USCGC ALERT (WMEC 630)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2019

Developed By: Donald D Deibler

(Rev-0, 16 Aug 2018)

USCGC ALERT (WMEC-210B) DOCKSIDE AVAILABILITY FY2019

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items .............................................................................................. x Principal Characteristics ............................................................................................................................... xi General Requirements WORK ITEM 1: Tanks (Aviation Fuel Service), Clean and Inspect WORK ITEM 2: Tanks (MP Fuel Service), Clean And Inspect WORK ITEM 3: Tanks (Potable Water), Clean and Inspect WORK ITEM 4: Tanks (MP Fuel Stowage And Overflow), Clean And Inspect WORK ITEM 5: Tanks (Dirty Oil and Waste), Clean and Inspect WORK ITEM 6: 28 Volt DC Helo Power Supply, Load Test WORK ITEM 7: Windspeed Transmitter (Anemometer), Renew WORK ITEM 8: Vent Ducts (Engine And Motor Room All), Commercial Cleaning WORK ITEM 9: Vent Ducts (Galley and Pantry Room All), Commercial Cleaning WORK ITEM 10: Vent Ducts (Laundry Exhaust), Commercial Cleaning WORK ITEM 11: Anchor Chain(s) and Ground Tackle, Inspect and Repair WORK ITEM 12: Anchor Windlass, Overhaul WORK ITEM 13: Hawse Pipes, Preserve WORK ITEM 14: Warping Capstan, Overhaul WORK ITEM 15: Helo Talon Grids, Inspect And Test WORK ITEM 16: Tanks (Grey Water Holding), Preserve “100%” WORK ITEM 17: Tanks (Sewage Holding), Preserve “100%” WORK ITEM 18: Chain Locker, Preserve 100% WORK ITEM 19: Decks, Helicopter Operating Areas, Preserve WORK ITEM 20: Ammunition Elevator, Service and Inspect WORK ITEM 21: 400 Hz Power Supply, Relocate (TCTO TD3030) WORK ITEM 22: Chain Locker Bulkhead Repairs (NCWR-20150016) WORK ITEM 23: Anchor Windlass Foundation, Repair (NCWR-20150016) WORK ITEM 24: Steam Kettle Piping (Galley), Renew (NCWR-20170025) WORK ITEM 25: Fuel Deck Riser, Renew (NCWR-20170037) WORK ITEM 26: Deck (Bos’n Stores), Repair (NCWR-20180001) WORK ITEM 27: Watertight Doors and Scuttles (External), Renew (NCWR-20160022 & 20170026) . 114 WORK ITEM 28: Foc’sle Deck Ventilator, Repair (NCWR-20170038) WORK ITEM 29: Boiler Feedwater Piping, Renew (NCWR- 20180003) WORK ITEM 30: Flow Meter (Aviation Fuel), Renew (TCTO TM4060) WORK ITEM 31: Watertight Hatch and Scuttle (External), Renew (NCWR-20170027) iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Bill of Materials 627 WMEC 11, Rev C; 3rd Dk, 2nd Dk, Main Dk, 02 Dk, & Bridge Dk

Pltg & Supports

Coast Guard Bill of Materials 627 WMEC 13, Rev F, Arrangement of Fuel Oil System

Coast Guard Bill of Materials 627 WMEC 327, Rev G, Watertight Doors Hatches & Scuttles

Coast Guard Bill of Materials 627 WMEC 41, Rev C, Arrgt Vent & Air Cond 01 Dk

Coast Guard Bill of Materials 627 WMEC 61, Rev H, Arr. Stm., Feed & Conds. Sys. Piping

Coast Guard Bill of Materials 627 WMEC 97, Rev F, Arrangement Aviation Fuel System

Coast Guard Drawing 618 WMEC 184-003, Rev K, IC & Gyro RM Electrical Foundation Details

Coast Guard Drawing 618 WMEC 314-001, Rev E, 400 Hz Static Converter and 28.5 VDC Helicopter

Start Rectifier Replacement Diagram

Coast Guard Drawing 618 WMEC 314-001, Rev G, Helo 400 HZ & 28 VDC Replacement Diag

Coast Guard Drawing 618 WMEC 401-001, Rev AF, IC & Gyro RM General Arrangement

Coast Guard Drawing 618 WMEC 430-050, Rev -, IC Switchboard Distribution Panel

Coast Guard Drawing 627 WMEC 085-301, Rev C, Booklet of General Plans

Coast Guard Drawing 627 WMEC 103-006, Rev-, Inboard Profile

Coast Guard Drawing 627 WMEC 111-001, Rev A, Shell Expansion Framing & C.V.K.

