80GSFC22B0003 IFB.pdf
PDF 723 KB Posted
- Attached to
- Wallops Flight Facility Restoration of Main Base Electrical Infrastructure – Phase 2 Federal contract opportunity
- Solicitation number
- 80GSFC22B0003
About this file
This document is a solicitation for the National Aeronautics and Space Administration Goddard Space Flight Center's Wallops Flight Facility Restoration of Main Base Electrical Infrastructure Phase 2 project. The project involves replacing approximately 20,000 linear feet of direct burial cable with new electrical power feeder in conduit using directional boring technology, replacing approximately 5 live front air switches with SF6 gas switches, and creating looped circuits for more flexibility and resiliency. The North American Industry Classification System code is 237130 and it is a total small business set-aside with a size standard of $39.5M. The contract will be a firm fixed price award with a completion date of 548 days from the notice to proceed. The anticipated contract award date is September 30, 2022 with a notice to proceed of November 30, 2022. The solicitation provides details on an optional site visit on August 17, 2022 and instructions for bid submission which is due by 11:00AM EST on August 31, 2022 along with the bid opening which will be held virtually via Microsoft Teams at 2:00PM EST on the same date.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 80GSFC22B0004 Amendment Two - Q and A.pdf | ||
| 80GSFC22B0003 - SF30 Amendment 2 - Signed.pdf | ||
| 80GSFC22B0003 Attachment C - Phase 2 Drawings.pdf | ||
| 80GSFC22B0003 Amendment One - Signed.pdf | ||
| Attachment F - DB Wage Determination.pdf | ||
| 80GSFC22B0003 Attachment B - Specs.pdf | ||
| 80GSFC22B0003 Attachment D - KTR RPT.pdf | ||
| 80GSFC22B0003 Attachment A - SOW.pdf | ||
| 80GSFC22B0003 IFB Cover Ltr.pdf | ||
| 80GSFC22B0003 Attachment G - Drawing Suppl.pdf | ||
| Attachment E - Safety and Health Plan.pdf | ||
| 80GSFC22B0003 Attachment C - Drawings.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER
80GSFC22B0003
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
7/29/2022
PAGE OF PAGES
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER
4200798519
6. PROJECT NUMBER
7. ISSUED BY CODE GSFC 8. ADDRESS OFFER TO
ELECTRONIC SUBMISSION VIA NASA BOX
NASA Goddard Space Flight Center Wallops Flight Facility Procurement Code 174 Leslie Adams, Contracting Officer Greenbelt, MD 20771
NASA Goddard Space Flight Center Wallops Flight Facility Procurement Code 174 Greenbelt, MD 20771
9. FOR INFORMATION
CALL:
a. NAME Leslie Adams
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
301-286-7241
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
The Contractor shall furnish Restoration of Main Base Electrical Infrastructure Phase 2 for the Code 228/Facilities Management Branch (FMB) located at the NASA/Wallops Flight Facility (WFF) in Wallops Island, Virginia.
In response to COVID-19 restrictions, Complete Bid Submission Proposal Packages SHALL ONLY be accepted via electronic commerce in accordance with FAR 52.214-5, Submission of Bids (DEC 2016). Mailed-In or Facsimile bids, modifications, or withdrawals, will not be considered. Electronic Bid Submission Proposal Packages shall be sent in an encrypted e-mail to the recipients listed in Item L.26 ELECTRONIC SUBMISSION OF PROPOSALS – PROPOSAL MARKING AND DELIVERY THROUGH NASA’s EFSS BOX (NOV 2021). Bid Opening will be held virtually in Microsoft Teams platform.
Interested parties MUST complete and sign Blocks 14 thru 20c of the attached Standard Form (SF) 1442, as well as complete the required Clause/Provision Fill-In sections.
The Prime Contractor shall also provide a bid bond with their electronic Bid Submission Proposal Package that clearly identifies the IFB number in the amount of twenty percent (20%) of the bid price, or $3 Million, whichever is lower, and MUST acknowledge any and all amendments.
Electronic Bid Submission Proposal Packages with missing information shall be considered incomplete and non-responsive.
Submission of Electronic Bid Proposal Packages shall be received by 11:00 AM EST on August 31, 2022.
11. The contractor shall begin performance within 15 calendar days and complete it within 548 calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See ).
