Attachment_2_Statement_of_Work.pdf
PDF 1 MB Posted
- Attached to
- USCGC HAMILTON Helicopter Hangar Door System
- Solicitation number
- 70Z08518QP45496
About this file
Attachment 2
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
58820_JSP_0817_418
WORK ITEM 1: Helo Hangar Door Curtain Assembly, Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew the Hanger Door
Curtain Assembly components of the Port and Starboard Helo Hangar doors.
1.2 Contractor Provided OEM Parts.
MTI ITEM DESCRIPTION NSN/PN QUANTITY
Y Hanger Door Curtain Assembly HH3060 2
Y Door Curtain Bottom Bar Assembly HH3070 2
N Hood Baffle Seal Kits HH3113 2
N Door LH Guide Seal Kits HH3031 2
N Door RH Guide Seal Kits HH3032 2
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 750 WMSL 100-001, Rev L, General Arrangements (ASC100001)
Coast Guard Drawing 750 WMSL 169-001, Rev E, Helo Hangar Door Installation (ASC169001)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 3100 (SFLC Std Spec 3100), 2014, Inspect, Test and Recondition AC Synchronous Machines In-Place
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2014, Shipboard Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Coast Guard Technical Publication (TP) 7181, 02-OCT-07, Helo Hangar Doors
OTHER REFERENCES
ASTM International (ASTM) B633, 2007, Standard Specification for Electrodeposited Coating of
Zinc on iron and Steel
EASA Standard AR 100-2015, Recommended Practice For The Repair Of Rotating Electrical
Apparatus.
Air Capable Ship Aviation Bulletin 1L (2009)
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:
3.2.2 (Operational test – initial).
3.1.2 Tech Rep. The Contractor shall provide the services of a certified Tech Rep, who is familiar with the Federal Equipment Co. Model HH3000 Series Helo Hangar door system (i.e. Figure 1) to accomplish the following tasks:
Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.
Assist with proper repair methods, and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, test and reassembly of the equipment/system.
3.1.2.1 Ensure that the Tech Rep is a Certified Representative of Federal Equipment Co.
3.1.2.2 The Contractor shall provide on-site Tech Rep services for following tasks:
Initial Inspection, Operation Test & Door Removal
Door Installation and Final Operation Test
3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Lighting fixtures.
Electrical wiring.
Storage shelves and racks.
Piping.
Brackets.
3.1.5 Rolling door installation instruction. The generic rolling door (i.e. Weather Tight Hanger and
Cargo Doors) installation instruction from Federal Equipments Company is attached at the end of this specification. The Contractor shall use this instruction as guide lines and Tech Rep shall provide all instruction and guidance to renew highlighted parts shown in the Figure 2.
3.1.6 Electrical requirements. The Contractor shall accomplish all electrical work in accordance with
SFLC Std Spec 3042, and test cables in accordance with SFLC Std Spec 3041.
3.1.8 Ship Force will provide key of the Control Panel to verify operation of exterior electronic controls.
3.2 Curtain assembly renewal particulars. The Contractor shall accomplish the following while using
Coast Guard Drawings Coast Guard Drawing 750 WMSL 169-001 and TP 7181 as guidance.
3.2.1 Tech Rep shall provide services to the Contractor for inspection, renewal of Hanger Door Curtain
Assembly components and testing of the Helo Hanger Port and Starboard Doors.
3.2.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the Port and Starboard Hell Hanger Doors in both
Normal and Emergency Operation in accordance with TP 7181 to demonstrate existing operational condition. Submit a CIR.
NOTE
If equipment and/or machinery are inoperable, conduct only a visual inspection
3.2.3 Hangar door curtain system. Remove the curtain door (i.e. Port and Starboard) system assembly which is comprised of the following components:
Curtain (with including horizontal slats, end locks, and roller wind locks).
Safety edge retainer assembly (with cable take-up reel, sheave assembly, and curtain deck dogs)
Door guide assemblies.
Hood assembly.
Barrel assembly (Consists of Barrel, Charging Wheel Assembly, End Plates and Sprocket).
Chain Assembly with Chain Tensor
Cable Reel Assembly
3.2.3.1 Inspection and renewal. Conduct following inspection and renewal of door curtain assembly components of the Port and Starboard Helo Hangar doors with support from Tech Rep. Submit a CFR.
3.2.3.2 Door spring barrel assembly. The Contractor shall remove existing door spring barrel assembly
(i.e. Port and Starboard) and renew with GFP door spring barrel assembly in accordance with TP 7181.
Barrel assembly is consist of the following parts and is shown in the Figure 3.
