This is a Statement of Work (SOW) for R.S. Harritan & Company, Inc. to remove, ship, inspect, rebuild, and reinstall two vacuum pumps at NASA Langley Research Center Building B1148.
The contractor shall furnish all labor, equipment, and supervision to safely remove the pumps using facility-provided rigging points, construct shipping crates, coordinate shipment to the original equipment manufacturer (OEM) for teardown and inspection, perform authorized rebuilds based on OEM findings and NASA approval, reinstall the pumps, and conduct operational checks to verify functionality. The NASA facility team is responsible for disconnecting electrical and control wiring, draining and refilling fluids, and removing and reinstalling drive belts. Environmental requirements mandate compliance with NASA, EPA, and state regulations for waste oil disposal, with personnel required to wear Tychem suits, nitrile gloves, goggles, and face shields when handling pump oil due to identified skin absorption hazards. Waste management must comply with LaRC Spec 01 35 40.00 41 and LPR 8500. The contractor must provide technical submittals including a safety plan, worker qualifications (mechanical/electrical/welding), equipment data sheets, a lifting/critical lift plan, and an inspection findings report prior to work commencement, with additional submittals required before final acceptance including a project materials usage spreadsheet, final acceptance test results, and warranty information. Work is scheduled for October/November or as coordinated with the NASA Facility Manager, with deliverables including rebuilt and installed pumps, the completed OEM inspection report, all required technical submittals, final acceptance test results, and warranty documentation covering all rebuilt components.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NASA Langley Research Center Statement of Work for R.S. Harritan & Company, Inc. to remove, ship, inspect, rebuild, and reinstall vacuum pumps at B1148.
1. Objective and Requirements
The objective of this Statement of Work is to remove two vacuum pumps from NASA LaRC Building B1148, ship them for OEM inspection, determination of refurbishment requirements, perform necessary rebuilds as authorized, and reinstall the pumps to restore operational capability. The effort includes coordination with facility personnel, safe handling of all fluids and equipment, and compliance with all NASA and OSHA regulations.
2. Characteristics, Scope, and Specifications
2.1 General Scope
The Contractor shall furnish all labor, equipment, and supervision required to:
• Remove two vacuum pumps from Building B1148 using facility-provided rigging points.
• Ship pumps to the OEM for teardown, inspection, and refurbishment cost determination.
• Perform authorized rebuilds following OEM inspection.
• Return rebuilt pumps to B1148 and reinstall them.
• Coordinate with facility technicians for wiring disconnects, drain/refill of fluids, and drive belt reinstallation.
2.2 Detailed Requirements
The Contractor shall perform the following tasks:
A. Removal Activities
• Use steel overhead structure as rigging points for pump removal and installation.
• Ensure safe removal with all electrical, mechanical, and fluid systems disconnected by facility staff.
• Support all remaining components properly during removal.
B. Shipping & OEM Inspection
• Construct shipping crates for both pumps.
• Coordinate shipment to OEM for teardown, inspection, and issuance of a refurbishment report.
• No repairs will be performed until the OEM’s inspection report and associated costs are approved by NASA.
C. Rebuild & Reinstallation
• Perform rebuild work authorized by NASA based on OEM findings.
• Reinstall pumps following refurbishment.
• Coordinate with facility staff for fluid refilling and drive belt installation.
• Conduct operational checks to verify correct functionality.
3. Facility Responsibilities
The NASA facility team shall be responsible for:
• Disconnecting/removing all power and control wiring prior to Contractor mobilization.
• Draining all fluids from pumps prior to removal and refilling after reinstallation.
• Removing and reinstalling drive belts.
4. Environmental Requirements
• Waste oil and oily debris from pumps shall be disposed of according to NASA, EPA, and state regulations.
• Personnel handling pump oil must wear Tychem suits, nitrile gloves, goggles, and face shields due to skin absorption hazards identified in prior waste oil sampling.
• All chemicals must be stored in secure, labeled containers.
• Waste management must comply with LaRC Spec 01 35 40.00 41 and LPR 8500.
5. Technical Submittals
The Contractor must provide the following for approval:
• Safety Plan
• Worker Qualifications (Mechanical/Electrical/Welding)
• Equipment Data Sheets
• Lifting/Critical Lift Plan
• Inspection Findings Report
Submittals required prior to final acceptance:
• Project Materials Usage Spreadsheet
• Final Acceptance Test
• Warranty Information
6. Cleanliness
The Contractor shall maintain a clean workspace, ensuring debris is removed daily and all areas remain safe and accessible.
7. Period of Performance
Work is expected to occur during the October/November timeframe, or as otherwise scheduled and coordinated with the NASA Facility Manager.
8. Deliverables
• Rebuilt and installed vacuum pumps.
• Completed inspection report from OEM.
• All required technical submittals.
• Final acceptance test results.
9. Warranty
Contractor shall provide warranty documentation covering all rebuilt components.