Boulevard) over Accotink Creek, from 0.03 miles north of Ridge Avenue to 0.1 miles south of Fairfax Circle.

b. Allowable working hours for this project are from 7:00 AM to 6:00 PM on weekdays and 8:30 AM to 5:00

PM on Saturdays. No work shall take place on Sundays or legal holidays unless pre-approved in writing by the Director of Public Works.

c. Work in active City streets shall be from 9:30 AM to 3:00 PM Monday-Thursday and 9:30 AM to 2:00 PM on Fridays unless otherwise directed by the City, no work shall take place in City streets on weekends or legal holidays unless pre-approved in writing by the Director of Public Works.

d. The contractor shall be responsible for securing pre-approval for staging, storing or parking materials and/or equipment on any property beyond the project limits. Approval for such activities on City or private property shall be documented in writing and a copy provided to the City prior to utilizing the area.

e. The Contractor shall abide by all plan directives indicating restrictions to work access, staging, timing, or other aspects of work to be performed.

f. Work may be required beyond the limits of right of way and easements secured for this project based on Contractor means and methods, however, the Contractor shall be responsible for coordination with property owner(s) as required to minimize the scope of work outside of existing easements and to eliminate disruptions to residential areas. Aside from the conditions explicitly mentioned above, the Contractor shall not enter, utilize, or disturb any areas outside of temporary and permanent easements as shown on the plans.

10. KEY PERSONNEL

a. The Contractor shall submit a list of key personnel that will be assigned to the project. Key personnel include. but are not limited to. project managers, superintendents, on-site supervisors, and emergency call staff. The list shall include the following:

1. Name of Individual

2. Company Title/Position

3. Contact Numbers – Office and Mobile

4. E-Mail Address

11. CONTRACT PERIOD

The period of this contract shall be from the date of award and subsequent issuance of Full Notice to Proceed and shall be in effect until work is completed and accepted by the City. The Contractor shall achieve substantial completion of all work within 390 calendar days from full Notice to Proceed and achieve final completion and acceptance within 420 days from full Notice to Proceed.

12. TIME FOR COMPLETION AND LIQUIDATED DAMAGES FOR NON-COMPLETION:

a. The time for completion of this Contract and assessment of liquidated damages is as prescribed in the

Contract Period section of this IFB.

b. Liquidated damages shall be assessed at $1,350 per day for each calendar day beyond the contract time limit during which the contract remains in an incomplete state.

13. BID SUBMISSION:

Sealed Bids shall be received and time stamped online through the eVA website, no later than the bid closing date and time on the Cover Page (“Bid Closing”) and will be publicly posted, following the Bid Closing.

Bidders are responsible for ensuring its submission prior to Bid Closing. The time a Bid is received shall be determined by the time stamp on the Bid receipt by the time clock on the eVA Sourcing and Contracting website. The City of Fairfax is not responsible for any technical difficulties which may result in the Bidders response not uploading in time, or any responses that are not properly uploaded. The City will not receive any bids in person. Paper bids will not be accepted. Any paper bids received will be not be considered and will be returned, unopened, to the bidder. Bids received after the Bid Closing shall not be considered.

14. QUALIFICATION OF BIDDERS

All prospective bidders, including all members of a joint venture, shall be prequalified with the Virginia Department of Transportation and shall have received a certification of qualification in accordance with the Rules Governing Prequalification Privileges prior to bidding. All subcontractors shall be prequalified prior to performing any Work on the Contract.

15. DISTRIBUTION OF SOLICITATION DOCUMENTS

The distribution of this solicitation, all addenda, and responses to questions will be by posting on the City of Fairfax, Virginia’s (the “City”) website Fairfax City Current Solicitations, and the Commonwealth of Virginia’s website eVA - Virginia's eProcurement Marketplace. The date and time of posting on the Virginia Business Opportunities (VBO) website shall be the date and time of the official issuance or notification of the solicitation or any modification to the solicitation process. It is the responsibility of each bidder to check the VBO website daily for posted notifications. The City will not consider modification of any date, time frame, or addendum due to late receipt of notification based on subsequent advertisements or posting at any location other than the VBO website.