Barrel
Charging Wheel Assembly
End Plates
Sprockets
Bearings
3.2.3.3 Hanger door curtain assembly. Inspect all door parts for damage/wear and renew Hanger Door
(i.e. Port and Starboard) Curtain Assembly components (i.e. HH3060) in accordance with TP 7181. The
Contractor with Tech Rep support shall remove existing hanger door curtain assembly (i.e. Port and
Starboard) and renew with GFP hanger door curtain assembly in accordance with TP 7181 and Figure 4.
3.2.3.4 Curtain drive system. Inspect and lubricate the curtain drive system.
3.2.3.5 Hand Crank Assembly and Drive Chain Assembly. Inspect all components of Hand Crank
Assembly and Drive Chain Assembly. Also inspect left and right hand guide rail assembly and charging wheel assembly.
3.2.3.6 Electric motor. Perform initial insulation test in accordance with the EASA Standard AR 100-
2015 or SFLC Std Spec 3100. Submit a CFR.
3.2.3.7 Door curtain bottom bar assembly. The Contractors shall remove existing door curtain bottom bar assembly (i.e. Port and Starboard) and renew door curtain bottom bar assembly ((i.e. Port and
Starboard) with GFP in accordance with TP 7181. Door curtain bottom bar assembly components are shown in Figure 5.
3.2.3.8 Dogging socket. Inspect dogging socket.
3.2.3.9 Chain Tensioner. Inspect chain tensioner components.
3.2.3.10 Control Enclosure. Inspect the control box and limit switches.
3.2.3.11 Exterior electronic controls.. Verify operation of exterior electronic controls and submit a CFR.
3.3 Safety markings. After the white coating has sufficiently dried in accordance with manufacturer’s instructions, restore all hangar door safety color markings, including safety stripes, using polysiloxane top coating black (17038), yellow (13538), and red (11105) colors in accordance with Air Capable Ship
Aviation Bulletin 1L (2009).
NOTE
Extreme precaution must be taken to prevent roller curtain door damage during preservation process.
3.3.1 After the white coating has sufficiently dried in accordance with manufacturer’s instructions, restore all hangar door safety color markings, including safety stripes, using polysiloxane top coating
Black (17038), Yellow (13538), and Red (11105) colors, as applicable, and in accordance with the following:
3.3.2. Per AVFAC Bulletin 1M: “On ships with vertically activated hangar doors, the lower 2 feet
(0.61m) of the door (exterior and interior) shall be painted with alternating yellow and red stripes (to provide a visual indication as to whether the door has been fully retracted prior to aircraft movement into and out of the hangar). The stripes shall be 4 inches (0.10 m) wide, and shall be painted at an angle of approximately 45 degrees rising from port to starboard. In addition, alignment stripes shall also be painted on hangar doors that, when fully retracted as designed, leave visible yellow/red stripes at the top of the doorway, yet still provide sufficient clearance for aircraft movement into/out of the hangar. With the hangar door fully retracted, the alignment stripes shall be painted in the upper corners of the doorway, on the door (exterior and interior), and on the adjacent track/bulkhead. The alignment stripes shall be readily visible from the deck, and should be approximately 6 inches (0.15m) long and 2 inches (0.05m) wide.”
3..3.3 Per AVFAC Bulletin 1M: “…where the approach line intersects a white forward superstructure or hangar face, two 12-inch black lines shall be painted on either side of the approach line, up the aft face of the superstructure from the flight deck to the top of the forward superstructure/hangar face. This will create an apparent 12-inch wide white extension of the approach line, up the white forward structure/hangar face for proper pilot alignment.”
3.4 Lubrication. The Contractor shall lubricate Helo Hanger Door Assembly (i.e. Port and Starboard) components in accordance with Table 2.1 of the TP 7181.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.5 Operational test – post repairs. After completion of installation, the Contractor and Tech Rep shall, in the presence of the Coast Guard Inspector, thoroughly test Port and Starboard Helo Hanger Door in
Normal and Emergency Operation in accordance with TP 7181 to demonstrate operating condition.
Submit a CFR.
3.5.1 Adjust and calibrate door curtain and chain assembly. Adjust spring tension.
3.5.2 Check operations of safety devices and adjust as necessary. Adjust the limit switches for proper operation.
3.5.3 Adjust roller curtain tie down dogs.
3.5.4 Check the electrical motor for proper operation.
3.6 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310, Appendix
A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting
Systems), respectively, and as applicable.
4. NOTES
FIGURE 1: HELO HANGER DOOR ASSEMBLY
FIGURE 2: HELO HANGER DOOR RENEWAL PARTS HIGHLIGHTED IN YELLOW.
FIGURE 3: DOOR SPRING BARREL ASSEMBLY
FIGURE 4: HANGER DOOR CURTAIN ASSEMBLY
FIGURE 5A: DOOR CURTAIN BOTTOM BAR ASSEMBLY
FIGURE 5B: DOOR CURTAIN BOTTOM BAR ASSEMBLY
File details come from the government source that posted it.