80ARC018R0007_SSPEDI_SpS_1DEC2017.pdf

PDF 790 KB Posted

Attached to
Small Spacecraft Prototyping Engineering Development and Integration - Space Solutions (SSPEDI SpS) Federal contract opportunity
Solicitation number
80ARC018R0007
Issued by
National Aeronautics and Space Administration Ames Research Center

About this file

This document provides details about a forthcoming multiple award indefinite delivery indefinite quantity contract for Small Spacecraft Prototyping Engineering Development and Integration (SSPEDI) Space Solutions (SpS). The contract focuses on developing small to medium spacecraft buses, payloads, and space vehicles based on technical and mission requirements for Operationally Responsive Space. Key details include a requirement for proposals by December 2017, contract awards by June 2018, and performance at contractors' facilities. The contract is for a five-year ordering period and contemplates cost-plus-fixed-fee, cost-plus-incentive-fee, and firm-fixed-price task orders. Small business subcontracting goals include 25% for small business and targets for small disadvantaged, woman-owned, historically underutilized, veteran-owned, and disabled veteran-owned small businesses. The National Aeronautics and Space Administration Ames Research Center will issue the request for proposal.

Revised solicitation 80ARC018R0007 dated 1 DEC 2017.

View the file

Other files for this federal contract opportunity

Other files attached to Small Spacecraft Prototyping Engineering Development and Integration - Space Solutions (SSPEDI SpS), newest first.
File Type Posted
SSPEDI_SpS_Source_Selection_Statement_FINAL_signed.pdf PDF
SSPEDI_SpS_QandA_Vol4_20DEC2017.pdf PDF
80ARC018R0007_SSPEDI_SpS_20DEC2017.pdf PDF
80ARC018R0007P00003_-_SF30.pdf PDF
SSPEDI_SpS_QandA_Vol3_7DEC2017.pdf PDF
80ARC018R0007_SF33_4DEC2017.pdf PDF
80ARC018R0007P00002_-_SF30.pdf PDF
SSPEDI_SpS_QandA_Vol2_1DEC2017.pdf PDF
80ARC018R0007_J.1(b)Attachment11_Technical_Document_Library_List_1DEC2017.pdf PDF
80ARC018R0007_J.1(b)Attachment4_Cost-Price_Template_Workbook_1DEC2017.xlsx XLSX spreadsheet
80ARC018R0007_J.1(b)Attachment5_Resource_Workbook_1DEC2017.xlsx XLSX spreadsheet
80ARC018R0007P00001_-_SF30.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

25. PAYMENT WILL BE MADE BY

C. E-MAIL ADDRESS

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

2. CONTRACT NUMBER 3. SOLICITATION NUMBER 6. REQUISITION/PURCHASE NUMBER5. DATE ISSUED

SOLICITATION, OFFER, AND AWARD

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

PAGE OF PAGESRATING

B. TELEPHONE (NO COLLECT CALLS)10. FOR

INFORMATION

CALL:

A. NAME:

8. ADDRESS OFFER TO (if other than item 7)7. ISSUED BY CODE

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

CAUTION - LATE Submission, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

9. Sealed offers in original and hand carried, in the depository located in (Hour) (Date)(City)

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is unusable

STANDARD FORM 33 (Rev.6/2014) Prescribed by GSA FAR (48 CFR) 53.214 (c)

CALENDAR DAYS (%)13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

10 CALENDAR DAYS (%) 20 CALENDAR DAYS (%) 30 CALENDAR DAYS (%)

OFFER (Must be fully completed by offeror)

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16 , Minimum Bid Acce ptance Period.

AWARD (To be completed by Government)

11. TABLE OF CONTENTS

16. NAME AND TITLE OF PERSON AUTHORIZED

TO SIGN OFFER (Type or print)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amend-ments to the SOLICITATION for offerors and related documents numbered and dated):

12. In compliance with the above, the undersigned agrees, if this offer is accepted within inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the set opposite each item, delivered at the desi gnated point(s ), whithin the time specified in the schedule.

CONTRACT ADMINISTRATION DATA L INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

SPECIAL CONTRACT REQUIREMENTS M EVALUATION FACTORS FOR AWARD

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

(X) DESCRIPTION PAGE (S ) SEC. DESCRIPTION PAGE (S )

SUPPLIES OR SERVICES AND PRICES/COSTS PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.

PART I - THE SCHEDULE PART II- CONTRACT CLAUSES

I CONTRACT CLAUSESSOLICITATION/CONTRACT FORM

DESCRIPTION/SPECS./WORK STATEMENT J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

PACKAGING AND MARKING PART IV - REPRESENTATIONS AND INSTRUCTIONS

DELIVERIES OR PERFORMANCE

K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

AMENDMENT NO. DATEAMENDMENT NO. DATE

G

H

SEC.

B

A

C

E

D

F

(X)

FACILITY CODECODE

18. OFFER DATE15C. CHECK IF REMITTANCE ADDRESS IS DIFFERENT FROM

ABOVE - ENTER SUCH ADDRESS IN SCHEDULE

15B. TELEPHONE NUMBER

17. SIGNATURE

20. AMOUNT19. ACCEPTED AS TO ITEMS NUMBERED 21. ACCOUNTING AND APPROPRIATION INFORMATION

23. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

24. ADMINISTERED BY (If other than item 7) CODE

28. AWARD DATE27. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

26. NAME OF CONTRACTING OFFICER (Type or print) calendar days (60 calendar days unless a different period is

15A. NAME

AND

ADDRESS

OF

OFFEROR

10 U.S.C. 2304 (c) ( 41 U.S.C. 3304 (a) () )

1 136

80ARC018R0007 X 11/03/2017

NASA

Ames Research Center M/S 241-1 Moffett Field CA 94035-0001 Attn: Rosalinda R. De Leon copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if