16. ADDITIONAL INFORMATION

https://www.fairfaxva.gov/government/procurement-services/current-solicitations https://eva.virginia.gov/index.html

All questions relating to this solicitation shall be submitted via email to the Contract Administrator named on the Cover Page. Bidders should cite the IFB number on the email. Questions should be succinct and must include the submitter’s name, title, company name, company address, and telephone number. Prior to the award of a contract resulting from this solicitation, bidders are prohibited from contacting City staff other than the City’s Procurement Manager. Any material question or interpretation of a requirement or specification, as determined by the City’s Procurement Manager, will be posted on the eVA as an addendum no later than ten (10) business days prior to the due date of bids. Only answers in writing by the City’s Procurement Manager to questions will have any force or effect.

NO QUESTIONS WILL BE CONSIDERED IF SUBMITTED WITHIN FEWER THAN TEN (10) BUSINESS DAYS PRIOR

TO THE DUE DATE OF BIDS.

17. CLARIFICATION OF TERMS:

If any prospective bidder has questions about the specifications or other solicitation documents, the prospective bidder should contact the Purchasing agent whose name appears on the face of the solicitation no later than ten working days before the due date. Any revisions to the solicitation will be made only by addendum issued by the Purchasing Agent.

18. ETHICS IN PUBLIC CONTRACTING:

By submitting their bids, bidders certify that their bids are made without collusion or fraud and that they have not offered or received any kickbacks or inducements from any other bidder, supplier, manufacturer or subcontractor in connection with their bid, and that they have not conferred on any public employee having official responsibility for this procurement transaction any payment, loan, subscription, advance, deposit of money, services or anything of more than nominal value, present or promised, unless consideration of substantially equal or greater value was exchanged.

19. ANTI‐DISCRIMINATION:

By submitting their bids, bidders certify to the City that they will conform to the provisions of the Federal Civil Rights Act of 1964, as amended, as well as the Virginia Fair Employment Contracting Act of 1975, as amended, where applicable, the Virginians With Disabilities Act, the Americans With Disabilities Act and § 2.2-4311 of the Virginia Public Procurement Act (VPPA). If the award is made to a faith-based organization, the organization shall not discriminate against any recipient of goods, services, or disbursements made pursuant to the contract on the basis of the recipient's religion, religious belief, refusal to participate in a religious practice, or on the basis of race, age, color, gender or national origin and shall be subject to the same rules as other organizations that contract with public bodies to account for the use of the funds provided; however, if the faith-based organization segregates public funds into separate accounts, only the accounts and programs funded with public funds shall be subject to audit by the public body. (Code of Virginia, § 2.2-4343.1E).

1. During the performance of this contract, the contractor agrees as follows:

a. The contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex, national origin, age, disability, or any other basis prohibited by state law relating to discrimination in employment, except where there is a bona fide occupational qualification reasonably necessary to the normal operation of the contractor. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause.

b. The contractor, in all solicitations or advertisements for employees placed by or on behalf of the contractor, will state that such contractor is an equal opportunity employer.

c. Notices, advertisements and solicitations placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this section.

d. The requirements of these provisions 1. and 2. are a material part of the contract. If the Contractor violates one of these provisions, the City may terminate the affected part of this contract for breach, or at its option, the whole contract. Violation of one of these provisions may also result in debarment regardless of whether the specific contract is terminated.

The contractor will include the provisions of 1. above in every subcontract or purchase order over $10,000, so that the provisions will be binding upon each subcontractor or vendor.

20. DEBARMENT STATUS:

By participating in this procurement, the vendor certifies that they are not currently debarred by the City of Fairfax from submitting a response for the type of goods and/or services covered by this solicitation. Vendor further certifies that they are not debarred from filling any order or accepting any resulting order, or that they are an agent of any person or entity that is currently debarred by the City of Fairfax.

If a vendor is created or used for the purpose of circumventing a debarment decision against another vendor, the non- debarred vendor will be debarred for the same time period as the debarred vendor.

21. ANTITRUST:

By entering into a contract, the Contractor conveys, sells, assigns, and transfers to the City of Fairfax all rights, title and interest in and to all causes of action it may now have or hereafter acquire under the antitrust laws of the United States and the Commonwealth of Virginia, relating to the particular goods or services purchased or acquired by the Commonwealth of Virginia under said contract.

