80KSC021R0029 1442 RFP.pdf
PDF 595 KB Posted
- Attached to
- Mobile Launcher 1 (ML-1) Emergency Egress System (EES) Conveyance Federal contract opportunity
- Solicitation number
- 80KSC021R0029
About this file
This is a solicitation for a firm-fixed price construction contract to install an Emergency Egress System conveyance on Mobile Launcher 1 at Kennedy Space Center in Florida. The contractor shall provide all labor, equipment, materials and activities to structurally modify and add a new conveyance system including basket assemblies, wire rope, braking system and safety control systems. The scope also includes fabrication and installation of platforms, modifications to existing structures and tower platforms. The contractor must perform all testing, verification and validation of the new and modified installations. The total period of performance is 406 calendar days from notice to proceed. The solicitation identifies evaluation factors for award and incorporates standard FAR clauses for fixed price construction contracts.
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
80KSC021R0029
TBD
John F. Kennedy Space Center, NASA Procurement Office Code: OP-CS Kennedy Space Center, FL 32899
The contractor shall furnish all labor, equipment, materials, and related activities necessary to the Emergency Egress System (EES) Conveyance Installation at Kennedy Space Center, Florida.
This is a Full and Open, Lowest Price Technically Acceptable (LPTA) procurement.
Offeror MUST enter their cage code and DUNS number in block 14, page 2 of the SF 1442.
Offeror MUST be registered SAM and VETS-4212.
Offeror MUST submit electronic offer as specified in section L.15.
KSC-IDIQbids@mail.nasa.gov Attn: C. M. Julius Williams John F. Kennedy Space Center, NASA Procurement Office Code: OP-CS Bldg M7-0301, Room: 5416A Kennedy Space Center, FL 32899
4200769759
OP-CS
C. M. Julius Williams, Contracting Officer (321) 861-2661
98967
1 9206/30/2021
08/03/2021
11:00 AM
*Section F.1
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
TBD
OP-CS
John F. Kennedy Space Center, NASA Procurement Office Code: OP-CS Kennedy Space Center, FL 32899
NASA Shared Services Center (NSSC) Financial Management Division (FMD) - Accounts Payable Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS 39529
TBD
See Attached
SF1442 BACK, Block 17 continued.
17. The offeror agrees to perform the work required at the prices below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within _______ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
_____________________________________ AWARD (To be completed by the Government)
SF1442 BACK, Block 21 continued.
21. ITEMS ACCEPTED:
CLIN DESCRIPTION UNIT UNIT PRICE
TASK 1,
All Segments
Emergency Egress System (EES) Conveyance Installation. This work will include all work, Segments 2 work being performed in 90 days.
1 JOB
0001A
TASK 1,
Accelerate Segment 2
Accelerate Task 1 Segment 2 work to be performed in a 75-day work window in lieu of 90 days .
1 JOB
0002 OPTION 1 Provide EES Parts for ML-2. 1 JOB $___________________________
0003 OPTION 2
Provide EES Parts for government to perform qualification testing .
1 JOB $___________________________
TOTAL
CLIN DESCRIPTION UNIT UNIT PRICE
TASK 1,
All Segments
Emergency Egress System (EES) Conveyance Installation. This work will include all work, Segments 2 work being performed in 90 days.
1 JOB
0001A
TASK 1,
Accelerate Segment 2
Accelerate Task 1 Segment 2 work to be performed in a 75-day work window in lieu of 90 days .
1 JOB
0002 OPTION 1 Provide EES Parts for ML-2. 1 JOB $___________________________
0003 OPTION 2
Provide EES Parts for government to perform qualification testing .
1 JOB
TOTAL AWARD
NASA/KSC SOLICITATION 80KSC021R0029
TABLE OF CONTENTS
SECTION A SOLICITATION/CONTRACT FORM (SF1442)
SECTION B SUPPLIES OR SERVICES AND PRICE/COSTS
SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF
WORK
SECTION D PACKAGING AND MARKING
SECTION E INSPECTION AND ACCEPTANCE
SECTION F DELIVERIES OR PERFORMANCE
SECTION G CONTRACT ADMINISTRATION DATA
SECTION H SPECIAL CONTRACT REQUIREMENTS
SECTION I CONTRACT CLAUSES
SECTION J LIST OF ATTACHMENTS
SECTION K REPRESENTATIONS, CERTIFICATIONS, AND OTHER
STATEMENTS OF OFFERORS OR RESPONDENTS
SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO
OFFERORS OR RESPONDENTS
SECTION M EVALUATION FACTORS FOR AWARD
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
B. 1 CONSTRUCTION SERVICES AND PRICES
Line Item Description Unit Total
0001 Task 1 – Emergency Egress System (EES) Conveyance Installation. This work will include all work, Segments 2 work being performed in 90 days.