BUILDING N241 ROOM 222 until 15:00:00 local time 01/08/2017

$0.00

AREA CODE NUMBER EXTENSION

AREA CODE NUMBER EXTENSION

A-1 B-1 C-1 D-1

F-1

H-1

E-1

G-1

I-1

J-1

K-1 L-1 M-1

X X X X X X X X

X

X

X

X X

ROSALINDA R. DE LEON

650 604-6038 ROSALINDA.R.DELEON@NASA.GOV

SEE SECTION L

NSSC – FMD Accounts Payable Bldg. 1111, C. Road, Stennis Space Center, MS 39529 NSSC-AccountsPayable@nasa.gov

X

80ARC018R0007

TABLE OF CONTENTS

A-1

SECTION A - SOLICITATION/CONTRACT FORM

Table of Contents and Section A pages are intentionally left blank.

B-1

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SUPPLIES AND/OR SERVICES TO BE PROVIDED

(a) This is an Indefinite Delivery Indefinite Quantity (IDIQ) multiple award contract with (Cost- Plus-Fixed-Fee (CPFF), Firm-Fixed-Price (FFP), and Cost-Plus-Incentive Fee (CPIF)). Tasks that can be well defined at task order award will be issued as FFP, tasks that contain more uncertainties in contract performance that do not permit costs to be estimated with sufficient accuracy will be issued as CPFF task orders. CPIF task orders will be issued when an incentive is needed to control cost or schedule and to achieve challenging technical goals. The contractor shall provide all resources (except as may be expressly stated in this contract as furnished by the Government) necessary to furnish the work in accordance with the Description/Specification/ Work Statement set forth in Section C and as identified under individual task orders.

(TBDTO = To be determined on each applicable task order)

Basic Contract CLINs

Item No. Description Ref. Type Qty Unit Maximum CLIN Value

0001 TBDTO J(a) Att. 1 CPFF 1 JOB $600,000,000

0002 TBDTO J(a) Att. 1 FFP 1 JOB $75,000,000

0003 TBDTO J(a) Att. 1 CPIF 1 JOB $75,000,000

Maximum IDIQ Contract Value $750,000,000.00

(End of clause)

B.2 MINIMUM/MAXIMUM AMOUNT OF SUPPLIES OR SERVICES

(a) The minimum amount of supplies or services that shall be ordered during the effective period of this contract is as follows:

Contract Type Minimum Order Amount Per Contract

(Including all contract types) CPFF, CPIF, and FFP $100K

The maximum value of supplies or services that may be ordered during the effective period of the contract is $750,000,000. All orders placed under this contract will be applied to the minimum and maximum specified in this paragraph.

B-2

(b) The minimum total amount is reached when the sum of the dollar amounts of all ordered supplies or services, except for any adjustments made pursuant to the Limitation of Cost or Limitation of Funds clause, equals or exceeds the minimum amount stated in paragraph (a).

(c) The maximum total amount is reached when the sum of the dollar amounts of all ordered supplies or services, except for any adjustments made pursuant to the Limitation of Cost or Limitation of Funds clause, equals the maximum amount stated in paragraph (a). For Cost-Plus- Incentive-Fee, the value of the task order will be based on the target cost and the maximum incentive fee (including performance incentives) to be adjusted later by a formula based on the relationship of the total allowable costs to total target costs and schedule.

(d) The maximum total amount, if reached, precludes the issuance of further orders for supplies or services under this contract. However, reaching the maximum amount does not preclude adjustments to the dollar amounts of existing placed orders, for actions that are within the scope of the placed orders, and which are made pursuant to existing contract authority, such as the Changes clause.

(e) The maximum amount of $750,000,000 may be adjusted unilaterally by the Government on an annual basis. Historic, current, and/or projected workload requirements will be used to determine the amount of upward adjustment. In no event will the adjusted maximum amount exceed 10% of the original $750,000,000 maximum amount.

1852.216-74 ESTIMATED COST AND FIXED FEE (DEC 1991)

The estimated cost of this contract is $ TBDTO exclusive of the fixed fee of $TBDTO. The total estimated cost and fixed fee is $ TBDTO.

1852.216-78 FIRM FIXED PRICE (DEC 1988)

The total Firm-Fixed-Price of this contract is $ TBDTO.

1852.216-84 ESTIMATED COST AND INCENTIVE FEE (OCT 1996)

The target cost of this contract is $ TBDTO. The target fee of this contract is $ TBDTO. The total target cost and target fee as contemplated by the Incentive Fee clause of this contract are $ TBDTO.

The maximum fee is $ TBDTO.

The minimum fee is $ TBDTO.

B-3

The cost sharing for cost underruns is: Government TBDTO percent; Contractor TBDTO percent.

The cost sharing for cost overruns is: Government TBDTO percent; Contractor TBDTO percent.

1852.216-88 PERFORMANCE INCENTIVE (APR 2015)

(a) A performance incentive applies to the following item(s) under this contract: (1).

The performance incentive will measure the performance of those items against the salient hardware performance requirement, called “unit(s) of measurement,” e.g., months in service or amount of data transmitted, identified below. The performance incentive becomes when the item is put into service. It includes a standard performance level, a positive incentive, and a negative incentive, which are described in this clause.

(b) Standard performance level. At the standard performance level, the Contractor has met the contract requirement for the unit of measurement. Neither positive nor negative incentives apply when this level is achieved but not exceeded. The standard performance level for (1) __ is established as follows: (2).