22. MANDATORY USE OF CITY FORM AND TERMS AND CONDITIONS:

Failure to submit a bid on the official City form provided for that purpose shall be a cause for rejection of the bid. Modification of or additions to any portion of the Invitation for Bids may be cause for rejection of the bid; however, the City reserves the right to decide, on a case by case basis, in its sole discretion, whether to reject such a bid as nonresponsive. As a precondition to its acceptance, the City may, in its sole discretion, request that the bidder withdraw or modify nonresponsive portions of a bid which do not affect quality, quantity, price, or delivery. No modification of or addition to the provisions of the contract shall be effective unless reduced to writing and signed by the parties.

23. PURCHASE ORDER:

To be valid, a purchase order issued under this Contract must be issued during the term of the Contract. The period specified for performance of the purchase order may extend past the term of the Contract. If a notice terminating this Contract is issued, the notice shall be construed as applying only to the Contract and not to any existing purchase order, unless the notice expressly states the intent to terminate the purchase order.

24. PAYMENT:

a. Invoices for items ordered, delivered and accepted shall be submitted by the Contractor directly to the payment address shown on the purchase order/contract. All invoices shall show the contract number and/or purchase order number.

b. Any payment terms requiring payment in less than 30 days will be regarded as requiring payment 30 days after invoice or delivery, whichever occurs last. This shall not affect offers of discounts for payment in less than 30 days, however.

c. Invoices shall be submitted to:

City of Fairfax – Accounts Payable or accountspayable@fairfaxva.gov 10455 Armstrong Street, Suite 312 Fairfax, VA 22030

25. UNREASONABLE CHARGES.

Under certain emergency procurements and for most time and material purchases, final job costs cannot be accurately determined at the time orders are placed. In such cases, contractors should be put on notice that final payment in full is contingent on a determination of reasonableness with respect to all invoiced charges. Charges which appear to be unreasonable will be resolved in accordance the Fairfax City Purchasing Resolution.

26. PRECEDENCE OF TERMS:

The following Contract Terms and Conditions, VENUE, ANTI-DISCRIMINATION, OFFICIALS NOT TO BENEFIT, IMMIGRATION REFORM AND CONTROL ACT OF 1986, DEBARMENT STATUS, ANTITRUST, CLARIFICATION OF TERMS, PAYMENT shall apply in all instances. In the event there is a conflict between any of the other Contract Terms and Conditions and any General Conditions of the Construction Contract in this solicitation, the General Conditions shall apply.

The Contract Documents shall be accorded the following order of precedence unless specifically changed elsewhere in these specifications:

Change Orders Contract General Conditions of the Contract Special Provisions of the Contract Technical Specifications Drawings Supplementary Drawings Invitation for Bid (including Appendix A and addenda)

27. CHANGES TO THE CONTRACT:

The parties may agree in writing to modify the terms, conditions, or scope of the contract. Any additional goods or services to be provided shall be of a sort that is ancillary to the contract goods or services, or within the same broad product or service categories as were included in the contract award. Any increase or decrease in the price of the contract resulting from such modification shall be agreed to by the parties as a part of their written agreement to modify the scope of the contract.

28. ANNOUNCEMENT OF AWARD:

Upon the award or the announcement of the decision to award a contract as a result of this solicitation, the mailto:accountspayable@fairfaxva.gov

City will publicly post such notice on the Virginia Business Opportunities website (www.eva.virginia.gov).

29. SUBCONTRACTS:

No portion of the work shall be subcontracted without prior written consent of the City. In the event that the Contractor desires to subcontract some part of the work specified herein, the contractor shall furnish the City the names, qualifications and experience of their proposed subcontractors. The Contractor shall, however, remain fully liable and responsible for the work to be done by its subcontractor(s) and shall assure compliance with all requirements of the contract.

30. E‐VERIFY PROGRAM:

Pursuant to Code of Virginia, §2.2-4308.2., any employer with more than an average of 50 employees for the previous 12 months entering into a contract in excess of $50,000 with any agency of the Commonwealth to perform work or provide services pursuant to such contract shall register and participate in the E- Verify program to verify information and work authorization of its newly hired employees performing work pursuant to such public contract. Any such employer who fails to comply with these provisions shall be debarred from contracting with the city for a period up to one year. Such debarment shall cease upon the employer’s registration and participation in the E-Verify program.