JOB $
0001A Accelerate Task 1 Segment 2 work to be performed in a 75-day work window in lieu of 90 days.
JOB $
0002 Option 1 – Provide EES Parts for ML-2 JOB $ 0003 Option 2 – Provide EES Parts for government to perform qualification testing
JOB $
TOTAL $ TBD
(End of Clause)
B. 2 NFS 1852.216-78 FIRM FIXED PRICE (DEC 1988)
The total firm fixed price of this contract is TBD.
B. 3 PROJECT DELIVERABLES (JAN 2018)
Contract deliverables (manuals, reports, plans, and other written documentation) to be provided under this contract are identified in Section J, Attachment J-A, Project Deliverables. The costs associated with providing the data in Attachment J-A are included in the firm-fixed price of the awarded contract. Nothing contained in Attachment J-A will relieve the Contractor from furnishing data called for by, or under the authority of, other provisions of this contract, which are not identified and described in Attachment J-A.
SECTION C – DESCRIPTION/SPECIFICATION/WORK STATEMENT
C. 1 SCOPE OF WORK (JAN 2018)
The Contractor must furnish all management, supervision, labor, transportation, facilities, materials, tools, equipment, disposal, and documentation (except any property, including utilities, specified in the Schedule to be Government-Furnished) to perform all work for the Task(s) named below, and defined in the contract drawings, maps, specifications, and/or statements of work.
Line Item Description
Task 1 – Emergency Egress System (EES) Conveyance Installation. This work will include all work, Segments 2 work being performed in 90 days.
0001A Accelerate Task 1 Segment 2 work to be performed in a 75-day work window in lieu of 90 days.
0002 Option 1 – Provide EES Parts for ML-2.
Option 2 – Provide EES Parts for government to perform qualification testing.
C. 2 CONTRACT DRAWINGS, MAPS, SPECIFICATIONS, AND/OR STATEMENTS OF
WORK (JAN 2018)
(a) Five sets of full scale contract drawings, maps, specifications, and/or statements of work (excluding publications incorporated into the technical provisions by reference), plus one CD or DVD containing electronic, portable document format (PDF) versions, will be furnished at award to the Contractor without charge. The work must conform to the following contract drawings, maps, specifications, and/or statements of work, attached to this contract.
See Attachment J-G, Section C.2 Summary of Drawings with Reference Drawings.
(b) Addenda to Drawings, Maps, Specifications, and/or Statements of Work:
(1) Specification K0000434325-SPC section 01 11 00, paragraph 1.2, is changed from:
Set up cost loading using a single lump sum labor resource. The Price/Unit must be $1/hr, Default Units/Time must be "8h/d", and settings "Auto Compute Actuals" and "Calculate costs from units" selected.
To:
Set up cost loading using the "Nonlabor" type resource (the project budget is neither labor/workers nor material/bricks and sticks), with Default Units/Time set to 1d/d and Max Units/Time at 1d/d with "Auto Compute Actuals" and "Calculate costs from units" deselected.
(2) Specification K0000434325-SPC section 01 11 00, paragraph 1.2, is changed from:
Drawing K0000151046 EES Basket Assembly with associated parts (total 522 sheets)
SECTION C – DESCRIPTION/SPECIFICATION/WORK STATEMENT
To:
Drawing K0000151046 EES Basket Assembly with associated parts (total 535 sheets)
(c) "Or Equal" Items”
Throughout the technical specifications and drawings of this contract, where certain manufacturers’ trade names and model numbers are specified and followed by the term "or equal," the manufacturer's name and data as specified will represent the minimum standard type, quality, and capacity acceptable for incorporation into the work covered by this contract.
The products of other manufacturers will be considered as being acceptable, provided that such products fully meet or exceed all minimum structural or use and operational features of the particular manufacturers’ items as specified, and provided that the other manufacturers’ items are easily interchangeable and can be adequately incorporated within the allocated space in the building or structure. In all cases, the acceptability of "or equal" items will be at the Contracting Officer's discretion, based upon data submitted by the Contractor in accordance with the requirements under the Shop Drawings Clause.
(d) Omissions from the drawings or specifications, or the omission or misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, will not relieve the Contractor from performing such omitted or misdescribed details of the work but they will be performed as if fully and correctly set forth and described in the drawings and specifications.
(e) The Contractor must check all drawings furnished him immediately upon their receipt and promptly notify the Contracting Officer of any discrepancies. Figures marked on drawings must in general be followed in preference to scale measurements. Large scale drawings will in general govern small scale drawings. The Contractor must compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.
SECTION D – PACKAGING AND MARKING
NOT APPLICABLE TO THIS SOLICITATION/CONTRACT
SECTION E - INSPECTION AND ACCEPTANCE
E. 1 FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
INCORPORATED BY REFERENCE
FAR 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
E. 2 NFS 1852.246-72 MATERIAL INSPECTION AND RECEIVING REPORT
(APR 2015)
(a) At the time of each delivery to the Government under this contract, the Contractor shall prepare and furnish a Material Inspection and Receiving Report (DD Form 250 series). The forms shall be prepared and distributed as follows: One copy shall be provided to the Contracting Officer’s Representative (COR).