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
12b. CALENDAR DAYS
15 Days
a. Sealed offers in original and 1 copies to perform the work required are due at the place specified in Item 8 by 11:00AM (hour) local time 8/31/2022 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
FMD Accounts Payable Bldg. 1111, Jerry Hlass Road Stennis Space Center, MS 39529 https://www.nssc.nasa.gov/vendor payment NSSC-AccountsPayable@nasa.gov
NASA’s Goddard Space Flight Center Wallops Flight Facility Procurement Code 174 Greenbelt, MD 20771
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office.) Contractor agrees tofurnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31a. NAME OF CONTRACTING OFFICER (Type or print)
Leslie Adams
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
AMOUNTS
- 3 -
Table of Contents
B.1 1852.216-78 FIRM FIXED PRICE (DEC 1988)
B.2 GSFC 52.211-90 SUPPLIES AND/OR SERVICES TO BE PROVIDED (SEP 2017)
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 GSFC 52.211-91 SCOPE OF WORK (FEB 2016)
SECTION E - INSPECTION AND ACCEPTANCE
E.1 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
E.2 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
E.3 52.246-13 INSPECTION – DISMANTLING, DEMOLITION, OR REMOVAL OF
IMPROVEMENTS (AUG 1996)
E.4 GSFC 52.246-93 ACCEPTANCE--LOCATION(S) (SEP 2013)
E.5 GSFC 52.246-102 INSPECTION SYSTEM RECORDS (APR 2013)
E.6 1852.246-71 GOVERNMENT CONTRACT QUALITY ASSURANCE FUNCTIONS... 9
(OCT 1988)
SECTION F CLAUSES INCORPORATED BY REFERENCE
F.1 52.211-13 TIME EXTENSIONS (SEP 2000)
F.2 52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
F.3 52.242-14 SUSPENSION OF WORK (APR 1984)
F.4 52.247-34 F.O.B. DESTINATION (JAN 1991)
F.5 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
F.6 52.211-12 LIQUIDATED DAMAGES-CONSTRUCTION (SEP 2000)
F.7 GSFC 52.217-92 PERIOD OF PERFORMANCE/EFFECTIVE ORDERING PERIOD
(JAN 2014)
F.8 GSFC 52.237-92 PLACE OF PERFORMANCE – SERVICES (NOV 2013)
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 1852.245-75 PROPERTY MANAGEMENT CHANGES (JAN 2011)
G.2 1852.245-82 OCCUPANCY MANAGEMENT REQUIREMENTS (SEP 2017)
G.3 1852.245-83 REAL PROPERTY MANAGEMENT REQUIREMENTS (JAN 2011)
G.4 1852.232-80 SUBMISSION OF VOUCHERS/INVOICES FOR PAYMENT (APR 2018)
G.5 GSFC 52.232-90 INVOICES FOR CONSTRUCTION CONTRACTS (MAY 2018)
SECTION H CLAUSES INCORPORATED BY REFERENCE
H.6 1852.243-72 EQUITABLE ADJUSTMENTS (APR 1998)
H.7 GSFC 52.204-99 CONTRACTOR PERSONNEL—IDENTIFICATION, ONSITE
REPORTING, AND CHECKOUT PROCEDURES (GSFC 52.204 99) (NOV 2021)
H.8 GSFC 52.211-95 GOVERNMENT PREMISES – PHYSICAL ACCESS AND
COMPLIANCE WITH PROCEDURES (NOV 2020)
H.9 SCHEDULE OF PRICES
H.10 GSFC 52.223-91 SAFETY AND HEALTH – ADDITIONAL REQUIREMENTS (NOV
2019) 22
SECTION I - CONTRACT CLAUSES
I.1 52.202-1 DEFINITIONS (JUN 2020)
I.124 52.223-20 AEROSOLS (JUN 2016)
I.125 52.223-21 FOAMS (JUN 2016)
I.126 52.225-9 BUY AMERICAN - CONSTRUCTION MATERIALS (NOV 2021)
I.127 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT— CONSTRUCTION
MATERIALS (MAY 2014)
I.128 52.232-40 PROVIDING ACCELERATED PAYMENT TO SMALL BUSINESS
SUBCONTRACTORS (NOV 2021)(DEVIATION 20-03B)
I.129 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) 42
I.130 52.236-4 PHYSICAL DATA (APR 1984) 42
I.131 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
I.132 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)
I.133 1852.225-71 RESTRICTION ON FUNDING ACTIVITY WITH CHINA
(FEB 2012) (DEVIATION)
J.1 GSFC 52.211-101 LIST OF ATTACHMENTS (FEB 2016)
K.1 52.236-28 PREPARATION OF PROPOSALS - CONSTRUCTION (OCT 1997)
K.2 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022)
K.3 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS
AND VIDEO SURVEILLANCE SERVICES OR EQIPMENT (OCT 2020)
K.5 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)58
K.6 52.209-12 CERTIFICATION REGARDING TAX MATTERS (OCT 2020)
K.7 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—
CERTIFICATION (FEB 2021)
K.8 1852.225-72 RESTRICTION ON FUNDING ACTIVITY WITH CHINA –
REPRESENTATION (DEVIATION 12-01A) (FEB 2012)
L.1 52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
L.15 1852.214-70 CAUTION TO OFFERORS FURNISHING DESCRIPTIVE LITERATURE
(DEC 1988)
L.17 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS – SECONDARY SITE
OF THE WORK (MAY 2014)
L.18 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE
EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
L.19 52.233-2 SERVICE OF PROTEST (SEP 2006)
L.20 52.236-27 SITE VISIT (CONSTRUCTION). (FEB 1995) - ALTERNATE I (FEB 1995)
L.21 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998) 65
L.22 52.252-5AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
L.23 1852.233-70 PROTEST TO NASA (DEC 2015)
L.24 1852.236-74 MAGNITUDE OF REQUIREMENT (DEC 1988)
L.25 GSFC 52.215-200 COMMUNICATIONS REGARDING THIS SOLICITATION (SEP
2017) 67
L.26 ELECTRONIC SUBMISSION OF PROPOSALS – PROPOSAL MARKING AND
DELIVERY THROUGH NASA’s EFSS BOX (NOV 2021)
M.1 52.214-19 CONTRACT AWARD -- SEALED BIDDING – CONSTRUCTION (AUG
1996) 71
M.2 GSFC 52.209-300 PROSPECTIVE CONTRACTOR RESPONSIBILITY (MAR 2019) . 71
SECTION A - SOLICITATION/CONTRACT FORM
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 1852.216-78 FIRM FIXED PRICE (DEC 1988)
The total firm fixed price of this contract is: $ (To Be Completed by Bidder)
(End of clause)
B.2 GSFC 52.211-90 SUPPLIES AND/OR SERVICES TO BE PROVIDED (SEP
2017)
The Contractor shall provide all resources (except as may be expressly stated in the contract as furnished by the Government) necessary to deliver and/or perform the items below in accordance with the Specifications and Drawings, incorporated as Attachments B and C.