31. DEFECTIVE SOLICITATION DOCUMENTS

Each bidder is responsible for having determined the accuracy and/or completeness of the solicitation documents upon which it relied in making its bid, and has an affirmative obligation to notify the City’s Purchasing Agent immediately upon discovery of an apparent or suspected inaccuracy, error in, or omission of any pages, drawings, sections, addenda whose omission from the documents was apparent from a reference or page numbering or other indication in the solicitation documents.

If the successful bidder proceeds with any activity that may be defective due to an inaccuracy, error in, or omission in the solicitation documents of which the bidder is aware but has not notified the City’s Purchasing Agent, the bidder hereby agrees to perform any Work described in such missing or incomplete documents at the bidder’s sole expense and at no additional cost to the City.

Failure to acknowledge all addenda issued during the solicitation process on the Receipt of Addenda form may cause the bid to be deemed incomplete.

32. COMPETITION INTENDED

It is the City’s intent that this IFB permit and promote competition. It shall be the bidder’s responsibility to advise the City’s procurement officer, in writing, if any language, requirements or specifications have the effect of restricting or limiting the purchase to a single source. Such notification must be submitted no later than ten (10) calendar days prior to the due date for bids. A review of such notifications will be made and the bidder notified of the results of the review. All qualified bidders are encouraged to submit bids.

33. EXCEPTIONS

Bidders taking exception to any part or section or term of this solicitation, including, by way of illustration and not limitation, the Specifications, the Special Conditions, and any attachments or references hereto or thereto, shall indicate such exceptions on the Bid Submission Form. Failure to indicate any exceptions shall be interpreted as the bidder’s intent to fully comply with the solicitation as written. However, conditional or qualified bids with such exceptions, unless specifically allowed in this solicitation, are subject to rejection in whole or in part as nonresponsive.

34. EXPENSES INCURRED IN PREPARING BID

The City accepts no responsibility for any expense incurred by any bidder in the preparation and presentation of a bid. All expenses related to a bid are the sole responsibility of the bidder.

35. SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK

Each bidder acknowledges by submitting a bid that it has taken steps reasonably necessary to ascertain the nature and locations of the Work of the solicitation, and that it has investigated and satisfied itself as to the general and local conditions and factors which can affect the Work or its cost, including but not limited to:

• Conditions bearing upon transportation, disposal, handling, and storage of materials; The availability of labor, water, electric power, and roads;

• Uncertainties of weather, floods, or similar physical conditions at the site; The conformation and conditions of the ground; and

• The character of equipment and facilities needed before and during work performance.

Each bidder also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work publicly or otherwise available, as well as from the drawings and specifications made a part of this solicitation. Any failure of a bidder to take the actions described and acknowledged in this paragraph will not relieve the bidder from responsibility for estimating properly the difficulty and cost of successfully performing the Work without additional expense to the City.

The locations of existing utilities, including underground utilities, which may affect the Work, are indicated on the drawings or in the specifications insofar as their existence and location were known at the time of preparation of the drawings. However, nothing in these drawings or specifications shall be construed as a guarantee that such utilities are in the location indicated or that they actually exist, or that other utilities are not within the area of operations. The bidder shall make all necessary investigations to determine the existence and locations of such utilities. The bidder will be held responsible for any damage to and maintenance and protection of existing utilities and structures, of both public and private ownership. However, if it is determined that such existing utility lines or structures require relocation or reconstruction or any other Work beyond normal protection or as called for in the Contract Documents, then such additional Work will be ordered under the terms of the clause entitled “Changes in Work.”

The City assumes no responsibility for any conclusions or interpretations made by the bidder based on the information made available by the City. The City assumes no responsibility for any understanding reached or representation made concerning conditions which can affect the Work by any of its officers or agents before the execution of the contract, unless that understanding or representation is expressly stated in the Contract.

36. DEBARMENT STATUS

The bidder shall indicate, in the space provided on the Bid Submission Form, whether or not it, or any of its principals, is/are currently debarred from submitting bids to the City or any other state or political subdivision, and whether or not it is an agent of any person or entity that is currently debarred from submitting bids to the City, or any other state or political subdivision. An affirmative response may be considered grounds for rejection of the bid.