Coast Guard Drawing 627 WMEC 111-001, Rev A, Shell Expansion Framing and CVK

Coast Guard Drawing 627 WMEC 116-001, Rev-, Forepeak Framing, Chain Locker & Transv. Bhds #12

& #15 1/2

Coast Guard Drawing 627 WMEC 116-001, Rev-, Forepeak Framing, Chain Locker and Transverse

Bulkheads 12 and 15-1/2

Coast Guard Drawing 627 WMEC 116-001, Rev-; Forepeak Framing, Chain Locker & Transv Bhds #12

& #15 1/2

Coast Guard Drawing 627 WMEC 123-002, Rev C, New Double Bottoms Fuel Tank Structure Details

Coast Guard Drawing 627 WMEC 123-003, Rev B, Lube Oil, Dirty Oil, & Diesel Oil Overflow Tanks

Structural Details

Coast Guard Drawing 627 WMEC 123-008, Rev-, LO, Dirty Oil & DO Ovfl Tank Struct Det

Coast Guard Drawing 627 WMEC 131-001, Rev D, 2nd & Main Deck Plating & Supports

Coast Guard Drawing 627 WMEC 131-001, Rev D, Second & Main Deck Plating & Supports v (Rev-0)

Coast Guard Drawing 627 WMEC 167-001, Rev L; Schedule of Steel Doors, Hatches, Scuttles &

Manholes

Coast Guard Drawing 627 WMEC 182-005, Rev B, Foundations for Oily Water Separator System

Coast Guard Drawing 627 WMEC 184-003, Rev G, IC & Gyro RM Electrical Foundation Details

Coast Guard Drawing 627 WMEC 186-002, Rev C, Talon Grid Fdn & Structural Mod 01 Level

Coast Guard Drawing 627 WMEC 186-005, Rev-, FDN of Warping Winch & Anchor Handling Gear

Coast Guard Drawing 627 WMEC 261-001, Rev C, Diagram Fuel Oil System

Coast Guard Drawing 627 WMEC 261-002, Rev E, Arrangement of Fuel Oil System

Coast Guard Drawing 627 WMEC 261-002, Rev F, Arrangement of Fuel Oil System

Coast Guard Drawing 627 WMEC 401-001, Rev AD, General Arrangement of IC & Gyro RM

Coast Guard Drawing 627 WMEC 437-002, Rev B, Wind speed & Direction Ind Sys Elem Wrg Diag IC

Ckt “HD & HE”

Coast Guard Drawing 627 WMEC 437-003, Rev A, Wind spd & Dir Ind Sys Ckt “HD & HE” Block and

Elem Wrg Diag

Coast Guard Drawing 627 WMEC 506-001, Rev C, Diagram Sounding Tubes and Air Escapes

Coast Guard Drawing 627 WMEC 506-002, Rev E, Arrangement of Sounding Tubes and Air Escapes

Coast Guard Drawing 627 WMEC 512-001, Rev D, Ventilation Equipment List

Coast Guard Drawing 627 WMEC 512-006, Rev D, Ventilation Diagram Second Deck

Coast Guard Drawing 627 WMEC 512-007, Rev D, Ventilation Diagram – Main Deck

Coast Guard Drawing 627 WMEC 512-007, Rev D, Ventilation Diagram Main Deck

Coast Guard Drawing 627 WMEC 512-008, Rev D, Ventilation Diagram 01 Dk & Abv

Coast Guard Drawing 627 WMEC 512-011, Rev H, Arrgt Ventilation & AC Main Deck

Coast Guard Drawing 627 WMEC 512-012, Rev D, Arrgt Vent & Air-Cond 01 Deck

Coast Guard Drawing 627 WMEC 512-019, Rev A, Ventilation ModsIncid to DC Shop and Steering Gr