Item Description Reference Schedule Delivery Method/Addressee(s)
Services, Deliverables, & Material Submittals in accordance with Attachments A –
SOW, B -
Specifications, and C
- Drawings
As Defined in Attachments A
– SOW, B -
Specifications, and C - Drawings
As Defined in Attachments A –
SOW, B -
Specifications, and C - Drawings
As Defined in Attachments
A – SOW, B -
Specifications, and C - Drawings
Standard Form 25 - Performance Bond or Irrevocable Letter of Credit
Section I
FAR
52.228-15
Within 15 days after notice of award or actual contract award
Electronic Format/Contracting Officer (CO)
Standard Form 25A - Payment Bond or Irrevocable Letter of Credit
Section I
FAR
52.228-15
Within 15 days after notice of award or actual contract award
Electronic Format/CO
Contractor’s Daily Reports
Attachment D
Daily, close of business on the first day of performance
Electronic Format/NASA Inspector and COR
Certified Payrolls
Section I 52.222-8
Weekly (within 7 days after the regular payment date of the payroll week covered)
Electronic or Hard Copy/CO and COR
Schedule of Prices
Clause H.9 Schedule of Prices 14 days after contract award date, Prior to Notice to Proceed
Electronic Format/CO, COR
7 Construction Progress Schedule
Section I 52.236-15
15 days after Contract Award Date, Prior to Notice to Proceed
Electronic Format/CO, COR
Standard Form 1413 - Subcontractor Statement and Acknowledgement
52.222-11
Within 14 days of award of contract and subsequent awarded subcontracts
Electronic Format/CO and
COR
Test Reports
Quality Control Testing Supplied by the Contractor as defined in Attachment B
Close of business on the day of the test
As specified in Attachment B
/COR
Government Real Property Maintenance Plan
Section G
NFS 1852.245-83
30 Days after Contract award Electronic Format/CO and
Safety & Health Plan Section H
FAR 52.236-13-
Alternate I
30 days after contract award, Prior to Notice to Proceed
Electronic Format /CO and
COR
Safety & Health Reporting
Section H
NFS 1852.223-70
Section H
NFS 1852.223-75
GSFC 52.223-91
Monthly/Quarterly Reports and As Required
NASA Mishap Information System (NMIS),CO and
Personal Identity Verification (PIV)
Documentation and Reporting
GSFC 52.204-99
10th Calendar Day of the Month and As Required
Electronic Format and Hard Copy/COR & Code 240
Certificate of Insurance
FAR 52.228-5
NFS 1852.228-75
As Specified by
FAR 52.228-5
Affirmative Procurement of Biobased Products
Section I
FAR 52.223-2
Annually by October 31 and Final Report www.sam.gov and copy to the
CO
Estimate of Recovered Material Content
Section I
FAR 52.223-9
Monthly Report and Upon Contract Completion
Service Contract Reporting
FAR 52.204-14
Annually by October 31 and Revisions, if needed, by November 30 www.sam.gov
18 Equal Opportunity Reports
Section I
FAR 52.222-26
As Specified by
FAR 52.222-26
Code 120
NOTE: Unless otherwise specified, “day” means “calendar day.”
No work shall begin on this contract until notice given in writing by the Contracting Officer to proceed.
(END OF SECTION B)
http://www.sam.gov/ http://www.sam.gov/
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 GSFC 52.211-91 SCOPE OF WORK (FEB 2016)
The Contractor shall provide the personnel, materials, and facilities, except as otherwise specified in this contract, necessary to perform the work and to furnish the items specified in the Supplies and/or Services To Be Provided clause of this contract in accordance with Attachment A, Statement of Work; Attachment B, “WFF Restoration of Main Base Electrical Infrastructure Phase 2 Specifications” and Attachment C, “Main Base Electrical Stamped Construction Drawings”
(END OF SECTION C)
SECTION D - PACKAGING AND MARKING
THERE ARE NO CLAUSES IN THIS SECTION D
(END OF SECTION D)
SECTION E - INSPECTION AND ACCEPTANCE
E.1 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
(a) The Contractor shall comply with the higher-level quality standard(s) listed below.
Title Number Date Tailoring
(To be specified if applicable)
(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in—
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require—
(i) Control of such things as design, work operations, in-process control, testing, and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
E.2 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
E.3 52.246-13 INSPECTION – DISMANTLING, DEMOLITION, OR REMOVAL OF
IMPROVEMENTS (AUG 1996)
E.4 GSFC 52.246-93 ACCEPTANCE--LOCATION(S) (SEP 2013)
The Contracting Officer or authorized representative will accomplish acceptance at the following location(s):
Deliverable Item No. Location Authorized Representative
1 through 18 WFF CO, COR
The Contracting Officer reserves the right to designate other Government agents as authorized representatives. The Contractor will be notified by a written notice or by a copy of the delegation letter if other agents are authorized.
If this is a fixed price type contract, acceptance shall be deemed to have occurred constructively--for the sole purpose of computing an interest penalty that might be due the Contractor under the Prompt Payment Act--on the 14th day after the
Contractor has delivered the supplies or services in accordance with the terms and conditions of the contract. In the event that actual acceptance occurs within the constructive acceptance period, the determination of an interest penalty shall be based on the date of the actual acceptance.
E.5 GSFC 52.246-102 INSPECTION SYSTEM RECORDS (APR 2013)
The Contractor shall maintain records evidencing inspections in accordance with the Inspection clause of this contract for six (6) years after delivery of all items and/or completion of all services called for by the contract.