37. NEW MATERIAL

Unless otherwise provided for in this solicitation, the bidder represents and warrants that the goods, materials, supplies, or components offered to the City under this solicitation and any resulting contract are new, not used or reconditioned, and are not of such age or deterioration as to impair their usefulness or safety, and that the goods, materials, supplies, or components offered are current production models of the respective manufacturer.

If the bidder believes that furnishing used or reconditioned goods, materials, supplies or components will be in the City's interest, the bidder shall notify the City in writing no later than ten (10) business days prior to the date set for the opening of bids. The notice shall include the reasons for the request and any benefits which may accrue to the City if the City authorizes the bidding of used or reconditioned goods, materials, supplies or components.

38. INFORMALITIES

The City reserves the right to waive minor defects or variations from the exact requirements of the solicitation in a bid insofar as those defects or variations do not affect the price, quality, quantity, or delivery schedule of the goods, services and/or construction being procured. If insufficient information is submitted for the City to properly evaluate the bid by a bidder, the City reserves the right to require such additional information as it may deem necessary after the bid opening time and date, provided that the information requested does not change the price, quality, quantity, or delivery schedule for the goods, services, or construction being procured.

39. CITY OF FAIRFAX BUSINESS LICENSE

Awarded Bidders must comply with the City’s business license requirements, if applicable. For information on the applicability of this requirement, contact the City’s Commissioner of the Revenue’s office, Suite 234, 10455 Armstrong Street, Fairfax, Virginia 22030; telephone number (703) 385-7905.

40. VIRGINIA CONTRACTOR LICENSE

For all Work that is classified as being performed by "Contractors" as defined by the Virginia State Board for Contractors, a Class A, B, or C License is required. This shall not be a condition for submitting a bid but shall be required prior to an award of contract pursuant to the provisions of this section.

Prior to award of contract for performing or managing construction, removal, repair or improvements is for $120,000 or more, or if the total value of all such construction, removal, repair, or improvements undertaken by the bidder within any twelve (12) month period is $750,000 or more, the bidder is required under Title 54.1, Chapter 11, Code of Virginia, as amended, to be licensed as a "CLASS A CONTRACTOR."

Prior to award of contract for performing or managing construction, removal, repair or improvements is for $10,000 or more, but less than $120,000, or if the total value of all such construction, removal, repair, or improvements undertaken by the bidder within any twelve (12) month period is $150,000 or more, but less than $750,000, the bidder is required under Title 54.1, Chapter 11, Code of Virginia, as amended, to be licensed as a "CLASS B CONTRACTOR."

Prior to award of contract performing construction, removal, repair or improvements is for $1,000 or more, but no more than $10,000 or if the total value of all such construction, removal, repair, or improvements undertaken by the bidder within any twelve (12) month period is less than $150,000, the bidder is required under Title 54.1, Chapter 11, Code of Virginia, as amended, to be licensed as a "CLASS C CONTRACTOR."

Class C contractors shall not include electrical, plumbing, and heating, ventilation and air conditioning contractors.

For further information, contact: the Virginia Board for Contractors, 9960 Mayland Drive Richmond VA 23233; (804) 367-8500.

41. SURETY REQUIRED BID SURETY:

A fully completed and properly executed original Bid Bond, cashier's check, certified check, money order, or cash escrow in the amount of five percent (5%) of the amount of the bid made payable to the Treasurer of the City shall accompany each bid. The Bid Surety of all bidders may be retained until after the award to the successful bidder is made. The Bid Surety of the successful bidder shall be retained until completion of the Contract or the posting of a Performance Bond, whichever occurs sooner. A bid submitted without a bid surety, or with a bid surety in an amount less than the required amount, shall be rejected. The attached form shall be utilized for submission of bid bonds.

PART TWO – GENERAL CONDITIONS OF THE CONTRACT

42. PARKING

A Contractor is responsible for the payment of any parking charges or fines resulting from illegal parking at any worksite(s) or elsewhere. Unless otherwise expressly permitted in writing by the City, no parking of Contractor vehicles shall be permitted in any City lot or facility.

43. FAILURE TO EXECUTE:

The failure to accept an award and file acceptable Performance and Payment Bonds within fifteen

(15) days after notice of award shall be just cause for cancellation of the award and the forfeiture of the Bid Surety to the City as liquidated damages. Award may then be made to the next lowest responsive and responsible bidder.