Rm

Coast Guard Drawing 627 WMEC 512-020, Rev -, Arrgt Vent & Air Cond 02 & Bridge Dk

Coast Guard Drawing 627 WMEC 512-021, Rev -, Arrgt Vent & Air Cond 01 Deck

Coast Guard Drawing 627 WMEC 512-026, Rev -, Arrangement Ventilation & Air Conditioning Main

Deck

Coast Guard Drawing 627 WMEC 512-029, Rev -, Arrangement Ventilation & Air Conditioning Second

Deck

Coast Guard Drawing 627 WMEC 512-030, Rev -, Arrangement Ventilation & Air Conditioning Third

Deck

Coast Guard Drawing 627 WMEC 533-001, Rev G, Diagram Hot & Cold Potable Water System

Coast Guard Drawing 627 WMEC 533-002, Rev H, Arr of Hot & Cold Potable Water

Coast Guard Drawing 627 WMEC 533-005, Rev-, Diagram Hot & Cold Potable Water

Coast Guard Drawing 627 WMEC 533-006, Rev-, Arr of Hot & Cold Potable Water

Coast Guard Drawing 627 WMEC 535-001, Rev G, Diagram Steam, Feed and Condensate System Piping

Coast Guard Drawing 627 WMEC 535-002, Rev H, Arr. Stm., Feed & Condensate System Piping

Coast Guard Drawing 627 WMEC 535-006, Rev-, Stm., Feed & Condensate System Piping Incidental to

Boiler Life Improvement

Coast Guard Drawing 627 WMEC 542-1, Rev E, Diagram Aviation Fuel System

Coast Guard Drawing 627 WMEC 542-2, Rev E, Arrangement of Aviation Fuel System vi (Rev-0)

Coast Guard Drawing 627 WMEC 581-001, Rev A, Anchor Handling

Coast Guard Drawing 627 WMEC 581-001, Rev B, Anchor Handling

Coast Guard Drawing 627 WMEC 581-001, Rev-, Anchor Handling

Coast Guard Drawing 627 WMEC 581-002, Rev A, Anchor Pocket Arrangement and Detail

Coast Guard Drawing 627 WMEC 581-003, Rev-, Capstan Windlass Assembly

Coast Guard Drawing 627 WMEC 581-005, Rev A, Anchor Windlass

Coast Guard Drawing 627 WMEC 581-005, Rev-, Anchor Windlass

Coast Guard Drawing 627 WMEC 582-001, Rev A, Warping Capstan General Arrangement

Coast Guard Drawing 627 WMEC 582-005, Rev A, Warping Capstan Assembly

Coast Guard Drawing 627 WMEC 583-010, Rev-, Capstan-Windlass Assembly

Coast Guard Drawing 627 WMEC 601-001, Rev F, Outboard Profile

Coast Guard Drawing 627 WMEC 601-002, Rev B, Inboard Profile

Coast Guard Drawing 627 WMEC 601-004, Rev D, General Arrangement Main & 01 Deck

Coast Guard Drawing 627 WMEC 601-004, Rev D, General Arrangement Main & 01 Dk

Coast Guard Drawing 627 WMEC 613-001, Rev B, Main Mast Rigging, Arrg’t & Dets

Coast Guard Drawing 627 WMEC 651-001, Rev H, Arrgt Crews Galley, Mess & Scullery

Coast Guard Drawing 627 WMEC 672-005, Rev A, Bosn Stores 2nd and Main Deck

Coast Guard Drawing 627 WMEC 711-1, Rev -, Ammo Hoist Coast Guard Publications

Coast Guard Drawing 627 WMEC 85-231, Rev C, Booklet of General Plans

Coast Guard Drawing 627 WMEC 85-301, Rev A, Booklet of General Plans

Coast Guard Drawing FL 3801_79, Rev B, Waterproof Ventilator Assembly & Details 12 inch