E.6 1852.246-71 GOVERNMENT CONTRACT QUALITY ASSURANCE FUNCTIONS
(OCT 1988)
In accordance with the inspection clause of this contract, the Government intends to perform the following functions at the locations indicated:
Item Quality Assurance Function Quality Assurance Location
TBD TBD TBD
(END OF SECTION E)
SECTION F – DELIVERIES OR PERFORMANCE
SECTION F CLAUSES INCORPORATED BY REFERENCE
F.1 52.211-13 TIME EXTENSIONS (SEP 2000)
F.2 52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
F.3 52.242-14 SUSPENSION OF WORK (APR 1984)
F.4 52.247-34 F.O.B. DESTINATION (JAN 1991)
F.5 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work, ready for use within 548 days after notice to proceed. The time stated for completion shall include final cleanup of the premises.
F.6 52.211-12 LIQUIDATED DAMAGES-CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,058 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
F.7 GSFC 52.217-92 PERIOD OF PERFORMANCE/EFFECTIVE ORDERING
PERIOD (JAN 2014)
The period of performance of this contract shall be for a period of 5 years from the contract effective date of TBD.
F.8 GSFC 52.237-92 PLACE OF PERFORMANCE – SERVICES (NOV 2013)
The services to be performed under this contract shall be performed at the following location(s): Wallops Flight Facility (WFF), Wallops Island, VA.
(END OF SECTION F)
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 1852.245-75 PROPERTY MANAGEMENT CHANGES (JAN 2011)
G.2 1852.245-82 OCCUPANCY MANAGEMENT REQUIREMENTS (SEP 2017)
(a) In addition to the requirements of the clause at FAR 52.245-1, Government Property, as included in this contract, the Contractor shall comply with the following in performance of work in and around Government real property:
(1) NPD 8800.14, Policy for Real Estate Management.
(2) NPD 8831.2, Facilities Maintenance and Operations Management.
(b) The Contractor shall obtain the written approval of the Contracting Officer before installing or removing Contractor-owned property onto or into any Government real property or when movement of Contractor-owned property may damage or destroy Government-owned property. The Contractor shall restore damaged property to its original condition at the Contractor's expense.
(c) The Contractor shall not acquire, construct or install any fixed improvement or structural alterations in Government buildings or other real property without the advance, written approval of the Contracting Officer. Fixed improvement or structural alterations, as used herein, means any alteration or improvement in the nature of the building or other real property that, after completion, cannot be removed without substantial loss of value or damage to the premises. Title to such property shall vest in the Government.
(d) The Contractor shall report any real property or any portion thereof when it is no longer required for performance under the contract, as directed by the Contracting Officer.
G.3 1852.245-83 REAL PROPERTY MANAGEMENT REQUIREMENTS (JAN
2011)
(a) In addition to the requirements of the FAR Government Property Clause incorporated in this contract (FAR 52.245–1), the Contractor shall comply with the following in performance of any maintenance, construction, modification, demolition, or management activities of any Government real property:
(1) NPD 8800.14, Policy for Real Property Management.
(2) NPR 8831.2, Facility Maintenance Management.
Within 30 calendar days following award, the Contractor shall provide a plan for maintenance of Government real property provided for use under this contract. The
Contractor’s maintenance program shall enable the identification, disclosure, and performance of normal and routine preventative maintenance and repair. The Contractor shall disclose and report to the Contracting Officer the need for replacement and/or capital rehabilitation. Upon acceptance by the Contracting Officer, the program shall become a requirement under this contract.
(b) Title to parts replaced by the Contractor in carrying out its normal maintenance obligations shall pass to and vest in the Government upon completion of their installation in the facilities. The Contractor shall keep the property free and clear of all liens and encumbrances.
(c) The Contractor shall keep records of all work done to real property, including plans, drawings, charts, warranties, and manuals. Records shall be complete and current. Record of all transactions shall be auditable. The Government shall have access to these records at all reasonable times, for the purposes of reviewing, inspecting, and evaluating the Contractor’s real property management effectiveness.
When real property is disposed of under this contract, the Contractor shall deliver the related records to the Government.
(d) The Contracting Officer may direct the Contractor in writing to reduce the work required by the maintenance program authorized in paragraph (b) of this clause at any time.
G.4 1852.232-80 SUBMISSION OF VOUCHERS/INVOICES FOR PAYMENT
(APR 2018)
(a) The designated payment office is the NASA Shared Services Center (NSSC) located at FMD Accounts Payable, Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS 39529.
(b) Except for classified vouchers, the Contractor shall submit all vouchers and invoices using the steps described at NSSC’s Vendor Payment information web site at:
https://www.nssc.nasa.gov/vendorpayment. Please contact the NSSC Customer Contact Center at 1-877-NSSC123 (1-877-677-2123) with any additional questions or comments.
(c) Payment requests.
(1) The payment periods are stipulated in the payment clause(s) contained in this contract.
(2) Vouchers submitted under cost-type contracts and invoices submitted under fixed-price contracts shall include the items delineated in FAR 32.905(b) supported by relevant back-up documentation. Back-up documentation shall include at a minimum, the following information:
(i) Vouchers.
https://www.nssc.nasa.gov/vendorpayment
(A) Breakdown of billed labor costs and associated contractor generated supporting documentation for billed direct labor costs to include rates used and number of hours incurred.
(B) Breakdown of billed other direct costs (ODCs) and associated contractor generated supporting documentation for billed ODCs.
(C) Indirect rate(s) used to calculate the amount of billed indirect expenses.
(D) Progress reports, as required.
(ii) Invoices.
(A) Description of goods and services delivered as part of the contract’s terms and conditions, including the dates of delivery/performance.
(B) Progress reports, as required.
(C) Date goods and services were performed.
(iii) Fee vouchers.
(A) Listing of all provisionally-billed fee by period or date earned since contract award.
(B) A reconciliation of all billed and earned fee.
(C) A clear explanation of the fee calculations.