(c) Positive incentive. The Contractor earns a separate positive incentive amount for each item listed in paragraph (a) of this clause when the standard performance level for that item is exceeded. The amount earned for each item varies with the units of measurement achieved, up to a maximum positive performance incentive amount of $ (3) __ per item. The units of measurement and the incentive amounts associated with achieving each unit are shown below:

(4).

(d) Negative incentive. The Contractor will pay to the Government a negative incentive amount for each item that fails to achieve the standard performance level. The amount to be paid for each item varies with the units of measurement achieved, up to the maximum negative incentive amount of $ (5) __. The units of measurement and the incentive amounts associated with achieving each unit are shown below: (6).

(e) The final calculation of positive or negative performance incentive amounts shall be done when performance (as defined by the unit of measurement) ceases or when the maximum positive incentive is reached.

(1) When the Contracting Officer determines that the performance level achieved fell below the standard performance level, the Contractor will either pay the amount due the Government or credit the next payment voucher for the amount due, as directed by the Contracting Officer.

(2) When the performance level exceeds the standard level, the Contractor may request payment of the incentive amount associated with a given level of performance, provided

B-4 that such payments shall not be more frequent than monthly. When performance ceases or the maximum positive incentive is reached, the Government shall calculate the final performance incentive earned and unpaid and promptly remit it to the contractor.

(f) If performance cannot be demonstrated, through no fault of the Contractor, within [TBDTO] after the date of acceptance by the Government, the Contractor will be paid [TBDTO] of the maximum performance incentive.

(g) The decisions made as to the amount(s) of positive or negative incentives are subject to the

Disputes clause.

(1) Insert applicable item number(s) descriptor and/or nomenclature.

(2) Insert a specific unit of measurement for each hardware item listed in (1) and each salient characteristic, if more than one.

(3) Insert the maximum positive performance incentive amount (see 1816.402-270(e) (1) and

(2)).

(4) Insert all units of measurement and associated dollar amounts up to the maximum performance incentive.

(5) Insert the appropriate amount in accordance with 1816.402-270(e).

(6) Insert all units of measurement and associated dollar amounts up to the maximum negative performance incentive.

1852.232-81 CONTRACT FUNDING (JUN 1990)

(a) For purposes of payment of cost, exclusive of fee, in accordance with the Limitation of Funds clause, the total amount allotted by the Government to this contract is $ TBDTO. This allotment is for [TBDTO] and covers the following estimated period of performance:

TBDTO.

(b) An additional amount of $ TBDTO is obligated under this contract for payment of fee.

C-1

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF WORK

The attached Statement of Work (SOW) describes the technical and programmatic requirements to manage and execute the development of spacecraft, payloads, buses, spacecraft subsystems, software, components, and ground systems; support the deployment of the spacecraft; and support mission operations based on technical, schedule, and cost requirements.

(a) In accordance with the contract’s terms and conditions, the Contractor shall furnish all personnel, services, equipment, materials, and facilities and do all other things necessary for, or incidental to, performance of the requirements set forth herein and in each task order.

(b) Work performed under each task order shall be accomplished in accordance with the Statement of Work entitled “Space Solutions (SpS) Basic SOW,” in Section J, Paragraph J.1(a), Attachment 1 and as identified in the requirements documents of the task order.

D-1

SECTION D - PACKAGING AND MARKING

1852.211-70 PACKAGING, HANDLING, AND TRANSPORTATION (SEP 2005)

DFARS 252.211-7003 ITEM UNIQUE IDENTIFICATION AND VALUATION (MAR 2016)

(a) Definitions. As used in this clause—

“Automatic identification device” means a device, such as a reader or interrogator, used to retrieve data encoded on machine-readable media.

“Concatenated unique item identifier” means—

(1) For items that are serialized within the enterprise identifier, the linking together of the unique identifier data elements in order of the issuing agency code, enterprise identifier, and unique serial number within the enterprise identifier; or

(2) For items that are serialized within the original part, lot, or batch number, the linking together of the unique identifier data elements in order of the issuing agency code; enterprise identifier; original part, lot, or batch number; and serial number within the original part, lot, or batch number.

“Data matrix” means a two-dimensional matrix symbology, which is made up of square or, in some cases, round modules arranged within a perimeter finder pattern and uses the Error Checking and Correction 200 (ECC200) specification found within International Standards Organization (ISO)/International Electrotechnical Commission (IEC) 16022.

“Data qualifier” means a specified character (or string of characters) that immediately precedes a data field that defines the general category or intended use of the data that follows.

“DoD recognized unique identification equivalent” means a unique identification method that is in commercial use and has been recognized by DoD. All DoD recognized unique identification equivalents are listed at http://www.acq.osd.mil/dpap/pdi/uid/iuid_equivalents.html.

“DoD item unique identification” means a system of marking items delivered to DoD with unique item identifiers that have machine-readable data elements to distinguish an item from all other like and unlike items. For items that are serialized within the enterprise identifier, the unique item identifier shall include the data elements of the enterprise identifier and a unique serial number. For items that are serialized within the part, lot, or batch number within the enterprise identifier, the unique item identifier shall include the data elements of the enterprise identifier; the original part, lot, or batch number; and the serial number.

“Enterprise” means the entity (e.g., a manufacturer or vendor) responsible for assigning unique item identifiers to items.

“Enterprise identifier” means a code that is uniquely assigned to an enterprise by an issuing agency.

“Government’s unit acquisition cost” means—

(1) For fixed-price type line, subline, or exhibit line items, the unit price identified in the contract at the time of delivery;

(2) For cost-type or undefinitized line, subline, or exhibit line items, the Contractor’s estimated fully burdened unit cost to the Government at the time of delivery; and

D-2

(3) For items produced under a time-and-materials contract, the Contractor’s estimated fully burdened unit cost to the Government at the time of delivery.

“Issuing agency” means an organization responsible for assigning a globally unique identifier to an enterprise, as indicated in the Register of Issuing Agency Codes for ISO/IEC 15459, located at http://www.aimglobal.org/?Reg_Authority15459.

“Issuing agency code” means a code that designates the registration (or controlling) authority for the enterprise identifier.

“Item” means a single hardware article or a single unit formed by a grouping of subassemblies, components, or constituent parts.

“Lot or batch number” means an identifying number assigned by the enterprise to a designated group of items, usually referred to as either a lot or a batch, all of which were manufactured under identical conditions.

“Machine-readable” means an automatic identification technology media, such as bar codes, contact memory buttons, radio frequency identification, or optical memory cards.

“Original part number” means a combination of numbers or letters assigned by the enterprise at item creation to a class of items with the same form, fit, function, and interface.

“Parent item” means the item assembly, intermediate component, or subassembly that has an embedded item with a unique item identifier or DoD recognized unique identification equivalent.

“Serial number within the enterprise identifier” means a combination of numbers, letters, or symbols assigned by the enterprise to an item that provides for the differentiation of that item from any other like and unlike item and is never used again within the enterprise.

“Serial number within the part, lot, or batch number” means a combination of numbers or letters assigned by the enterprise to an item that provides for the differentiation of that item from any other like item within a part, lot, or batch number assignment.

“Serialization within the enterprise identifier” means each item produced is assigned a serial number that is unique among all the tangible items produced by the enterprise and is never used again. The enterprise is responsible for ensuring unique serialization within the enterprise identifier.

“Serialization within the part, lot, or batch number” means each item of a particular part, lot, or batch number is assigned a unique serial number within that part, lot, or batch number assignment. The enterprise is responsible for ensuring unique serialization within the part, lot, or batch number within the enterprise identifier.

“Type designation” means a combination of letters and numerals assigned by the Government to a major end item, assembly or subassembly, as appropriate, to provide a convenient means of differentiating between items having the same basic name and to indicate modifications and changes thereto.

“Unique item identifier” means a set of data elements marked on items that is globally unique and unambiguous. The term includes a concatenated unique item identifier or a DoD recognized unique identification equivalent.

“Unique item identifier type” means a designator to indicate which method of uniquely identifying a part has been used. The current list of accepted unique item identifier types is maintained at http://www.acq.osd.mil/dpap/pdi/uid/uii_types.html.

(b) The Contractor shall deliver all items under a contract line, subline, or exhibit line item.

(c) Unique item identifier.

(1) The Contractor shall provide a unique item identifier for the following:

D-3

(i) Delivered items for which the Government’s unit acquisition cost is $5,000 or more, except for the following line items:

Contract Line, Subline, or Exhibit Line Item Number Item Description

TBDTO.

(ii) Items for which the Government’s unit acquisition cost is less than $5,000 that are identified in the Schedule or the following table:

Contract Line, Subline, or Exhibit Line Item Number Item Description

TBDTO.

(If items are identified in the Schedule, insert “See Schedule” in this table.)

(iii) Subassemblies, components, and parts embedded within delivered items, items with warranty requirements, DoD serially managed reparables and DoD serially managed nonreparables as specified in each applicable task order.

(iv) Any item of special tooling or special test equipment as defined in FAR 2.101 that have been designated for preservation and storage for a Major Defense Acquisition Program as specified in each applicable task order.

(v) Any item not included in (i), (ii), (iii), or (iv) for which the contractor creates and marks a unique item identifier for traceability.

(2) The unique item identifier assignment and its component data element combination shall not be duplicated on any other item marked or registered in the DoD Item Unique Identification Registry by the contractor.

(3) The unique item identifier component data elements shall be marked on an item using two dimensional data matrix symbology that complies with ISO/IEC International Standard 16022, Information technology – International symbology specification – Data matrix; ECC200 data matrix specification.

(4) Data syntax and semantics of unique item identifiers. The Contractor shall ensure that—

(i) The data elements (except issuing agency code) of the unique item identifier are encoded within the data matrix symbol that is marked on the item using one of the following three types of data qualifiers, as determined by the Contractor:

(A) Application Identifiers (AIs) (Format Indicator 05 of ISO/IEC International Standard 15434), in accordance with ISO/IEC International Standard 15418, Information Technology – EAN/UCC Application Identifiers and Fact Data Identifiers and Maintenance and ANSI MH 10.8.2 Data Identifier and Application Identifier Standard.

(B) Data Identifiers (DIs) (Format Indicator 06 of ISO/IEC International Standard 15434), in accordance with ISO/IEC International Standard 15418, Information Technology – EAN/UCC Application Identifiers and Fact Data Identifiers and Maintenance and ANSI MH 10.8.2 Data Identifier and Application Identifier Standard.

(C) Text Element Identifiers (TEIs) (Format Indicator 12 of ISO/IEC International Standard 15434), in accordance with the Air Transport Association Common Support Data Dictionary;

and

D-4

(ii) The encoded data elements of the unique item identifier conform to the transfer structure, syntax, and coding of messages and data formats specified for Format Indicators 05, 06, and 12 in ISO/IEC International Standard 15434, Information Technology – Transfer Syntax for High Capacity Automatic Data Capture Media.

(5) Unique item identifier.