Coast Guard Drawing FL 3801_82, Rev A, Waterproof Ventilator Assembly & Details 15 inch

Coast Guard Drawing FL-588-003, Rev -, Talon Grid, Supporting Skirt & Cover Fabrication & Instl

Coast Guard Technical Publication (TP) 3241B, Jan 2006, Manufacturers Instruction Book, SWBS

Group(s) 651-712

NAVSEA Drawing 803-1385866, Rev E, Penetration, Bulkhead and Deck

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual

Coast Guard Technical Publication (TP) 3234A, Dec 2012, Distribution Switchboard

Coast Guard Technical Publication (TP) 3239A, SWBS 542, Nov 2016, JP-5 Flow Meter

Coast Guard Technical Publication (TP) 3240A, SWBS 581, Oct 2011, Anchor Windlass

Coast Guard Technical Publication (TP) 3240A, SWBS 582, Oct 2011, Warping Capstan

Coast Guard Technical Publication (TP) 3368, Feb 2015, Talon Helicopter Landing Grid - Type 18-22-01

Multiple Class Cutters

Coast Guard Technical Publication (TP) 3934, Aug 2009, Section 321A, Precision Frequency Converters

Coast Guard Technical Publication (TP) 4931, Aug 2009, FCX Systems Precision Frequency Converters

Coast Guard Technical Publication (TP) 5461, Nov 2012, Anemometer

Coast Guard Technical Publication (TP) 7099, SWBS 314, 10 Oct 2007, Rectifier Power Supply, 28

VDC, 300 Amp

Coast Guard Technical Publication (TP) 9142, Nov 2016, Meter – Model M-5-2 Direct Drive

NAVSEA Drawing 803-1385866, Rev E, Penetration, Bulkhead and Deck vii (Rev-0)

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2014, Overhaul AC

Electrical Motors In-Shop

Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2014, Shipboard

Electrical Cable Test

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard

Electrical Cable removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary

Machine Systems

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean

Shipboard Ventilation Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2014, Temporary

Hull Accesses

OTHER REFERENCES

American Bureau of Shipping (ABS) Approved Chain, Accessory and Bar Manufacturing Facilities List, Oct 2016

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System

Components - Health Effects

ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component

Adhesives (AN)

Commercial Item Description (CID) A-A-59316, 2003, Abrasive Materials for Blasting

Enclosure (1) – Test Memorandum, U.S. Coast Guard Yard

Federal Specification (Fed Spec) QQ-N-281D(2), Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections

Federal Specification (Fed Spec) RR-C-271, Rev E, Mar 2016, Chains and Attachments, Carbon and

Alloy Steel

MIL-C-24633, Oct 2014, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded

MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of

Reliability Is Required

MIL-DTL-23549, Sep 2016, Grease, General Purpose

MIL-PRF-16173, 2006, Corrosion Preventive Compound, Solvent Cutback, Cold-Application

MIL-PRF-24667, May 2008, Coating system, Non-Skid, for Roll or Spray Application

Naval (NAVAIR) Drawing 626348, Rev C, Visual Landing Aids Installation WMEC-210 Class Ships

QPL-24667, Jul 2014, Qualified Product List of Products Qualified under Performance

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and

Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets viii (Rev-0)

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and

Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183A, 2013, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 6/NACE No. 3, 2007, Commercial Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE), 2006, Joint Surface

Preparation Standard SSPC-SP 10/NACE No.2, Near-White Blast Cleaning ix (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM

DESCRIPTION

NSN/PN QTY ESTIMATED

COST

($/UNIT)

8 Y Anemometer NSN: 6600-709-9947 2 ea. 1,250.00

15 N M16 Bolts NSN: 5305-01-393-1827 24 ea. 25.65

15 N M12 Bolts NSN: 5305-01-584-6095 12 ea. 33.75

15 N **Talon Grid

Stanchion Bolt

Assembly, Including

Locking Nut

NSN: 5340-01-481-3786 60 ea. 31.50

21 Y 400 HZ Power

Supply

PN: PFC010-40-FN 1 ea. 30,084.00

27 N 46” X 42” Raised

Watertight Hatch with 25” Quick

Acting Water Tight

Scuttle

1 ea 9,000.00

27 N 26” X 66” Quick

Acting Water Tight

Door

NSN: 2040-00-542-0209 1 ea 9,000.00

30 N **JP-5 Flow meter, Meter

NSN: 6680-01-658-6663 1 ea. 3,100.00

30 N ** Counter Rotating, Register

NSN: 6680-01-439-2365 1 ea. 388.00

31 N 48” X 48” Raised

Watertight Hatch with 18” Quick

Acting Water Tight

Scuttle

1 ea 9,000.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter x (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5

(Inspection report particulars)):

Work

Item Title

11 Anchor Chain(s) and Ground Tackle, Inspect and Repair

12 Anchor Windlass, Overhaul

14 Warping Capstan, Overhaul

15 Helo Talon Grids, Inspect And Test xi (Rev-0)

PRINCIPAL CHARACTERISTICS

210' WMEC (B-CLASS)

PHYSICAL

Length overall 210' 6"

Length between perpendiculars 200' 0"

Beam molded 34' 0"

Depth molded, main deck amidships 19' 6"

Full load displacement 1,170 long tons

Draft, full load to baseline amidships

*Baseline is 9” below keel amidships

12' 0"

Design drag between perpendiculars 1' 6"

Highest projection above baseline

*VHF-FM ADF antenna

90' 0"

Shore tie voltage requirements 400A / 440V

Frame spacing 1' 0"

MACHINERY

Main propulsion 2 ALCO Model 16-251-B Diesel Engines, 5,000 BHP total

Ship's service generators 2 Caterpillar Model 3406B Diesel-driven SR4, 250 KW each @ 0.8 power factor, 440VAC, 3 phase, 60 cycle

Emergency generator Caterpillar Model 3306B Diesel-driven SR4, 180 KW @ 0.8 power factor, 440VAC, 3 phase 60 cycle

Number of propellers 2

Propeller diameter 7' 6"

Number of blades, each 4

Pitch Controllable

Shaft RPM 300

Shaft diameter 8.25" at exit of hull

Anchor & chain Two 2,800 lb Navy Stockless Anchors, 7 shots of chain each

TANK CAPACITIES

Diesel fuel total (95%) 48,427 gal.

Fresh water total (100%) 11,693 gal.

JP-5 fuel total (95%) 4,683 gal.

Lube oil total (95%) 2,390 gal.

1 (Rev-0)

00000_0518_FLT

REC_00000_FLT_Commercial Project @ CG Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec

0000, in accomplishing the following task:

Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to six Coast Guard fire watch personnel.

Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes

(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC

Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable

Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

APM: If applicable, provide the list of unit-specific plans and permits required, and provide description of the specifics of these plans in paragraph 3.5.1.2. Otherwise delete paragraph 3.5.1.2.

CG Base or Sector Environmental POC must provide theses details.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an

NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

3 (Rev-0)

Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste

Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the

Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the

Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For

Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor shall be aware of the following:

3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the

Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast

Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. None.

4 (Rev-0)

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2018 Edition Standard Specifications and supersede published content:

none

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

6 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

7 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

8 (Rev-0)

TIME

9 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading

(mils)

Mean Reading (mils) IAW ASTM DD4417).

10 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

11 (Rev-0)

12 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic

Pull-Off (Type I/Banana) Gauge Is

Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

13 (Rev-0)

12300_0617_FLT

REC_12311_FLT_210’ WMEC ‘B’ Class (ALL) (0717)

WORK ITEM 1: Tanks (Aviation Fuel Service), Clean and Inspect

APM: Do not edit title.

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):

TYPE OF TANK LOCATION CAPACITY - 95%

(GALLONS)

LOW SUCTION (GALLONS)

JP-5 Fuel Service 4-164-1-J 898 26

NOTE TO USER: Format merged table and associated notes. Review table and table notes, and modify as required. Ensure all blocks in the table are filled in.