(d) Non-electronic payment requests. The Contractor may submit a non-electronic voucher/invoice using the steps for non-electronic payment requests described at https://www.nssc.nasa.gov/vendorpayment, when any of the following conditions are met:
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor.
(2) The contract includes provisions allowing the contractor to submit vouchers or invoices using the steps for non-electronic payment requests. In such instances the Contractor agrees to submit non-electronic payment requests using the method or methods specified in Section G of the contract.
(e) Improper vouchers/invoices. The NSSC Payment Office will notify the contractor of any apparent error, defect, or impropriety in a voucher/invoice within seven calendar days of receipt by the NSSC Payment Office. Inquiries regarding requests for payment should be directed to the NSSC as specified in paragraph (b) of this section.
(f) Other payment clauses. In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payment requests.
(g) In the event that amounts are withheld from payment in accordance with provisions of this contract, a separate payment request for the amount withheld will be required before payment for that amount may be made.
https://www.nssc.nasa.gov/vendorpayment
G.5 GSFC 52.232-90 INVOICES FOR CONSTRUCTION CONTRACTS (MAY 2018)
(a) Payment Office. The designated payment office is the NASA Shared Services Center (NSSC) located at FMD Accounts Payable, Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS 39529. Please contact the NSSC Customer Contact Center at 1-877- NSSC123 (1-877-677-2123) with any additional questions or comments.
(b) Invoices. Invoices shall be prepared in accordance with the Prompt Payment for Construction Contracts clause (FAR 52.232-27) and contain the certification and all information required by the Payments under Fixed-Price Construction Contracts clause (FAR 52.232-5) of this contract. In addition, invoices shall be submitted using the steps described at the NSSC’s Vendor Payment information web site at https://www.nssc.nasa.gov/vendorpayment.
(c) At the time of submittal to the payment office, an information copy of each invoice and supporting documents shall be submitted to:
Contracting Officer: Leslie Adams Code: 174 Email: Leslie.M.Adams@nasa.gov
Contracting Officer’s Representative: Stephen A. Mariner Code: 228 Email: Stephen.A.Mariner@nasa.gov
(c) Improper invoices. The NSSC Payment Office will notify the contractor of any apparent error, defect, or impropriety in an invoices within seven calendar days of receipt by the NSSC Payment Office. Inquiries regarding requests for payment should be directed to the NSSC as specified in paragraph (b) of this section.
(d) In the event that amounts are withheld from payment in accordance with provisions of this award, a separate payment request for the amount withheld will be required before payment for that amount may be made.
(END OF SECTION G)
http://www.nssc.nasa.gov/vendorpayment http://www.nssc.nasa.gov/vendorpayment mailto:Email:%20Leslie.M.Adams@nasa.gov mailto:Email:%20%20Stephen.A.Mariner@nasa.gov
SECTION H – SPECIAL CONTRACT REQUIREMENTS
SECTION H CLAUSES INCORPORATED BY REFERENCE
H.1 1852.223-70 SAFETY AND HEALTH MEASURES AND MISHAP
REPORTING (DEC 2015)
H.2 1852.223-75 MAJOR BREACH OF SAFETY OR SECURITY (FEB 2002)
H.3 1852.242-72 DENIED ACCESS TO NASA FACILITIES (OCT 2015)
H.4 52.236-13 ACCIDENT PREVENTION (NOV 1991) - ALTERNATE I (NOV 1991)
(a) The Contractor shall provide and maintain work environments and procedures which will—
(1) Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities;
(2) Avoid interruptions of Government operations and delays in project completion dates;
and
(3) Control costs in the performance of this contract.
(b) For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall—
(1) Provide appropriate safety barricades, signs, and signal lights;
(2) Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910; and
(3) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.
(c) If this contract is for construction or dismantling, demolition or removal of improvements with any Department of Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.
(d) Reserved.
(e) The Contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.
(f) Before commencing the work, the Contractor shall—
(1) Submit a written Safety and Health Plan in accordance with NPR 8715.3, NASA Safety Manual, Appendices;
(2) The plan shall be submitted to the Contracting Officer within 30 days after contract award. This plan, as approved by the Contracting Officer, will be incorporated into the contract; and
(3) The contractor may perform the following work prior to the plan being approved and incorporated into the contract: "None".
H.5 1852.225-70 EXPORT LICENSES (FEB 2000)
(a) The Contractor shall comply with all U.S. export control laws and regulations, including the International Traffic in Arms Regulations (ITAR), 22 CFR Parts 120 through 130, and the Export Administration Regulations (EAR), 15 CFR Parts 730 through 799, in the performance of this contract. In the absence of available license exemptions/exceptions, the Contractor shall be responsible for obtaining the appropriate licenses or other approvals, if required, for exports of hardware, technical data, and software, or for the provision of technical assistance.
(b) The Contractor shall be responsible for obtaining export licenses, if required, before utilizing foreign persons in the performance of this contract, including instances where the work is to be performed on-site at Wallops Flight Facility, Wallops Island, Virginia where the foreign person will have access to export-controlled technical data or software.
(c) The Contractor shall be responsible for all regulatory record keeping requirements associated with the use of licenses and license exemptions/exceptions.
(d) The Contractor shall be responsible for ensuring that the provisions of this clause apply to its subcontractors.
H.6 1852.243-72 EQUITABLE ADJUSTMENTS (APR 1998)
(a) The provisions of all other clauses contained in this contract which provide for an equitable adjustment, including those clauses incorporated by reference with the exception of the "Suspension of Work" clause (FAR 52.242-14), are supplemented as follows:
Upon written request, the Contractor shall submit a proposal for review by the Government. The proposal shall be submitted to the contracting officer within the time limit indicated in the request or any extension thereto subsequently granted.
The proposal shall provide an itemized breakdown of all increases and decreases in the contract for the Contractor and each subcontractor in at least the following detail: material quantities and costs; direct labor hours and rates for each trade;
the associated FICA, FUTA, SUTA, and Workmen's Compensation Insurance;
and equipment hours and rates.
(b) The overhead percentage cited below shall be considered to include all indirect costs including, but not limited to, field and office supervisors and assistants, incidental job burdens, small tools, and general overhead allocations.
"Commission" is defined as profit on work performed by others. The percentages for overhead, profit, and commission are negotiable according to the nature, extent, and complexity of the work involved, but in no case shall they exceed the following ceilings:
Overhead (Percent)
Profit (Percent)
Commission
To Contractor on work performed by other than its own forces
10 percent
To first tier subcontractor on work performed by its subcontractors
To Contractor and/or subcontractors on work performed with their own forces
(c) Not more than four percentages for overhead, profit, and commission shall be allowed regardless of the number of subcontractor tiers.
(d) The Contractor or subcontractor shall not be allowed overhead or commission on the overhead, profit, and/or commission received by its subcontractors.
(e) Equitable adjustments for deleted work shall include credits, limited to the same percentages for overhead, profit, and commission in paragraph (b) of this clause.
(f) On proposals covering both increases and decreases in the amount of the contract, the application of the overhead, profit, and commission shall be on the net change in direct costs for the Contractor or the subcontractor performing the work.
(g) After receipt of the Contractor's proposal, the contracting officer shall act within a reasonable period, provided that when the necessity to proceed with a change does not permit time to properly check the proposal, or in the event of a failure to reach an agreement on a proposal, the contracting officer may order the Contractor to proceed on the basis of the price being determined at the earliest practicable date. In such a case, the price shall not be more than the increase or less than the decrease proposed.
H.7 GSFC 52.204-99 CONTRACTOR PERSONNEL—IDENTIFICATION,
ONSITE REPORTING, AND CHECKOUT PROCEDURES (GSFC 52.204
99) (NOV 2021)
(a) In accordance with FAR 52.204-9, Personal Identity Verification of Contractor Personnel, the Contractor shall follow the procedures in NASA Procedural Requirements (NPR) 1600.4, for each contract employee (prime and subcontractor) who will have physical access to a NASA-controlled facility (also referred to as “onsite”). The Contractor must apply for permanent NASA/GSFC PIV cards for those contract employees who will be employed by the Contractor onsite for at least six months. GSFC Protective Services will consider permanent PIV cards for other employees of the Contractor on a case-by-case basis, such as employees that are not resident onsite, but must frequently visit. In the future, upon written notice from the Contracting Officer, the Contractor shall follow the steps outlined in NPR 1600.4 for each offsite contract employee (prime and subcontractor) who require remote access to a NASA information system for contract performance.
(b) The Contractor shall notify GSFC Protective Services, Code 240, Attention: Badging Supervisor, and the Contracting Officer’s Representative (COR) of the contractor’s designated PIV Requester within 15 calendar days after award of this contract. The NASA maintained PIV system (Identify and Access Management – IdMAX) contains work and home location and contact information for personnel that have permanent NASA PIV cards. The Contractor may contact the Badging Supervisor, Tel 301-286-2306 for assistance regarding IdMAX.
(c) Each contract employee shall provide to the Contractor’s designated PIV Requester the basic identifying information required for a PIV Request to be initiated in IdMAX. The PIV Request must be approved by the PIV Sponsor (COR or the Contracting Officer). The COR will resolve any housing or access issues and review the request for accuracy and completeness. Requests that are approved by the PIV Sponsor will be forwarded to GSFC Protective Services, Code 240, PIV Authorization, Badge enrollment, and Badge issuance.
(d) The Contractor shall submit an annotated PIV Report each month. The GSFC Badging Supervisor will furnish a PIV print-out to the Contractor no later than the end of each month. The Contractor shall annotate this provided report monthly to correct and update the information as follows:
(1) Draw a line through the names of employees who are no longer employed by the contractor or that no longer work onsite under the contract; and
(2) Make handwritten changes to any other incorrect data.
The annotated PIV Report shall be separately submitted to GSFC Protective Services, Code 240, Attention: Badging Supervisor, and to the COR by the 10th calendar day of the month.
For the final PIV Report under the contract, the GSFC Badging Supervisor will furnish a PIV print-out to the Contractor no later than two weeks prior to the end of the contract. The Contractor shall submit its annotated final PIV Report no later than three (3) days prior to the end of the contract.
If this is a follow-on contract, at the end of the phase-in period (if any)/start of the basic contract period, GSFC Protective Services will provide the Contractor a copy of the final PIV Report from the previous contract. The Contractor shall review the list and redline it as necessary to reflect its employees requiring PIV cards. The redlined list shall be provided GSFC Protective Services within 30 days after the start of the contract.
(e) The Contractor shall ensure that all personnel who have NASA/GSFC issued PIV cards, keys or other property who leave its employment or that no longer work onsite, process out through GSFC Protective Services, Code 240 and complete the GSFC form 17-26A, which shall be signed off and maintained by the contract Program Manager once completed. Employees must return all GSFC issued identification and any Government property no later than the last day of their employment or the last day they work onsite under this contract. The Contractor shall establish appropriate procedures and controls to ensure this is accomplished. In addition, it is the responsibility of the contractor to notify the government of any termination/removal that occurs when the PIV has not been turned in to or received by the government. Failure to comply may result in the exercise of Government rights to limit and control access to Government premises, including denial of access and invalidation of NASA issued PIV cards and identification.
H.8 GSFC 52.211-95 GOVERNMENT PREMISES – PHYSICAL ACCESS
AND COMPLIANCE WITH PROCEDURES (NOV 2020)
(a)(1) The Contractor must apply for permanent NASA/GSFC Personal Identity Verification (PIV) cards (badges) for those employees that will be employed by the Contractor and subcontractors and that will be resident for at least six months at GSFC or at locations controlled by GSFC, such as GSFC leased space. Other personnel may be issued a temporary badge. All personnel must conspicuously display the GSFC PIV card at, or above, the waistline. Refer to GSFC clause 52.204-99, “Contractor Personnel – Identification, Onsite Reporting, and Checkout Procedures” for permanent PIV card issuance procedures.
(2) Visits by foreign nationals are restricted and must be necessary for the performance of the contract and concurred with by the Contracting Officer or by the Contracting Officer’s Representative. Approval of such visits must be approved in advance in accordance with Goddard Procedural Requirement (GPR) 1600.1.
(3) Access to the GSFC may be changed or adjusted in response to threat conditions or special situations.
(b) While on Government premises, the Contractor shall comply with all requirements governing the conduct of personnel and the operation of the facility. These requirements are set forth in NASA Procedural Requirements (NPR), NASA Policy Directives (NPD), GPRs, GSFC Policy Directives (GPD), handbooks and announcements. The following cover many of the requirements:
(1) Harassment and Discrimination Announcements:
https://eeo.gsfc.nasa.gov/article/anti-harassment
(2) GSFC Workplace Violence Announcement:
https://ohcm.gsfc.nasa.gov/content/gsfc-workplace-domestic-violence
(3) GPR 1600.1, GSFC Security Requirements
(4) NPD 1600.3, Policy on Prevention of and Response to Workplace Violence
(5) GPR 1700.1, Occupational Safety Program at GSFC
(6) GPR 1700.2, Chemical Hygiene Program
(7) GPR 1700.5, Control of Hazardous Energy (Lockout/Tagout)
(8) GPR 1700.6, Confined Space Program at GSFC https://eeo.gsfc.nasa.gov/article/anti-harassment https://ohcm.gsfc.nasa.gov/content/gsfc-workplace-domestic-violence
(9) GPR 1700.7, Electrical Safety
(10) GPR 1700.8, GSFC Hazard Communication Program
(11) GPR 1800.1, GSFC Smoking and Other Tobacco Use Requirements
(12) GPR 1800.6, Occupational Health, Medicine and Employee Assistance Programs
(13) GPR 1840.2, Industrial Hygiene Program
(14) GPR 1860.1, Ionizing Radiation Protection
(15) GPR 1860.2, Laser Radiation Protection
(16) GPR 1860.3, Radio Frequency Radiation Protection
(17) GPR 1860.4, Ultraviolet and High Intensity Light Radiation Protection
(18) NPD 2540.1, Personal Use of Government Office Equipment Including Information Technology
(19) GPR 2570.1, Spectrum Management and Radio Frequency (RF) Equipment Licensing
(20) NPR 3713.3, Anti-Harassment Procedures
(21) GPD 8500.1, Environmental Policy and Program Management
(22) GPR 8621.4, GSFC Mishap Preparedness and Contingency Plan
(23) GPR 8710.2, GSFC Emergency Management Program Plan
(24) GPR 8710.7, Cryogenic Safety
(25) GPR 8710.8, GSFC Safety Program Management
(26) GPD 8715.1, GSFC Safety Policy
(27) GPR 8715.1, Processing of NASA Safety Reporting System (NSRS) Incident Reports
(28) GPR 8715.8, Fall Protection Requirements for GSFC
Copies of the current issuances of the GPD/GPRs may be obtained at http://gdms.gsfc.nasa.gov from a computer onsite (GSFC Government Facility) or from the Contracting Officer. Copies of the current issuances of the NPD/NPRs may be obtained at http://nodis3.gsfc.nasa.gov or from the Contracting
Officer. The above list may be modified by the Contracting Officer to include additional issuances pertaining to the conduct of personnel and the operation of the facility.
(c) The Contractor may not use official Government mail (indicia or "eagle" mail). Contractors found in violation could be liable for a fine of $300 per piece of indicia mail used. However, the Contractor is allowed to use internal GSFC mail to the extent necessary for purposes of the contract.
H.9 SCHEDULE OF PRICES
Fourteen days after award of contract, prior to issuance of the notice to proceed, the Contractor shall submit to the Contracting Officer a price breakdown to include a projected construction schedule, a schedule of price values and a list of critical work sequences necessary for proper and timely execution of the work in accordance with Clause 52.232-5--Payment under Fixed Price Construction. Where several buildings and/or structures are involved, each shall be shown separately. This breakdown shall be in such detail as to make possible a quick check of estimates for partial payments, and shall separate material prices from labor prices for each portion of the work.
http://gdms.gsfc.nasa.gov/ http://nodis3.gsfc.nasa.gov/
(End of text)
H.10 GSFC 52.223-91 SAFETY AND HEALTH – ADDITIONAL
REQUIREMENTS (NOV 2019)
In addition to compliance with all Federal, state, and local laws as required by paragraph
(b) of NFS clause 1852.223-70, the Contractor shall comply with the following:
(a) Incident Reporting: The immediate notification and prompt reporting requirement included in paragraph (d) of NFS clause 1852.223-70 shall be to Wallops Flight Facility Safety Office, Code 803, Telephone 757-824-1625 and to the Contracting Officer (CO).
This verbal notification should be confirmed in writing via E-Mail to the CO and Logan.J.Wright@nasa.gov and entered into the NASA Mishap Information System (NMIS) within 24 hours. This notification is also required for any unsafe or environmentally hazardous condition associated with Government-owned property that is provided or made available for the performance of the contract.