44. PERFORMANCE SURETY:

The awardee shall submit a fully completed and properly executed original Performance Bond in the amount of 100% of the Contract Amount using the form provided by the City for this purpose.

The bond shall be a corporate surety bond issued by a surety company authorized to do business in the Commonwealth of Virginia and acceptable to the City. The Performance Bond shall be renewable annually in the original amount through completion of the Contract, including expiration of all warranty and guarantee periods.

PAYMENT BOND:

The awardee shall submit a fully completed and properly executed original Payment Bond in the amount of 100% of the Contract Amount using the form provided by the City for this purpose. The bond shall be for the protection of all persons who have and fulfill contracts for the Contractor for performing labor, providing equipment, or providing material in the performance of the Work provided for in the Contract. The Bond shall be a corporate surety bond issued by a surety company authorized to do business in the Commonwealth of Virginia and acceptable to the City. The Payment Bond shall be renewable annually in the original amount for the duration of the Contract Term.

ALTERNATE SURETY:

If approved by the City Attorney, a bidder may furnish a personal bond, property bond, or bank or savings and loan association's letter of credit on certain designated funds in the face amount required for the bid bond, payment bond or performance bond. Approval shall be granted only upon a determination by the City that the alternative form of security proffered affords protection to the City equivalent to a corporate surety's bond.

45. FAILURE TO COMPLETE ON TIME GENERAL

For each calendar day that any work remains incomplete after the Contract time limit specified for the completion of the work, the City will assess liquidated damages against the Contractor. Liquidated damages will be assessed at the rate applicable to the Contract as specified below. Liquidated damages will be deducted from any monies due the Contractor for each calendar day of additional time consumed until final completion and acceptance of the Work, not as a penalty, but as liquidated damages. The Contractor waives any defense as to the validity of any liquidated damages stated in the Contract or these Specifications and assessed by the City against the Contractor on the grounds that such liquidated damages are void as penalties or are not reasonably related to actual damages.

Liquidated Damages

The following Schedule of Liquidated Damages, representing the cost of administration, engineering, supervision, inspection and other expenses, will be charged against the Contractor for each calendar day beyond the Contract time limit that the Contract remains in an incomplete state:

Daily Charge: $ 1,350

46. VDOT AND/OR FEDERAL GOVERNMENT CONTRACTOR REQUIREMENTS

Any purchase order, task(s) or task order under any contract resulting from this IFB funded in whole or in part by the Virginia Department of Transportation (VDOT) or any other State or Federal Government funding source, the Bidder shall comply with supplemental terms and conditions. The City reserves the right to amend the contract, as is permitted, for inclusion of such terms, conditions and provisions.

For each purchase order, task or task order issued under the contract funded by VDOT or Federal Government sources, the City shall notify Bidder of the funding source and the Bidder shall comply with the associated requirements.

Necessary specifications, provisions and clauses in Federal and/or VDOT documents, including but not limited to the most current versions of the Virginia Department of Transportation Road and Bridge Specifications, Virginia Department of Transportation Road and Bridge Standards, and the Virginia Work Area Protection Manual are incorporated herein by reference and made a part hereof.

If any task issued by the City is funded by grant monies, the Bidder and the City shall adhere to terms and conditions specified in individual grant agreements.

Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (2 CFR 200). The City and its consultants/contractors must agree to compliance with all applicable federal regulations, recognizing that (1) these funds are subject to applicable statutory provisions and regulations; and (2) grant awards are subject to the applicable provisions of the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (2

CFR200).

47. EXECUTION OFAGREEMENT

Within fifteen (15) calendar days after the Agreement forms are presented by the City to the successful Bidder for signature, the Contractor shall deliver to the City Purchasing Agent the executed Agreement. Within the same fifteen (15) day period, the Contractor shall deliver to the City Purchasing Agent executed performance and payment bonds, if such are required in the solicitation, and the required certificate(s) of insurance. Failure by the Contractor to execute the Agreement and to supply any required bonds and certificates within the stipulated fifteen (15) day period, or within such extended period as the City Purchasing Agent may grant, shall constitute a material default, and the City may then, without further notice, award the Contract to the next lowest responsive and responsible bidder or, in the City’s discretion, solicit new bids. The City may then charge the Contractor’s bond for the difference between the amount of the Contract award and the amount for which a Contract is subsequently executed, up to the total amount of the Contractor's bid security.