(b) The Contractor shall prepare the DD Form 250 in accordance with NASA FAR Supplement
1846.6. The Contractor shall enclose the copies of the DD Form 250 in the package or seal them in a waterproof envelope, which shall be securely attached to the exterior of the package in the most protected location.
(c) When more than one package is involved in a shipment, the Contractor shall list on the DD Form 250, as additional information, the quantity of packages and the package numbers. The Contractor shall forward the DD Form 250 with the lowest numbered package of the shipment and print the words "CONTAINS DD FORM 250" on the package.
(End of clause)
E. 3 BASIC INSPECTION SYSTEM (JAN 2018)
Pursuant to FAR Clause 52.246-12, Inspection of Construction
The Contractor must maintain and implement a basic inspection system as identified below:
(a) Definitions:
"Inspection" means examining and testing supplies or services (including, when appropriate, raw materials, components, and intermediate assemblies) to determine whether they conform to contract requirements.
"Testing" means that element of inspection that determines the properties or elements, including functional operation of supplies or their components, by the application of established scientific principles and procedures.
"Independent Testing Laboratory" means an independent organization, accepted by the Contracting Officer, engaged to perform specific inspections or tests of the work, either at the site or elsewhere, and report the results of these inspections or tests.
(b) The inspection system must be documented to ensure and provide objective evidence of quality control in the form of records of inspections and test results. The system must also ensure that nonconforming articles or materials are discovered, documented, and controlled through effective remedial and preventive actions.
The Contractor may use, at his option, in whole or in part, his existing higher level inspection system or quality assurance program provided such system is revised and identified to the requirements below.
(c) The Contractor must provide a narrative description of an inspection system which provides for compliance with the quality requirements and technical criteria of the contract.
(1) The description must be submitted for review by the Contracting Officer not later than 7 days after contract award.
(2) The description must address each of the Basic Inspection System Requirements identified in paragraph (d) below. This submittal must address both the general inspection system that will be used during the performance of all work under the contract, including but not limited to those items identified under paragraphs d(1), d(2)(iv), d(2)(v), and d(2)(vi) below.
(d) Basic Inspection System Requirements: The Contractor must describe how each of the following requirements is to be satisfied and what records will be maintained, both on-site and offsite.
(1) The Contractor must identify the individual responsible for on-site contact and communication relative to implementation and operation of the inspection system. The name of this individual must be provided, in writing, to the Contracting Officer’s Representative (COR).
(2) Standard requirements:
(i) A purchasing control system which ensures that all purchasing documents, including those of subcontractors and suppliers, are traceable to the drawings, specifications, and approved submittal requirements.
(ii) A receiving inspection system with documented evidence of Contractor inspection traceable to the procurement documents.
(iii) A system of controls and records for handling, recording, identification and disposition of nonconforming articles and materials.
(iv) A system of identification of inspections required by each specific section of the specifications and drawings and what records will be maintained.
(v) Identification of tests to be performed, including test procedures, test records, and the independent testing organization(s) be utilized.
(vi) Additional requirements (if included in the drawings, specifications, or contract provisions):
(A) Certification or recertification of personnel and qualification of procedures.
(B) Management and accountability of Government furnished equipment, components, or materials.
(C) Calibration of inspection test gages, tools, measuring instruments, and independent laboratories to be utilized.
E. 4 SYSTEMS ACCEPTANCE AND TESTING
Pursuant to FAR 52.246-12, Inspection of Construction:
Systems tests must be performed as described below:
(a) SYSTEMS
Systems tests shall be performed on the Emergency Egress System, Grounding and bonding, leak check and connect, cleaning, drying and sampling, resistance tests, megger tests, proof loading tests, and all other assemblies of components which must be tested as an inter-related whole to verify proper functioning.
(b) SYSTEM TEST PROCEDURES
A test procedure and a recording form which documents every step of the system test must be submitted for approval under the terms of the "Shop Drawings" clause of this contract. Test procedures must be approved prior to requesting a date for testing. Each step in the test procedure must be witnessed by the Contracting Officer's Representative who will then date and sign the approved recording form for each step witnessed.
The procedure must consist of step by step instructions for testing all specified system parameters, system components, and proper overall functioning of the system.
(c) SYSTEM TESTING AND ACCEPTANCE
The following tests must be performed by the Contractor in strict accordance to the approved test procedure described above.
(1) Functional Test -- This must be an "in house" test to verify proper installation and functioning of the system and its components. This functional test must be performed in the presence of Government inspectors and be repeated until the Contractor can perform one full test without device or system malfunction.
(2) System Acceptance Test -- After successful completion of the functional testing the system must be tested formally with full documentation using the previously approved recording form. The Contractor must notify the Contracting Officer, in writing, forty-eight (48) hours prior to system acceptance testing. The appointed Contracting Officer Representative will witness, date and stamp each test in the procedure. Acceptance of the system will be based upon the written approval of the Contracting Officer’s Representative.
Nothing in this clause will relieve the contractor from the requirements of FAR 52.246-12, "Inspection of Construction."
E. 5 QUALITY REQUIREMENTS
(a) Construction Quality Control - General
The Contractor must maintain an effective Quality Program that encompasses all actions involving selection of construction materials and sources, suppliers, subcontractor, on-site and off-site fabrication of Contractor-furnished items to be included in the work; on-site and off-site assembly, erection, work-placement procedures, workmanship, inspection, and testing.
The Contractor' program must provide for a functional system of records to provide objective evidence that the quality provisions of the contract schedule, specifications, and drawings have been satisfactorily performed and recorded. The contractor must meet weekly with the government to review as-builts and other quality documents.
(b) Management and Organization
The Contractor must ensure that effectiveness of the quality functions and the ability of assigned personnel to provide the necessary supervision, inspection, and test of all items of work, including that of his suppliers and subcontractors.
The program must encompass all management and supervisory actions that affect quality of the finished construction work.
(1) The Contractor must designate a qualified individual within his on-site organization whose sole responsibility will be the day-to-day on-site management and direction of the Quality Program. Qualification credentials of the designated individual must be provided to the Contracting Officer for review and concurrence. The individual may be assigned to more than one contract provided that the assigned contracts are all located at the Kennedy
Space Center. The individual designated to direct the program must report to the Contractor's management and must have the necessary authority to discharge his responsibilities.
(2) The Contractor must submit a monthly performance report that summarizes all quality operations. This summary report must identify inspections made, tests performed, nonconformances, corrective action taken, status of plans/procedures being developed, and status of open items/problems in work.
(c) Quality and Assurance Plan
(1) Within 30 calendar days after Notice to Proceed, the Contractor must submit an electronic copy of their Quality Program Plan for the contract to the Contracting Officer for review and approval. Such approval will not relieve the Contractor of his responsibility for compliance with the contract requirements.
(2) The plan must describe how the Contractor intends to ensure compliance with the quality requirements of the specifications and must address each of the following as a minimum:
(i) Authority and responsibilities of quality control personnel along with a copy of the letter of delegation to the Contractor's representative and his staff for quality control that defines their delegated duties and responsibilities.
(ii) That part of the Contractor's organization that is concerned with the construction contract activities.
(iii) The Contractor's on-site organization, including his quality organization.
(iv) The Contractor's operational plan for accomplishing and reviewing work supervision, inspection, tests, construction material work controls, fabrication controls, certifications, and documentation of quality control operations, inspections, and tests records, including those for subcontractors. These provisions must include the methods to be affected during the procurement cycle (order to deliver) for those items of materials or equipment which require source inspection, shop fabrication, and like operations away from the work site.
(v) The registered land surveyor or key individuals designated to accomplish the layout of the work.
(vi) Define the on-site/off-site coordinating procedures and authorities for the quality functions accomplished by personnel not located at the site or not directly under the control of the project manager.
(vii) Training
(viii) Certification(s) of personnel as required by the specifications.
(ix) Recertification of personnel.
(x) Certification of processes or equipment as required by the Specification.
(xi) Qualification of procedures.
(xii) Non-destructive testing requirements identified in the specification.
(xiii) Identification of independent certifying and testing laboratories to be used.
(xiv) The plan must contain an appendix with a reproduction of each form, report format, or other similar records to be used in the program.
The Contractor may use, at his option, in whole or in part, his existing Quality
Assurance Plan and procedures provided they are revised/updated and identified to these requirements and submitted to the Contracting Officer for review as to acceptability.
The Contractor must develop and maintain detailed quality control procedures to be scheduled as required to implement the Quality Program Plan and the requirements of the specifications and drawings.
(d) Identification and Data Retrieval
The Contractor must develop and maintain an identification and data retrieval system to provide traceability of materials, equipment, inspections and tests to the requirements of the specifications, drawings, and contract provisions. All records, drawings, submittals, and equipment (as required) must be identified and related as appropriate, to reference the following minimum controls:
(1) Contract Number
(2) Contract Specification Number
(3) Contract Drawing Number
(4) Submittal Document (SD) Numbers
(5) Contract Change Number
(6) Contractor's Drawing Number System
(e) Control of Procurements
The Contractor will be responsible for adequate and effective control over his procurement sources and those of his subcontractors, to ensure that materials, supplies, and services purchased, including all subcontracts, meet all quality requirements.
(1) The Contractor must ensure that his purchase documents include:
(i) The basic quality requirements, standards, drawings, and specifications called out in the contract specifications.
(ii) Inspection and test characteristics.
(iii) Inspection and test records.
(iv) O&M manuals, instructions, certification of compliance, and such other data as may be required by the specification.
(v) Preservation, packaging, shipping direction.
(2) When Government source inspection is required on a Contractor's purchase document, the document must include the following statement:
"All work on this order is subject to inspection and test by the Government at any time and place. The Government Representative who has been delegated NASA Quality Assurance functions on this procurement must be notified immediately upon receipt of this order. The Government Representative must also be notified forty-eight (48) hours in advance of the time articles or processes are ready for inspection or test."
(3) Procurements which do not require Government source inspections must include the following statement:
"The Government reserves the right to inspect any or all of the materials included on this order at the Contractor's plant."
(4) The need for Government source inspection will be determined by the Contracting
Officer. Source inspection determined by the Contracting Officer. Source inspection performed by the Government on procured articles or materials will not replace Contractor inspection or relieve the Contractor of his responsibility for ensuring the quality of procured articles and materials and the records necessary to verify all required quality control activities.
(f) Receiving Inspection Systems
The Contractor must maintain a Receiving Inspection System which ensures that all procured materials and equipment are inspected and tested as prescribed by the applicable specifications and drawings, and the approved submittal documents (SD's).
A Receiving Inspection Record will accompany each materials/equipment delivery to the construction site. Records of all receiving inspections/tests and nonconformance records must be maintained at the construction site by the Contractor.
These records must include documentation of any defects, discrepancies, disposition and/or waivers, including evidence of Government source inspection when required.
(g) Nonconforming Articles and Material Control
The Contractor must ensure control and recording of nonconformances discovered by the Contractor, subcontractors, suppliers or designated Government quality representatives to prevent their use and to correct deficient operations and procedures.
(1) The Contractor must prepare a "nonconformance" report for each nonconformance comprising as a minimum:
(i) A unique and traceable number.
(ii) The nomenclature and identification of the nonconforming article or material.
(iii) A description of the nonconformance and the required characteristics(s) or specifications requirement.
(iv) Cause or reason for the nonconformance.
(v) Remedial actions taken or recommended.
(vi) Disposition of the nonconforming article or material.
(2) The Contractor must identify and tag the nonconforming article and segregate/remove it from the work area.
(3) The Contractors must establish a system for monitoring and correcting deficient procedures and operations.
(h) Responsibility for Inspection
The Contractor is responsible for the performance, on a one hundred percent (100%) basis of all inspections and tests and record requirements specified in the contract. Unless otherwise specified in the contract, the Contractor may utilize independent inspection and testing laboratories or services that are acceptable to the Government.
(i) Fabrication, Process, and Work Control
(1) The Contractor's procedures and operations controls must be derived from the Quality requirements and work execution standards required by each section of the contract specification and drawings.
(2) The Contractor must establish those in-process inspection points and controls over the work as necessary to ensure compliance with quality requirements and work standards which are not readily detectable, sealed, or measurable by inspection and test of a finished article or work element. When approval or certification of special processes, operating personnel, special equipment or procedures, is required by the specifications, the Contractor must obtain necessary approvals or certification prior to starting the work/process.
(3) These special processes may include but are not limited to plating, anodizing, nondestructive testing, welding, soldering, etc. Records of in-process inspections and control away from the job site may be used as evidence of quality of materials/work and may reduce, but not eliminate further inspection or testing when delivery is made to the job site or during final testing and acceptance.
(j) Quality Control Records
(1) All quality control records must be maintained in a central on-site location by the
Contractor. These records must include all quality control data; factory tests or manufacturer's certification, quality control coordinating actions; records of quality control training/certifications as well as routine hydrostatic, electrical continuity, grounding, welding, and line cleaning, and similar tests. The quality records must be available for examination by the Contracting Officer and the Contractor must provide copies of tests and data to the Contracting Officer's on-site representative(s).
(2) The requirements to maintain quality control records, as described above, will not be construed to relieve the Contractor of submitting samples, test data, shop drawings, material certificates, or other information required by the submittal documents (SD's) called out in the specification.
(3) The Contractor must assure that each record of inspection, test, nonconformance and corrective action is identified and traceable to the specific requirement of the specifications and drawings.
(k) Inspection and Test Records
The Contractor must maintain current records on site of each inspection and test performed, on appropriate form(s) throughout the life of the contract. These records must include but not be limited to, factual evidence that the required inspections or tests have been performed, including type and number of inspections or tests involved, identification of operators and inspectors, result of inspections or tests, nature of defects, causes for rejection, proposed remedial action, and corrective actions taken.
All inspection records, test procedures, test results, and associated forms must contain a place/space to indicate verification or witness by Government Inspectors or Representatives.
Legible copies of these records must be furnished to the Contracting Officer and his on-site representative. The records must cover all work placements, traceable to the contract schedule, specifications, and drawings, and must be verified by the Prime Contractor's designated Quality Program on-site representative.
(l) Drawing and Change Control
A drawing-control system must be maintained to provide for timely drawing and change distribution to all work locations and subcontractors and prompt removal of obsolete drawings from work areas. The system must provide for timely initiation of drawings change requests.
Changes which involve interface with other work areas or that affect articles or materials controlled by others must be numbered, logged, and controlled by the Prime Contractor. This system must be effectively integrated with other document control requirements of the contract. Drawing-change affectivity must be clearly specified. Accomplished changes must be appropriately and clearly marked or identified and associated drawings must be revised accordingly. Only shop drawings that have been approved or approved as noted by the Contracting Officer shall be used for fabrication and inspection.
(m) Inspection, Measuring and Test Equipment - Calibration
(1) The Contractor must provide and maintain currently calibrated gages and other measuring and testing devices necessary to assure that the work conforms to contract requirements.
These devices must be calibrated against certified measurement standards which are traceable to national standards, as required by individual sections of the specification.
(2) Calibration records must be maintained for each item of test/measuring equipment. Any equipment exceeding its required due date or tolerance must be isolated, tagged, or otherwise marked to prevent its use.
(3) The Contractor may utilize his own certified test facilities or those of an independent testing laboratory acceptable to the Contracting Officer.
(n) Government Property Control
The Contractor must establish property controls, inspections, and records as required by the provisions of the Contract Schedule.
(o) Handling, Storage, Preservation, and Shipping
(1) The Contractor must establish a control system and appropriate procedures consistent with the requirements of each section of the Specifications.
(2) The Contractor must include a complete documentation package with his shipment. The data package must consist of any documentation required by the Contract Schedule and the Specifications required to identify, store, preserve, operate and maintain the equipment or assemblies shipped.
(p) Quality Program Audits
(1) The Contractor's program is subject to continuous evaluation, review and verification by the Contracting Officer or by his designated representatives. The Contractor will be notified in writing of any acceptance areas and will be given an appropriate period of time to correct identified deficiencies.
(2) The Contractor must establish his own system of scheduled or random audits of his program to assure the objectives are met.
E. 6 FINAL INSPECTION AND ACCEPTANCE (JAN 2018)
Final inspection and acceptance of all work under this contract will be conducted by the Contracting Officer’s Representative (COR). Upon satisfactory completion of the contract, the Contractor will be paid the fixed-price value of the contract, less the amount of any progress payments made under FAR Clause 52.232.5, Payments Under Fixed-Price Construction Contracts, or FAR Clause 52.237-4, Payment by Government to Contractor.
NOTE: The contractor must include a line item in the schedule of values and progress schedule for completion of punch-list items, site clean-up, demobilization and final construction (as-built) drawings. The amount of this line item must be equal to 10% of the contract value.
The Government will not pay final invoices for this amount until all punch-list, site clean-up, and demobilization activities are complete; final construction drawings are delivered; and final acceptance is made on DD Form 250, Material Inspection and Receiving Report.
SECTION F – DELIVERIES OR PERFORMANCE
F. 1 FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK (APR 1984)
Fill-Ins:
(a) The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed.
(c) complete the entire work ready for use not later than 406 calendar days after the date the contractor receives the notice to proceed.
See Table Below
Contract Line Item
Time Stated for Completion 406 days for All Tasks and Options
TASK 1
Complete the entire EES Conveyance work as defined in the contract drawings and specifications for use not later than the 90 days after the ML-1 Move to Pad LC-39B which is currently scheduled for July 1, 2022. The completion date is based on the assumption that the successful offeror will receive the Pre- ML-1 Move to Pad LC-39B notice to proceed* by September 17, 2021.
Complete Task 1, Segment 2 on site Post-ML-1 Move to Pad LC-39B work as defined in the contract drawings and specification for use not later than 90 calendar days after the date the contractor receives the Post- ML-1 Move to Pad LC-39B notice to proceed* (a second NTP). NTP for the Post- ML-1 Move to Pad LC-39B work is anticipated to be issued the day after ML-1 gets to the Pad and is powered up.
0001A
TASK 1A
Complete Segment 2 in 75 calendar days in lieu of 90 calendar days
OPTION
Complete Option 1 work as defined in the contract drawings and specifications for use not later than 300 calendar days after the date the contractor receives the notice to proceed
OPTION
Complete Option 2 work as defined in the contract drawings and specifications for use not later than 90 calendar days after the date the contractor receives the notice to proceed.
*THE PRE-ML-1 MOVE TO THE PAD NOTICE TO PROCEED WILL BE ISSUED
1ST. A SECOND NOTICE TO PROCEED WILL BE ISSUED FOR POST-ML-1
MOVE TO THE PAD WORK.
FAR 52.242-14 SUSPENSION OF WORK (APR 1984)
F. 2 KSC 52.211-92 WORK PERIOD
The Contractor will determine the work schedule best suited for completion of the identified tasks in the timeframe allotted. The contractor shall coordinate work hours with the Contracting Officer prior to implementation. All mandatory inspections by the Government are to be scheduled during normal work hours (7:00AM to 3:30PM, on Monday through Friday). Any other work period outside the coordinated work hours will require special/written approval from the Contracting Officer seven (7) days in advance of the proposed change in work periods.
F. 3 PLACE OF PERFORMANCE (JAN 2018)
This is a firm-fixed price construction contract for Emergency Egress System Installation for
Artemis II on Launch Complex 39B (LC39B) at Kennedy Space Center, FL.
F. 4 DOWNTIME AND EXCAVATION HOLDS (JAN 2018)
For the purposes of this contract, the Contractor must assume a maximum of 15 days during which all construction activities will be prohibited for Segment 2 work. In addition, the Contractor must assume a maximum of 5 days during which all excavation and other subsurface activities will be prohibited but other construction activities will be allowed.
F. 5 OPERATIONAL WORK AREA ACCESS CONSTRAINTS (JAN 2018)
Access to the ML-1 and Launch Complex 39B (LC-39B) construction sites will be limited due to ongoing operational requirements. No work will be allowed on the work site(s) except during assigned work windows.
(a) DEFINITIONS:
Work Window: A block of time, established by the Government, during which it is anticipated that scheduled launch or payload processing operations will permit on-site construction. The Contractor is responsible for completing construction tasks, including punch list items, within established work windows.
Downtime: A period of time within a work window when the Government must temporarily deny the Contractor access to the work site. The Government will provide twenty-four hour notice each time these restrictions are invoked. (Requests to excavate on days designated as “no dig days” must be submitted on KSC Form 50-1, Excavation Category Waiver, 7-10 days in advance of the designated “no dig days”.) Downtime days will be assessed when (1) a work window is active, and (2) the Government requires the Contractor to temporarily vacate the work site.
Days: Any reference to “days” must be construed to mean calendar days.
(b) CONSTRAINTS:
(1) Access to the work sites for pre-construction activities occurring before the construction work window, such as field measurements and field investigations, must be coordinated with the Contracting Officer at least 7 days prior to desired access date.
(2) The Government will notify the Contractor at least 7 days in advance of a work window. Multiple work windows may occur. Each work window will be broken into work segments, seen below. If the project involves work in more than one operational area, the contractor must schedule all work activities in each area independently. The minimum time that will be made available for completing all on-site construction is 90 days. The total of all work windows combined will be 406 days.
Work window milestone requirements, the project will be broken down in segments:
Segment 1: a notice to proceed (NTP) limited to submittals and off-site fabrications and testing (from NTP until the day after ML-1 move to LC-39B, (currently scheduled for July 1, 2022).
During Segment 1, after the launch of Artemis I (Currently scheduled for the end of November 2021), the contractor will be allowed to perform limited work on LC-39B without ML-1 such as set up of trailers and staging material in designated laydown areas shown on the drawings. (Note: The Crawler path will need to remain clear for the Crawler to bring ML-1 to LC-39B.)
Segment 2: a second NTP will be provided for work performed at the LC-39B. The work in Segment 2 must include installation and commissioning of all activities on site.
(3) Work windows may occur any time during the contract performance period. The
Government will schedule each work window depending on the availability of access to the areas affected.
(c) ADDITIONAL REQUIREMENT TO WORK WITHIN THE ML1 AND LC-39B:
(1) ML-1 (all locations)
Due to COVID restrictions, the elevators on ML-1 will be limited to 4 people at a time.
The contractor shall remove or secure all contractor equipment and debris for each movement of ML-1.
(2) ML Access
ML-1 is an Access Controlled Area within KSC. In addition to the security requirements in FAR 52.204-9, the following security controls apply:
All contractor personnel shall request a personal orange safety badge at the badging station located on SR 405 when receiving their initial KSC access/identification badges. If previously badged, the employee shall request a personal orange safety badge from the badging station. This orange safety badge may be required to be deposited in a badge board to facilitate an active headcount of personnel on site after entering ML-1.
In order to receive “unescorted temporary area access” overlay to ML-1 and be able to escort up to five (5) personnel, at a minimum a person must take and pass the following training courses in SATERN (https://satern.nasa.gov) or live (as applicable), and retaken at the intervals noted in parentheses:
(i) QG014KSC CLASS 1, DIVISION 2 FAMILIARIZATION SATERN Training
(ii) QG07CKSC- ELSA TRAINING SATERN Training
(iii) QG015KSC FLIGHT HARDWARE AWARENESS FOR VEHICLE PROXIMITY SATERN Training
(iv) QF135KSC ML AREA ACCESS ORIENTATION SATERN Training
(v) QG012KSC GENERAL PSM SATERN Training
(vi) KSC-QE-WBT-243: CLEANLINESS & CONTAMINATION CONTROL OVERVIEW SATERN Training
(vii) KSC-QE-WBT-244: CONTROL OF FOREIGN OBJECT DEBRIS SATERN Training
The above training applies to all personnel (civil servant and contractor) at KSC requiring unescorted access to ML-1. Lack of completion of the above training at the required intervals prior to badge expiration will result in denial of unescorted access to ML-1. As noted in KSC 52.204-9, it is the contractor’s responsibility to keep training records of all personnel and have required training completed prior to expiration for each person.
PLEASE NOTE: It typically takes 48-hours for training to update in the area access system, which may result in temporary revocation of access.
(3) Launch Complex 39B Access
LC-39B is an Access Controlled Area within KSC. In addition to the security requirements in FAR 52.204-9, the following security controls apply:
All contractor personnel shall request a personal orange safety badge at the badging station located on SR 405 when receiving their initial KSC access/identification badges. If previously badged, the employee shall request a personal orange safety badge from the badging station. This orange safety badge may be required to be deposited in a badge board to facilitate an active headcount of personnel on site after entering the LC-39B perimeter.
In order to receive “unescorted temporary area access” to the LC-39B perimeter and be able to escort up to five (5) personnel, at a minimum a person must take and pass the following training courses in SATERN (https://satern.nasa.gov) or live (as applicable), and retaken at the intervals noted in parentheses:
(i) QF110KSC, KSC General Hazards Familiarization (3-years)
(ii) QF130KSC, Pad 39B Area Access Orientation (3-years)
(iii) QG012KSC, General PSM - Process Safety Management (1-year)
(iv) QE-WBT-244, Control of Foreign Object Debris (1-year)
(v) QG07CKSC, ELSA Training (1-year, Live Training Only—Schedule through COR)
The above training applies to all personnel (civil servant and contractor) at KSC requiring unescorted access to LC-39B. Lack of completion of the above training at the required intervals prior to badge expiration will result in denial of unescorted access to LC-39B. As noted in KSC 52.204-9, it is the contractor’s responsibility to keep training records of all personnel and have required training completed prior to expiration for each person.
PLEASE NOTE: It typically takes 48-hours for training to update in the area access system, which may result in temporary revocation of access.
The government does not provide escorts for contractor personnel. The contractor is responsible for properly escorting personnel in compliance with security procedures. As noted above, a person granted “unescorted temporary area access” may escort up to five
(5) personnel who have been issued “to be escorted temporary area access.” The escorted personnel must remain in visual contact with the escort at all times, within reason (for example, the escorted personnel may use a restroom or work in a confined space with single entry like an electrical manhole, while the escort remains directly outside). Repeated reports of improperly escorted personnel by security personnel typically results in revocation of “unescorted temporary area access” for the escort and possible disciplinary actions.
(4) Entering Launch Complex 39B
All personnel entering Launch Complex 39B are required to be processed through LC-39B main gate. Personnel will be required to have approved access through the KSC NASA Access Management System (NAMS) prior to entry and coordinated with the COR.
Personnel will be approved for either unescorted or escorted access. Any personnel approved for escorted access must have an escort with unescorted access approval.
All personnel approved for escorted access must be escorted at all times by personnel approved for unescorted access. Personnel approved for unescorted access may escort up to 5 personnel at any time unless specifically directed otherwise by the Contracting Officer.
Escorted personnel must remain within sight of the escort at all times.
In addition to being properly badged and having access approved, all personnel entering the Pad are required to have a Lenel PIN programmed onto their badge. This can be accomplished at the Badging Office at Gate 3.
(5) Driving within Launch Complex 39B Perimeter – Official Business Only
LC 39B has limitations on vehicle access. The contractor and subcontractors will use their privately owned vehicles (POVs) to access LC 39B. POVs include those vehicles owned by a company or corporation (i.e. contractor or subcontractor owned), and those owned by an individual. Vehicles must be licensed, registered, and insured within the requirements of applicable laws. Drivers must be licensed for the vehicle they drive. In order to have vehicle access to LC 39B, POVs are required to be issued a hang tag from the Pad Leader’s Office in the LC 39B Operations Building, J7-0689 (located east of LC 39B entry gate). Vehicles requiring temporary access to LC 39B will be issued a hang tag daily, picked up after 7:00AM and returned before 5:00PM, except where a special request to the CO for extended work hours has been approved. A process also exists for the contractor to request longer term hang tags for vehicles regularly requiring access to the LC 39B for the entire contract duration or extended periods within the contract that do not require daily return. The quantity of longer-term hang tags that can be issued is limited.
This is the start of the file's text. The full file is on GovTribe.