(b) Submit a monthly safety and health report using NMIS. Specify incidents (mishaps and close calls) and man-hours worked/month. Access to NMIS must be requested through the NASA Access Management System (NAMS) within 30 days of the contract effective date at https://idmax.nasa.gov. Until access is approved, use the Contractor Monthly Statistics Report Template available at http://safety1st.gsfc.nasa.gov under Contractor Safety and e-mail the completed form to Logan.J.Wright@nasa.gov.
(END OF SECTION H)
mailto:Logan.J.Wright@nasa.gov mailto:Logan.J.Wright@nasa.gov http://safety1st.gsfc.nasa.gov/ mailto:Logan.J.Wright@nasa.gov
SECTION I - CONTRACT CLAUSES
I.1 52.202-1 DEFINITIONS (JUN 2020)
I.2 52.203-3 GRATUITIES (APR 1984)
I.3 52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
I.4 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN
2020)
I.5 52.203-7 ANTI-KICKBACK PROCEDURES (JUN 2020)
I.6 52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS
FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
I.7 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER
ACTIVITY (MAY 2014)
I.8 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN
FEDERAL TRANSACTIONS (JUN 2020)
I.9 52.203-14 DISPLAY OF HOTLINE POSTER(S) (JUN 2021)
[PARAGRAPH (B)(3) HTTP://OIG.NASA.GOV/HOTLINE.HTML,
I.10 52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL
CONFIDENTIALITY AGREEMENTS OR STATEMENTS (JAN 2017)
I.11 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON
POSTCONSUMER FIBER CONTENT PAPER (MAY 2011)
I.12 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR
PERSONNEL (JAN 2011)
I.13 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER
SUBCONTRACT AWARDS (JUN 2020)
I.14 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT
2018)
I.15 52.204-14 SERVICE CONTRACTING REPORTING REQUIREMENTS
(OCT 2016)
I.16 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE
MAINTENANCE (AUG 2020)
I.17 52.204-19 INCORPORATION BY REFERENCE OF
http://oig.nasa.gov/HOTLINE.HTML, REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)
I.18 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE,
SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KAPERSKY
LAB AND OTHER COVERED ENTITIES (NOV 2021)
I.19 52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN
SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR
PROPOSED FOR DEBARMENT (NOV 2021)
I.20 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION
REGARDING RESPONSIBILITY MATTERS (OCT 2018)
I.21 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED
DOMESTIC CORPORATIONS (NOV 2015)
I.22 52.210-1 MARKET RESEARCH (NOV 2021)
I.23 52.214-26 AUDIT AND RECORDS - SEALED BIDDING (JUN 2020)
I.24 52.214-27 PRICE REDUCTION FOR DEFECTIVE COST OR PRICING
DATA - MODIFICATIONS - SEALED BIDDING (JUN 2020)
I.25 52.214-28 SUBCONTRACTOR CERTIFIED COST OR PRICING DATA -
MODIFICATIONS - SEALED BIDDING (JUN 2020)
I.26 52.214-29 ORDER OF PRECEDENCE - SEALED BIDDING (JAN 1986)
I.27 52.215-17 WAIVER OF FACILITIES CAPITAL COST OF MONEY (OCT 1997)
I.28 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)
I.29 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2018)
I.30 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(SEP 2021)
I.31 52.222-1 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (FEB 1997)
I.32 52.222-3 CONVICT LABOR (JUN 2003)
I.33 52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS -
OVERTIME COMPENSATION (MAY 2018)
I.34 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (AUG 2018)
I.35 52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
I.36 52.222-8 PAYROLLS AND BASIC RECORDS (JUL 2021)
I.37 52.222-9 APPRENTICES AND TRAINEES (JUL 2005)
I.38 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB
1988)
I.39 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
I.40 52.222-12 CONTRACT TERMINATION – DEBARMENT (MAY 2014)
I.41 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE
REQUIREMENTS AND RELATED REGULATIONS (MAY 2014)
I.42 52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
I.43 52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
I.44 52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)
I.45 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO
ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION
(FEB 1999)
I.46 52.222-26 EQUAL OPPORTUNITY (SEPT 2016)
I.47 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR
CONSTRUCTION (APR 2015)
I.48 52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUN 2020)
I.49 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER NATIONAL LABOR
RELATIONS ACT (DEC 2010)
I.50 52.222-50 COMBATING TRAFFICKING IN PERSONS (NOV 2021)
I.51 52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (MAY 2022)
I.52 52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658
(JAN 2022)
I.53 52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706
(JAN 2022)
I.54 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS
UNDER SERVICE AND CONSTRUCTION CONTRACTS (SEP 2013)
I.55 52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL
SAFETY DATA (FEB 2021) - ALTERNATE I (FEB 2021)
Material (If none, insert None)
Identification No.
I.56 52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW
INFORMATION (MAY 2011) – ALTERNATE I (MAY 2011)
I.57 52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
I.58 52.223-10 WASTE REDUCTION PROGRAM (MAY 2011)
I.59 52.223-15 ENERGY EFFICIENCY IN ENERGY-CONSUMING PRODUCTS (MAY 2020)
I.60 52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE
AND CONSTRUCTION CONTRACTS (AUG 2018)
I.61 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT
MESSAGING WHILE DRIVING (JUN 2020)
I.62 52.223-19 COMPLIANCE WITH ENVIRONMENTAL MANAGEMENT
SYSTEMS (MAY 2011)
I.63 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB
2021)
I.64 52.227-1 AUTHORIZATION AND CONSENT (JUN 2020)
I.65 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT
INFRINGEMENT (JUN 2020)
I.66 52.227-4 PATENT INDEMNITY--CONSTRUCTION CONTRACTS (DEC
2007)
I.67 52.228-2 ADDITIONAL…