48. CIVILITY IN CITY WORKPLACES:

The Contractor shall take all reasonable steps to ensure that no individual, while performing work on behalf of the Contractor or any subcontractor in connection with this agreement (each, a “Contract Worker”), shall engage in 1) harassment (including sexual harassment), bullying, cyber-bullying, or threatening or violent conduct, or 2) discriminatory behavior on the basis of race, sex, color, national origin, religious belief, sexual orientation, gender identity or expression, age, political affiliation, veteran status, or disability.

The Contractor shall provide each Contract Worker with a copy of this Section and will require Contract Workers to participate in agency training on civility in the City workplace if Contractor’s (and any subcontractor’s) regular mandatory training programs do not already encompass equivalent or greater expectations. Upon request, the Contractor shall provide documentation that each Contract Worker has received such training.

For purposes of this Section, “City workplace” includes any location, permanent or temporary, where a City employee performs any work-related duty or is representing his or her agency, as well as surrounding perimeters, parking lots, outside meeting locations, and means of travel to and from these locations. Communications are deemed to occur in a City workplace if the Contract Worker reasonably should know that the phone number, email, or other method of communication is associated with a State workplace or is associated with a person who is a City employee.

The City of Fairfax may require, at its sole discretion, the removal and replacement of any Contract Worker who the City reasonably believes to have violated this Section.

This Section creates obligations solely on the part of the Contractor. Employees or other third parties may benefit incidentally from this Section and from training materials or other communications distributed on this topic , but the Parties to this agreement intend this Section to be enforceable solely by the City and not by employees or other third parties.

PART THREE– SPECIAL CONDITIONS OF THE CONTRACT

49. DEFINITIONS

The Definitions, Abbreviations, Acronyms and Terms as presented in Section 101 of the 2020 VDOT Road and Bridge Specifications and 2022 VDOT Road and Bridge Specifications Update are incorporated by reference. The following is a summary of Acronyms and Definitions as noted within this document.

A. A&E of Record: Architect or Engineer of Record for the project.

B. Agency: Refers to the City of Fairfax and other representative departments responsible for the oversight of the proposed project.

C. COR: Change Order Request.

D. City’s Representative: Designated party that has been delegated authority to conduct inspections, monitor and / or perform testing and report to the City all and any issues of significance.

E. PM: City Project Manager or designated authority.

F. Project Closeout: Term utilized to describe certain collective project requirements, signifying completion of the work that is to be fulfilled to achieve contract completion in preparation for final payments to the respective parties.

G. Third Party: Designated as a company, firm, or special inspections service provider that is under a contractual agreement with the City of Fairfax, to perform professional and/or non-professional services for the project.

50. COMMENCEMENT OF CONTRACT TIME; NOTICE TO PROCEED

See paragraph 11.

51. STARTING THE PROJECT

The Contractor shall start to perform the Work on the date when the Contract Time commences to run. No Work shall be done at the site prior to that date.

52. BEFORE STARTING WORK

Within fourteen (14) days after the Effective Date of the Agreement, in the formats specified in the General Requirements, the Contractor shall submit to the Project Officer the following:

A preliminary Progress Schedule indicating the starting and completion dates of the various stages of the Work, including any Milestones specified in the Contract Documents;

A preliminary Schedule of Submittals

A preliminary Schedule of Values for all of the Work which includes quantities and prices of items which, when added together, equal the Contract Price, and subdivides the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work.

Such prices will include an appropriate amount for overhead and profit applicable to each item of Work. The schedule of values shall be consistent with the itemized breakdown of the Total Bid and with the provisions of the General Requirements.

53. PRECONSTRUCTION CONFERENCE

Before the Contractor starts the Work at the site, a conference attended by the Project Officer, Contractor and others as appropriate will be held to discuss:

• The schedules referred to in the paragraph above;

• The procedures for handling Shop Drawings and other submittals and for processing

Applications for Payment and maintaining required records;

• Review of the Contractor’s project organization and the qualifications of the Contractor’s resident Project Manager and the qualifications of similar authorized representatives for proposed Subcontractors; and,

• Discussion of the Contractor’s plans for complying with the City’s required Health and Safety program and quality control program, and to establish a working understanding among the parties as to the Work.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .