Q&A-2_70Z03820QB2000002.docx

DOCX document 26 KB Posted

Attached to
H-65 FIRST ARTICLE / PRODUCTION BUY COOLING MANIFOLDS
Solicitation number
70Z03820QB2000002
Issued by

View the file

Other files

File Type Posted
Q&A_70Z03820QB2000002.docx DOCX document
SOW.docx DOCX document
DHS_11000-6_NDA.pdf PDF
Requirements_-_70Z03820QB2000002.xlsx XLSX spreadsheet
Technical_Acceptability_Worksheet.xlsx XLSX spreadsheet
Terms_and_Conditions_70Z03820QB2000002.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

70Z03820QB2000002 – Amendment 0003 Solicitation 70Z03820QB2000002 Q&A

Q1) I understand you need a 1st article of parts sent to you prior to releasing the remaining sets, but do you need a formal First Article Inspection Report (FAIR) for the first sets too? Or will our six point inspection report be acceptable for the first set of parts?

A1) Six point inspection report will be acceptable