Solicitation # 80KSC018R0020

NASA/KSC Refuse Collection & Disposal Services

Questions and Answers

1. QUESTION: How many trucks are currently being used by the incumbent?

ANSWER: The requested information is not available. Proprietary to current contractor.

2. QUESTION: Is it possible to receive the number of miles between the northernmost and southernmost locations?

ANSWER: 34 road miles between “KARS I (Hall Road) KARS I Recreation Area” and the “E3-1133 Mid-Course Radar Facility (North of Haulover Canal)”.

3. QUESTION: Regarding the Wage Determination: Does the below apply? Will our employees be exposed to any of the below listed in the wage determination?

ANSWER: No, the Contractor will not need hazard pay differential.

4. QUESTION: We are required to complete TABLE B.1-1 Schedule of Services however in the document provided CLINs 0001, 1001, 2001, 3001 and 4001 all have

“TBD” entered into the UNIT PRICE and AMOUNT sections of the Tables. Could you please provide copy of the schedule without the TBD’s, which can be used to submit pricing?

ANSWER: Yes. See attached pages 4 and 5 of 47, TABLE B.1-1 SCHEDULE OF

SERVICES, in which the “TBD” has been removed, for your ease of use. (Ref.

80KSC018R0020 Amend 01)

5. QUESTION: Pg. 7 of 47 C.1.1.1 Ordering refers to B.5.2 however there is not a paragraph B.5.2 included in the solicitation.

Solicitation # 80KSC018R0020

NASA/KSC Refuse Collection & Disposal Services

Questions and Answers

ANSWER: Typographical error corrected. Please see attached Pg. 7 of 47 C.1.1.2

Work Authorization Procedures. (Ref. 80KSC018R0020 Amend 01)

6. QUESTION: Please confirm that the government will be providing the dumpsters at each indicated building location.

ANSWER: No, per the Attachment 1, Performance Work Statement, dated May 22, 2018, Paragraphs 1.2, 1.2.1, 1.4.1, and 1.5, states the Contractor shall provide all containers.