1.2 Government-furnished property.

APM: Validate all GFP data. If the Spec Package's Consolidated List of GFP is changed, ensure it is changed in the source WI and GFP style is applied.

None.

2. REFERENCES

APM: If editing a WI's References, change the same reference in the Spec's

Consolidated List of References and send feedback to the WI's Developer.

COAST GUARD DRAWINGS

Coast Guard Drawing 627 WMEC 123-002, Rev C, New Double Bottoms Fuel Tank Structure

Details

Coast Guard Drawing 627 WMEC 123-003, Rev B, Lube Oil, Dirty Oil, & Diesel Oil Overflow

Tanks Structural Details

Coast Guard Drawing 627 WMEC 261-001, Rev C, Diagram Fuel Oil System

Coast Guard Drawing 627 WMEC 261-002, Rev E, Arrangement of Fuel Oil System

14 (Rev-0)

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

OTHER REFERENCES

Federal Specification (Fed Spec) QQ-N-281D(2), Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183A, 2013, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

3. REQUIREMENTS

3.1 General. The Contractor shall refer to Coast Guard drawings 627 WMEC 627 WMEC 123-002, 627

WMEC 123-003, 627 WMEC 261-001 and 627 WMEC 261-002 for guidance.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel’s components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following: up to a total of 5,000 gallons of diesel fuel. .

Note to A-team: Compare paragraph 3.1.4 and low suction quantities in designated tanks. Ensure amount in paragraph 3.1.4 is sufficient to include all disposals required.

NOTE

Vessel may come in with less tank fluid contents than specified above. The

Contractor is responsible for providing all materials, equipment and services necessary to comply with local environmental regulations.

3.1.5 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

15 (Rev-0)

3.2 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as residual water, sediment, sludge, rust, and bacterial growth, taking care not to damage the coating system (if applicable).

3.2.1 Remove cleaning media and residues continuously during the washing process. Wash the tank with high-pressure cold fresh water before it has a chance to dry after emptying. Do not use steam; it can damage the tank’s coating.

3.2.2 Drain and dry the tank using a portable air-driven pump. When dry, and after final visual inspection, close the tank. Submit a CFR.

WARNING

Do not use the Fuel Service or Transfer systems to drain water from the tank.

Excessive fuel contamination will result.

3.3 Tank content and waste disposal. The Contractor shall dispose of tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.

3.4 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:

Tank structural condition.

Inaccessible areas.

Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.

Tank level indicator (TLI) and/or float switch condition.

Sounding/vent tube and striker plate condition.

Suction and discharge piping condition.

Fastener material and condition.

3.4.1 Pit measurement. Measure up to 10 “pits” within each tank as designated by the Coast Guard

Inspector using a Contractor supplied ‘Pit Gauge’. The results of these measurements shall be included in the inspection report showing location of pit measurements and depth of pit(s).

3.5 Ultrasonic thickness (UT) measurement. The Contractor shall take a total of 50 UT measurements of tank plating in accordance with SFLC Std Spec 0740, Appendix C in locations designated by the Coast

Guard Inspector and using drawings in Section 2 (References) as guidance. Submit a CFR.

16 (Rev-0)

NOTES TO USER:

Discuss w/A-TEAM members whether or not UT inspection report should be submitted as a CIR. If yes, then do the following:

a. Change “Submit CFR” to “Submit a CIR”

b. Add the SFLC CIR standard phrase to 3.1.1 and indicate paragraph 3.5

3.6 Tank closing. The Contractor shall ensure that the tank(s) remain open for approximately 24 hours after completion of any KO-authorized repair and preservation procedures. Notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to

AMS-C-6183. Chase threads on studs to ensure even installation of the access covers. Renew any damaged or non-monel nuts with Nickel-Copper alloy (monel) nuts meeting QQ-N-281, Class A or B.

The nuts and bolts shall be of different classes to prevent galling. Existing undamaged fasteners meeting this specification may be reused. For purpose of bid, assume 100% of existing fasteners will require renewal.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.7 Operational test, post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

4. NOTES

4.1 Tank content removal. The Ship’s force will pump down the tanks to the maximum extent possible with the installed pumping system.

4.2 Tank inspection. The Coast Guard Inspector will visually inspect the tank interior immediately prior to closing.

4.3 Refilling. After final visual inspection and tank closure, Ship’s force will refill tank with JP-5 fuel.

Recirculate the fuel until it is clear and bright and passes the MK I and MK III detector kit tests. Flush all lines, pipes, and fittings before placing the JP-5 system back in service.

17 (Rev-0)

12305_0917_FLT

WORK ITEM 2: Tanks (MP Fuel Service), Clean And Inspect

APM: Do not edit title.

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following

TABLE 1 - FUEL SERVICE TANKS

LOW SUCTION (GALLONS)

Diesel Fuel Service 4-143-1-F 5766 190

Diesel Fuel Service 4-143-2-F 5766 190

APM: Format merged table and associated notes. Review table and table notes, and modify as required. Ensure all blocks in the table are filled in.

1.2 Government-furnished property.

APM: Validate all GFP data. If the Spec Package's Consolidated List of GFP is changed, ensure it is changed in the source WI and GFP style is applied.

None.

2. REFERENCES

APM: If editing a WI's References, change the same reference in the Spec's

Consolidated List of References and send feedback to the WI's Developer.

COAST GUARD DRAWINGS

Coast Guard Drawing 627 WMEC 123-002, Rev C, New Double Bottoms Fuel Tank Structure

Details

Coast Guard Drawing 627 WMEC 123-003, Rev B, Lube Oil, Dirty Oil, & Diesel Oil Overflow

Tanks Structural Details

18 (Rev-0)

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

OTHER REFERENCES

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of Reliability Is Required

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

A-Team Note: Compare paragraph 3.1.4.1 and low suction quantities in designated tanks. Ensure amount in paragraph 3.1.4.1 is sufficient to include all disposals required.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

Fuel

Piping

Tank access cover

3.1.4.1 The Contractor shall remove up to a total of 5,000 gallons of diesel fuel. Document a complete chain of custody record of the removed tank contents from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.

19 (Rev-0)

A-Team Note: Select applicable paragraph 3.1.4.2 and delete the other and this note box.

3.1.4.2 Dispose of removed fluids in accordance with all applicable Federal, state, and local regulations

(see 4.2 (Tank content restoration)).

NOTE

Vessel may come in with less tank fluid contents than specified above.

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast Guard

Personnel perform an initial operational test of the TLI’s for tanks listed in paragraph 1.1 (Intent), to demonstrate existing operational condition. Submit a CFR.

3.3 Plug log. The Contractor shall keep a written record of all plugs put in any tanks vents. A separate list shall be kept for each tank being entered.

3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.

3.3.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.

NOTE

Initial and post repair operational tests apply only to tanks that possess TLIs.

3.4 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as residual fuel or water, sediment, sludge, rust, or biological growth, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths. The Contractor shall refer to Coast Guard drawings 627 WMEC 627

WMEC 123-002, 627 WMEC 123-003, 627 WMEC 261-001 and 627 WMEC 261-002 for guidance.

3.5 Tank content and waste disposal. The Contractor shall dispose of residual tank contents and any cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.

3.6 Inspection. The Contractor shall accomplish the following tasks:

3.6.1 Visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces.

Submit a CFR including the following, as applicable:

Tank structural condition.

Inaccessible areas.

20 (Rev-0)

Condition of tank coating, including measurements taken, percentage, location, and type of coating failure (if tank interior surfaces are coated).

Tank level indicator (TLI) and/or float switch condition, as applicable.

Sounding/vent tube and striker plate condition.

Suction and discharge piping condition.

Fastener material and condition (correct fastener material is stainless steel).

3.6.2 Measure up to 10 “pits” within each tank as designated by the Coast Guard Inspector using a

Contractor supplied ‘Pit Gauge’. Include pit measurement results in CFR specified above, showing where pit measurements were taken and the depth of the pit.

3.7 Tank closing. The Contractor shall ensure that the tank(s) remain open for at least 24 hours after completion of any KO-authorized repair and…

This is the start of the file's text. The full file is on GovTribe.