(i) The Contractor shall—

(A) Determine whether to—

(1) Serialize within the enterprise identifier;

(2) Serialize within the part, lot, or batch number; or

(3) Use a DoD recognized unique identification equivalent (e.g. Vehicle Identification Number);

and

(B) Place the data elements of the unique item identifier (enterprise identifier; serial number;

DoD recognized unique identification equivalent; and for serialization within the part, lot, or batch number only: original part, lot, or batch number) on items requiring marking by paragraph (c)(1) of this clause, based on the criteria provided in MIL-STD-130, Identification Marking of U.S. Military Property, latest version;

(C) Label shipments, storage containers and packages that contain uniquely identified items in accordance with the requirements of MIL-STD-129, Military Marking for Shipment and Storage, latest version; and

(D) Verify that the marks on items and labels on shipments, storage containers, and packages are machine readable and conform to the applicable standards. The contractor shall use an automatic identification technology device for this verification that has been programmed to the requirements of Appendix A, MIL-STD-130, latest version.

(ii) The issuing agency code—

(A) Shall not be placed on the item; and

(B) Shall be derived from the data qualifier for the enterprise identifier.

(d) For each item that requires item unique identification under paragraph (c)(1)(i), (ii), or (iv) of this clause or when item unique identification is provided under paragraph (c)(1)(v), in addition to the information provided as part of the Material Inspection and Receiving Report specified elsewhere in this contract, the Contractor shall report at the time of delivery, as part of the Material Inspection and Receiving Report, the following information:

(1) Unique item identifier.

(2) Unique item identifier type.

(3) Issuing agency code (if concatenated unique item identifier is used).

(4) Enterprise identifier (if concatenated unique item identifier is used).

(5) Original part number (if there is serialization within the original part number).

(6) Lot or batch number (if there is serialization within the lot or batch number).

(7) Current part number (optional and only if not the same as the original part number).

(8) Current part number effective date (optional and only if current part number is used).

(9) Serial number (if concatenated unique item identifier is used).

(10) Government’s unit acquisition cost.

(11) Unit of measure.

(12) Type designation of the item as specified in the contract schedule, if any.

(13) Whether the item is an item of Special Tooling or Special Test Equipment.

(14) Whether the item is covered by a warranty.

D-5

(e) For embedded subassemblies, components, and parts that require DoD item unique identification under paragraph (c)(1)(iii) of this clause or when item unique identification is provided under paragraph (c)(1)(v), the Contractor shall report as part of the Material Inspection and Receiving Report specified elsewhere in this contract, the following information:

(1) Unique item identifier of the parent item under paragraph (c)(1) of this clause that contains the embedded subassembly, component, or part.

(2) Unique item identifier of the embedded subassembly, component, or part.

(3) Unique item identifier type.**

(4) Issuing agency code (if concatenated unique item identifier is used).**

(5) Enterprise identifier (if concatenated unique item identifier is used).**

(6) Original part number (if there is serialization within the original part number).**

(7) Lot or batch number (if there is serialization within the lot or batch number).**

(8) Current part number (optional and only if not the same as the original part number).**

(9) Current part number effective date (optional and only if current part number is used).**

(10) Serial number (if concatenated unique item identifier is used).**

(11) Description.

** Once per item.

(f) The Contractor shall submit the information required by paragraphs (d) and (e) of this clause as follows:

(1) End items shall be reported using the receiving report capability in Wide Area WorkFlow (WAWF) in accordance with the clause at 252.232-7003. If WAWF is not required by this contract, and the contractor is not using WAWF, follow the procedures at http://dodprocurementtoolbox.com/site/uidregistry/.

(2) Embedded items shall be reported by one of the following methods—

(i) Use of the embedded items capability in WAWF;

(ii) Direct data submission to the IUID Registry following the procedures and formats at http://dodprocurementtoolbox.com/site/uidregistry/; or

(iii) Via WAWF as a deliverable attachment for exhibit line item number N/A, Unique Item Identifier Report for Embedded Items, Contract Data Requirements List, DD Form 1423.

(g) Subcontracts. If the Contractor acquires by subcontract, any item(s) for which item unique identification is required in accordance with paragraph (c)(1) of this clause, the Contractor shall include this clause, including this paragraph (g), in the applicable subcontract(s), including subcontracts for commercial items.

E-1

SECTION E - INSPECTION AND ACCEPTANCE

52.246-2 INSPECTION OF SUPPLIES -- FIXED-PRICE (AUG 1996)

52.246-3 INSPECTION OF SUPPLIES -- COST-REIMBURSEMENT (May 2001)

52.246-4 INSPECTION OF SERVICES -- FIXED-PRICE (AUG 1996)

52.246-5 INSPECTION OF SERVICES -- COST-REIMBURSEMENT (APR 1984)

52.246-7 INSPECTION OF RESEARCH AND DEVELOPMENT--FIXED-PRICE (AUG 1996)

52.246-8 INSPECTION OF RESEARCH AND DEVELOPMENT--COST-REIMBURSEMENT

(MAY 2001)

52.246-16 RESPONSIBILITY FOR SUPPLIES (APR 1984)

52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)

(a) The Contractor shall comply with the higher-level quality standard(s) listed below.

(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in—

(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or

(2) When the technical requirements of a subcontract require—

(i) Control of such things as design, work operations, in-process control, testing, and inspection; or

(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.

Title

Number

Date

Tailoring

TBDTO TBDTO TBDTO TBDTO

E-2

1852.246-71 GOVERNMENT CONTRACT QUALITY ASSURANCE FUNCTIONS (OCT

1988)

In accordance with the inspection clause of this contract, the Government intends to perform the following functions at the locations indicated:

Item Quality Assurance Function Location

TBDTO TBDTO TBDTO

1852.246-72 MATERIAL INSPECTION AND RECEIVING REPORT (APR 2015)

(a) At the time of each delivery to the Government under this contract, the Contractor shall prepare and furnish a Material Inspection and Receiving Report (DD Form 250 series). The form(s) shall be prepared and distributed as follows:

TBDTO.

(b) The Contractor shall prepare the DD Form 250 in accordance with NASA FAR Supplement

1846.6. The Contractor shall enclose the copies of the DD Form 250 in the package or seal them in a waterproof envelope, which shall be securely attached to the exterior of the package in the most protected location.

(c) When more than one package is involved in a shipment, the Contractor shall list on the DD

Form 250, as additional information, the quantity of packages and the package numbers. The Contractor shall forward the DD Form 250 with the lowest numbered package of the shipment and print the words “CONTAINS DD FORM 250” on the package.

F-1

SECTION F - DELIVERIES OR PERFORMANCE

52.211-17 DELIVERY OF EXCESS QUANTITIES (SEP 1989)

52.242-15 STOP-WORK ORDER (AUG 1989)

52.242-15 STOP-WORK ORDER (AUG 1989) ALTERNATE I (APR 1984)

52.242-17 GOVERNMENT DELAY OF WORK (APR 1984)

52.247-34 F.O.B. DESTINATION (NOV 1991)

52.247-55 F.O.B. POINT FOR DELIVERY OF GOVERNMENT-FURNISHED PROPERTY

(JUN 2003)

52.211-8 TIME OF DELIVERY (JUN 1997) ALTERNATE I (APR 1984)

(a) The Government requires delivery to be made according to the following schedule:

REQUIRED DELIVERY SCHEDULE

ITEM NO. QUANTITY WITHIN DAYS AFTER DATE OF CONTRACT

The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.

OFFEROR’S PROPOSED DELIVERY SCHEDULE

ITEM NO. QUANTITY WITHIN DAYS AFTER DATE OF CONTRACT

(b) The delivery dates or specific periods above are based on the assumption that the

Government will make award by TBDTO. Each delivery date in the delivery schedule above will be extended by the number of calendar days after the above date that the contract is in fact awarded. Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed or otherwise furnished to the successful offeror results in a binding contract. Therefore, the offeror should compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the Contracting Officer through the ordinary mails.

F-2

1852.247-72 ADVANCE NOTICE OF SHIPMENT (OCT 1988)

TBDTO work days prior to shipping item(s) TBDTO, the Contractor shall furnish the anticipated shipment date, bill of lading number (if applicable), and carrier identity to TBDTO and to the Contracting Officer.

ARC 52.249-90 NOTICE OF DELAY (FEB 1997)

If, because of technical difficulties, the Contractor becomes unable to complete the contract work at the time specified, notwithstanding the exercise of good faith and diligent efforts in performing the work called for under this contract, the Contractor shall give the Contracting Officer written notice of the anticipated delay and the reasons for it. The notice and reasons shall be delivered promptly after the condition creating the anticipated delay becomes known to the Contractor but in no event less than 45 days before the completion date specified in this contract, unless otherwise permitted by the Contracting Officer. When notice is given, the Contracting Officer may extend the time specified in the Schedule for such period as is deemed advisable.

F.1 PERIOD OF PERFORMANCE

The performance period for issuing task orders under this contract is set forth below.

1. Basic Contract Period

The period of performance of the basic contract shall be for five (5) years from the effective date of the contract.

2. Each individual task order will include its own period of performance. Performance of orders placed within the ordering period may extend for up to one year past the end of the contract’s effective period if the Contracting Officer determines that performance of the order cannot reasonably be deferred to any planned follow-on contract.

F.2 DELIVERY SCHEDULE

(a) The Contractor shall deliver the supplies and services as identified in each task order.

(b) Unless specified otherwise, all items shall be delivered to: TBDTO

(c) Unless otherwise specified, all reports and documentation shall be submitted and addressed to the recipients listed the Contract Data Requirements List attached to each task order.

G-1

SECTION G - CONTRACT ADMINISTRATION DATA

1852.216-75 PAYMENT OF FIXED FEE (DEC 1988)

1852.227-70 NEW TECHNOLOGY—OTHER THAN A SMALL BUSINESS FIRM OR

NONPROFIT ORGANIZATION (APR 2015)

1852.227-72 DESIGNATION OF NEW TECHNOLOGY REPRESENTATIVE AND PATENT

REPRESENTATIVE (APR 2015)

1852.242-73 NASA CONTRACTOR FINANCIAL MANAGEMENT REPORTING (NOV

2004)

1852.245-70 CONTRACTOR REQUESTS FOR GOVERNMENT-FURNISHED PROPERTY

(AUG 2015)

1852.245-75 PROPERTY MANAGEMENT CHANGES (JAN 2011)

1852.232-80 SUBMISSION OF VOUCHERS FOR PAYMENT (SEP 2016)

(a) The designated payment office is the NASA Shared Services Center (NSSC) located at FMD

Accounts Payable, Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS 39529.

(b) Except for classified vouchers, the Contractor shall submit all vouchers electronically using the steps described at NSSC’s Vendor Payment information web site at:

https://www.nssc.nasa.gov/vendorpayment. Please contact the NSSC Customer Contact Center at 1-877-NSSC123 (1-877-677-2123) with any additional questions or comments.

(c) Payment requests.

(1) The payment periods designated in the payment clause(s) contained in this contract will begin on the date a proper request for payment is received by the NSSC payment office specified in paragraph (b) of this section. Vouchers shall be prepared in accordance with the guidance provided by the NSSC at the following website:

https://answers.nssc.nasa.gov/app/answers/detail/a_id/6643.

(2) Vouchers shall include the items delineated in FAR 32.905(b) supported by relevant back-up documentation. Back-up documentation shall include at a minimum, the following information:

(i) Breakdown of billed labor costs and associated contractor generated supporting documentation for billed direct labor costs to include rates used and number of hours incurred.

(ii) Breakdown of billed other direct costs (ODCs) and associated contractor generated supporting documentation for billed ODCs.

G-2

(iii) Indirect rate(s) used to calculate the amount of billed indirect expenses.

(d) Non-electronic payment. The Contractor may submit a voucher using other than the steps described at NSSC’s Vendor Payment information through any of the means described at https://www.nssc.nasa.gov/vendorpayment, if any of the following conditions are met:

(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer’s determination with each request for payment when the Governmentwide commercial purchase card is used as the method of payment.

(2) The contract includes provisions allowing the contractor to submit vouchers using other than the steps prescribed at NSSC’s Vender Payment information website. In such instances the Contractor agrees to submit non-electronic payment requests using the method or methods specified in Section G of the contract.

(e) Improper vouchers. The NSSC Payment Office will notify the contractor of any apparent error, defect, or impropriety in a voucher within seven calendar days of receipt by the NSSC Payment Office. Inquiries regarding requests for payment should be directed to the NSSC as specified in paragraph (b) of this section.

(f) Other payment clauses. In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payment requests.

(g) In the event that amounts are withheld from payment in accordance with provisions of this contract, a separate payment request for the amount withheld will be required before payment for that amount may be made.

1852.245-76 LIST OF GOVERNMENT PROPERTY FURNISHED PURSUANT TO FAR

52.245-1 (JAN 2011)

For performance of work under this contract, the Government will make available Government property identified below or in Attachment TBDTO of this contract on a no charge-for-use basis pursuant to the clause at FAR 52.245-1, Government Property, as incorporated in this contract.

The Contractor shall use this property in the performance of this contract at TBDTO and at other location(s) as may be approved by the Contracting Officer. Under FAR 52.245-1, the Contractor is accountable for the identified property.

G-3

ARC 52.232-90 SUBMISSION OF INVOICES (FEB 2017)

(Applicable to FFP task orders)

(a) Invoices shall be prepared and submitted to the designated billing and payment office noted below in accordance with FAR 52.232-TBDTO Prompt Payment clause:

NSSC – FMD Accounts Payable Bldg. 1111, Jerry Hlass Road Stennis Space Center, MS 39529

Invoices shall include the Contractor's Taxpayer Identification Number (TIN). Electronic submission is preferred, via email NSSC-AccountsPayable@nasa.gov or fax 866-209-5415.

A copy of the invoice shall be provided to the Contracting Officer.

(b) In the event that amounts are withheld from payment in accordance with the New

Technology clause or other provisions of this contract, a separate invoice for the amount withheld shall be required before payment of that amount is made.

(c) This Contract TBDTO does TBDTO does not provide for partial payments. If applicable, payments will be made in accordance with the following schedule: TBDTO

Payment will be made for separately priced items which have been received and accepted by NASA, and upon receipt of a payable invoice submitted in accordance with this clause.

H-1

SECTION H - SPECIAL CONTRACT REQUIREMENTS

1852.223-70 SAFETY AND HEALTH MEASURES AND MISHAP REPORTING (DEC 2015)

1852.223-72 SAFETY AND HEALTH (SHORT FORM) (JUL 2015)

1852.223-75 MAJOR BREACH OF SAFETY OR SECURITY (FEB 2002)

1852.228-78 CROSS-WAIVER OF LIABILITY FOR SCIENCE OR SPACE EXPLORATION

ACTIVITIES UNRELATED TO THE INTERNATIONAL SPACE STATION (OCT 2012)

1852.235-73 FINAL SCIENTIFIC AND TECHNICAL REPORTS (DEC 2006) ALTERNATE

II (DEC 2005)

1852.244-70 GEOGRAPHIC PARTICIPATION IN THE AEROSPACE PROGRAM (APR

1985)

5352.223-9001 HEALTH AND SAFETY ON GOVERNMENT INSTALLATIONS (JUN 1997)

1852.225-70 EXPORT LICENSES (FEB 2000)

(a) The Contractor shall comply with all U.S. export control laws and regulations, including the

International Traffic in Arms Regulations (ITAR), 22 CFR parts 120-130, and the Export Administration Regulations (EAR), 15 CFR parts 730-799, in the performance of this contract. In the absence of available license exemptions/exceptions, the Contractor shall be responsible for obtaining the appropriate licenses or other approvals, if required, for exports of hardware, technical data, and software, or for the provision of technical assistance.

(b) The Contractor shall be responsible for obtaining export licenses, if required, before utilizing foreign persons in the performance of this contract, including instances where the work is to be performed on-site at a Government facility, where the foreign person will have access to export-controlled technical data or software.

(c) The Contractor shall be responsible for all regulatory record keeping requirements associated with the use of licenses and license exemptions/exceptions.

(d) The Contractor shall be responsible for ensuring that the provisions of this clause apply to its subcontractors.

H-2

1852.232-77 LIMITATION OF FUNDS (FIXED-PRICE CONTRACT) (MAR 1989)

(a) Of the total price of items _TBDTO_ through _TBDTO_, the sum of $_TBDTO_ is presently available for payment and allotted to this contract. It is anticipated that from time to time additional funds will be allocated to the contract in accordance with the following schedule, until the total price of said items is allotted:

SCHEDULE FOR ALLOTMENT OF FUNDS

Date Amounts

(b) The Contractor agrees to perform or have performed work on the items specified in paragraph (a) of this clause up to the point at which, if this contract is terminated pursuant to the Termination for Convenience of the Government clause of this contract, the total amount payable by the Government (including amounts payable for subcontracts and settlement costs) pursuant to paragraphs (f) and (g) of that clause would, in the exercise of reasonable judgment by the Contractor, approximate the total amount at the time allotted to the contract. The Contractor is not obligated to continue performance of the work beyond that point. The Government is not obligated in any event to pay or reimburse the Contractor more than the amount from time to time allotted to the contract, anything to the contrary in the Termination for Convenience of the Government clause notwithstanding.

(c) (1) It is contemplated that funds presently allotted to this contract will cover the work to be performed until __.

(2) If funds allotted are considered by the Contractor to be inadequate to cover the work to be performed until that date, or an agreed date substituted for it, the Contractor shall notify the Contracting Officer in writing when within the next 60 days the work will reach a point at which, if the contract is terminated pursuant to the Termination for Convenience of the Government clause of this contract, the total amount payable by the Government (including amounts payable for subcontracts and settlement costs) pursuant to paragraphs

(f) and (g) of that clause will approximate 75 percent of the total amount then allotted to the contract.

(3) (i) The notice shall state the estimated date when the point referred to in paragraph (c)(2) of this clause will be reached and the estimated amount of additional funds required to continue performance to the date specified in paragraph (c)(1) of this clause, or an agreed date substituted for it.

(ii) The Contractor shall, 60 days in advance of the date specified in paragraph (c)(1) of this clause, or an agreed date substituted for it, advise the Contracting Officer in writing as to the estimated amount of additional funds required for the timely performance of the contract for a further period as may be specified in the contract or otherwise agreed to by the parties.

H-3

(4) If, after the notification referred to in paragraph (c)(3)(ii) of this clause, additional funds are not allotted by the date specified in paragraph (c)(1) of this clause, or an agreed date substituted for it, the Contracting Officer shall, upon the Contractor’s written request, terminate this contract on that date or on the date set forth in the request, whichever is later, pursuant to the Termination for Convenience of the Government clause.

(d) When additional funds are allotted from time to time for continued performance of the work under this contract, the parties shall agree on the applicable period of contract performance to be covered by these funds. The provisions of paragraphs (b) and (c) of this clause shall apply to these additional allotted funds and the substituted date pertaining to them, and the contract shall be modified accordingly.

(e) If, solely by reason of the Government’s failure to allot additional funds in amounts sufficient for the timely performance of this contract, the Contractor incurs additional costs or is delayed in the performance of the work under this contract, and if additional funds are allotted, an equitable adjustment shall be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of the items to be delivered, or in the time of delivery, or both.

(f) The Government may at any time before termination, and, with the consent of the Contractor, after notice of termination, allot additional funds for this contract.

(g) The provisions of this clause with respect to termination shall in no way be deemed to limit the rights of the Government under the default clause of this contract. The provisions of this Limitation of Funds clause are limited to the work on and allotment of funds for the items set forth in paragraph (a). This clause shall become inoperative upon the allotment of funds for the total price of said work except for rights and obligations then existing under this clause.

(h) Nothing in this clause shall affect the right of the Government to terminate this contract pursuant to the Termination for Convenience of the Government clause of this contract.

1852.235-74 ADDITIONAL REPORTS OF WORK—RESEARCH AND DEVELOPMENT

(FEB 2003)

In addition to the final report required under each applicable task order, the Contractor shall submit the following report(s) to the Contracting Officer:

(a) Monthly progress reports. The Contractor shall submit separate monthly reports of all work accomplished during each month of task order performance. Reports shall be in narrative form, brief, and informal. They shall include a quantitative description of progress, an indication of any current problems that may impede performance, proposed corrective action, and a discussion of the work to be performed during the next monthly reporting period.

H-4

(b) Quarterly progress reports. The Contractor shall submit separate quarterly reports of all work accomplished during each three-month period of task order performance. In addition to factual data, these reports should include a separate analysis section interpreting the results obtained, recommending further action, and relating occurrences to the ultimate objectives of the contract. Sufficient diagrams, sketches, curves, photographs, and drawings should be included to convey the intended meaning.

(c) Submission dates. Monthly and quarterly reports shall be submitted by the 15th day of the month following the month or quarter being reported. If the contract is awarded beyond the middle of a month, the first monthly report shall cover the period from award until the end of the following month. No monthly report need be submitted for the third month of contract effort for which a quarterly report is required. No quarterly report need be submitted for the final three months of contract effort since that period will be covered in the final report. The final report shall be submitted within TBDTO days after the completion of the effort under the contract.

ARC 52.209-99 ORGANIZATIONAL CONFLICTS OF INTEREST, AND LIMITATION OF

FUTURE CONTRACTING (JUL 2016)

(a) The Contracting Officer has determined that this acquisition may give rise to a potential organizational conflict of interest. Accordingly, the attention of prospective offerors is directed to FAR Subpart 9.5 - Organizational Conflicts of Interest.

(b) The nature of this potential Organizational Conflict is:

The SpS Contractors (and subcontractors or teaming partners, if applicable) may have potential conflicts of interest through unequal access of information if the Contractors or its subcontractors also provide support services (requirements development or integration) for the requiring organization.

(c) To avoid neutralize, or mitigate the potential organizational conflict of interest, the following restrictions upon this solicitation and future contracting shall apply:

The Government will prohibit any SpS prime or subcontractor from being a prime or subcontractor on the Operationally Responsive Space’s support service contract, Rapid Response Space Works (all work performed under NNA10DF16B), or its follow-on Space Enablers (SpE). The Contracting Officer may grant an exception to this subcontracting prohibition on a case by case basis, either based on a determination that a particular conflict has been successfully mitigated or neutralized, or that a waiver is appropriate.

(d) If, in the performance of work under this Contract, the Contractor has access to Government Sensitive Data or third-party proprietary data, the Contractor shall protect such data from unauthorized use or disclosure so long as it remains proprietary. In addition, the Contractor shall not be permitted to use such data other than in performance under this Contract, unless:

H-5

(1)…